Sie sind auf Seite 1von 14

SATELLITE FIELD DEVELOPMENT PROJECT

(PHASE I)
ITUT AND ABANG JACKET WEIGHING PROCEDURE

MOBIL
P RODUCING
NIGERIA

Prepared, Reviewed, Endorsed and Approved by:


Person

Description

Gordon Dunthorne
NIGERDOCK Engineer
Manager

Prepared
by

Melchor Yaun
NIGERDOCK Lead Engineer

Checked
by

Jagba Smart
NIGERDOCK QA/QC
Engineer
Edward York
NIGERDOCK Project
Manager

Endorsed
by

MPN Representative

NGTA-NK-NPZZZ-00-XXXXXXX Rev. A

Signature

Approved
by
Approved
by

ii

Date

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING PROCEDURE

MOBIL
P RODUCING
NIGERIA

REVISION MODIFICATION LOG

Revision

Section

Rev. A

ALL

ACTION

Description

Initial Document

NGTA-NK-NPZZZ-00-XXXXXXX Rev. A

Issued for Review/Comments

iii

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING PROCEDURE

MOBIL
P RODUCING
NIGERIA

TABLE OF CONTENTS

1.0

SCOPE OF WORK

2.0

INTRODUCTION

3.0

CONCLUSION

4.0

SAFETY

5.0

EQUIPMENT

6.0

ORGANIZATIONAL CHART

7.0

PERSONNEL

8.0

COMMUNICATION

9.0

METHOD

10.0

ANALYSIS

10

11.0

DATA ANALYSIS

13

12.0

REFERENCES

13

APPENDIX A
APPENDIX B

NGTA-NK-NPZZZ-00-XXXXXXX Rev. A

iv

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

1.0

MOBIL
P RODUCING
NIGERIA

SCOPE OF WORK
This procedure describes the method that will be utilized for the weighing of
SFDP Jackets pertaining to NDs Scope of work for Mobil Producing Nigeria.
This procedure is based on SFDP Jackets, SFDP Jacket Weight is 258.2 Mt
(as of estimate 27-01-).

2.0

INTRODUCTION
This document describes the weighing of ITUT Jacket Structural Analysis of the
Jacking point currently being fabricated at Nigerdock Nigeria FZE, located at
Snake Island Apapa Lagos.
The method of weighing will be firstly place sheets of 30mm thick steel plate
under the jacket grillage points, then insert jacking stool frames in position
directly under the centre of each platform support leg and to place the enerpac
load cells immediately on top of this jacking stool support frame (shimmed to
suit) This will enable 4 enerpac load cells wires to be run and utilized along with
the enerpac control panel ensuring accurate recording of the weighing exercise.
Drawing ND-ITT-710-GA-200-A1 Below clearly shows enerpac locations and
wiring connected to the main control panel
The structural analysis on the jacking stool was carried out using Staad Pro
2004, the design and checking is in accordance with AISC ASD 9th Edition and
API RP2A All Dimensions used in this procedure are based on SI units and
weight calculation in Mtons.

3.0

CONCLUSION:

The analysis performed on the jacking stool satisfies the structural integrity to
withstand the stresses and that the deflection is within the allowable limits
Maximum stress ratios for weighing are listed below:
-

0.608 for load cell C3


0.649 for all other load cells

Page 1

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

Page 2

MOBIL
P RODUCING
NIGERIA

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

Page 3

MOBIL
P RODUCING
NIGERIA

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

MOBIL
P RODUCING
NIGERIA

4.0 SAFETY

Before the Weighing operations commence, risk assessments followed by Job


safety analysis (JSA) will be completed for all work undertaken by NDs personnel,
and any subcontractor employed in the work. The approved JSA will be discussed
among the workforce prior to commencing any Jacking activity.

The Gantry side where the intended structure for Weighing will be temporarily
positioned must be cordoned off from unauthorized persons and visitors. Barrier
control will be strictly enforced. No personnel will be allowed in the vicinity of
suspended loads.

