Beruflich Dokumente
Kultur Dokumente
For
Kamal Constructions
408, Thalawa Road
Kekirawa
CONTENTS
1.0 OBJECTIVE
2.0 SCOPE
4.1
2
RESPONSIBILITY
4.2
2
SITE MANAGER
4.3
2
SITE SUPERVISOR
4.4
3
MANPOWER
5.0 EQUIPMENTS
7.1
4
PROCEDURE
7.2SETTING OUT
7.3SITE PREPARATION
7.5EXCAVATION
7.7CONCRETE WORKS
7.7.1
7
PLACING OF CONCRETE
7.7.2
7
CURING OF CONCRETE
1.0 OBJECTIVE
The purpose of this method of statement is to define the
procedures
to
ensure
that
the
proposed
materials
and
2.0 SCOPE
Scope of works covered by this document include for all earth
/concrete works and it is to be adopted during activities in
Improvements to MARUTHAMADU Irrigation Scheme in
Vavuniya District under European Union- Support to District
Development Program(EU-SDDP)
4.1
RESPONSIBILITY
including;
4.4 MANPOWER
Engineer
Supervisor / Foremen
Surveyor
Operators
Drivers
Skilled Workers
Unskilled Workers
5.1 EQUIPMENTS
Excavator
Dump Truck
Service Vehicle for General Workers
Roller
Grader
Bulldozer
7.1 PROCEDURE
7.2SETTING OUT
Prior to any commencement of any physical works, a
professional technical officer shall be appointed to carryout
demarcation works and establish bench marks on site. Upon
obtaining all the necessary survey data, a joint survey to check
existing ground levels shall be carried out with the consulting
engineers.
7.3SITE PREPARATION
When any material is disposed outside the site, the disposed
material shall be graded to a neat appearance and shall not
obstruct natural drainage or cause damage to highways or
property. All precautions shall be taken to prevent any erosion
of the soil on the affected areas.
All unsuitable material and surplus suitable material shall be
run to spoil in tips approved by the Engineer.
7.5EXCAVATION
The excavation shall be carried out in accordance with the
relevant approved drawings and to the levels, widths and
heights shown thereon.
Hauling of material from borrows area or the importation of
fill material to the embankment, shall proceed only when
sufficient compaction plant is operating at the place of
deposition to ensure compliance with the specification
requirements.
Any excess depth excavated below the formation level
exceeding tolerance of 300 mm shall be made good by
backfilling with suitable material of similar characteristic of
that
removed
and
compacted
in
accordance
with
specifications.
Finish level shall be recorded in accordance to survey practice
and jointly inspected in the presence of Engineer.
The side slopes of cuttings and embankments shall be formed
as per the approved drawings.
mm
7.7
7.7.1
CONCRETE WORKS
PLACING OF CONCRETE
7.7.2
CURING OF CONCRETE
After the initial set of the concrete and when the concrete is hard
enough to not be damaged by such an action, the exposed concrete
surface shall be covered with gunny bags. These gunny bags shall
be left in position and maintained in a soaked condition for seven
days. For formed surfaces the curing shall be applied as described
after the formwork has been removed, or a curing compound shall
be applied.
7.7.3
7.8
CONSTRUCTION OF RIP-RAP
7.8.1
SUBGRADE PREPARATION
7.8.2