Beruflich Dokumente
Kultur Dokumente
OTHER
INADEQUATE
INSPECTION
OPERATING
ERRORS
POOR DESIGN
IMPROPER
MAINTENANCE
IMPROPER
PROCEDURES
Example 1
Force = pressure multiplied by area so:
0.7
barg
300mm X
300mm Square
Door
650 kilogrammes of Force
0.7 bag pressure on a 300mm X 300mm square surface area (90,000mm2) is 650
kg of force!
This is equivalent to an object that weighs 650 kg or1,400 lbs.
And as the door weighs about 50 kg lbs -- if suddenly released it goes
flying!
Be Aware
Can you get hurt with low pressure?
ABSOLUTELY !
Beware of large surfaces as even 0.05 bar which
may not even register on the pressure gauge but
its enough to send a hatch flying.
Vacuum Safety
Same concepts
In vacuum systems the
pressure is pushing
inward, not outward.
The pressure comes
from the atmosphere
We dont feel it but
a tank does when you
pull a vacuum on it!
Atmospheric Pressure
Vacuum
Covered Vent
This tank collapsed while being pumped out!
Painters had covered the vent with plastic sheeting.
The Incident
What Happened
The elbow failed due to erosion-corrosion damage.
180 te of LPG vapour escaped; ignited after c.20
secs
Fireballs 30 m (100ft) in height
Wall thickness was reduced from 7-8 mm (0.25 in)
to 0.3 mm (0.01 in)
Water injection point returned to use (from
intermittent to permanent) without full MoC
Failed elbow had not been inspected in 20 years
Damage Details
Ma
n
ess
Pro
c
ag
em
en
to
f
&
Ch
a
Me
ch
an
ica
l
ng
e
In
teg
rit
Piping Design
Size Must accommodate range of flow rates
Orientation Must disengage vapor from liquid
- Low points, dead legs, under road
crossings
Support Static and dynamic stress
Material Must resist failure under range of
exposures
Wall thickness Compatible with system design
pressure
The Process
Flow Schematic
M
TO GAS COMPRESSSOR
NATURAL GAS
LGO
STRIPPER
SCRUBBER
FRACTIONATOR
FEED
SURGE
DRUM
REACTOR
LGO
M
BITUMEN
FEED
RINGS
G-1
INITIAL
FAILURE
HGO
BITUMEN FEED
G-2
RECYCLE SLURRY
BOTTOM
PUMPAROUND
G-3
M
PUMPAROUND
The Incident
Coker 8-2 was operating normally with no
apparent problems. Feed rate 82 KB/SD.
Line failed on overhead pipe rack between
reactor structure and compressor house.
Hot oil release accompanied by a large fire in
unit and explosion in compressor house.
Intense fire burned for 4 hours.
Total physical damage $120 million. Four
months to rebuild.
Damage Details
What Happened
Initiating failure was in 18 in (0.5 m) section of 6
in (150 mm) carbon steel pipe that had been
welded into 5Cr Mo line.
Operators were unable to shutoff other hot oil
pumps or isolate piping circuits to and from reactor.
As fire spread, several other lines ruptured and
this further aggravated the fire.
Abrasive solids in slurry was a contributing factor.
However improper metallurgy made failure
inevitable.
Pipe wall thinning had pre-existed prior to fire.
Initial failure attributed to hot sulphidation
corrosion.
En
gin
ee
rin
gS
yst
em
ss
&
Tr
a
Me
ch
an
ica
l
In
teg
ini
rit
ng
y
/C
om
pe
ten
cy
Pipe Failures
Corrosion
Pinhole leaks
10
Brittle fracture
Thinning
Pitting
11
Stress crack
Fired Heaters
Provides high level heat to process
streams or incinerate waste streams.
Critical operating parameters /
hazardous conditions.
Major fuel release source in many
plants.
- high throughput
- moderate to high pressure
-high temperature
Source of major loss in many plants.
12
Tankage
Hazards
Largest inventory of hazardous material on sites.
Significant vapor space and high confinement.
Tank defects and upsets are difficult to detect.
Tank incidents are difficult to isolate.
Remedial action is usually only partly effective.
Often regarded as low to moderate in severity/risk
and dont receive prime attention.
Buncefield
13
The Incident
What Happened
Tank in Bund (containment dike) A was being
filled with unleaded motor fuel at a rate of
550 m3/hr (2,422 U.S. gpm)
Level gauge recorded an unchanged reading,
the tank continued for more than 2 hours.
Continued pumping caused fuel (300tes
(661,380 lbs)) to cascade down the side of the
tank.
Escaping fuel formed a massive vapour cloud
which eventually found an ignition source.
Buncefield summarised
Graphic interpretation of 3rd investigation report
BPA
HOSL West
?
ESD Trip
SCADA
Alarm panel
ATG
Override
switch
for tests
E
AFT
TED
TES
C
R IN
O
NT :
ID E
Substation
?
LI
HLA
Overflow
after 05:20 (appx 300 t)
Tank 912 (fitted with
Internal Floating Roof)
Gasoline vapour cloud
develops
14 T/K
South pipeline
TI
Ignition at 06:01
Open
Pumping rate into tank: 550 m3/h from 19:00 to appx. 05:50
890 m3/h from 05:50 to incident
(Unleaded gasoline)
14
Notice car
22 minutes later
BUNCEFIELD:
700 to 1,000 mbars
Catherine House
Fuji
15
Damage Details
16
Transport
Helicopter
Dropped Objects
Riser Break
This is not a drill
drill
Lower Riser
supported by
drill pipe
Riser Jt
No.1
against
BOP
Mud falling
from broken
upper riser
Top of Lower
Marine Riser
Package (BOP)
Riser Jt #1
against BOP
controls
Riser Jts
resting on
other wellhead
17