Only authorized persons shall partake in the JSA meeting

ND shall ensure all procedures are understood and workers are briefed as to any
potential worksite hazards. All identified hazards or potential hazards shall be
promptly eliminated or controlled.

ND shall ensure all works related to the Weighing are carried out in a safe and
efficient manner and that safe systems of work are prepared and implemented.

ND shall ensure all equipment are safe, suitable for the operation, kept in good
condition and that defects are identified and follow up action initiated to repair
defective equipment or withdraw it from site.

All Weighing Equipment shall be inspected prior to use and will have an up to date
certification.

A pre-weighing checklist shall be used to verify safe systems of work are in place,
the check list shall be endorsed by MPN Heavy Lift Advisor.

ND shall ensure all places of work, including work at heights, etc are safe and
where necessary adequate control measures shall be implemented through JSA,
Risk Assessment or Toolbox talks.

Risk assessment will be carried out by ND and Company and will be developed by
the Risk Charter Group as per required procedures.

JSA will be developed based on the RA findings.

Page 4

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

MOBIL
P RODUCING
NIGERIA

An emergency response plan will be developed by the Safety Group.

All personnel involved in this operation shall:


Avoid harm to themselves and prevent harm to others
Utilize and maintain all issued protective equipment in the correct
manner.
Be aware of, and comply with all relevant project HSE procedures.
Make appropriate suggestions for the improvement of safety within the
operations.
ND shall ensure all personnel involved in the Weighing campaign are PPE
compliance at all times (Coveralls, steel toe shoes, Hard hat, Safety Glasses)
as minimum requirements..
5.0

EQUIPMENT:
This section describes the minimum equipment needed to perform this
operation. All Equipment to be used in this procedure shall be checked and
certified by a recognized certifying authority. Equipments required for the
Weighing operation are not limited to the following list:

ENERPAC
4 off ENERPAC 500t LOAD CELLS complete with central control panel
JACKING STOOL
As fabricated by Nigerdock

Page 5

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

6.0

ORGANIZATIONAL CHART (FOR WEIGHING OPERATION)

MPN Rigging Supt.


Mr. Allistair Thompson

Construction Support
Mgr James Cunningham

Enerpac Load Cell operator

7.0

MOBIL
P RODUCING
NIGERIA

Watch Over Assistant


Odom Anefiok

Stand-by Team
plus
Maintenance
Group:
Scaffolders
Welders
Electrician
Helpers
Fitters
Forklift

Safety Officer In charge


Mr. Kayode Omojagbara

PERSONNEL AND RESPOSIBILITIES


7.1.1

CONSTRUCTION SUPPORT MANAGER (1) He is in charge of the


Over all Operation during weighing. All personnel involved in this
operation will report to him. He gives the instructions to any Load Cell
Operators, and Assistance Personnel. He is also responsible to have all
certification to hand over to Company for review prior to weighing.

7.1.2 MPN Rigging Superintendent (1) He is responsible for checking that


the overall approved methodology has been followed before, during and
after the weighing.
7.1.4

SAFETY PERSONNEL Responsible for all works related to the


Weighing are carried out in a safe and efficient manner and that safe
systems of work are prepared and implemented. During Operation one
single Safety Officer will be inside the Barricaded area for
communication with Safety Personnel on the outside of the barrier.

Page 6

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

7.1.5

MOBIL
P RODUCING
NIGERIA

STANDBY TEAM A support team for any immediate fabrication


required or assistance in related matters. It comprises of the following:
The number of personnel will be determined by Construction Support
Manager.
Scaffolders
Welders
Electrician
Helpers
Fitters
Forklift Operators
Load Cell Maintenance Personnel (1) Part of the support team to assist
on any mechanical fault on cranes during operation.

