Repot and Action plan for the NCR and Site Instructions

Date:24/02/2015
Project Title

: Palm Mall Muscat

Client

: TAMANI GLOBAL DEVELOPMENT & INVESTMENT LLC(TGDI)

Project Manager : Project management consultancy (PMC)


Consultant

: Engineering innovation Design & consulting LLC (EIDC)

Contractor

: SMC Infra LLC(SMC)

TO
Mohammad Fayazuddin
Resident Manager
EIDC
WE CONFIRM THE FOLLOWING INSTRUCTION:-

NC
R/
SI

NC
R1
7

Description

Cold
joint
concrete
segregation
concrete

Detailed Report

and
in

Location:Part03/po
ur 2/SF/Grid F/6-9.

For SMC

Regarding concreting the second floor


slab in the area Part 03- Pour 01, from
the pouring plan that we have submitted
before concrete, We can understand that
some of portion those cannot cover with
the 49 meter pump, were decided to
pour with chute and bucket. Up to the
grid F-06, concrete pouring was done in a
good condition. The rate of discharge of
concrete from plant should be minimized
while pouring in chute and bucket. But by
mistake, the plant was completely
stopped and rerouted the transit mixers.
Restarting the plant takes more time
than expected for getting the required
pouring rate. That was the main reason
for delay in pouring. The effect of delay
was much bigger because of the pouring
methods. Based on our senior engineers
comment, we have arranged the 58
meter pump for the getting smooth
pouring for balance portions.

(Name)

Action Plan

We can do the core testing


for this particular area of the
slab for ensuring the quality
and strength.

(Signature)
SMC INFRA LLC, P.O.BOX:1126,P.C:130,AZAIBA,SULTNAT OF OMAN,TEL:+96824492105,FAX:
+96824492115 SMC/IMS/PRJ/021 REV 00
ISSUED DATE:01/09/2014

Repot and Action plan for the NCR and Site Instructions
Date:24/02/2015
Project Title
Client

: Palm Mall Muscat


: TAMANI GLOBAL DEVELOPMENT & INVESTMENT LLC(TGDI)

Project Manager : Project management consultancy (PMC)


Consultant

: Engineering innovation Design & consulting LLC (EIDC)

Contractor

: SMC Infra LLC(SMC)

TO
Mohammad Fayazuddin
Resident Manager
EIDC
WE CONFIRM THE FOLLOWING INSTRUCTION:-

NC
R/S
I

Description

Detailed Report

Action Plan

NC
R1
8

Water leakage
occurred from soffit
floor level slab

The found cracks are surface


airline/shrinkage cracks, the marked
cracks were not developed anymore
in the slab by width and depth wise

The cracks area to be sealed


with the crystalline
waterproofing as approved by
the consultant. The cracks
will be poured by the
crystalline waterproofing
itself. Moreover after the
crystalline waterproofing
work, water test to be
conducted where ever
leakage occurred

Location: Part
02/Pour 03/ First
floor slab/Grid H/1722

For SMC

(Name)

(Signature)
SMC INFRA LLC, P.O.BOX:1126,P.C:130,AZAIBA,SULTNAT OF OMAN,TEL:+96824492105,FAX:
+96824492115 SMC/IMS/PRJ/021 REV 00
ISSUED DATE:01/09/2014

Repot and Action plan for the NCR and Site Instructions
Date:24/02/2015
Project Title
Client

: Palm Mall Muscat


: TAMANI GLOBAL DEVELOPMENT & INVESTMENT LLC(TGDI)

Project Manager : Project management consultancy (PMC)


Consultant

: Engineering innovation Design & consulting LLC (EIDC)

Contractor

: SMC Infra LLC(SMC)

TO
Mohammad Fayazuddin
Resident Manager
EIDC
WE CONFIRM THE FOLLOWING INSTRUCTION:-

NC
R/S
I

Descriptio
n

Detailed Report

Action Plan

SI17

Steel storage
issues
Location:
Steel Yard

For the easy access of the rebar from the


yard, we have stored in the tower crane
accessible area around the mall. Steels are
stored in place but without not enough
earth clearance.

Already we have done the


PCC for the steel storage in
yard area. Around the
building, we will provide the
plywood & concrete blocks for
the steel storage to prevent
from the earth.

Ge
n

MEP Block
work
Coordination
issue(As
discussed in
the QA /QC
meeting)

It has been co-ordinated with the MEP


team while doing the block work. We have
not noticed the pipeline wherever running
parallel to the block work.

We have implemented the


area handing over format to
improve the co-ordination at
site level. Also if any
complication will arise in the
time of plaster or painting,
the MEP team agreed that to
removing pipe.

For SMC
(Signature)

(Name)

SMC INFRA LLC, P.O.BOX:1126,P.C:130,AZAIBA,SULTNAT OF OMAN,TEL:+96824492105,FAX:


+96824492115 SMC/IMS/PRJ/021 REV 00
ISSUED DATE:01/09/2014