Beruflich Dokumente
Kultur Dokumente
FOR
VOLUME II
June 2008
GENERAL SPECIFICATION
FOR
ROADS AND BRIDGES
VOLUME II
June 2008
GENERAL SPECIFICATION
CONTENTS
Page
1.
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
1.11
1.12
1.13
1.14
1.15
GENERAL SPECIFICATIONS
Definition of Engineering Terms
Alignment
The Carriageway
Horizontal Curves and Super Elevation
Office for Engineers Representative
Assistance for Engineers Representative
Name Boards
Datum
Taking Over Of Site By Contractor
Contractor Not To Enter Neighbouring Land
Notice Of Operations
Weather Conditions
Precautions Against Pollution Of Streams
Copies Of Orders
Work During Period Of Maintenance
1
1
1
1
2
2
3
3
3
4
4
4
4
4
4
5
2.
2.1
2.2
2.3
SITE CLEARANCE
Clearance Of Trees, Bushes And Vegetation
Limits of Clearance For Road Works
Removal Of Top Soil and Unsuitable Materials
6
6
6
6
3.
3.1
3.2
3.3
3.4
3.5
3.6
ROAD MATERIALS
Quality of Materials
Supply of Materials
Defective Materials
Handling and Storage of Materials
Liquid Limit, Plasticity Index and Linear Shrinkage
Local Materials Naturally Occurring Materials
8
8
8
8
8
8
9
4.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
MANUFACTURED MATERIALS
Cement
Lime for Base-Course Stabilization
Bitumen
Steel Reinforcement
Structural Steel Work
Bolts and Washers
Steel Tubing
Galvanised Corrugated Metal Pipe
Mould Oil
Expansion Joint Filler
Expansion Joint Sealing Compound
Concrete Admixtures
Water Bars
Flexible Bridge Bearings
Pile Shoes
Road Marking Materials
Road Signs
16
16
16
16
16
17
17
17
17
18
18
18
18
18
18
18
18
19
5.
5.1
5.2
5.3
5.4
20
20
20
20
20
GENERAL SPECIFICATION
5.5
5.6
5.7
5.8
5.9
5.10
22
22
23
23
23
24
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
6.14
6.15
26
26
26
28
28
28
28
28
29
29
29
29
29
30
30
30
7.
7.1
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
32
32
32
32
32
32
33
33
33
33
8.
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
8.9
8.10
8.11
8.12
8.13
8.14
8.15
8.16
8.17
8.18
8.19
8.20
8.21
CONCRETE
Fixings and Cavities
Gauge Boxes
Proportions of Concrete Mix
Water Cement Ratio
Preliminary Testing of Concrete
Concrete Test Cubes
Standard of Acceptance for Cube Tests
Unsatisfactory Test Results
Consistency of Concrete Slump Test
Mixing Concrete
Transport and Placing of Concrete
Compaction of Concrete
Construction Joints
Curing of Concrete
Removal of Shuttering
Finishes
Defects in Concrete
Termination of Concrete Pour
Approval Before Concreting
Placing Under Water
Mass Concrete Backing to Masonry or Brickwork
34
34
34
34
35
35
35
36
36
37
37
37
38
39
40
40
41
41
41
42
42
42
GENERAL SPECIFICATION
8.22
8.23
8.24
8.25
8.26
8.27
Displacers
Delays Due To Defective Concrete
Cement Mortar Mixing
Cement Mortar Proportions
Concrete Mixes for Different Types of Construction
Precast Concrete Units
42
42
42
43
44
46
9.
9.1
9.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
9.10
9.11
9.12
9.13
9.14
9.15
9.16
9.17
9.18
9.19
9.20
9.21
9.22
PRESTRESSED CONCRETE
Cement
Aggregates
Water
Untensioned Reinforcement
Pre-Stressing Steel
Sheathing
Concrete Proportions
Field Tests
Batching and Mixing
Placing of Concrete
Curing of Concrete
Removal of Shuttering
Surface Finish
Tolerances
Pre-stressing
Tensioning
Grouting
Pre-Tensioning
Transverse Pre-Stressing
Additional Requirements
Lifting and Handling
Concrete Mixes
48
48
48
49
49
49
51
51
52
52
53
53
53
53
54
54
55
56
56
57
57
58
59
10.
10.1
10.2
10.3
10.4
10.5
10.6
10.7
10.8
CONCRETE PILES
Pre-Cast Concrete Piles
Shuttering for Pre-Cast Piles
Test Piles
Procedure for Testing Piles
Stripping Heads of Piles
Splicing of Piles
Pile Shoes
Cased Piles (British Steel Piling or other approved)
60
60
61
61
61
62
62
62
62
11.
11.1
64
64
12.
12.1
12.2
12.3
12.4
12.5
12.6
12.7
69
69
70
70
70
71
71
71
13.
13.1
13.2
13.3
STRUCTURAL STEELWORK
Supply, Transport and Erection of Structural Steelwork
Steel Sheet Piling
Hand Railing
72
72
74
75
GENERAL SPECIFICATION
14.
14.1
14.2
14.3
14.4
14.5
14.6
14.7
14.8
BITUMINOUS SURFACING
Prime Coat
Seal Coat Surface Dressing
Heating of Cutback Bitumen
Spraying of Cut-Back Bitumen
Spreading of Blinding Material
Take of Blinding Aggregate
Rain Damage
Tolerance of Finished Surface
76
76
77
78
78
79
79
79
79
15.
15.1
15.2
15.3
MISCELLANEOUS
Grassing
Removal of Concrete in Existing Structures
Tree Planting
80
80
80
80
GENERAL SPECIFICATION
1.
GENERAL SPECIFICATIONS
1.1
1.2
a]
Carriageway: the portion of the road surface which is formed for the use of
vehicles. It includes the pavement and hard shoulders.
b]
c]
Hard Shoulders: The paved or unpaved portions of the outer edge of the
carriageway, which are designed to contain the pavement and for the occasional
use of vehicles.
d]
Formation: The surface of the ground in its final shape after the completion of the
earthworks, immediately below the base-course (or sub-base if any).
e]
Formation Level: The level of the formation along the centre line of the road.
f]
Formation Profile: The cross section profile of the formation at any particular
point along the road.
g]
Sub-Grade: The natural foundation or the fill, which directly receives the loads
from the pavement.
h]
Sub-base: A layer of material sometime provided between the formation and the
base to aid strength to the formation or to reduce the cost of the base.
i]
Base-course: (Or base). The layer in a road construction, which provides the
principal support to the surfacing.
Alignment
In the case of reconstruction of an existing road and where the contract drawings do not show
the plan of the new alignment of the reconstructed road, the contractor must allow in this
Tender for the expenses incurred in eliminating kinks or bends in the road as shown in the
Schedule of Works. Except where otherwise directed, on the drawing, or by Engineers
Representative, no horizontal curve on a reconstructed road will have radius less than 350
metres.
1.3
The Carriageway
The carriageway shall conform, in cross-section to the drawings. Horizontal curves shall be
circular. On curves of less than 350 metres radius, the pavement shall be widened by 600mm.
Where such curves are in cutting or on embankment this shall be increased by 600mm. The
increase of width on curves shall be applied uniformly over a distance of 30 meters on the
straight road at each end of the curve, and shall be applied to the inner edge of the curve only.
Horizontal curves of 3 000 metres radius or less shall be super elevated at the rates shown
below. The inner edge of the pavement will follow the grade line. Super elevation will be
constant throughout the circular curve and will be applied uniformly from zero to maximum
throughout the transition lengths shown below:
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 1
GENERAL SPECIFICATION
1.4
100
80
65
0.45
0.50
0.58
55
45
40
1.5
20%
33%
Plan table, 2.700m x 0.900m x 0.825m internal measurements, with stool and footrest.
Lockable cupboard.
Two T-squares, two sets of setsquares, and one set of railway curves.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 2
GENERAL SPECIFICATION
The Contractor shall supply for the duration of the Contract, suitable separate latrines for the
Engineers Representative and for this office staff, constructed to the satisfaction of the
Engineers Representative, and shall ensure adequate clearing and cleaning of the latrines.
1.6
1.7
2 x Levelling staffs
4 x Plumb bobs
Name Boards
At the commencement of the work two name boards shall be erected, one at either end of the
length of road under construction. These boards shall be moved and re-erected as directed in
order that they are in close proximity to the site of the work under construction. The boards
shall be painted with 2 coats of approved weatherproof paint and shall be maintained in good
condition for the period of the contract. The boards shall be removed by the end of the period
of maintenance.
The letters shall be black on a yellow background and the wording shall be Ministry of
Works in 100mm high letters with the contract title in 75mm high letters, and the Contractor
may place his name and address below the job title in 50mm high letters.
The cost of such boards shall be included in the contract rates.
1.8
Datum
The Datum on which the various levels are based shall be the Nigerian National datum as
established by the Federal Surveys. The concrete beacons at the intersection points of curves
are to be used as Temporary Bench Marks during the progress of the contract. Values for the
Temporary Bench Marks are shown on the drawings but the Contractor at the commencement
of the contract must check the Employer will take these values and no responsibility for the
accuracy of the levels of Temporary Bench Marks given on the drawings.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 3
GENERAL SPECIFICATION
1.9
1.10
1.11
Notice Of Operations
No important operation and particularly no blocking or cutting of any road, water pipe or
other services shall be carried out without the consent in writing of the Engineer no without
full and complete notice being given to him also in writing, sufficiently in advance of the time
of operation so as to enable him to make such arrangements as may be deemed necessary for
its inspection and the provision of all relevant safety precautions.
1.12
Weather Conditions
The Contractor shall be deemed to have taken weather conditions into account when preparing
his Tender and he shall not be entitled to extension of time by reason of the occurrence of
delays due to weather unless he can show that such conditions could not have been reasonably
foreseen in the area of the site.
1.13
1.14
Copies Of Orders
The Contractor and Sub-contractors shall provide the Engineers Representative with copies
of all order, which they may place for the supply of materials or goods required in connection
with the Works.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 4
GENERAL SPECIFICATION
1.15
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 5
GENERAL SPECIFICATION
2.
SITE CLEARANCE
2.1
2.2
Between the top of the side drains and 1 metre outside the drain on both sides
Clearance shall also be carried out over the top width of cut-off drains and turnouts, plus
450mm on either side of such drain or turnout. Clearance shall also be carried out beyond the
limits denoted above, on the inside of bends, in order to obtain and unobstructed sight distance
of 150 metres.
The cost of all operations in Item 2.1 and 2.2 shall be included in the rate for site clearance
and shall be measured in hectares of cleared area.
2.3
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 6
GENERAL SPECIFICATION
The excavated soil shall either be stacked for re-use on side slopes or margins when so
directed, or shall be deposited and spread evenly not less than the clearance limits defined in
Item 2.2
Whether stacked for re-use or deposited outside the drains measurement for this item shall be
in cubic meters of material measured in-situ before excavation by means of cross-sections
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 7
GENERAL SPECIFICATION
3.
ROAD MATERIALS
3.1
Quality of Materials
All materials used in the Works shall be new and have the quality and kind specified. They
shall comply with the requirements, unless modified herein, of the current amended editions,
at the date of invitation to tender, of the British Standards (hereinafter abbreviated to B.S.)
published by the British Standards Institution, or any other recognised Standards, which may
be quoted. All materials may be checked at both the source and on site and approval of any
material at its source does not necessarily imply that it will be approved on site.
3.2
Supply of Materials
The Suppliers of all manufactured materials shall be subject to approval and wherever
possible such materials shall be manufactured in Nigeria. All imported materials shall be
shipped wherever possible to Nigeria in Nigerian ships.
3.3
Defective Materials
All materials, which do not comply with the requirements of this Specification, shall be
rejected and the Contractor, at his expense, whether in place or not, shall immediately remove
all such materials, from site.
3.4
3.5
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 8
GENERAL SPECIFICATION
3.6
Fill Materials
All fill material shall be obtained from sites approved by the Engineers Representative, after
the satisfactory completion of the following tests:
Liquid Limit
Plasticity Index
Minimum of 15%
The material shall be capable of being readily compacted, shall be without pockets of clay or
sand, and shall be free from trees, stumps, standing or matted bush, roots, rubbish or large
stones. Stones larger than 150mm in greatest dimension may be required to be removed.
3.6.2
Sub-Base Material
Sub-base material shall be the nearest approved available material which complies with the
following tests:
Liquid Limit
Plasticity Index
Minimum of 25%
The material shall be free from all deleterious matter as in Item 3.6.1 above and stones with
any larger dimensions than 50mm shall be removed.
3.6.3
Surfacing material for side slopes and margins shall consist of the nearest approved material,
which complies with the following tests:
Liquid Limit
20 - 50%
Plasticity Index
10 - 20%
The material shall be free from logs or stones of more than 50mm greatest dimension. A
small amount of vegetation matter will be accepted, so long as the amount is approved.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 9
GENERAL SPECIFICATION
3.6.4
Granular Base
Grading (Metric
equivalent of
Imperial B.S.
Sieves
38.10mm max
size
25.40mm max
size
19.05mm max
size
38.10mm
100
25.40mm
70 100
100
19.05mm
60 100
70 100
100
12.70mm
60 100
9.52mm
45 80
50 90
60 100
4.76mm
37 60
35 70
40 75
No.7 (2.40mm)
23 50
25 55
27 60
36
10 50
15 35
15 35
200
5 - 15
5 - 15
5 15
This material shall be either in-situ material or soil imported from the nearest
available source, which shall be approved by the Engineer and comply with
the following tests:
Grading
As above
Liquid Limit
Plasticity Index
Minimum of 80%
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 10
GENERAL SPECIFICATION
Percentage Passing
Sieve Size
9.52mm
100
4.76mm
80 100
100
No. 7 (2.40mm)
50 100
80 100
No. 14
35 90
40 90
No. 36
24 70
25 70
No. 200
5 - 25
7 25
The material shall comply with the following tests and requirements:
Grading
As above
Liquid Limit
Plasticity Index
Not exceeding 5%
Minimum of 80%
Grading
As in (a) or (b)
Liquid Limit
Plasticity Index
Minimum of 80%
Plant Mix
140%
120%
80%
80%
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 11
GENERAL SPECIFICATION
This specification shall be obtained on samples tested after six days curing
followed by 24 hours soaking.
With silt and clay soils, further samples will be tested at 7 days and 14 days
soaking, to examine the resistance to weathering. There should not be any
more than 5% drop in C.B.R. value.
e. Lime Stabilised Base Course
As for (d) with Lime instead of cement.
f.
General
Base-course material shall be free from logs, or stones more than 50mm
greatest dimension, vegetation or any other deleterious matter.
3.6.5
The sand shall consist of hard, durable, rough surfaced grains, free from lumps of clay, loam,
and other foreign matter for from a coating of any injurious material, which will prevent
adhesion of the bitumen. The sand shall comply with the following:
Clay content
Not exceeding 5%
When mixed with the specified grade of bitumen, the minimum acceptable stability of the
sand-asphalt as given by the Hubbard-Field test, shall be decided by the Engineer, but shall
not be less than 400kg.
3.6.6
The blinding material shall consist of clear, granular material matter, free from all vegetation
matter, and shall comply with the following gradation:
Maximum size
6.35mm
0-20%
3.6.7
It shall consist of screened, washed natural gravel or crushed stone chipping, clean and free
from dust and from vegetation matter, or any other matter, which will prevent the adhesion of
the bitumen to the aggregate.
The aggregate shall comply with the following requirements:
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 12
GENERAL SPECIFICATION
Percentage Passing
B.S. Sieve
12.70mm
9.52mm
25.40mm
100
19.05mm
85 100
100
12.70mm
0 35
85 100
100
9.52mm
07
0 45
85 100
6.35mm
07
0 40
4.76mm
02
No. 7 (2.04mm)
0-2
0-2
0-2
a. All aggregates, either fine or coarse, shall be free from loam, vegetable matter, dust or any
other impurity that will adversely affect the strength of the concrete or attack the
reinforcement (if present). If required by the Engineers Representative, the Contractor
shall wash the aggregate at his own expenses.
b. Fine Aggregate
Fine Aggregate shall consist of natural sand, crushed stone or gravel sand and shall be
clean and sharp and as in (a) above. It shall comply with the requirements of B.S. 882,
particularly in regard to the grading prescribed in Zones 1, 2 or 3 of the Table of the 1973
edition and B.S. 182.
c. Coarse Aggregate
Coarse Aggregate shall consist of natural gravel, crushed gravel or crushed stone and shall
be clean, angular or rounded in shape, and shall have granular, crystalline or smooth (but
not glassy) non-powdery surfaces.