8.0

COMMUNICATION
A communication exercise between the involving personnel will be established
prior to Weighing Operation. A minimum of two (2) days is expected for this
exercise before the final Weighing operation and one (1) day prior to Pre-Weigh
meeting.
During the operation the Hand Signaling, Verbal and Radio will be the means of
communication. Spare radio equipment will be made available.
All the Instructions will come from the Construction Support Manager; he gives
the instructions and receives the information from his subordinates. This
coordination will come from Load Cell Operators and Safety In charge.
The communication between the involved personnel will be by means of one
radio channel in order to ensure clear communication.
The Load Cell Operators and any assistant will communicate to the
Construction Support Manager whenever the event or situation of the Load Cell
is in dangerous position. The instruction will be three STOPS, ex. STOP!
STOP!! STOP!!!.
The four (4) Load Cells used in the operation will be named and identified as
follows:
Load Cell C1
Load Cell C2
Load Cell C3
Load Cell C4

Page 7

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

MOBIL
P RODUCING
NIGERIA

Name tags will be placed on each load cell for identification.


A co-ordination exercise will be undertaken 3 days prior to the operation with
Load Cell operators if the Construction Support Manager feels they are not
experienced enough.
9.0

METHOD
9.1

PREPARATION:

All Rigging and Weighing Appliances should have all certifications checked
prior to use.
Remove all obstructions that will hinder the operations.
During operation the area shall be limited to nominated yard personnel only.
All other personnel shall observe operation from outside the taped area.
Load Cells shall be positioned as specified in the drawings.
Any Required Rigging equipment shall be positioned in accordance to the
specified drawings.
All radio communication shall be checked if working properly.
The Over all control of the operation shall be Construction Support Manager
who will be in touch with the personnel as defined by Communication
sections of the procedures.
During Weighing Operation, all client communicate shall be addressed
through Project Manager or his deputy.
A pre-weighing meeting shall be held between ND Team and Company to
discuss the procedure and issues concerned. All procedure shall be clear to
both parties and pass JSA (Job Safety Analyses) prepared by the
Construction Support Manager with support from the Safety Department.
9.2

A pre weighing meeting shall be held to ensure that everyone involved


understand the procedure. This will also ensure that the coordination
between load cell operator, Construction Support Manager and safety
personnel is achieved.

9.3
During weighing a 50% load shall be tested on each load cell as
specified on the above theoretical value of each load point, and measurement
shall be taken and recorded. All loads in the load cells will be measured. When
the 50% load is achieved, the structure will be lifted gradually until a full 100%
load is achieved at a height of 100mm from the support and this operation is to
be repeated a minimum of 3 times and readings recorded for each lift
operation.

Page 8

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

MOBIL
P RODUCING
NIGERIA

9.4
Acceptance criteria of the final recorded value of the 3 weighing
operations shall be the average of the 3 recorded values and this value should
not differ from the maximum of any of the 3 values by more than 0.7%. The
tolerance of the enerpac load cell should be equal to or less than 1%.
9.5 The maximum load on any one load cell shall between 20-80% of their
total load capacity.
9.6

10.0

If the weighing is achieved and satisfies the operation, the structure will
be put back in original position otherwise the weighing operation will be
repeated again.

ANALYSIS:
This section explains the procedure performed for the analysis of the ITUT
jacking stool.
The data for the model was taken from the weight control and CofG report
produced by Nigerdock and analysis was performed on Staad-pro
See attachements in Appendix A

11.0 DATA ANALYSIS


The following members are included in this analysis are:
LOAD LIST
SELF WEIGHT
C.O.G.
LOAD CELL REACTIONS
CODE CHECK AISC LFRD
12.0

REFERENCES:
Nigerdock Shop Drawings Reference:
1. ND-ITT-710-GA-200-A1
2. ND-ITT-710-GA-201-A1

The reports of the analysis are based on the following specifications:

Page 9

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

1. AISC 9th Edition


2. API 2A (RP2A)
APPENDIX A
SFDP-TOPSIDE WEIGHING-BEAM-1
SFDP-TOPSIDE WEIGHING-BEAM-2
APPENDIX B
CURRENT JACKET WEIGHT CONTROL SUMMARY

Page
10

MOBIL
P RODUCING
NIGERIA

SATELLITE FIELD DEVELOPMENT PROJECT


(PHASE I)
ITUT AND ABANG JACKET WEIGHING
PROCEDURE

Page
11

MOBIL
P RODUCING
NIGERIA

Das könnte Ihnen auch gefallen