Beruflich Dokumente
Kultur Dokumente
ASSIGNMENT
TOPIC: STRENGHTHENING OF EXISTING TRANSMISSION
CORRIDOR AND TRANSMISSION PLANNING TOOLS
SUBMITTED BY :
ANIL KUMAR GUPTA 11-EES-10
ANIRUDH SHARMA 11-EES-11
ANURAG CHADHA 11-EES-13
ARSHI ZAKI 11-EES-14
CLASS: B.TECH, ELECTRICAL ENGG., 8TH SEMESTER, IV YEAR.
NAME OF INSTITUTION: F/O ENGG. AND TECH., JAMIA MILLIA
ISLAMIA, NEW DELHI.
DATE OF SUBMISSION: 10-03-2015
46,027 million kilowatt hours of power exchange between and across the regions against a
target of 46,000 million kilowatt hours.
71,447 circuit km of transmission capacity against a target of 71,000 circuit km.
79,522 Megavolt Ampere (MVA) of transformation capacity against a target of 75,000
MVA.
Also, the National Load Despatch Centre, the apex body to ensure integrated operation of the
national power system, commenced operations as targeted in April 2009. Indias electricity
transmission system operator is also consistently maintaining transmission system
availability at over 99 percent, which is at par with international utilities.
The goals of transmission system planning include those common to all utility system
planners: assuring reasonable reliability and quality of service to energy consumers, minimizing costs,
assuring the system is safe and built and operable within all laws, codes, and regulations.
In addition, transmission system planning for regional and wholesale grids normally has
to take into account system interconnected security, transmission congestion constraints, transmission
market costs including in some cases locational marginal based pricing, the availability and esthetic
impacts of required rights-of-way and transmission switching substation sites that will be required,
and community and social acceptance in determining what plans best meet current and future needs.
They are used to evaluate the performance of proposed additions to the transmission system
against reliability criteria for system performance.
They result in transmission system ratings that allow system operators to maintain system
reliability while serving the energy needs of the system users.
Transmission system is accessed using a variety of system modelling and simulation tools to
measure the transmission systems capabilities against design criteria.
This is done for present and planned configurations for present and future load levels,
respectively.
The simulations are validated using real-time measurements made under normal and
contingency conditions whenever possible.
Assessments are made in the following areas, using standardised software packages to study the
systems performance:
a) Thermal:
Load flow studies method is used to assess the performance of the transmission
system.
The softwares used for this purpose are MATLAB, PSCAD, Mipower and PSS/E.
The load flow levels established by the studies are measured against the thermal
ratings of transmission facilities.
Transmission equipments including lines and transformer banks are assigned with
thermal ratings for normal operation, long-time emergency operation and short-time
emergency operation.
Load flow studies are conducted to simulate normal operation under peak forecast
loads.
No transmission facilities should exceed their normal ratings at this operating
condition.
b) Voltage:
c)
Load flow studies method is used to check the voltages throughout the transmission
system.
It checks voltage support and control provided by reactive power, measured in
MVAR.
Short Circuit:
Short circuit studies are conducted to assess the following:
The ability of circuit breakers on the transmission system to interrupt fault currents.
The ability of all equipments on the transmission system to withstand the mechanical
forces associated with fault currents.
d)
e) Extreme contingencies:
In order to determine whether the system will remain within mandatory performance
criteria under various operating scenarios, planners measure system performance under three
increasingly stressed conditions:
All facilities in service (No contingencies or N-0).
A single element out of service (single contingency or N-1).
Multiple elements out or removed from service (multiple, due to a single contingency
or a sequence of contingencies, i.e., N-1-1).
In the N-1-1 scenario, planners assume one element is out of service followed by
another event that occurs after a certain period.
After the first contingency, operators make adjustments to the system in preparation
for the next potential event, such as switching in or out certain elements, resetting
inter-regional tie flows where that ability exists, and turning on peaking generators,
In such scenario, if the software used to simulate the electric grid shows that the
system cannot maintain acceptable levels of power flow and voltage, a solution is
required to resolve the reliability concern.
f)
Tools:
The various methods used for planning are as follows:
1. Trend Analysis method:
In this method, load is predicted on the basis of past data or trend. For eg. For
the 5 years plan of the duration 2007-2017, the past data of 2002-2007 is considered and studied. The
constants or variables to be considered are:
2. Econometric method:
It estimates the relationship between energy consumption and factors
influencing the consumption. Economic variables , such as, pricing, sales, and statistics are
considered.
Analytical Tools :
Transmission system analysis involves complicated computations of power flow, fault currents,
transient phenomena and a host of other engineering factors related to system performance and
equipment suitability.
Analytical Tools used are:
PSS/E
PSS/O
Power Factory
Power World
EMTP
EDSA INSITE
Matlab
Mathematica
Types of planning:
Strategic Transmission Planning:
It involves the determination of the best long-term approach to handling the
wholesale power transmission needs in a region. These usually lead to a long range (20-year)
overview plan that identifies the preferred voltage ranges (e.g,. 765 and 500 kV) and general
characteristics of the future grid.
Regional Grid Planning:
It involves most of the factors of strategic transmission planning in addition to
the factors considered in most transmission planning studies, such as policy issues involving
complicated regional issues and equity of distribution costs and capability which may have to be
accommodated.
Sub-Transmission Planning:
It involves planning of the transmission-voltage portions of local power delivery
systems, lines most often of delta configuration and operating at nominal voltages of anywhere from
34.5kV to 345kV. While of high-voltage, the predominate reason these lines are needed and operated
is to route power to local distribution substations. As such, they are legally and practically part of the
local delivery system rather than the regional wholesale power grid, and are best planned as part of
that local delivery system.
Substation-Planning:
It involves the determination of the sites, sizes and configurations, and timing of
future additions of distribution and transmission switching stations, as well as additions and upgrades
to existing substations. The planning of transmission switching stations (e.g., 500 kV to 230 kV
stations) is a key element of good transmission planning and accomplished as part of that function.
projections and generation plants under various stages of implementation. Part two gives broad
transmission corridors. Perspective Transmission Plan for Twenty Years (2014-2034) - 7 - plants in
this timeframe are yet to take off, it is not possible to identify the optimum generation plan for 202234. In such a scenario, it is prudent to identify the transmission plan in accordance with the location of
generation resources/ generation potential along with projected demand.
Table 2 : 18th EPS Forecast of Annual Peak Load for 12th and 13th Plans (figs. in MW)
Table 3 : Installed Capacity during 12th and 13th Plans (All figures are in MW)
Table-4 Load Generation Balance at the end of 13th Plan (2021-22) for Study
The load generation balance shows that NR is having a deficit of about 18500-22200 MW while the
deficit of SR is about 13000 to 19100 MW at the end of 13th Plan condition.
The above load generation balance shows that NR is having a deficit of about 18500-22200 MW
while the deficit of SR is about 13000 to 19100 MW at the end of 13th Plan condition. Surplus in WR
is about 11500-15900 MW in Summer Peak, Winter Peak and Winter Off-peak condition while
during Monsoon Peak condition the surplus gets reduced to about 2000 MW only. Surplus in ER,
NER and Bhutan also varies from 17800-24700, 2800-6100 and 600-5500 respectively. NER is
experiencing deficit of about 1400 MW during Winter Off-peak condition.