Friable, flaky or laminated pieces of mica and shale shall only be present in such
quantities as not to adversely affect the strength and durability of the concrete. The coarse
aggregate shall meet with the requirements of B.S. 882 and 812 and the test cubes be as
specified in B.S. 1881. The aggregate crushing value shall not exceed 25 percent.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 13
GENERAL SPECIFICATION
d. Combined Aggregate
The combined coarse and fine aggregate shall have a grading within the limits given in the
following table:
B.S. Sieve
Max. 9.52mm
Max. 19.05mm
Max. 38.10mm
38.10mm
100
100
97 100
19.05mm
100
97 100
50 75
9.52mm
95 100
45 75
36 60
4.76mm
30 60
30 48
24 47
No. 7
20 46
23 42
18 38
No. 14
16 37
16 24
12 30
No. 25
12 28
9 27
7 23
No. 52
4 14
2 12
3 15
No. 100
0-3
0 - 15
25
The grading of the combined aggregate shall be parallel to the above limits and be nearer
the lower limit than the higher.
The combined grading can be obtained by the use of two parts of coarse aggregate with
one part of the fine aggregate.
3.6.9
If of concrete blocks, the concrete shall be 1:3:6 in accordance with Specification Item 8.3 and
8.26. If of stone, this shall be durable stone of approved quality, sound, hard and free from
seams, cracks or other structural defects.
80% Of the blocks or stones shall be approximately 300mm x 300mm x 225mm thick, but in
no case shall a surface dimension be less than 200mm or a surface area less than 500 square
metre nor the weight of each stone less than 30kg.
At least one stone per square metre shall be 450mm thick.
3.6.10
Rubble Filling
It shall consist of broken stone, concrete or well-burned brick, of a quality approved by the
Engineers Representative. The rubble shall be graded 150mm to 50mm and shall be rejected
if it contains more than 20% of material by volume passing a 50mm square sieve.
3.6.11
Water
Water used in the works shall be clean and fresh and free from any matter injurious to the
works, and shall only be used with the approval of Engineers Representative. If required, the
Contractor will arrange for an approved tester to analyse samples of water.
Water used for concrete, grout, mortar or cement stabilization shall comply with the
requirements of B.S. 3148 and shall be tested if necessary.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 14
GENERAL SPECIFICATION
3.6.12
Grass
The grass used for sowing verges, margins and slopes of embankments and cuttings etc., shall
be approved Dhub or Bahama grass. Tall, quick grown or tussock grasses shall not be used
unless specified.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 15
GENERAL SPECIFICATION
4.
MANUFACTURED MATERIALS
4.1
Cement
Cement shall be delivered to the site in the manufacturers original bags with unbroken seal,
or, if in bulk, in approved tankers. Each variety of cement used on a site, shall be kept
separate and no mixing will be allowed.
Any bag, package or container that has been damaged, or any container of cement that shows
signs of deteriorated, shall be rejected.
The cement shall be of normal Portland type and shall comply in every respect with B.S. 12 of
1971 Rapid Hardening Cement and cements other than normal Portland, shall only be used
when specifically required or permitted by the Engineer.
Note The Contractors attention is drawn to the fact that Nigercem cement usually has the
qualities of both Ordinary and Rapid Hardening Portland Cement, as required by B.S. 12 and
if this is so, may be used where either type is specified.
4.2
4.3
Bitumen
a. For Prime Coats
The bituminous binder shall e a cut-back of approved manufacture and having viscosity
measured by the Furol Viscometer as shown in the following table.
The symbols M.C.O., M.C.1 and M.C.2 are those of the American Asphalt Institute
Specifications.
Grade
Viscosity
M.C.O.
M.C.1
M.C.2
4.4
Steel Reinforcement
Steel for normal reinforced concrete shall be free from oil, paint, grease, excessive rust and
scale, or any other coating that may damage its bond with the concrete. It shall comply with
the following specifications:
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 16
GENERAL SPECIFICATION
For each consignment of steel reinforcement used in the work, the Contractor shall supply a
certificate giving ultimate strength, yield stress and elongation and the result of the cold bend
test described in the appropriate B.S. If no test data are supplied by the Contractor, the
Engineer reserves the right to select pieces of steel for testing at the Contractors expense.
4.5
4.6
4.7
Turned bolts shall be made from steel complying with B.S. 4360 and shall be finished
to provide a driving fit.
Steel Tubing
Steel tubes for hand railing, drains through concrete and toggle holes for precast pipes, shall
be made form Heavy tube that complies with the requirements of B.S. 1387. The galvanising
shall comply with the appropriate tests in B.S. 729. If required the Contractor shall provide
manufacturers certificates to this effect.
4.8
All exposed structural steel work shall be painted every five years. All the paint used on the
work shall be ready mixed in sealed drums. The primer shall be Lexide Penetrating Primer or
similar paint approved by the Engineers. The finishing paint shall be a heat and exposure
resistant aluminium paints. The paint shall be used exactly as received from the manufacturer
and without any admixture whatsoever. Before the paint drums are opened, they shall be
inverted for the purpose of loosening the deposit at the bottom, and the paint shall be
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 17
GENERAL SPECIFICATION
thoroughly stirred before pouring into smaller containers for use. During the application, the
paint shall be kept thoroughly stirred.
4.8.3
4.9
Mould Oil
All faces of shuttering and moulds in contact with wet concrete shall be treated with mould oil
or other approved coating, to prevent adherence of the concrete. Such coatings shall be
insoluble in water, non-staining, not injurious to the concrete and shall not become flaky nor
be removable by rain or wash water.
4.10
4.11
4.12
Concrete Admixtures
Admixtures of any kind for accelerating the setting of cement, plasticisers, waterproofing
agents, retarders etc. shall not be used except with the written permission of the Engineer.
Samples of the proposed admixture shall, if required, be submitted to an approved testing
authority by the Contractor, to ascertain its suitability for use of the works.
4.13
Water Bars
Water bars shall be as specified on the drawings. Samples shall be submitted for approval by
the Engineer.
4.14
4.15
Pile Shoes
The Contractor shall submit for the approval of the Engineer, his pattern for pile shoes made
to the dimensions shown on the drawings.
4.16
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 18
GENERAL SPECIFICATION
b. Thermoplastic Materials
They shall be of an approved manufacture and comply with B.S. 3262.
4.17
Road Signs
All road signs shall be in accordance with the approved International Signs, as modified for
use in Nigeria.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 19
GENERAL SPECIFICATION
5.
5.1
5.2
5.3
Borrow Pits
The Contractor shall be fully responsible for obtaining and working his own borrow pits, and
shall not use existing Ministry of Works borrow pits without the approval of the Engineer or
his Representative.
Borrow pits shall be excavated to a regular shape only on that side of the road where the
natural slope of the ground is away from the road and the nearest edge of the pit shall be not
less than 15.00 metres from the central line of the new road nor less than 5.00 metres from any
side drain or toe of a embankment, whichever is the greater distance.
The Contractor may be allowed to form side borrow pits for fill material providing such pits
are self-draining having a minimum fall along the line of the road of 1:120 and maximum
depth as directed by the Engineers Representative. All pits shall be properly drained to the
satisfaction of the Engineers Representative by the construction of turnouts or other approved
methods.
No borrow pits shall be abandoned until the sides have been battered to a slope of 1:1 so that
animals may not be trapped.
The Contractor must observe regulations under the Mineral Ordinances.
Government shall make no payment for clearing overburden, or for compensating owners for
the use of or for making access roads to borrow pits.
5.4
Plasticity Test
Grading Test
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 20
GENERAL SPECIFICATION
5.4.1
Plasticity Test
This test shall be carried out in accordance with B.S. 1377 of 1975 with the following
modifications:
a. Materials for testing shall be moisturised and sealed in an airtight tin or jar for a minimum
period of twelve hours before testing.
b. For the method of determining the Liquid Limit as laid down in B.S. 1377 of 1975 tests,
at least five points in the range 10-50 blows, evenly distributed when plotted on a
logarithmic scale, shall be made. Consecutive tests with respect to moisture content shall
form a drying and not a wetting curve.
c. The one point method of determining the Liquid Limit shall not be used.
d. The Plastic Limit of material shall be taken as the mean of at least three tests carried out
in accordance with B.S. 1377 of 1975.
5.4.2
Grading Test
This test shall be carried out in accordance with B.S. 1377 of 1961 with the following
modifications:
a. Of the material passing the 4.76mm sieve, a representative portion shall be obtained of
approximately 250 300 grams. This portion shall be oven-dried to constant weight, and
a portion of exactly 200 grams will then be weighed from this dry material. This will be
placed in a mortar and a small quantity of water shall be added. This mixture shall then
pestle, after which the whole shall be transferred to a No. 200 sieve.
The material on the sieve shall be thoroughly washed through with a moderate jet of
water, until the water passing though the sieve is clean. The washing shall take not less
than five minutes. The material remaining on No. 200 sieve shall be dried and reweighed, and the loss in weight shall be recorded as the portion passing the No. 200 sieve
shall be dry sieved through the following sieves, Nos 7, 14, 25, 36, 52, 72 and 100 and
each increment shall be separately weighed.
b. Material retained on the 4.76mm B.S. sieve shall also be wet-sieve as described in the
paragraph above, full allowance being made for the air-dry moisture content.
c. Pre-treatment and the analysis of the fraction passing No. 200 sieve may be omitted.
5.4.3
This test shall be carried out in accordance with B.S. 1377 of 1961 with the following
modifications:
a. A fresh sample of material shall be taken at each moisture content.
b. Tests shall be made for at least five moisture contents and the material for testing shall be
moisturised and sealed in airtight tins for a minimum period of 12 hours before testing.
c. The test shall be carried out in a mould of 150mm internal diameter and 1250mm internal
height. The material shall be compacted in five layers, each layer being subjected to 25
blows of a 4.45kg hammer falling freely through 450mm (West African Standard
Compaction).
d. At least three moisture contents shall be taken from the mould after each test and a mean
moisture content calculated. Where the terms maximum dry density (M.D.D.) and
Optimum moisture content are used in this specification, they shall mean the maximum
dry density and optimum moisture content as determined by the above test.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 21
GENERAL SPECIFICATION
5.4.4
This test shall be carried out in accordance with the California Bearing Ratio test as outlined
in B.S. 1377 of 1975, subject to the following modifications:
a. The samples shall be prepared by dynamic compaction to optimum moisture content and
maximum dry density.
b. The material for test shall be moisturised and sealed in an airtight tin for a minimum
period of 12 hours before testing.
c. The compacted sample for fill material shall be totally immersed in water for the specified
period of soaking, following by 15 minutes draining before testing. Sub-base, base and
verge materials, which are normally 1 metre above flood or water table level, will not be
immersed or soaked before testing.
The Contractor shall ensure that the results of the selection tests for road materials are
submitted to the Engineer in good time and the cost of any delay to the works caused by late
submission of test results will be borne by the Contractor. No material shall be used for fill or
sub-base or base-course or verges, without the prior approval of the Engineers
Representative.
5.5
Grading
Samples of any material proposed by the Contractor for stabilization to form the base-course,
together with a copy of the road materials selection test results shall be submitted to the
Engineer for determination of the cement content at least six weeks before the material is
required for incorporation in the works.
Test No. 1 and 2 shall be carried out in accordance with Item 5.4.4 with paragraph (b) of the
Density/Moisture Content Compaction Test deemed to read:
Tests shall be made at least five moisture contents and the material for testing shall be
moisturised, mixed and sealed in airtight tins for a minimum period of 12 hours. The
required proportion of cement is then added and mixed thoroughly before testing.
Test No. 3 shall be carried out in accordance with B.S. 1924 of 1967 with the following
modifications:
a. For selection purposes all stabilised soil samples for testing shall be compacted at the
optimum moisture content to the maximum dry density. Samples shall be cured by
coating with wax. The Contractor should allow for the provision of 100m x 50mm and
150mm x 125mm moulds and the provision of a 3000kg compression-testing machine.
5.6
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 22
GENERAL SPECIFICATION
5.7
5.8
5.9
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 23
GENERAL SPECIFICATION
5.10
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 24
GENERAL SPECIFICATION
6. Uniformity of mix can be checked by digging short trenches at regular intervals, to the
full depth of the stabilised mix. When the mixture is of uniform colour over the whole
exposed face, the mix is satisfactory. When the mixture has a streaky or patched
appearance, more mixing is required.
7. This can be checked while carrying out the examination for uniformity.
8. Compaction will be checked in accordance with Item 5.9.
9. A satisfactory finish must be smooth, dense and free of ridges, cracks and surface
compaction planes. It is essential that satisfactory compaction and surface finish must be
obtained in as short a time as possible, as detailed in Item 7.3. Allowance should be
made, sot that the finished smooth and correctly shaped base-course if of the required
depth.
10. Adequate curing of the soil-cement base, as detailed in Item 7.5 is essential.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 25
GENERAL SPECIFICATION
6.
6.1
General
The materials used in the works shall be new and / or of the qualities and kinds specified, and
no materials shall be used in the works unless approved. Materials delivered to the works
shall be equal to the approved samples. Deliveries shall be made sufficiently in advance of
constructional requirements to enable samples to be selected by the Engineers Representative
for testing before using the materials in the Works. Materials failing to comply with the
Specification shall be immediately removed from the Works at the Contractors expense.
These Specifications on materials shall be read in conjunction with latest amended report of
The Lagos Materials Testing Conference , a copy of which will be made available to the
Contractor on request.
No material shall be used until it has been approved by the Engineer or his Representative.
Permission to use any material shall not be construed as an approval of its source nor any
acceptance as continued acceptance.
In no case will material which contains organic matter or other deleterious substance be used.
Material for filling in the embankment shall be obtained from sources approved by the
Engineers Representative and no slurry, mud or soft or otherwise unsuitable materials shall
on any account or under any circumstances be placed in embankments. Large pieces of rock,
clay or other materials shall be properly broken up and beaten down and no accumulation at
the foot of side slopes of embankments of boulders or lumps having no cohesion will under
any circumstances be permitted. The Engineers decision regarding the suitability of any
material shall be final, and any material of which more than 35% passes the No. 200 B.S.
sieve may be rejected depending on the plasticity characteristics of this material and its
disposition within the Works.
6.2
Sandfill
Where sand fill, either hydraulic or otherwise, is specified, it shall be obtained from a source
or sources approved by the Engineer. Where such sources occur in waters or areas under the
jurisdiction o the Nigerian Ports Authority or the Inland Waterway Department of the Federal
Ministry of Transport or other appropriate Authority, then the Contractor shall first obtain
written permission to remove material from the Authority concerned and shall comply, in all
respects with all regulations laid down by such an Authority.
The quality of the material intended for use as sand fill shall be subject to the approval of the
Engineer. For hydraulic sand fill the grading of the material shall be such that not more than
15% passes the No. 200 B.S. sieve, and in no case will isolated pockets or layers of silt, clay
or other organic impurities be accepted. For sand fill placed by any method other than the
hydraulic, the grading shall be such that not more than 30% passes the No. 200 B.S. sieve and
in no case will isolated pockets or layers of silt, clay or other organic impurities be accepted.
The relative density of hydraulic sand fill placed in embankment shall be as follows:
(A)
Top 600mm
90%
(B)
Next 600mm
80%
(C)
70%
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 26
GENERAL SPECIFICATION
Sand fill placed by any method other than the hydraulic shall be compacted in layers by a
method approved by the Engineers Representative to a density of not less than 100% of the
maximum dry density obtained in the British Standard Compaction Test.
In the case of hydraulic sand fill the Contractor shall construct all drains, ditches, spillways,
marginal bunds necessary for the proper protection of the Works. Such drains, marginal
bunds etc., shall be constructed sufficiently in advance of the deposit of the sand fill so as to
effectively drain and retain the sand fill and to prevent any of the material from flowing into
any harbours, creeks, canals, drains etc., or from causing any damage or nuisance to persons
or property. The Contractor shall be responsible for any slips or settlements which may occur
during the construction of the sand fill or the bunds, drains, etc., and shall also be responsible
for same during the maintenance period. The Contractor shall make good such slips and
settlements to the satisfaction of the Engineers Representative. The Contractor shall be
responsible for the full and efficient drainage of water resulting from the hydraulic sand fill
operation and shall construct such open drains as may be necessary to drain all surface and
rainwater, so as to avoid all ponding. The Contractor shall make due allowance for settlement
and drying-out of the sand fill and for the making good of same.
Before any hydraulic sand fill is commenced, the Contractor shall, in conjunction with the
Engineers Representative, survey the Site and mutually agree the surface levels, and such
agreement shall be recorded in writing by both parties.
The levels shall be taken on a grid with points at not exceeding 15 metre centres and the
Contractor shall construct concrete pilot-pillars to the satisfaction of the Engineers
Representative to enable the grid lines to be located during the filling operations. The
Contractor shall construct sufficient tell-tales, consisting of a 50.8 x 50.9.4 mm angle of
adequate length with a flange of 1 metre in diameter fixed at one end, all in non-corrosive
metal, to the satisfaction of the Engineers Representative, to enable any subsidence of the
original ground level to be measured. The method of measurement of hydraulic sand fill shall
be on the basis of the volume of material placed as determined from the area filled and the
depth of fill to the finished level from the original ground level for the subsided original
ground level, as applicable. Should any dispute arise as to the subsided original ground level,
as indicated by the tell-tales, then the same shall be determined by the taking of borings or by
the digging of trial pits.
Hydraulic sand fill shall be deposited in layers as directed by the Engineer, but in any case the
thickness of such layers shall not exceed the limits stipulated as follows:
(A)
(B)
(C)
The finished level shall be as shown on the drawings or as directed by the Engineer, and shall
be agreed as the result of a joint survey carried out by the Contractor and the Engineers
Representative. A tolerance of 75mm above or below the finished level may be permitted
during pumping operations, but the same shall be made good by subsequent grading or dozing
to the satisfaction of the Engineers Representative and to the tolerances stipulated for the subgrade. Without limiting his commitments under the terms of the Contract the contractor shall
not be required to make good any normal expected settlement of the original ground level after
completion of the sand fill. The contractor shall be deemed to have allowed for all the
foregoing provisions in his rates and prices for sand filling. Should the Engineer so desire the
Contractor shall place stock-piles of material in quantities and areas as directed. Payment for
these stockpiles shall be made at the Tendered Rates and Prices for Hydraulic Sand fill.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 27
GENERAL SPECIFICATION
6.3
6.4
6.5
Cuttings
The bottom width of cuttings shall be as shown on the drawings.
The normal side slopes of cuttings shall be 1 to 2 but may be either increased or decreased, as
directed by the Engineers Representative.
6.6
Embankments
Selected fill materials, as specified in Item 3.6.1 shall be spread evenly in horizontal layers of
not more than 225mm compacted over the full width of the embankment, and compacted in
accordance with the results obtained from the tests carried out under Item 5.8 of this
Specification, and in accordance with Item 6.4. The embankment shall be constructed as
shown in the drawings. The side slopes shall be 1 vertical to 2 horizontal, except where
otherwise directed y the Engineers Representative. Adequate bond shall be formed between
successive layers of fill material and between the existing sub-soil and the fill material.
6.7
Widening of Embankments
Where alignment permits, existing embankments shall be widened on one side only to the new
profile shown on the drawing by cutting out approved steps in the existing slope of by
levelling the existing embankment to fill the lower limits of the profile.
Selected fill material shall be placed and compacted within the profile. All exposed horizontal
surfaces, shall be compacted to 95% M.D.D./W.A.S.C. to a depth of 15cm. All new fill
material shall be spread in layers, adequately bonded to the previous layer, and compacted in
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 28
GENERAL SPECIFICATION
accordance with the results obtained from the tests carried out under Item 5.8 of this
Specification, and in accordance with Item 6.4.
6.8
6.9
6.10
6.11
Side Drains
Side drains shall normally be constructed on either side of the road expect where the road is
built on embankment or where the Engineers Representative directs that a drain is
unnecessary.
The drains shall be constructed in accordance with the types shown on the drawings, as
directed by the Engineers Representative. The side, shallow drain shall be excavated by
machine and the soil spread over the formation as directed. The narrow type drain shall be
construction either by manual excavation or by machine.
Drain inverts shall be finished smooth, and to a steady fall of not less than 1:120. This fall
shall, in all cases, be toward a culvert or turnout.
Material excavated from drains, if unsuitable for re-use as fill material, shall be deposited
away from the road, at least 1m clear of the drain, or of the top of cutting.
See Item 6.12 for the action required to obviate scouring in drains in cuttings.
6.12
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 29
GENERAL SPECIFICATION
6.13
Interceptor Drains
Where the road is in cutting and the natural fall of the adjacent ground is towards the road,
interceptor drains of type A shall be formed behind the top edge of the cutting and parallel to
the road to prevent run-off into the cutting. The top of the inside edge of the interceptor drain
shall be not less than 5m from the top of the cutting.
Where the adjacent ground has a cross-fall, interceptor drains shall be formed, as directed by
the Engineers Representative, on the high side of the road to prevent run-off into the road.
6.14
Turnouts
Turnout drains shall be constructed to discharge freely the water carried by the side drain on
to lower ground falling away from the road, so that the side drain water does not adversely
affect the road formation. As a guide, the spacing of such turnouts is found from the formula
3S where S is the distance in metres along the road in which it falls 1m. Normally the
maximum distance part of turnouts shall be 30m, but where due to the surrounding
topography this cannot be achieved, special consideration will be given to enlarging and/or
concreting the side drains or putting in additional culverts.
The minimum base width of a turnout drain shall be 300mm but they shall be constructed to
the width directed by the Engineer and the side slopes shall be 1 horizontal to 2 vertical. The
invert of a turnout shall fall away from the road, at a slope not less than 1:120 and not greater
then 1:20. The drain shall terminate where the invert coincides with the natural ground level,
but it is essential that the natural ground continue to fall away to avoid the drain backing up in
times of storms.
Turnouts must be constructed in such places where their discharge is not likely to cause land
erosion or harm to property, and in order to prevent such erosion or harm, the Engineer may
direct that open or covered concrete turnouts or other works be constructed.
6.15
Laying of Pitching
The pitching shall be in accordance with Item 3.6.9. The blocks or stones when laid shall be
clean and have no weak points, or projections more than 25mm beyond the expose surface
plans. Selected stones roughly squared, shall be used at the edges and ends of the pitching.
Stones shall be laid with the minimum practical amount of space between them in such a
manner as to break joints with those immediately below, and so that their weight is carried by
the embankment material as well as the adjacent stones.
No pitching shall be laid until the embankment has been properly compacted in accordance
with the specification and no pitching shall be laid at a steeper slope than 1 vertical or 1
horizontal. After the stones have been laid, the spaces between them may be filled with clean
rock fragments from the stone dressing that will not pass 18mm sieve.
Grout for grouted pitching shall be 1-part cement to 3-parts sand, with sufficient water to
ensure a good mix and the right consistency. The interstices between the stones shall be
completely fitted with grout through the entire thickness of the pitching after which the
surface shall be swept with a stiff broom.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 30
GENERAL SPECIFICATION
Grouting operations shall progress from the bottom of the slope towards the top.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 31
GENERAL SPECIFICATION
7.
7.1
Sub-Base
On completion and finishing of the formation, and if directed by the Engineers
Representative a sub-base of approved material shall be laid on the formation. The sub-base
material shall comply with the requirements of Item 3.6.2 and shall be provided and laid to the
dimensions on the drawings or as directed by the Engineers Representative.
The sub-base shall be compacted in accordance with the test results under Item 5.8 and shall
be compacted in 150mm (compacted) layers to 100% M.D.D./W/A.S.C. Adequate bond shall
be ensured between the sub-base and formation.
On curves of less than 300m radius, the width of the sub-base shall be increased by 600mm
such increase being applied to the inside of the curve, gradually over a distance of 30m on the
straight road at each end of the curve in accordance with Item 1.3.
7.2
Tolerance on Sub-Base
The finished surface of the sub-base shall meet the same tolerance requirements as stated in
Item 6.9 for the formation.
7.3
7.4
7.5
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 32
GENERAL SPECIFICATION
The selected base-course material shall be stabilised with a percentage of cement as directed
by the Engineers Representative, determined from the tests outlined in Item 5.5. The
stabilised material shall be compacted to 100% M.D.D./B.S.C. at O.M.C. The method
adopted and plant used must ensure an adequate mixture and compaction of the material, to
the satisfaction of the Engineers Representative and the maximum period between mixing in
of the cement and the completion of compaction of the stabilised material shall be 2 hours.
After compaction, the base-course shall be cured for 7 days and kept free of all traffic. It shall
be cured with M.C.1. or M.C.2 at the rate of approximately 5 square metre per 4.5 litre, the
type of bitumen to be as decided by the Engineer. Great care must be taken to remove all dirt
before applying the bitumen, and not to damage the surface. Alternatively if required, by the
Engineer, the clean surface may be covered with a 50mm layer of sand, kept moist for 7 days.
All transverse and longitudinal joints in the base-course shall be cut back to ensure that
adequate bond is obtained and uniformity of construction is maintained.
The Engineers Representative in accordance with Item 4.9 and 4.10 will carry out tests for
the control of mixing and compaction. The average of a series of control tests must not be
less than the laboratory tests results set out in Item 3.6.4 (d) and the minimum test result must
be no more than 2% lower than the laboratory test and occur less frequently than 1 in 10 tests.
If this average is not obtained by the Contractor he shall, at his own expense, scarify and
remove the unsatisfactory stabilised base, re-shape and re-compact the sub-base or formation,
supply, spread and compact the new base-course material and stabilise and compact as before.
If conditions are suitable, the Engineer may agree to 100mm stabilised base on top of the substandard stabilised base instead of replacing the original base.
7.6
7.7
7.8
Tolerance on Base-Course
The finished surface of the base-course shall conform to the same accuracy as required for the
formation profile (Item 6.9) except that the limit of tolerance shall be 10mm.
7.9
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 33
GENERAL SPECIFICATION
8.
CONCRETE
8.1
No holes or other cavities shall be cut in any concrete work unless approved. The Contractor
shall ascertain from the drawings or from sub-contractors or from elsewhere particulars of all
bolts and other fixings, and of all openings, holes, pockets, chases, recesses and bolts and
fixings shall be in position, and the cores, gas-pipe, or other approved ferrules, or any other
inserts necessary for forming all holes and other cavities, shall be fixed to the shutter.
8.2
Gauge Boxes
Boxes of the size corresponding with the proper quantities of the aggregates as determined
from time to time shall be used for gauging the materials and in such a way that the control
exercised over the proportions of the ingredients can be easily verified.
Boxes shall be proportioned so that the heights are large compared with the widths, the cross
sectional area being correspondingly small. The height shall be between 1 and 2 times the
width.
Weigh-batching machines of types approved by the Engineer may be used for charging the
hoppers of the mixer. They shall be maintained in a clean condition and in full working order
and shall be calibrated regularly as directed by the Engineers Representative to ensure that
their accuracy is maintained.
The quantity of one mixing shall be so arranged to use one or more whole bags of cement.
8.3
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 34
GENERAL SPECIFICATION
Cement, fine and coarse aggregates shall be as specified in Item 4.1 and 3.6.8 respectively.
8.4
8.5
8.6
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 35
GENERAL SPECIFICATION
A least three specimens of 150mm test cubes, preferably from different batches shall be made
for testing at each selected age, and the precise location of the concrete and the time of placing
noted.
Should the concrete in the work be compacted by hand, the test cubes shall be compacted by
hand as specified in Clause 53 (a) (i) of B.S. 1881. Should the concrete in the work be
compacted by machine vibration as specified in Clause 53 (a) (ii) B.S. 1881 the test cube shall
also be compacted by machine vibration. The Engineers Representative may make test cubes
in the Laboratory for any purposes from site materials, and the Contractor shall supply such
materials as required free of charge.
The test cubes shall be stored at the site of construction at a place free from vibration, under
damp sacks for 24 hours (plus or minus hour) after which time they shall be removed from
their moulds, market and buried in damp sand until the time fro sending to the testing
laboratory. They shall then be packed in damp sand or other suitable damp material and sent
to the testing laboratory, where they shall be similarly stored until the date of test. Test cubes
shall be kept on the site for as long as practicable, but at least three-fourths of the period
before test, except for tests at ages less than seven days.
The Contractor shall bear the cost of carrying out and supplying all labour, materials and
equipment for the sieve, silt, organic impurities, bulking compacting required by the Engineer
or the Engineers Representative to ensure proper quality control of the concrete. The
Contractor shall also bear the cost of supplying all labour, materials and equipment necessary
for the preparation of the compression test cubes and their subsequent storing, curing,
packing, transportation and testing. All costs arising out of modifications to the concrete
mixes, cutting out and replacing of defective concrete and all other work carried out in
accordance with this clause shall be borne by the Contractor.
8.7
8.8
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 36
GENERAL SPECIFICATION
Engineers discretion, be accepted but otherwise the work will remain liable to rejection
as above.
The cost of all such cutting, preparation of specimens, testing and of making good the
portions of the structure affected shall be borne by the Contractor.
8.9
8.10
Mass concrete
Reinforced concrete
50mm
Heavy sections
50mm
125mm
Mixing Concrete
Concrete shall be mixed for not less than 2 minutes in a power driven mixer. The mixer shall
be fitted with adequate water storage tanks and accurate water measuring devices designed to
that no unauthorised person could vary the quantity discharged into the mix. Mixers shall be
maintained in first-class condition throughout the contract and any mixer of plant, which is
faulty in any respect, shall not be used. The drums on all mixers shall revolve at the speed
recommended by the maker.
A mixer of any type, which has been out of use for more than 20 minutes, shall be thoroughly
cleaned out before any fresh concrete is mixed.
The Contractor shall provide a mixer of mixers of sufficient size and number than can
adequately deal with the volume of concrete to be placed. Where the exposed face of the
concrete is to be permanently visible, he shall satisfy the Engineers Representative that the
mixer output is sufficient to deal expeditiously with the volume required, in order that the face
of the concrete shall not be marred by joint lines due to one layer having set before another is
placed within the lifts approved.
8.11
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 37
GENERAL SPECIFICATION
No concrete shall be placed in any part of the works until written permission to do so have
been obtained from the Engineers Representative. Well in advance of the intention to place
concrete the Contractor shall forward to the Engineers Representative for his approval full
information about the order in which he proposed to place concrete in the various parts of the
works, the height of each lift of concrete, details of the shuttering which it is proposed to
employ with relevant calculations, and positions of all construction joints.
All construction joint shall be formed as specified in Item 8.13 and there shall be no stoppage
of the placing of concrete except at such proper construction joints.
The Contractor will be required to furnish the Engineers Representative with satisfactory
evidence that all preparations, precautions and provisions have been made to ensure that the
concrete shall be placed and compacted in accordance with this specification before the
Engineers Representative will give his permission for concreting to proceed.
For members involving vertical placing of the concrete (e.g. piers) each lift shall be
deposited in layers extending for the full width between the shuttering and of such dept that
each lay can be easily and effectively incorporated with the layer below by the means of
compaction being employed. The layers shall be placed horizontally, sloping bends not being
permitted unless particularly so specified.
For members involving horizontal placing of the concrete (e.g. deck slabs) the concrete
shall be placed along the line of the starting point in such quantities as will allow the member
to be cost to its full depth along the full width between side shuttering and then gradually
brought towards the finishing point along its entire front, parallel to the starting line, the
tampers for giving the required surface and compaction following as closely behind as
practicable.
All members shall be concreted at such a rate as will eliminate any possibility of fresh batched
of concrete being deposited immediately adjacent to batches which have commenced to site
and all members shall be poured in one continuous operation until completed, no interval
being allowed to lapse while the work is in hand.
Care shall be taken to ensure that the process of placing concrete does not cause any harmful
vibration to adjacent work that has insufficiently hardened.
Should any unforeseen occurrence result in a stoppage of concreting for such a time as might
allow the concrete already placed to being to set before the next batches can be compacted
into place the Contractor shall immediately insert, at his own cost, a proper end-shutter to
form a proper tongue and groove construction joint, as specified in Item 8.13 normal to the
work at that point which will ensure that the section already cast is formed completely in
accordance with this specification. The Contractor shall at this own expense provide any
additional reinforcement required as a result of the joint.
No concrete for work, which will present a large, exposed surface (e.g. deck slab) shall be
placed in the direct rays of the sun and the Contractor shall erect shades to protect such work
there from.
8.12
Compaction of Concrete
After concrete has been placed in position it shall be compacted in such a manner as to
produce a dense uniform mass, special car being exercised to ensure that the concrete between
and around the reinforcement and adjacent to the forms is free from voids and other
imperfections.
In the case of reinforced concrete, a competent steel fixer shall be in constant attendance
during the mixing of the concrete to adjust and correct the position of the reinforcement if
required, immediately before the concrete is placed.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 38
GENERAL SPECIFICATION
Vibrators, preferably of the immersion type, and punners shall be used on conjunction for
compacting all classes of concrete both mass and reinforced, whose mix reference as shown in
the Bill of Quantities or drawings is suffixed with a V except that the written approval of
the Engineers Representative must be obtained before the use of vibrator is dispensed with.
This approval will normally be given only for compacting small-dispersed volumes of
concrete.
Vibrators shall be of a type approved by the Engineer and capable of producing vibrations of
not less than 3 000 cycles per minute with an acceleration of not less that 4G. In no
circumstances shall vibrators be attached to the reinforcement and every care shall be taken to
see that immersion vibrators avoid contact with the reinforcement.
Together with each immersion vibrator there shall be operated at least one hand punner of
weight not less than 3.2kg. With mould vibrators there shall be operated an adequate number
of 3.2kg hand punners. When hand compaction is sanctioned there shall be operated in
conjunction one 3.2kg hand punner and one pointed steel bar weighing not less than 4.53kg
and there shall be sufficient of these pairs to deal adequately with the volume of concrete.
Each freshly placed layer of concrete must be thoroughly compacted and worked into the
preceding one, but care shall be taken that no damage is done to previous work that has
already set.
Excessive compaction of concrete, whether by hand or mechanical means, shall be avoided.
8.13
Construction Joints
All construction joints in all classes of work shall be formed by inserting stopping-off boards
normally to the work to form a tongue and groove joint as detailed on the drawings and
against which the concrete can be properly compacted. They shall be formed in the position
shown on the drawings or as directed and approved by the Engineers Representative. There
shall be no construction joints in precast members nor in the reinforced concrete deck slabs of
minor spans. In the case of tee beams the rib and slab shall be cast together in one continuous
operation. In other work, construction joints shall be located at points where shear tresses or
tensile concrete stresses are a minimum and are placed whereby they will least affect the
appearance and properties of the finished works, but no construction joint may be inserted
without the written approval of the Engineers Representative. All reinforcement required by
the Engineers Representative as a consequence of the position selected for any proposed
construction joint shall be provided by the Contractor at this own expense, unless, in the
opinion of the Engineers Representative, the joint is absolutely necessary and there is no
alternative position for such joint.
When work is resumed against a horizontal surface, which has hardened or recently set, the
surface of the concrete shall be roughed by hacking and all laitance, loose and porous material
and poorly compacted concrete, shall be removed from it. Where reinforcement or fittings
project from the older concrete, these shall be carefully cleaned, utmost care being taken not
to break the bond, and freed from all adherent coatings of concrete and other matter likely to
reduce the bond between the steel and the concrete about to be poured. The surface of the
concrete (and steel if applicable) shall then be swept clean, brushed with a steel wire brush to
remove all loose material, saturated with water, thoroughly cleaned and all surplus water
removed. A 15mm layer of stiff, freshly mixed mortar containing the same proportions of
cement and fine aggregate as the grade of concrete used shall be applied to the damp surface
of the concrete immediately before concreting commences and the fresh concrete carefully
punned into it without delay.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 39
GENERAL SPECIFICATION
When work is to be resumed against a vertical face which has hardened or recently set, the
surface of the concrete (and projecting steel and fittings if any) shall be treated exactly as
described above for horizontal surfaces, but the application of the 15mm layer of mortar shall
be omitted and the fresh concrete shall be thoroughly compacted against the damp vertical
surfaces after the final saturation with water and the final thorough cleaning.
All costs incurred in complying with the requirements of this Item shall be deemed to be
included in the tendered rates for concrete.
Where it is specified on the drawings that a joint is to be inserted to prevent bonding between
two adjacent parts of the structure, the Contractor shall insert two layers of approved
waterproof building paper between those arts of the structure in the positions specified. The
paper shall be tailored to fit the surfaces accurately without any folding or wrinkling, and cut
overlapping edges shall be covered with adhesive tape to prevent any turning or movement
during concreting operations. Throughout the area of the joint there must be not less than two
thickness of approved waterproof building paper. Concreting operations and punning etc. shall
be carried out carefully to ensure that no damage shall be done to the paper.
8.14
Curing of Concrete
Freshly deposited concrete shall be protected from the sun, wind and rain until it has set
properly, and it shall also be prevented from drying too quickly by being kept covered with
constantly damp sacking or other approved means for a least 7 days after deposition.
Arrangements are to be made for a standby supply of water for curing purposes. The cost of
curing shall be deemed to be included in the tendered rates for concrete.
8.15
Removal of Shuttering
Shuttering shall be removed by gradual easing without jarring, and only in the presence of a
competent supervisor. Before removal of the shuttering the concrete shall be examined and
removal shall only proceed if the concrete has attained sufficient strength to support its own
weight and any constructional or other loads likely to come upon it. If any loading is excess
of the design load be anticipated, approved props shall be provided after removal of the
shuttering. The Contractor shall record on the drawing or elsewhere the date upon which each
part of the work is concrete together with the date upon which the shuttering is removed.
No shuttering shall be removed until an approved period has elapsed since the last day on
which concrete was placed in the part of the works concerned. Notwithstanding the approval
of the Engineer, the assessment of the period that shall so elapse and any damage or other
consequences arising there from shall be the Contractors entire responsibility The following
schedule is a guide to the number of days shuttering must be left after casting concrete:
3 days
4 days
7 days
24 days
28 days
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 40
GENERAL SPECIFICATION
8.16
Finishes
All concrete surfaces not requiring shuttering shall be smooth finished with approved floats to
give a dense surface with a minimum of cement and fine materials being brought to the
surface.
The top surface of deck slab shall be tamped to a smooth finish, aided by floats if necessary,
to the levels falls and cambers shown on the drawings or as instructed. The tamping shall not
be done to the extent of brining an excess of fine materials to the surface.
Shuttered surfaces of work in mass concrete which will always be in contact with the ground
and more than two feed below finished ground level on the external surfaces of abutments and
piers may be cast against sawn timber shuttering. All other surfaces, including all reinforced
work and all precast and pre-stressed shall be cast against steel or planed timber formwork.
Any surfaces, irrespective of the shuttering employed, which show honeycombing or voids
shall be made good by cutting back the concrete to behind the reinforcement in the cast of
reinforced work or to such depth s the Engineers Representative may specify in the case of
mass work and in either case to sufficient dept to remove all defective concrete, but no repair
work shall be started until after the defective surfaces have inspected by the Engineers
Representative. The cut shall be slightly belled to ensure that the new surface will be cast in
accordance with the requirements of this specification and against shuttering which has been
carefully aligned with the sound concrete on either side and rightly secured in position by
wedging etc.
All exposed concrete surfaces shall be fair finished to the entire satisfaction of the Engineers
Representative.
All concrete surfaces shall be protected from damage and disfigurement due to the subsequent
pouting of concrete or the carrying out of other work in the vicinity or any cause whatsoever,
and the Contractor shall remove all blemishes and repair all such damages to the satisfaction
of the Engineers Representative.
All costs for making good honeycombed and defective concrete and repairing damaged
surfaces shall be deemed to be included in the rates for concrete and shuttering inserted in the
Bill of Quantities.
8.17
Defects in Concrete
a. Regardless of satisfactory test cube results, any concrete work which, in the opinion of the
Engineers Representative, is excessively honeycombed or in any other way defective,
shall be liable to rejection.
b. Minor surface defects apparent on stripping the shuttering must be made good at the
Contractors expense, but no such making good shall be carried out until after inspection
by the Engineer or his Representative, and his approval of the proposed treatment. Work
which has not been previously inspected but which shows signs of such treatment shall be
immediately liable to rejection as defective work.
8.18
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 41
GENERAL SPECIFICATION
8.19
8.20
8.21
8.22
Displacers
When permitted by the Engineers Representative, displacers or plums may be used in mass
concrete but they shall not be less than 0.2 cubic metre in volume and no displacer shall come
within 0.5m of any foundation or exposed face of concrete or be nearer any other displacer
than 150mm. Displacers shall consist of blocks of stone or P.C. concrete with no sharp
corners or soft seams and shall be thoroughly washed before being used in the work and shall
be well worked down into the concrete on which they are placed.
8.23
8.24
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 42
GENERAL SPECIFICATION
The cement and sand will be mixed until such time as a uniform colour shall have been
obtained and the mortar will be discharged onto clean boards or into clean barrows. Any mix
deemed unsatisfactory whether too wet or for any other reason shall be disposed of as directed
by the Engineers Representative and at the Contractors expense.
Where the cement mortar is mixed by hand then clean close-boarded platforms of adequate
size shall be provided and the material turned over dry and thoroughly mixed before the
admixture of water. Any completed road surface will not be used as a platform for mixing
mortar.
8.25
Proportion By Volume
Cement
Purposes
Sand
1:1
1:2
1:3
1:4
Stone Pitching
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
Page 43
GENERAL SPECIFICATION
8.26
Class of
Concrete
Max size
of
Aggregate
Reinforced 9:38mm
for slabs
Total
volume
of DRY
aggregate
s
measured
separatel
y to 50kg
of
cement
cu. metre
0.1575
Fine
0.0525
Coarse
0.15
Max
water/
cement
ratio
Ratio
0.45
Preliminary Tests
Compressive strength in
kgs per sq. metre at
Minimum compressive
strength in kgs per sq.
metre at
7 days
28 days
7 days
28 days
2300x10
3150x10
3150x10
4200x10
Mix
Reference
3A or 3AV
Nominal
Mix
1:1 :3
3B or 3BV
18.75mm
elsewhere
Reinforced 9.38mm
for slabs
0.21
0.07
0.14
0.55
1580x10
2100x10
2100x10
2810x10
4A or 4AV
1:2:4
4B of 4BV
18.75mm
elsewhere
Mass
18.75mm
0.315
0.105
0.21
0.6
950x10
1260x10
6A or 6AV
1:3:6
Mass
18.75mm
0.42
0.14
0.28
0.65
700x10
1050x10
8A of 8AV
1:4:8
Volume II
44
GENERAL SPECIFICATION
Ratios given are for compaction without vibration and are the maximum allowable. Wherever justified ratio is to
be reduced to a minimum as agreed with the Engineer.
Proportions of Mix
The proportions given in the table are nominal and may be altered by the Engineer if the specified strengths are
not achieved of if the combined aggregate grading is unsatisfactory. The extra cost if any of such alterations
shall be deemed to be included in the tendered rates and prices.
3A or 3B
3A or 3AV
Volume II
45
GENERAL SPECIFICATION
8.27
B.S. 340
1963
B.S. 368
1971
B.S. 556
1972
B.S. 1194
1969
B.S.2028
1968
Should any portion of the work give evidence, in the opinion of the Engineer or his
Representative, that the concrete is of inferior quality, insufficiently compacted, segregated or
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 46
GENERAL SPECIFICATION
improperly deposited and rammed in the forms of that any of the reinforcement or fittings has
been omitted, incorrectly placed or subsequently displaced or that it suffers from any defects,
omission or injury from any cause whatsoever which may adversely affect the strength or
durability of the construction, the Contractor shall, on the written instructions of the Engineer,
remove and reconstruct that portion of the work in such a manner as the Engineer shall direct
or approve to ensure that the requirements of this specification are fulfilled.
No repairs shall be made to any faulty work until is has been inspected by the Engineers
Representative and his permission to proceed obtained. All costs involved in the
reconstruction of faulty work shall be borne by the Contractor.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 47
GENERAL SPECIFICATION
9.
PRESTRESSED CONCRETE
9.1
Cement
In additional to any relevant clause of this specification, the following shall be deemed to
apply in particular to prestressed concrete work, and shall be read in conjunction with all other
relevant clauses (especially those referring to mass and reinforced concrete) of the conditions
of contract and this specification.
a. The cements shall be rapid-hardening Portland cement in accordance with the latest B.S.
12 or other cement not labelled as such but having the same qualities. The use of high
alumina cement will not be permitted.
b. The cement is to be packed in waterproof steel drums and delivered to the site in first
class conditions. Each consignment is to be clearly marked with the date of manufacture
and the date of arrival. The drums of cement are to be lifted and handled with care so as
to avoid damage, and the sealed lids are to remain intact until ready for use.
c. Cement is to be stored on site under cover from the weather and is to be protected from
deterioration. Each drum is to be fully used up once opened, and no cement is to be
stored in drums, which have previously been opened.
9.2
Aggregates
All concrete aggregates to be used for prestressed concrete work shall be properly cleaned and
graded strictly to the requirements of the latest B.S. 882 to which end the Contractor shall
provide washing and grading equipment on the site.
Materials, which are rejected from the grading process, may be used up in 6A or 8A grade
concrete in other parts of the works at the discretion of the Engineers Representative. Any
rejected material is to be removed forthwith from the site by the Contractor at this own
expense.
Fine aggregate shall consist of naturally occurring sand obtained from fresh water river
deposits approved by the Engineers Representative. The grading of sand particles shall
satisfy the percentages stated for Zones 1 or 2 in B.S. 882, and given in the following table.
Coarse aggregate shall consist of natural gravel or of crushed granite rock obtained from a
source to be approved by the Engineer or his Representative. The grading of coarse aggregate
particles shall strictly satisfy the percentages for 19.05mm 4.76mm nominal size stated in
B.S. 882 as given in the following table with a content not exceeding 1% passing the B.S No.
7 sieve size.
Percentage Passing
Aggregate
Sieve Size
No.100
No.52
No. 25
No. 14
No. 7
4.76mm
9.52mm
19.05mm
38.1mm
Fine
aggregate
Zone 1
0-10
5-20
15-34
30-70
60-95
90-100
100
Fine
aggregate
Zone 2
0-10
8-30
35-59
55-90
75-100
90-100
100
0-1
0-10
25-55
95-100
100
Coarse
aggregate
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 48
GENERAL SPECIFICATION
Samples of the chosen aggregates shall be delivered to site and prepared by the Contractor at
this own expense, using the methods proposed for the whole works.
Samples of each aggregate as it is to be used are to be submitted by the Contractor to a testing
authority approved by the Engineer or his Representative. Each sample should consist of not
less than 45kg weight of fine aggregate and 90kg weight of coarse aggregate, and are to be
tested to examine the compliance of the specified requirements. The Contractor shall obtain
from the Engineer or his Representative written approval of the tests and types of aggregates
chosen, together with the proposed arrangements for use on the works.
Washing of aggregates may only be carried out using clean fresh water, obtained from an
approved source. The Contractor is to provide adequate storage facilities and arrange to
obtain this water at times chosen so as to cause the minimum of inconvenience to other
consumers.
9.3
Water
The water to be used for concrete manufacture shall be clean fresh water taken from an
approved source and shall at all times be kept free from chemical or organic impurities and
dissolved salt solutions which may have a harmful effect on the concrete.
9.4
Untensioned Reinforcement
Such reinforcement is to be of mild steel or high tensile steel as specified in the drawings.
a. Mild steel reinforcement shall be rolled mild steel bars are for reinforced concrete works
and shall comply in all respects with the latest B.S. 4449 and 4482.
b. Untensioned high-tensile steel reinforcement shall be either hard drawn pre-stressing
wires as specified hereunder or shall be deformed bars of quality and manufacture
approved by the Engineer.
9.5
Pre-Stressing Steel
For the purpose of this specification, the term pre-stressing tendon or tendons shall mean
a single wire, bar or strand or a number of wires or strands grouped into a cable or a group of
bars.
Steel for the pre-stressing tendons shall be one of the following types as specified in the
drawings.
a. Hard drawn high tensile steel wires for pre-stressing, conforming to the requirements of
the latest B.S. 2691 (1969). The wire shall have a minimum ultimate tensile strength of
100 to 110 tons/sq in and a 0.2% proof stress of not less than 85% of the ultimate strength.
b. Open-hearth silicon-manganese steel bars to the latest B.S. 970 hot-rolled and
subsequently processed to give the required physical properties for use in pre-stressed
concrete. The bars shall have a minimum ultimate tensile strength range of 64-72 tons/sq.
in and a 0.2% proof stress being not less than 85% of the ultimate strength.
c. Pre-stressing strands produced from high tensile plain carbon steel wires of quality and
manufacture approved by the Engineer.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 49
GENERAL SPECIFICATION
Type of
Strand
Nominal
Dia.
Min.
Breaking
Strength
Min.
Proportional limit
(0.01%
offset)
Min. load at
1.0%
extension
Min.
Elongation
to fracture in
610mm
Seven wire
pre-stressing
strand
12.5mm
37,000
22,200
31,450
Multi-layer
pre-stressing
strand
22.2mm
113,000
25.4mm
148,000
28.6mm
185,000
The mechanical properties, which are not specified in this table, shall be subject to the
approval of the Engineer.
a. The Engineer may permit the use of pre-stressing steel manufactured to standards
equivalent to those mentioned above provided that minimum strength requirements are
complied with, as indicated in this specification.
b. Copies of manufacturers test certificates and stress/strain diagrams shall be obtained by
the Contractor and given to the Engineer or his Representative for each consignment of
pre-stressing steel reinforcement. These certificates may be obtained and approved by the
Engineer or his Representative before the pre-stressing steel reinforcement is used in the
works.
c. Pre-stressing steel wires, strands or bars shall be delivered to the site in coils or in bundles
as specified by the manufacturers. If in coils, these shall be of such diameter as to be selfstraightening when unrolled. The coils shall be securely tied and fully wrapped in a
strong waterproof protective covering with the diameter and length of wire or strand
indicated on the outside.
d. Coils and bundles of pre-stressing steel shall be stored flat on a floor raised off the ground
and under full cover from the weather. They shall be protected from damage, oil,
corrosion or any deleterious matter, and shall not be opened until required. Before being
manufactured into pre-stressing cables the wire shall be cleaned free from loose rust and
any deleterious matter and inspected by the Engineers Representative for approval. Prestressing steel reinforcement which shows signs of pitting or has any surface defects such
as splits, roughness or necking is not to be used, and any lengths of wire or strand so
affected are to be cut out of the coil and rejected.
e. The Engineer may require tests on pre-stressing steel in addition to those of manufacture,
and the Contractor is to make all arrangements to supply samples for testing to a
nominated testing authority.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 50
GENERAL SPECIFICATION
9.6
Sheathing
Sheathing to pre-stressing tendons is to be of corrugated type such as hydra rigid or similar
approved by the Engineer.
Corrugated sheathing is to be delivered to the site coiled onto large diameter wooden drums,
securely fastened and protected from damage.
Corrugated sheathing is to be stored on site under cover from the weather, and shall be
protected from rusting, damage, oil or any other deleterious matter and shall be clean and free
from all such matter before being used in the works.
Sheathing shall be carefully examined prior to use and any damaged lengths shall be cut away
and rejected.
Joints in corrugated sheathing shall be formed by the use of couplers and/or by wrapping the
joints with tape. They shall be so designed as to prevent the ingress of cement, concrete or
other material during casting. All joints in sheathing shall be approved by the Engineers
Representative.
9.7
Concrete Proportions
9.7.1
Preliminary Tests
Preliminary tests to determine the grade concrete mix proportions for pre-stressed work shall
be undertaken as soon as the sources and qualities of cement, water and aggregate have been
chosen.
The Contractor shall deliver to a testing authority to be approved by the Engineer, sufficient
quantity of cement and prepared aggregates to enable concrete cubes to be made. Such cubes
shall be manufactured under laboratory conditions, using dry aggregates and proportions
calculated to give the desired workability and 10% more than the average 28 days works cube
strength given in Table Item 9.22. At the same time, the Contractor shall arrange to make
two concrete mixes on site using the same proportions of cement, water and aggregates as
used in the laboratory tests, which the methods to be adopted for the whole of the works. Six
cubes shall be made from the second batch of concrete out the mixer, and subsequently tested
by the approved testing authority. The amount of water used for mixing under site conditions
shall take into account the weight of water contained in the wet aggregates used shall be
adjusted accordingly.
The results of these preliminary tests shall give cube strengths of not less than those stated in
the Table Item 9.22.
All cubes shall be 150 x 1 50 x 150mm and made in standard steel moulds according to the
procedures described in B.S. 1881 and shall be vibrated. As a result of these tests, the mix
proportions for the pre-stressed concrete work shall be chosen and approved by the Engineer.
Thereafter, these proportions shall be adhered to throughout the works and may be varied only
on instructions given by the Engineers Representative.
9.7.2
Water-Cement Ratio
The water-cement ratio shall be chosen from the laboratory tests, and shall be taken as the
total weight of water added to the mix using completely dry aggregates, divided by the total
weight of cement. The amount of water to be added to each batch of concrete under site
conditions, shall be calculated from the results of moisture tests on the aggregates and the
weight of cement used for each batch, using the same total water-cement ratio as used in the
laboratory tests. No deviation from this water-cement ratio shall be made except with the
written approval of the Engineers Representative.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 51
GENERAL SPECIFICATION
9.8
Field Tests
The Contractor is to provide the following apparatus on site, for the testing of aggregates and
concrete mixes which, where applicable shall apply with the requirements of B.S. 1881 and
812.
a. Sampling pans for aggregate moisture tests.
b. Electric ovens for drying out samples of wet aggregates.
c. Accurate compensating balances weighing up to 10 kilograms with weights.
d. 12 No. Steel moulds for 6 cubes, with base plates.
e. Kango Hammer vibrator for making cubes.
f.
j.
Apparatus for testing contents of silt, clay, organic impurities in fine aggregates.
9.9
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 52
GENERAL SPECIFICATION
Stockpiles of aggregates are led in while casting of the beams is taking place. The mixer and
adjacent aggregate stockpiles shall be placed under temporary roofing so as to be fully
protected from the direct rays of the sun and rain.
9.10
Placing of Concrete
Casting of pre-stressed beams shall be carried out on specially prepared casting beds, which
are to be constructed under a temporary roofing so as to be fully protected from the direct rays
of the sun and rain.
The methods of vibration to be used shall be carefully designed to ensure full compaction of
the concrete and first class appearance without subsequent patching of concrete faces. Full
details of the Contractors proposed methods of manufacturing the beams shall be submitted
to the Engineers Representative for approval.
The Contractor is to allow for a preliminary casting of a short length of beam complete with
pre-stressing cables and reinforcement, using the proposed methods of vibration for the whole
works, which shall show that full compaction is achieved and verify that adequate workability
is provided by the proposed concrete mix proportions.
Each pre-stressed component shall be cast in one continuous operation and no construction
joints will be allowed.
9.11
Curing of Concrete
Curing of the pre-stressed components shall ensure a slow heat evolution in the concrete and
that shrinkage cracks are avoided.
Pre-stressed components shall be completely covered with hessian, which shall be kept
continuously wet for a period of seven days. If tensioning of the pre-stressing tendons takes
place before this time, the hessian shall be retained in position until the period of seven days
has expired.
The pre-stressed components shall then be cured in air for a further period of seven days
before being erected into position on the bridge.
9.12
Removal of Shuttering
Subject to the approval of the Engineers Representative, stripping of side formwork may take
place as soon as is convenient after the concrete had reached its final set. Stripping of bottom
formwork shall not be carried out until after transfer of pre-stress to the pre-stressed
component.
Moulds shall be of such a nature as not to allow the concrete member to deform when the prestress is applied. The bottom portions of the moulds shall be prevented from adhering to the
concrete.
9.13
Surface Finish
Pre-stressed concrete work shall, unless otherwise specified, have a smooth finish on all
surfaces exposed in the completed work. Surfaces which will be contact with concrete cast in
place for form a composite construction shall be purposely left very rough, in order to provide
an adequate key. The valleys and ridges of a roughening system shall not be parallel with the
direction of stressing.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 53
GENERAL SPECIFICATION
9.14
Tolerances
The Contractor shall provide continuous, experienced supervision during all mould-assembly
and concreting operations, in order to ensure that the tolerance in longitudinal dimensions for
all concrete work shall remain within the following limits:
a. For component about
9m long 6mm
The tolerance for lack o straightness on plan or variation in camber shall also be of the same
order as shown above for the respective lengths of the components.
The dimensional tolerances on web steel shall be of the order 3mm.
9.15
Pre-stressing
9.15.1
General
Post Tensioning
The system of pre-stressing and the magnitude of the post tension in a structural component
shall be as shown on the drawings.
Pre-stressing cables shall be manufactured on site from coils of wires or strands. The cable
consisting of a number of high tensile steel wires or strands shall be formed in the manner as
directed by the Engineer or his Representative. In estimating the length of all cables, extra
allowance must be made for attaching either one or two tensioning jacks as instructed by the
Engineer. The method of measurement for the purpose of payment shall be the length of the
finished cable placed, positioned, tensioned, anchored, cut and grouted complete as in the
finished structure.
Tendons shall be carefully handled so as to avoid sudden bends or kinks, and threaded into the
flexible sheathing before being placed into the beam formwork. The sheathing and the prestressing tendon shall be rigidly supported in the exact positions as shown on the drawings so
that no movement can take place during casting of the beams.
The anchorages shall be placed accurately in accordance with the drawings and firmly fixed to
resist displacement during vibration of the concrete. The anchorages shall be fixed so as to be
perfectly collinear with the axis of the tendons and to remain so throughout the casting of the
component.
An approved system of post-tensioning shall comply with the following requirements:
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 54
GENERAL SPECIFICATION
a. The method of tensioning and final anchorage shall be of such a nature that the controlled
total force is imposed and maintained without slip relative to the concrete after the
application of pre-stress.
b. The tensioning apparatus shall efficiently transfer the force from the pre-stressing steel to
the concrete by means of the anchorage without inducing dangerous secondary stressed in
the steel, the anchorage, or the concrete.
c. The anchorage system shall be secure against both sustained and fluctuating load and
against the effect of shock.
d. The anchorage itself shall be adequately protected against corrosion following the
completion of the final stressing operation.
e. Tendons after being placed in ducts or sheaths shall be so arranged as to allow an
unrestricted flow of grout and it shall be ensured that tensioned tendons are completely
embedded and the ducts effectively filled, unless specific instructions are given on the
drawing that the tendons are to be left un-bonded. The treatment of un-bonded tendons
shall be as approved by the Engineer or his Representative.
Joints in the spaces between a series of precast concrete elements, which are to be prestressed together, shall be made precisely in accordance with the requirements shown on
the drawings.
Suitable extensions or connection of the ducts through the gaps shall be provided and
steps taken to ensure that the jointing material does not enter the duct or press against the
pre-stressing steel. The holes for the pre-stressing steel shall be accurately made and meet
one another in true alignment at the ends and shall permit unobstructed passage of the
grout.
9.16
Tensioning
a. No post-tensioning of pre-stressing tendons shall take place until the concrete has attained
the specified strength as ascertained from tests on cubes cured and hardened under the
same conditions as the concrete or the member. Before stressing, single wires or strands,
the wires or stands in each cable shall be of equal length and tension.
b. Tensioning shall be carried out with the approved type of jacks.
c. Before tensioning the anchorages shall be carefully cleaned on all surfaces.
d. The amount of tension given to the tendons shall conform to a schedule of tendon
tensions, to be supplied by the Engineer, and will be based on the test data for the prestressing steel.
e. Measurement of the force shall be by an accurate gauge indicating the force on the
hydraulic jack and also by the elongation of the steel, after allowing for any initial slip in
the wedges or jaws of the grips. The Engineer may also specify the use of a load cell to
determine the tendon tension directly.
f.
Approval shall be obtained from the Engineers Representative before each tendon is
anchored. The Contractor shall provide printed sheets and supply the Engineers
Representative with a record of all extensions and pressure readings for each tendon in
every pre-stressed structural component.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 55
GENERAL SPECIFICATION
i.
The pre-stressing force should be applied from one or both ends as specified on the
drawings.
j.
Each wire, pair of wires, cables, stands or bar shall be attached in such a manner as to
ensure that the elongation is uniform throughout its length. Should any tensioned steel or
anchorage break or be damaged; it should be replaced if so ordered. Throughout all
tensioning operations, a spare jack capable of maintaining the designated load should be
available.
k. All tensioning shall be carried out in the order specified or approved. After tensioning,
the wires, strands or bars shall be secured in position and cut off as directed.
l.
9.17
The men employed shall be experienced in this class of work. Every precaution shall be
taken to ensure the safety of the workmen during the tensioning period.
Grouting
a. After tendons have been tensioned and anchored they shall be grouted up solid throughout
suitable outlets with plugs being provided to prevent air locks unless otherwise specified.
The Engineer shall approve the methods of mixing and injecting the grout before grouting
is commenced. The pressure at which the grouting is to be pumped into the duct shall be
approved by the Engineer and shall not normally exceed 80lbs per square inch.
b. Grout shall be either a neat cement grout with a water-cement ratio not exceeding 0.4 or
cement mortar (1:1 by weight). An expanding plasticising admixture should be used. All
ducts and holes shall be thoroughly washed out with water immediately before grouting
and after the stressing operation has been completed. Grouting is to be carried out
continuously, the discharge from consecutive air holes being observed throughout. The
mixer shall be thoroughly cleaned before grouting is commenced. A complete squaregrouting plan for immediate use in case of emergency or breakdown of the equipment in
operation shall be available.
c. Care shall be taken to avoid lumps in the cement, and sieving shall be carried out before
mixing the grout. It is essential to mix up a quantity of grout sufficient for a particular
duct immediately prior to its injection and to use only this batch on the duct.
d. During the grouting operation, grout shall be continuously added to the bucket from
which the grout is being pumped and bucket shall not be changed, otherwise air may enter
the sheathing with the grout.
e. Before the commencement of grouting and after the completion of it, reports shall be
made to the Engineers Representative in writing. The duct shall be plugged when grout
is issuing freely from the outlet end, and once plugged the pressure shall be gradually
reduced to prevent blowbacks or air pockets.
After grouting, the ends of the anchorages and any projecting ends of cut-off tendons shall
be covered over by a 1:1 mix mortar packed hard into the recesses on the beam.
9.18
Pre-Tensioning
In long line beds for pre-tensioning due consideration shall be given to the friction caused by
the varying shape and number of diaphragms which will affect the magnitude of the applied
pre-stressing force.
In order to obtain concrete of uniform strength where members are cast in a long-line bed, the
difference in strength at transfer between components of the same type cast in the same line
shall not exceed 15%. The Contractor shall satisfy the Engineers Representative by tests on
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 56
GENERAL SPECIFICATION
special cubes cured under the same conditions as the members that this condition is complied
with.
With pre-tensioning, the specified force shall be maintained by the use of approved fixing
devices at the ends of the tensioned steel during concreting and curing, until the concrete has
attained the strength specified. The tensioned steel shall then be released gradually and
uniformly.
9.19
Transverse Pre-Stressing
Transverse pre-stress shall be as specified and shown on the drawings.
Joints between precast concrete units are to be made in accordance with the drawings or
instructions from the Engineers Representative. They shall consist of dry or wet joints. In
the case of dry joints, they shall be filled with dry concrete quality (see Item 9.22), which shall
be mechanically rammed into position, and in the case of wet joints they shall be filled with
wet concrete quality (see Item 9.22) and fully vibrated into position. In both cases, joints shall
be finished flush with the pre-cast concrete faces. During jointing, protection and
continuation shall be given to the transverse cable holes, using a method to be approved by the
Engineers Representative.
Transverse pre-stressing tendons shall be as indicated on the respective drawing and threaded
through the transverse holes after the structural components are in position. Tensioning will
be carried out to a schedule of tendon tensions to be supplied by the Engineer, and must be
commenced at the centre working towards the ends symmetrically. The tendons are to be
grouted up in the same way as for the longitudinal pre-stressing.
Permission shall be obtained from the Engineers Representative prior to the commencement
of stressing and grouting and the completion of stressing and grouting shall be reported to the
Engineers Representative all as for the longitudinal pre-stressing.
9.20
Additional Requirements
The following additional requirements shall be complied with.
No cracks will be permitted on account if:
a. Shrinkage, settlement of formwork, or damage in handling before application of prestress.
b. Local weakness of concrete at or immediately following pre-stressing, or
c. Improper handling and transporting after application of pre-stress.
Where grooves are provided in which tendons have been placed, they shall be cleaned before
the mortar is inserted.
Mortar shall consist of one part by weight of cement to three parts of sand with a watercement ratio not exceeding 0.4 and shall be thoroughly compacted in the grooves, preferably
the use of vibrators, and subsequently cured.
Alternatively, mortar comprising one part of cement to one part by weight of sand together
with an approved expanding plasticising agent and less water may be used. External cables
shall be embedded in mortar of these proportions, an upper cover being placed over the cables
after vibration is completed to ensure the expansion occurs uniformly within the original
profile.
Any tension and retensioning procedure when allowed for offsetting losses shall be strictly in
accordance with the instructions of the Engineers Representative.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 57
GENERAL SPECIFICATION
The procedure to be adopted for all operations, using large diameter single strands used as
pre-stressing tendons shall be specifically approved by the Engineer.
9.21
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 58
GENERAL SPECIFICATION
9.22
Concrete Mixes
(1)
(2)
(3)
(4)
(5)
(6)
(7)
Class of
Concrete
Max. size of
Aggregate
Total volume of
Dry aggregates
measured
separately to
50kg of cement
cu. metre
Volume of dry
fine and coarse
aggregates to
50kg of cement
cu. metre
Maximu
m
water/
cement
ratio
Preliminary Tests
Compressive strength in
kgs per sq. metre at
Fine
Pre-stressed
concrete
Note
0.128
0.0427
Coarse
0.0853
Ratio
0.4
7 days
3585 x 10
28 days
4220 x 10
7 days
3950 x 10
28 days
4645 x 10
18.75mm
elsewhere
Water/Cement Ratio
Ratios given are for compaction without vibration and are the maximum allowable.
Wherever justified, ratio is to be reduced to a minimum as agreed with the Engineer
Proportions of Mix
The proportions given in the table are nominal and may be altered by the Engineer if the specified strengths are
not achieved or if the combined aggregate grading is unsatisfactory. The extra cost if any of such alterations
shall be deemed to be included in the tendered rates and prices.
GENERAL SPECIFICATION
10.
CONCRETE PILES
10.1
The pre-cast reinforced concrete piles shall be manufactured on the site in lengths as directed.
The concrete shall be quality 3BV as hereinbefore specified.
Shoes, reinforcement, forks, links, toggle-hole tubes, and other fittings shall be fixed
accurately in the position shown on the drawings. Shoes shall be fitted with the point axial
with the pile. The lower ends of the reinforcement bars shall bear on the top of the shoe and
the upper ends of the bars shall not differ in level by more than 6mm.
The moulds shall be so supported that the pile is not distorted during casting or subsequently.
The sides of the moulds shall not be removed until three days after casting and the pile shall
not be disturbed for at least seven days after casting.
Notwithstanding the foregoing requirements, the Contractor shall be responsible for any
damage done to the pile due to the sides of the mould being removed or the pile being
removed from the mould bottom too soon or from any other cause, and all piles damaged
during manufacture, handling, driving, or at any other time, shall be replaced at the
Contractors expense.
The piles shall be removed from the mould bottom only by canting sideways and rolling to the
stacking ground for curing. The runners or other supports upon which the piles are canted or
rolled shall be not more than 3m apart and shall be level with each other.
The piles are to be kept continuously damp for a period of at least ten days after casting.
Otherwise than aforesaid the piles shall not be handled, slung, pitched or driven until six
weeks after casting, and shall be protected from damage by any cause. The pile shall only be
slung from the toggle-holes provided in the positions shown on the drawings.
The piles shall be driven with approval driving equipment operated from an approved type of
frame. Weight of hammer and length of drop shall be as directed or approved by the
Engineer. During driving, the pile head shall be fitted with an approved cast steel helmet with
a timber stub-dolly and packing shall be renewed as often as necessary to protect the pile head
from damage. When the driving of any pile commences, it shall continue without cessation
from any avoidable cause until the pile has been driven to an approved set to the satisfaction
of the Engineer. The Contractor will be informed by the Engineer of the set required after the
test piles have been driven.
The piles shall be driven in the position shown on the drawings or within 75mm thereof, ands
shall be at the inclination shown on the drawings or within 1 degree thereof. The sequence
of driving the piles shall be left to the discretion of the Contractor who shall be responsible in
the driving of a pile shall cause defects in position or inclination, except within the
aforementioned tolerances of piles already driven. If a pile is at any time out of position, or
inclination by more than the aforementioned tolerances, the Engineer shall direct that at the
Contractors expense, the pile be extracted and re-driven, or a new pile driven in lieu thereof
in conformity with this specification.
A record of the driving of each pile shall be kept in the form to be prescribed by the Engineer.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 60
GENERAL SPECIFICATION
10.2
10.3
Test Piles
Before casting the bulk of the piles the Contractor shall, at the location of each bridge
requiring piling, manufacture cure and drive entirely in accordance with this specification and
in position as directed, two test piles of the same cross section as the remaining piles, each of
the maximum length which can be driven using the piling frame available, which shall remain
as two of the permanent piles. Records of the driving of the two tests piles shall be taken as
directed. The Contractor shall allow for the manufacture of the remaining piles to commence
only after these test piles have been driven and when so instructed by the Engineer.
Payment for the fabrication and driving of the test piles shall be made at the tendered rates and
prices for working piles of the working piles of the same type entered in the Bill of Quantities.
10.4
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 61
GENERAL SPECIFICATION
10.5
10.6
Splicing of Piles
Where a pile is to have another length cast onto it the reinforcement at the to of the lower part
should be exposed for a distance of not less than forty times the diameter of the longitudinal
reinforcement. The upper lengths of main reinforcement shall be butted against the lower, and
the butts overlapped by splice bars of the same diameter as the main reinforcement, and eighty
diameters long as shown on the drawings.
The extension should be truly in line with the remainder of the pile, and be cured and allowed
to harden sufficiently to develop the strength necessary for further driving.
If he wishes, the Contractor will be allowed to cast these extra lengths of piles using concrete
made with Rapid Hardening Portland Cement.
The period of delay between casting and driving shall be as follows for the different types of
concrete:
10.7
28 days
Pile Shoes
See Item 4.15.
10.8
Design
The soil data well below the anticipated depth of pile, must be obtained, also the loading
details, information on possible length of pile, and conditions of driving. These details will be
forwarded to British Steel Piling for them to specify casing size and thickness and weight of
hammer, and final set.
10.8.2
The casings can be lifted by manilla rope slings and do not have any special lifting points.
In order to prevent denting, the casing should not be bumped violently against hard
projections and care should be taken to prevent damage to the ends of the casings.
10.8.3
Driving Casing
A special cylindrical internal drop hammer of the correct weight and diameter appropriate to
the casing diameter must be used. This will be as specified by British Steel Piling.
Immediately before driving is commenced, plugs of dry 1:2:4 concrete must be deposited at
the bottom of the casing. This plug should have a compacted height of not less than about 2
times the pile diameter; allowance must be made for diving compaction causing 20-25%
reduction in height of plug.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 62
GENERAL SPECIFICATION
The amount of water/cement ratio must not exceed about 0.25 by weight, less than half the
normal amount. The aggregate used should comply with the specification for aggregate,
maximum size 25mm.
At the start of driving, small hammer drops should be employed for a number of blows until
the concrete plug has been compacted. If additional plugs have to be added, the same should
be done. The drop thereafter, should not exceed the final set, i.e. usually between 1.2m 2m.
The hammer rope should not be snatched before the hammer has completed its full drop.
Driving on one plug should not continue more than 1 hour after the concrete was mixed; a
similar dry plug should be inserted and driving continued as on the first plug.
The internal drop hammer may be operated from the jib of a crane or from a pile frame with a
winch.
10.8.4
Cast piles are normally provided with shoes consisting of a circular flat steel plate, welded to
the casing by means of a full strength butt weld, having a throat thickness not less than the
casing thickness; the plate diameter is approximately equal to the outside diameter of the
casing.
If the shoes are not fitted with the casing manufacturer, the following tale is a guide to the
thickness of plate to use:
10.8.5
250mm
10mm
300mm
10mm
350mm
12.5mm
400mm
12.5mm
450mm
16mm
500mm
16mm
Flame cutting can do this, but in order to produce a sound weld when subsequently joining the
cutting must be carefully carried out so that the whole cut is square across the pile width.
10.8.6
Site Joints
Welding an extension length by means of a full-strength butt weld, having a throat thickness
not less than the casing thickness, can carry these out. The detailed system of jointing is to be
that recommended by the manufacturer, as the joint will be subject to severe impact stresses
during subsequent pile driving.
10.8.7
Concrete Filling
Unless otherwise stated, the concrete filling shall be 4B concrete, dropped in fro the top. No
steel reinforcement is required in the main pile length unless the pile is subject to tension
loads. Short bounding or starter bars at the top of the piles, should be used to connect into pile
caps or beams etc. Reinforcement may also be required in the upper portions of piles, which
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 63
GENERAL SPECIFICATION
project above ground level, as in a jetty. If this reinforcement is heavy, 4BV concrete may be
required.
11.
11.1
Minor Culverts
11.1.1
Concrete Pipes
Concrete pipes for use in culverts, shall be constructed in 1:2:4 concrete (9mm maximum
coarse aggregate) and in maximum lengths of 1.2m. All pipes shall be circular in crosssection, with wall of uniform thickness throughout. The thickness of the walls of the pipes
may be as shown below, but shall comply with the requirements of B.S. 556. All exterior and
interior surfaces shall be smooth, even and have uniform texture.
Internal Diameter of Pipe
Thickness of Wall
600mm
80mm
750mm
80mm
800mm
85mm
900mm
85mm
1000mm
95mm
1200mm
120mm
Forms shall not be removed until the concrete is at least 12 hours old and pipes must be cured
for at least 7 days before removal from the place of manufacture.
11.1.2
Inverts of culverts not built in existing streambeds, ditches, gullies, etc. shall be at the same
level as the surrounding ground. As an exception, the invert of a culvert may be placed lower
than the surrounding ground where it is possible for the outlet drain or ditch to be dug within
the building line. Inverts of culverts built in existing streambeds, ditches, gullies, etc. shall be
at the same level as the bed of the stream, ditch, gully, etc. The fall of the inverts shall
conform, as far as possible, to the natural fall of the surrounding ground, or bed of streams,
ditch, gully, etc.
11.1.3
Concrete pipe culverts shall be constructed in accordance with the drawings. Excavations
shall be taken out to the required dimensions sufficient to allow a 150mm thickness of
concrete around the pipes. The pipes shall be laid on their prepared bed true to line and level
and jointed in 3:1 sand/cement mortar and the whole surrounded with a 150mm thickness of
1:3:6 mass concrete for the entire length of the piped culverts.
11.1.4
Where existing concrete pipe culverts are to be extended, the extension shall be carried out in
accordance with the provisions of Item 11.1.3. The existing culvert shall be given a 150mm
surround of 1:3:6 mass concrete. Where existing head walls occur within the formation width,
they shall be removed to a minimum depth of 300mm below the new road level.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 64
GENERAL SPECIFICATION
The exiting culvert and the new extensions shall be cleared out and flushed as necessary on
completion to clear all dirt, cement mortar and other obstructions to allow the free passage of
water through its full internal area.
11.1.5
Galvanised corrugated metal pipe culverts shall be constructed strictly in accordance with the
makers instructions, and to the size shown on the drawings. They shall be laid to uniform
line and grade, on 150mm of packed gravel. The lower quarter of the circumference of the fill
material, which must comply with the provisions of Items 3.6.1, 3.6.3 and 3.6.4. The fill
material around the structure shall be placed in 150mm layers and compacted to 100%
M.D.D./W.A.S.C. and shall be brought up evenly both sides of the pipe. It is important that
the fill material is kept at substantially the same height on both sides of the structure at all
times. Fill over the pipe shall be placed and compacted in the same manner. The fill must be
placed and compacted before any lengthy period of heavy rain has elapsed.
11.1.6
Multi-plate culvert shall be constructed in accordance with the drawings, and to the length and
depth shown on the detailed drawings. The base slab and buttress walls shall be constructed
in 1:3:6 concrete and the approved segmental section shall be jointed together with the
coupling supplied by the manufacturer. The junction of the approved segmental section with
the buttress wall shall suit the units involved and shall be to the approval of the Engineers
Representative.
11.1.7
Rectangular Culverts
Box culverts shall be constructed to the grades and dimensions shown on the drawing, or as
directed by the Engineers Representative, and the finished surface shall be smooth and
regular, free from flaws, air holes and excrescences with a constant grade.
The grades of concrete and quantity and size of reinforcement to be used shall be as shown on
the drawings and shall comply in all respects with the requirements stipulated for mass and
reinforced concrete.
Culvert construction shall comply in all respects with the requirements of this specification or
such modification thereof as the Engineer may decide.
Extensions to the existing rectangular culverts shall be constructed in the same manner and
standards as new rectangular culverts.
11.1.8
Backfilling to Culverts
All filling or backfilling shall be of materials approved by the Engineers Representative and
shall be free of boulders, large lump rocks, rubbish or other undesirable material. Materials
obtained from the adjacent excavation may be utilised if found satisfactory and approved by
the Engineers Representative.
Backfill at culverts shall be placed in layers and carefully compacted to the required density
conforming with Items 3.6.1, 3.6.3 and 3.6.4.
No backfilling shall be carried out until the Engineers Representative has inspected and
passed the culverts and other structures, which will be covered up.
11.1.9
Culvert Outlets
The positions, lengths, dimensions and levels of all culverts including aprons shall be as
shown on the drawings or as directed by the Engineers Representative. The culvert shall be
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 65
GENERAL SPECIFICATION
cleaned out and flushed as necessary on completion to clear all dirt and other obstructions to
allow the free flow of water through its full internal cross-sectional area.
The outlets of all culverts shall be protected from erosion by stone pitching or concrete to a
minimum length of 6 feet from its face. The width of the pitching or concrete shall be decided
by the Engineers Representative and a toe-wall 500mm deep shall be constructed at the edge
of such pitching or concrete. The inlets to culvert shall be similarly protected, only where
directed by the Engineers Representative.
Where the gradient of the roadside drainage ditch would be excessive if the ditch were graded
to the invert level of culverts, catch pits shall be construction as and where directed by the
Engineers Representative. The catch pits shall be constructed of mass concrete to such
dimensions as required by the Engineers Representative.
Before any drain or culvert is brought into use, the Contractor shall ensure to the satisfaction
of the Engineers Representative that it is free from all extraneous material, all such material
being completely removed from the site.
During the period of maintenance the Contractor shall ensure that the drains and culverts shall
be kept clear of all obstructions and before the maintenance certificate is granted all drains
and culverts must be cleaned out to the satisfaction of the Engineer. All costs incurred shall
be deemed to the included in the tendered rates and prices.
11.1.10
Pitching
Pitching will be provided where shown on the drawings or as directed by the Engineers
Representative, and shall comply with Items 3.6.9 and 6.15.
11.1.11
Excavation for foundations shall be of the width and length necessary for the construction of
the foundations, and shall be taken out to the depth shown on the drawing or to such depth as
directed by the Engineers Representative. The Engineers Representative shall agree the
final levels and dimensions and the Contractors measurement shall be nett, no allowance
being made for working space.
The Contractor shall supply, maintain and remove on completion, any timbering, sheet piling,
cofferdams, or other temporary work necessary for the retention of the faces of the excavation,
and for the safety of the workmen engaged thereon, and shall be entirely responsible for the
sufficiency thereof. During work thereon the excavations shall be kept free from water, by
pumping or other approved means. The term timbering shall mean all planking strutting,
wedges, dogs, straps, bolts, spikes, rails and other fastening and fittings whatsoever and of any
material. No payment shall be made to the Contractor for any timbering left in position unless
so left in by instruction of the Engineers Representative.
Should any slips occur in the faces of the excavation, the cavities shall be filled with concrete,
dry stone, or other materials, as directed by the Engineers Representative, at the Contractors
expense. Any sumps dug in the bottom of an excavation shall be filled in the same way.
Excavations shall be left open for as short period as possible. Immediately before
construction work is started within an excavation, the sides of the latter shall be trimmed, if
necessary and if so required under Item11.1.13, a further 50mm excavated from the bottom to
allow for the concrete blinding layer as specified in Item 11.1.13 hereof.
Suitable earth and other material taken from an excavation shall be set aside for re-use as
filling material. Unsuitable material shall be disposed of by the Contractor at least 15m from
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 66
GENERAL SPECIFICATION
the centre line of the road. Should any of the suitable material excavated from lost from any
cause, the Contractor shall replace it with an equal quantity of other approved material, at his
own expense.
Where excavations have to be made and foundations formed below water level, suitable
arrangements shall be made to exclude the water from the site, and the Contractor shall, when
tendering, submit a full and clear description, supported by drawings and sketches, of the
methods he proposed to use in respect of each foundation where these conditions will be
encountered. The methods proposed shall be directed in all cases to permit the execution of
the whole of the work in the dry unless this is shown in the method statement to be entirely
impracticable and uneconomical. The Contractor must satisfy himself absolutely as to what
levels may be experienced at and during the period of construction, whether such water levels
be above ground level or below and as to what flows and water levels will be attained during
flood and high tide periods and as to the condition of soils and subsoil and all other matters
pertaining to the adequacy of the temporary works and the efficient and proper construction of
the works themselves. The Contractor shall take all precautions to prevent flooding of the
works and shall make good any loss or damage to the temporary works and the works
themselves caused thereby at this own cost and to the satisfaction of the Engineers
Representative.
11.1.12
The Contractor shall re-fill large box culverts and bridge abutment excavations with approved
fill material (including selected material excavated at the site), taking the utmost care not to
damage or disturb the structure.
Special attention shall be paid to compaction of the filling material placed behind bridge
abutments, or large box culverts. Compaction shall be carried out in layers, and each layer
shall be compacted, by means of suitable punners, or other approved means to 100% M.D.D./
W.A.S.C. Full compaction shall be attained over a wedge of material, tapering from zero
distance at full depth of fill to a distance of 7m back (or a distance equal to twice the depth of
fill, which ever is the greater) at deck level over the whole width of the embankment.
Distances back shall be measured from the edge of the rubble-filling see Item 11.1.16.
11.1.13
Concrete Blinding
Immediately after the bottom 50mm of the excavation has been removed as specified in Item
10.11, the entire area of the bottom of the excavation shall, where shown on the drawing or
otherwise required by the Engineers Representative, be blinded with a 50mm (finished thick
layer of concrete quality 8A). The concrete shall be as dry as practicable and shall be well
tamped into the ground. Where plain concrete is to be deposited on the blinding layer the
surface of the latter shall be left roughly grooved. Where reinforced concrete is to be
constructed thereon the surface of the blinding layer shall be spade finished and the specified
cover of concrete under the reinforcement shall be provided entirely above the blinding layer.
11.1.14
Loading Test
The Engineer shall arrange that a loading test be made on the works or any part thereof if in
his opinion such a test be deemed necessary for one or more of the following reasons:
a. The site-made concrete test cubes failing to attain the specified strength.
b. The shuttering being prematurely removed.
c. Overloading during construction of the walls or part thereof.
d. Concrete improperly cured.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 67
GENERAL SPECIFICATION
e. Any other circumstances attributable to alleged negligence of the part of the Contractor,
which in the opinion of the Engineer results in the works, or part thereof being less than
the expected strength.
f.
If the loading test be instructed to be made solely or in part for the reasons (a), the test shall be
made at the Contractors own expense. If the test were instructed to be made for one or more
of the reasons (b) to (e) inclusive the Contractor shall be reimbursed for the cost of the test if
the result thereof were satisfactory. If the test be instructed to be made for reason (f) specified
above, the Contractor should be reimbursed for all costs relating thereto irrespective of the
result of the test.
The test load shall not be applied within eighty-four days of the completion of placing of the
concrete in the part of the works to be testing and the latter shall not be supported during the
test by the shuttering of other non-permanent support. Means shall however be taken to
ensure that in the event of failure under the test temporary support of the loaded member shall
be immediately available. The test shall proceed strictly as instructed.
If the result of the loading test is not satisfactory in the opinion of the Engineer, the Engineer
shall instruct that the part of the works concerned shall be taken down or cut out and
reconstructed to comply with this specification, or that other remedial measures shall be taken
to made the work secure. If the test be instructed to be made for one or more of the reasons
(a) to (e) inclusive and the work is found to be unsatisfactory, the Contractor shall take down
or cut out and reconstruct the defective work or shall take the remedial measures instructed at
his own cost.
The test load to be applied shall be a series of tractors, lorries, or road rollers equivalent to the
1.10 times the design load of the particular structure, disposed of in one or more arrangement
so that the maximum bending moments, thrusts tensions and shear forces due to the test load
are produced at the critical sections. During the test a record of the sequence of al cracks and
deflections at mid-span will be kept together with any other observations which the Engineer
may elect to record. The residual deflection if any shall be recorded and if required by the
Engineer the test will be repeated. The period of loading shall be one hour in any particular
case or as otherwise directed by the Engineer.
11.1.15
The Engineer may require the Contractor to remove all or part of existing bridges or box
culverts. The Contractor shall take every precaution to salvage all sound members of the
existing structure such a timber beams and decking, steel joints and hand railing. All such
members which in the opinion of the Engineer are suitable for re-use shall remain the property
of the Employer and shall be cleaned and transported by the Contractor at this own expense to
a Ministry of Works Yard as directed by the Engineer.
Where possible existing piles shall be withdrawn, failing which they shall be cut-off at a level
to be directed by the Engineer.
The Contractor may make use of any other materials resulting from the removal of the
existing structure subject to the approval of the Engineer.
11.1.16
Rubble Filling
Approved rubble filling shall be placed over a width of 300mm behind all bridge abutments
and outer walls and wing-walls to large box culverts.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 68
GENERAL SPECIFICATION
11.1.17
Expansion Joints
Vertical expansion joints shall be formed in the positions shown on the drawings and at such
other positions at the Engineer may direct. The joints shall be formed for the full depth of the
slab or wall and shall be 12mm wide unless otherwise shown on the drawings. The joint shall
be filled with approved joint filler as specified in Item 4.10 and after the adjacent concrete has
been placed and cured, the exposed sides of the joint shall be cleaned out for a depth o 50mm
and sealed with approved sealing compound (Item 4.11).
12.
12.1
Bending Reinforcement
Schedules of steel reinforcement giving the location, bending, diameter, length and number of
various bars may be incorporated in the drawings or prepared on separate sheets. These
schedules have been prepared for the convenience of the Contractor, but their accuracy is not
guaranteed. It will be the Contractors responsibility to check all the schedules against the
drawings and to satisfy him as to errors, omissions and all other things regarding their
suitability for the work before such work is put into operation. All discrepancies shall be
brought to the notice of the Engineers Representative immediately and well in advance of
placing the reinforcement in the works. Where new schedules are required or existing ones
required to be amended, the Contractor shall prepare such new or amended schedules in
accordance with B.S. 4466 (1969) and forward three copies of each to the Engineers
Representative well in advance of placing reinforcement in the works. The Contractor shall
be responsible for his own ordering sheets.
The cost of checking all new and amended schedules as specified above shall be deemed to be
included in the tendered rates for reinforcement.
Reinforcement bars shall be bent by machine or other approved means producing a gradual
and even motion. Bars shall be bent cold unless the Engineer shall approve bars of over
25mm in diameter being bent hot. Bars bent hot shall not be heated beyond cherry-red colour,
and after bending shall be allowed to cool slowly without quenching.
Bars incorrectly bent shall only be used if the means adopted for straightening and rebending
be such as shall not injure the material. Without approval no reinforcement shall be bent
when in position in the works whether or not partially embedded in hardened concrete.
Bends shall comply with the dimensions described in the bending schedules or elsewhere.
Overall dimensions shall not be exceed and shall not be less than 6mm below the required
dimension. The size of binders and the like shall be within a tolerance of 3mm under or over
the specified dimensions. Any tolerance in the total length of the bar as cut shall be taken up
in the end hooks or other approved portions of the bar. Any discrepancies found by the
Contractor in the bending schedules, on the drawing, or in other documents shall be
immediately reported to the Engineer whose interpretation and instructions relating thereto
shall be accepted.
The internal radius of a bend shall be not less than twice the diameter of the bar nor less than
the radius given on the bending schedule or elsewhere. A hook and other end anchorage shall
be bent to an internal radius of twice the diameter of the bar. The internal radius of the bends
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 69
GENERAL SPECIFICATION
at corners of binders and the like shall equal half the diameter of the bar embraced by the
binder. All bending shall be in accordance with B.S. 4466.
12.2
Fixing Reinforcement
Reinforcement shall be accurately fixed, and by approved means maintained in the position
shown on the drawings or elsewhere. Bars intended to be in contact where passing each other
shall be securely wired together at such points with No. 1 gauge annealed soft iron tying wire.
Binders and the like shall tightly embrace the bars with which they are intended to be in
contact, and shall be securely wired or if approved spot-welded, thereto. The ends of the wire
shall be bent into the body of the work and not left projecting towards the surface of the
concrete.
Reinforcement shall be lapped, joined or spliced only where shown on the drawings. If
splices and the like are necessary elsewhere they shall be formed only as directed by the
Engineer.
Where practicable, bars for each member shall be assembled and fixed in the form of a rigid
cage before placing in the mould or shuttering.
Immediately before concreting, the reinforcement should be checked for position, cleanliness,
freedom from rust, or retarding liquid. Means shall be taken to ensure that reinforcement
remains correctly in position during the placing and consolidation of the concrete.
Reinforcement projecting from work being concreted or already concreted shall not be bent
out of its correct position unless so approved and shall be protected from deformation or other
damage.
12.3
Horizontal, vertical, or inclined slabs, wall, arch slab etc. 25mm or the size of the bar,
whichever is greater.
Beams, columns, piles, etc main bars 37mm or the size of the main bar whichever is
greater.
The specified cover shall be provided and maintained within a tolerance 3mm under or over
(except where specified as a minimum) by means of accurately made cement mortar or other
approved non-corrosive distance pieces.
12.4
Spacing of Bars
The minimum clear horizontal distance between adjacent bars in any one layer in beams or
similar, shall be 25mm or the diameter of the bar, whichever is the greater. The minimum
clear vertical distance between successive layers of main bars in beams, or similar, shall be
25mm unless otherwise stated on the drawings. These vertical clearances shall be maintained
by the provision of mild steel spacer bars of the required diameter inserted at such intervals
that the main bars do not perceptibly sag between adjacent spacer bars.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 70
GENERAL SPECIFICATION
12.5
Construction of Shuttering
Shuttering and moulds for concrete shall be substantially and rigidly constructed of timber or
steel or pre-case concrete or other approved material and shall be true to the shape and
dimensions shown on the drawings.
Timber shall be well seasoned, free from loose knots and for shuttering of exposed concrete
faces, wrought on all faces. Faces in contact with concrete shall be free from adhering grout,
projecting nails, splits, or other defects that will mar the concrete surface. Shuttering for
foundations and other concealed work may be of undressed or rough timber.
All joints, except as hereinafter specified, shall be sufficiently tight to prevent leakage of
cement grout and to avoid the formation of fins or other blemished, and all faulty joints shall
be caulked. If timber boarding be continuously wet throughout the period of use, allowance in
the joints shall be made for timber expansion, when the shuttering is first constructed. Where
the appearance of the concrete face is important, the position and direction of the joints shall
be as directed.
Unless described on the drawings or elsewhere to the contrary, fillets shall be fixed in the
shuttering to form a 25mm chamfer on all external corners of the concrete whether or not such
chamfers be shown on the drawings.
Openings for inspection of the inside of the shuttering for walls, beams and similar work and
for the escape of wash-water, shall be formed in such a way that they can be conveniently
closed before starting to place the concrete.
Connections shall be constructed to permit of easy removal of the shuttering and shall be
either nailed, screwed, bolted, clamped, braced or otherwise secured so as to be sufficiently
strong to retain the correct shape during consolidation of the concrete by tamping, ramming,
vibration or other means. Wire ties shall not be used. Boltholes in the concrete shall be made
good by plugging with cement mortar after the removal of the bolts.
Top shuttering shall be provided to concrete faces where the slope exceeds 1 vertical to 2
horizontal. Such shuttering shall be counter-weighted or otherwise anchored against floating.
12.6
Erection of Shuttering
Shuttering shall be erected true to line and traced and strutted to prevent deformation under
the weight and pressure of the wet concrete, construction loads, wind pressure, or other forces.
The deflection shall not exceed 12mm. Beam soffits shall be erected with an upward camber
of 6mm for each 3m of horizontal span. It so directed calculations of designs of the shuttering
shall be submitted to the Engineers Representative for approval before construction, but
irrespective of such approval, the Contractor shall be held responsible for the sufficiency and
strength of the shuttering, and all other false work.
Beam and slab shuttering shall be so erected that the shuttering on beam sides and slab soffit
can be removed without disturbing the beam bottom boards. Re-propping of beams shall not
be approved except when props are reinstated to relieve the beams of loads in excess of the
design load as hereinafter specified. Vertical props shall be supported on folding wedges on
soleplates, or other measures shall be taken whereby the props can be gently lowered
vertically when commencing to remove the shuttering.
12.7
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 71
GENERAL SPECIFICATION
13.
STRUCTURAL STEELWORK
13.1
General
All materials and workmanship involved in the fabrication of steelwork shall comply with the
requirements of B.S. 152 1972 together with the additional requirements and modifications
specified hereinafter. All materials and fittings shall be the best of their respective kinds and
free from defects. All works shall be neatly finished; open joints will not be accepted.
Accurate workmanship is essential to ensure easy erection.
13.1.2
Working Drawings
Before any part of the work is put in hand the Contractor shall prepare working drawings.
The working drawing shall be submitted as mechanically reproduced prints on medium weight
paper showing either black lines on a white background or white lines on a blue background,
and all costs involved in supplying them shall be deemed to be included in the rates for
steelwork.
As soon as possible after the placing of the Contract, the Contractor shall prepare schedules of
all parts which go to make up the work, including bought out material, and shall forward a
copy to the Engineers Representative duly authorised inspector for guidance during
inspection.
13.1.3
All holes for rivets and black bolts shall be 1.5mm larger than the nominal diameter of the
cold rivet or bolt as manufactured and all holes shall be drilled, or drilled small and reamered.
Punching and sub punching and reamering shall be permitted only for floor plates and
troughing and only when these do not exceed 12.5mm in thickness.
Holes for turned bolts shall first be drilled at least 3m small in diameter and afterwards when
the structure is assembled, they shall be reamered or drilled to the correct size through all
thicknesses in one operation. The turned bolts shall not be easier than a light push fit in the
holes. No sub-punching will be permitted.
Where required, the Engineers Representative shall cut out rivets for examination and
afterwards replaced free of charge.
13.1.4
Washers
All bolts shall be provided with washers, those for turned bolts being bright finished. Round
washers shall not be less than 6mm thick for turned bolts and not less than 3mm thick for
black bolts. Tapered washers of the correct angle of taper shall be provided under all heads
and nuts bearing of bevelled surfaces and where tapered washers are required for turned bolts,
round washers shall also be supplied. Tapered washers shall be not less than 5mm mean
thickness.
13.1.5
Welding
No welding of any description will be permitted except where shown on the drawings. Site
welding will be permitted only with the written permission of the Engineer and then carried
out to the Engineers specific requirements.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 72
GENERAL SPECIFICATION
13.1.6
Joints
Joints shall not be made in any plate or section or in any part of the work, except shown on the
drawings.
13.1.7
When the flanges or webs of any joint or channel have to be cut or notched to enable the
section to be trimmed into another member, a hole of suitable diameter shall first be drilled
through the flange or web so as to leave a fillet at the intersection of the cut lines.
13.1.8
Troughing up to 8mm thick may be pressed cold. Over 8mm and up to 12.5mm thick cold
pressing shall be subject to the approval of the Engineers Representative.
13.1.9
Shop Assembly
Members shall not be riveted up until the parts have been thoroughly scraped, cleaned and
feed from all scale and other deleterious matter. Thereafter, surfaces, which will be in
permanent contact after shop assembly, shall be given one coat of priming paint on each face
and the parts drawn firmly together with bolts whilst the paint is still wet. All rivet holes shall
be thoroughly brushed out and all burrs and exuded paint removed before rivets are inserted
and riveting commenced. Surfaces not in contact but which will be inaccessible after shop
assembly shall receive the full protective painting treatment before assembly, viz., one coat of
priming paint, one undercoat and one finishing coat. All paint and painting shall be in
accordance with the requirements of this Clause. All reamering of holes shall be carried out
in the Manufacturers works and the edges of all holes on the outside faces of member shall be
slightly arrised.
13.1.10
Machining
The bearing surfaces of bearing plates etc. shall be planed level, the cut being made in the
direction of expansion of the girder. Surfaces, which require planing and other parts that
require machining, are generally indicated on the drawings.
13.1.11
Before being dispatched, all bridge spans shall be temporarily erected completed in the
Manufacturers works so that the inspection Engineer can be satisfied as to both the alignment
and fit all connections.
After the work has been passed by the inspection Engineer and before it is dismantled, each
part shall be stamped with the distinguishing mark assigned to it on the marking drawings, in
figures not less than 15mm high, in such a manner that the pieces may be readily identified on
arrival at site and put together in their proper positions. The marking shall also be stencilled
on each part in one or more places after it has received the first coat of priming paint and a
circle of white paint shall be placed round each stamped erection mark. No marking other
than that specified shall be put on the steel work.
13.1.12
Painting
All paint shall be in accordance with Item 4.8.2. All exposed structural steelwork shall only
be painted when dry. No outside paintwork shall be carried out during wet weather or in the
early morning when the dew is still lying.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 73
GENERAL SPECIFICATION
All points of contact of the steelwork before assembly shall be cleared from rust, scale, dirt,
grease etc., by scraping, or wire brushing and shall be given one coat of Lexide Primer. After
assembly, the whole of the steelwork shall be thoroughly cleaned as described above, and
given a coat of Lexide Primer.
The second coat of heat and exposure resistant Aluminium Paint shall be applied when the
first coat has dried satisfactorily, at least 12 hours after the first coat application.
The third coat shall be of the same Aluminium Paint and shall be applied when the second
coat has dried satisfactorily, at least 12 hours after the second coat application.
As soon as the painting is otherwise complete, the date on which the work was finished shall
be stencilled on the structure in an obvious position.
13.1.13
Site Painting
Surfaces, which will be in permanent contact after site assembly or erection, shall be
thoroughly cleaned and freed from all scale, loose paint, grease and other deleterious coatings.
Areas of rust shall be cleaned down to the bare metal. The surfaces shall be thoroughly dried
and one coat of priming paint applied to each face. The parts shall then be drawn firmly
together whilst the paint is still wet. All rivet holes shall be brushed out and exuded paint
removed before the rivets are inserted. Similarly for bolts and boltholes.
Surfaces, which will be inaccessible after site assembly or erection, shall be thoroughly
cleaned and freed from all scale, loose paint, grease and other deleterious coatings. Areas of
rust shall be cleaned down to the bare metal. The surfaces shall be thoroughly dried and then
give one priming coat, one undercoat and one finishing coat of paint.
Care shall be taken to ensure that no paint shall be applied to or allowed to foul any
reinforcement or other steel work which is to be embedded in concrete. In the case of steel
joists which will be so embedded and steel troughing which will be concrete filled, and all
other such surfaces, those surfaces which will be in contact with the concrete shall be
thoroughly cleaned and freed from all rust, scale, loose paint, grease and other deleterious
coatings before the concrete is poured against them.
Where concreting or any other operation likely to foul the steel work has to be carried out
(e.g. pouring of concrete deck slabs supported on R.S. J.S), preparation and painting of
surfaces shall not be undertaken until such time as the cause of likely fouling or damage no
longer exists.
All paint and painting shall be in accordance with Item 13.1 of this specification.
13.2
4.3309
Construction
4.3310
Steel sheet piling, which is specifically order for permanent works by the Engineer, shall be
painted as specified for structural steel work above and paid for at the rate entered in the Bill
of Quantities. Otherwise, steel sheet piling left in by the Contractor if ordered by the Engineer
shall be so painted at the Contractors expense.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 74
GENERAL SPECIFICATION
13.3
Hand Railing
The Contractor shall supply and fix all necessary hand railing as shown on the drawings, in
accordance with Item 4.36 of this specification. If required by the Engineer, the Contractor
shall paint all hand railing in accordance with Item 4.40 and 13.1.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 75
GENERAL SPECIFICATION
14.
BITUMINOUS SURFACING
14.1
Prime Coat
a
Bitumen
The bitumen used shall be as specified in Item 4.32.
The following table is a guide for the type of bitumen to be used, but in all new works, or
where the nature of the base-course changes, 15m test sections using the possible
alternative grades of bitumen shall first be laid. The grade that gives the most satisfactory
penetration (between 6mm and 12mm as approved by the Engineer) will be used.
Type of Base-Course
Surface
Grades of Bitumen
Temperature of
Application
Tightly bonded
M.C.O.
38 0 66C
Fine Open
M.C.1.
54 - 80C
Coarse Open
M.C.2.
66 - 107C
If bitumen is specified for curing soil-cement or soil-lime roads, M.C.1 or M.C.2 will be
used (Item 7.5), as directed, spread at approximately 5 square metres per 4.5 litres.
b
Preparation of Surface
Immediately before applying the bituminous primer, the surface should be brushed free of
all dirt and loose dust to present a clean hard surface. The road shall be thoroughly dried
and the surface approved by the Engineers Representative before the primer is applied.
Should any weak areas be found they shall be cut out and replaced with approved material
property compacted.
Application
The spread of bitumen from the Distributor shall be checked by the Depot Tray Test,
carried out in accordance with any one of the methods laid down in B.S. 1707, 1959,
Appendix A.
The bitumen shall be heated so that the temperature at application shall be as specified in
Item 14.1. The bitumen shall be sprayed over the full width of the road surface at the rate
of approximately 1.00 litre per square metre of road surface by means of an approved
engine operated or hand sprayer or multiple distributor.
Only if approved by the Engineers Representative will the Contractor spray half the
width of the road at a time. Except with special approval and direction of the Engineers
Representative, the bituminous primer shall not be covered with sand or mineral
aggregate, but shall be left to soak into the road. Where absorption is not sufficiently
rapid or where it is necessary to permit traffic over the freshly primed surface within a
short time after spraying, a small amount of sand or mineral aggregate shall be lightly
spread as directed by the Engineers Representative but not within a shorter period than
seven hours after spraying. The quantities shown in the Bill of Quantities are based on a
rate of spread of bitumen of 1.00 litres per square meter and blinding at cubic metre per
320 square meter of surfacing. The material for blinding shall be as specified in Item
4.15.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 76
GENERAL SPECIFICATION
14.2
S.125
132C - 160C
Esso 100/150
126C - 143C
Other makes
Preparation of Surface
The seal coat surface dressing shall not be laid until at least 10 days after the application
of the prime coat. During this period additional blinding sand shall be added if directed
and the blinding brushed over the surface to present damage by traffic. After such period
all damaged or weak spots shall be cut out, refilled, re-compacted flush with the existing
surface, primed and blinded as specified and re-rolled to the satisfaction of the Engineers
Representative.
After all repair work has been allowed sufficient time to harden, the surface shall be swept
clean of all loose material immediately prior to the application of the wearing coat.
Application
The seal coat surface dressing in (a) above shall be evenly applied to the clean, dry
surface, by means of an approved sprayer, the spread being checked by the Depot Tray
Test as in 14.1 (c). The first surface dressing shall have a spread of 1.0 to 1.4 litres per
square metre for 12mm sized aggregate. See Item 3.6.7 for details of single sized
aggregate.
With the Engineers approval 18mm single sized aggregate may be used. The second
surface dressing shall be done after approximately 12 months and will have a spread of
0.9 to 1.3 litres per square meter with 9mm sized aggregate or 1.0 to 1.4 litres per square
meter for 12mm sized aggregate. If the first surface dressing has 12mm sized aggregate
than a second shall be with 9mm sized aggregate.
The following table is a guide for the spread of bitumen and aggregate:
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 77
GENERAL SPECIFICATION
Rates of Spread
Notes
Single Size
Aggregate
Aggregate
Bitumen
12m
17 20
1.0 1.4
18mm
25 28
1.35 1.75
9mm
13 16
0.9 1.3
12mm
17 - 20
1.0 1.4
The blinding material shall be applied immediately after spraying the bitumen, and
brushed to ensure even coverage.
d
Rolling
Immediately following the application of the blinding material, the whole area treated
shall be rolled with a light roller i.e. 3560kg or such weight that there is no excessive
crushing. Uniform traffic compaction shall be achieved by suitably placed drums or
barricades that the whole of the surface is covered by vehicles moving at reduced speeds,
and speed limit of 25km per hour shall be enforced by the Contractor. Traffic shall be
controlled for at least 48 hours after the dressing has been laid.
14.3
14.4
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 78
GENERAL SPECIFICATION
14.5
14.6
14.7
Rain Damage
If heavy rain occurs before the bitumen has been kneaded up sufficiently around the chips to
prevent whip-off, the road shall preferably be closed to all traffic until the surface dries out.
Where this is not possible every precaution by placed barricades and stationing flagman shall
be taken to ensure that all vehicles traverse the affected section at greatly reduced speed or not
more than 16km per hour. If chips or gravel are whipped off from the surface owing to heavy
rain, such material, if free from dirt, shall be broomed or shovelled back over the road and
thoroughly rolled during the hottest part of the day. Any area, which cannot be made good in
this way, shall be brought up to standard by ordinary patching or resealing. Any remedial
measures of repairs necessitated by the weather conditions will be entirely at the expense of
the Contractor.
14.8
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 79
GENERAL SPECIFICATION
15.
MISCELLANEOUS
15.1
Grassing
Areas as specified or directed to be grassed shall be sown broadcast with seed of an approved
type (See Item 3.6.12), or planted individually with approved plants at 0.25m centres running
parallel to the centre line of the road.
15.2
15.3
Tree Planting
a. Seed Germination
Germination of seeds at the Lowland Rain Forest belt (e.g. Uyo to Calabar) shall be as
follows:
Spread fruits under the sun for 2 weeks, soak in warm water for 2 days and
after than sow broadcast. Germination occurs within 4 days with above
treatment.
b. Nursery Activities
Where direct sowing into pots is not practised, beds must be prepared. Seedlings of
chosen plant species shall be broadcast on a rectangular 900mm wide Seedbed with an
elevation of 40 to 80m higher in the middle than at the sides. The seedbed shall be
prepared by firstly pegging the area so that the dimensions of the beds and paths are
marked with pegs fixed at the required points. Strings shall then be tied to the pegs and
beds shaped. Bed shaping shall be done by removing soil from the paths and throwing in
into the adjacent supposed beds until the desired elevations are obtained. The seedbeds
shall have a fine tilt and in heavy rainfall regions such a Calabar and shall have ground
frames to check the seeds from being washed away by rain. These frames ma consist of
poles arranged end to end around the beds and supported by short stakes driven into the
soil at suitable intervals.
c. Transplanting
Depending on the nature of seeds, the method of sowing and density of sowing, seedlings
are transplanted directly from the seedbeds to the plantation. Often the seedlings shall be
first transferred to transplant beds and shall be maintained there for as long a period at it
will be necessary for them to attain the required sizes for planting out. The transplant
beds shall be prepared in the same way as the seedbeds except that they can be of any
dimension.
They could be 18m by 9m but in some areas could be 1.2m to 1.5m wide and 10m long.
The beds shall be slightly raised from the ground level and separated from each other by
paths about 40mm to 600mm wide.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 80
GENERAL SPECIFICATION
d. Sowing
i. Germination Beds
In broadcast sowing, the seeds are scattered over the bed as evenly as possible,
usually with hands. If the bed had been previously rolled, the topsoil shall be
slightly loosened by raking to prevent the seeds from moving when they strike the
soil and to give the surface of the bed a fine tilt.
ii. Sowing Boxes
Most species can only be raised successfully in a sowing mixture and to this end,
sowing boxes are recommended. Small seeds shall be sown in boxes of
convenient dimensions of say 600mm x 450mm x 80mm with bottom slates
10mm apart for drainage purposes.
iii. Pot Sowing
Sowing in pots is practiced when the soil is poor, and partly for ease of
conveyance to distant planting sites. In pot sowing the polythene pots shall be
filled with potting mixtures depending on the edaphic conditions of the place and
the species to be sown. Suitable mix shall have one of 4 parts of local sandy soil
to 3 parts of compost prepared thus:
Three pits each about 1.8m long x 1.2m wide x 90m deep are dug
close together. The first pit shall be filled full with vegetable
matter missed with cow dung and ammonium sulphate all arranged
in layers as follows:
The materials shall then be kept moist and remain in the first pit for at least one
month before they are emptied into the second pit where it shall again remain for
about a month. From the second pit the material shall be moved into the third pit
and allowed to remain for at least one month to ensure complete decomposition of
the materials. The compost shall be available for use after three months. Where
these process conflicts with speedy planting schedule and/or lack of the above
mentioned essentials, a sandy loamy soil from refuse dumps may be used.
Sowing shall be carried out in standard polythene pots obtainable from the
Forestry Division of the Ministry of Agriculture of most of the States of the
Federation of Nigeria.
After the pots are filled with hand or metal scoops and arranged, they shall be
thoroughly watered before actual sowing is done. Only viable seeds shall be
sown direct into pots and the maximum number of seeds per pot shall be two.
Seeds shall not be buried too deep and shall be sown at the centre of the pots.
After sowing, the pots shall be watered once more. Watering and tending shall be
by trained hands using knapsack or pump sprayers. The amount of shade required
for good germination shall be regulated.
iv. Nursery Stock
The time, which plants shall remain in the nursery to mature for planting out,
depends of the species, the method of raising them and on whether such species
will be planted out as stumps or striplings. The Federal Forestry Department shall
be consulted on this aspect of the work.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 81
GENERAL SPECIFICATION
Stumps
Only stout and vigorous plants shall be lifted up for use as stumps.
The plants shall be as thick as the middle finger, about .2 to 1.8m in
height and able to coppice well. Stumping shall be by cutting the
roots and shoots and trimming the side roots to at least 25cm long.
The shoot shall then be cut at slant so as to prevent water from
collecting on the surface of the stump when planted in the field.
Striplings
A stripling is an over-grown seedling about 1.8 2.4m high, which
is cut out in a plantation with the shoot stripped of leaves but
otherwise intact, and with as much of the main system as can
conveniently be lifted. The plants shall be lifted more carefully than
the stumps, and the leaves shall be removed without causing any
damage to the bark.
Puddling
Once the plants have been prepared either as stumps or striplings,
the exposed surface shall be protected from desiccation by coating
the roots with wet soils or mud.
e. Planting Programme
This shall be in conformity with the standard Silvicultural Forestry Practice in Nigeria
Lowland Rainforest Belt.
C:\USERS\PATRICK.KOLAWOLE\DESKTOP\POK
SPECIFICATION\CODES\ROADS BRIDGES SPECIFICATION 2008 JUNE 9
BUN.DOC
VOLUME II
PAGE 82