Beruflich Dokumente
Kultur Dokumente
INTRODUCTION
PERIODIC
TESTMETHODS
Periodic test methods, i.e., manually acquired measureduction far exceeds the cost to replace the failed component.
ments taken from time to time rather than continuously, can be
Safety can be compromised as well. The failure may result in
divided into three groups based on the characteristic of the exan exposure hazard, or the pressure to restore power may recitation source used in the test. These are direct current, altersult in unsafe worker practices. In some cases the unexpected
nating current, and surge tests. Applicable techniques within
failure may result in damage that goes beyond the failed comeach of these groups will be discussed in this paper.
ponent itself. These problems are well-known, and a variety
of techniques have been developed to aid in detecting deteriDC TESTS
oration, which signals a future failure. When detected, a corDirect-current methods are widely used in motor insularective action can be scheduled, thereby avoiding production
tion testing, probably because of their convenience of use as
delays, safety problems associated with emergency maintemuch as anything else. The test apparatus is lightweight and
nance, and additional damage to the power system.
portable, the tests are relatively safe, and very large values of
It would seem that with the existence of these techniques and
resistance (megohms) can be measured. A megohmmeter is
the well-understood benefits of detecting incipient failures,
typically used for performing the tests although hypots (i.e.,
they would be widely used. In some industries they are used,
high-potential testers) may also be used.
but in mining they generally are not. There are three apparent
The dc test methods are based on measuring total current as
reasons for this: first, interpreting the results of such tests
a function of test voltage and specimen resistance. Actually,
is sometimes problematic, leading to a loss of confidence in
this total current is composed of three separate components.
the method; second, a knowledge of these techniques is not
The first component of the total current, commonly known
well-understood throughout the mining industry; and third,
as geometric capacitance current, is defined as
many of the existing test techniques are not easily performed
in mines, and particularly in underground mines.
i l = (V/R)e-'/RC
(1)
As part of an ongoing effort to develop continuous monitoring techniques for incipient-failure detection, it was recently where
993
(2)
where
i3 = VIR
(3)
where
equipment. It is believed that such dc tests are capable of revealing incipient problems that could not otherwise be found.
The technique for performing this type of analysis consists of
applying two or more dc voltages and observing any reduction
in insulation values at the higher voltage levels. It is important to discharge the specimen between steps during this test.
Otherwise the absorption current at each voltage level will be
superimposed, resulting in a cumulative value that would not
be useful for field applications [l].
Evaluation
The results of dc tests are relative, and therefore evaluation
is based on trends over time rather than on the specific value
of one reading. For this reason, it is best to observe the trend
of the readings by plotting the resistance over time for each
piece of equipment.
It is also important for the person making the evaluation to
be aware of any possible test problems or conditions that may
cause sudden changes in the insulation resistance. In many
994
Rmin= kV
+ 1,
(4)
where
6
Fig. 1. Circuit model of dielectric.
problems. In addition, the prospect of accessing the individual motor leads for testing is not attractive.
At longwall faces, motor maintenance is more easily justified, particularly with the longer faces and the introduction of
high voltage at the face. The ability to predict motor failure
so that changeouts could be made during moves or on a weekend would be very valuable. Also, by the nature of longwall
mining systems, there are opportunities for performing more
thorough tests at surface facilities as opposed to underground.
These tests could include ac tests or surge tests.
AC
TESTS
Losses
Partial discharges can represent significant losses in large
high-voltage machinery. It is doubtful that partial discharges
represent a source of concern in most underground mining
machinery; therefore, it is only mentioned here for completeness. It is, however, possible that partial discharges could occur in some of the high-voltage equipment on longwall faces,
particularly if there are many voids in the insulation [7].
The effect of polarization from an alternating-voltage
source is quite different from that of a direct voltage. For dc
tests, the current component that resulted from the impressed
voltage was termed absorption current, and it decayed to zero
after a short time. Under the influence of an alternating voltage field, this polarization effect is continuously occurring
because of the effect of the changing field. This polarization
process now represents a loss in the dielectric. It is generally believed that the values of dissipation factor are largely
determined by the existence of polarization.
Two types of polarization are known to occur: dipole
and interfacial. Dipole polarization is produced by polar
molecules, i.e., the electrical centers of the positive and negative charges do not coincide. Under the influence of an alter-
995
Tests
Tests that detect partial discharges essentially measure the
charge transfer that takes place in the voids during discharges.
This charge transfer may be represented in loop traces using
bridge techniques or pulse-counting techniques, among others.
Details of these tests are not given because their applicability
for mining operations is questionable.
Power-factor tests may find application in some surface facilities or repair shops. The principle behind power-factor testing of equipment is straightforward. The insulation under test
is essentially the dielectric of a capacitor. With a perfect dielectric and infinite resistance, the in-phase leakage current
across the capacitor is zero, no real power is consumed, and
the power factor would be zero. This is of course for a theoretical case; most insulation systems have power factors in
the range of fractions of a percent to a few percent. This
power factor represents the power lost through the insulation
in phase with the applied voltage. As insulation systems deteriorate, power factor increases.
Dielectric loss is the property of insulation most closely
associated with power-factor testing (although dielectric loss is
not actually measured). This loss occurs because of the timevarying polarization of the molecules in the insulation when
an ac voltage is applied to the insulating material. Dielectric
loss is a function of applied frequency and temperature and
generally decreases with these two parameters [9].
A common test performed is the power-factor tip-up test.
Power-factor tip-up has been used as a test on individual coils
or groups of coils. Typically, measurements are made on each
coil to determine the power-factor increment between two designated voltages, with the data being analyzed on a statistical
basis. A change in the tip-up value over a period of time is an
indication of a change in the condition of the coil insulation.
A limiting value of tip-up may be selected on the basis of the
deviation from the statistically determined normal tip-up.
To determine power-factor tip-up, tests should be made at
predetermined voltages. The recommended voltages for determining tip-up are 25 percent and 100 percent of operating
line-to-ground voltage. The value of tip-up is then calculated
by subtracting the low-voltage power factor from the highvoltage power factor [lo].
996
TABLE I
'a
Maximum
Impulse
ZMYP
ZMYN
Machine
Rating
100 hp
440 v
500 hp
2.5 kV
6.0 kV
'Ik
2300 V
12 kV
1500 hp
4160 V
24 kV
8000 hp
13.2 kV
V , = kVL
(5)
Fig. 3.
where
V,
CONTINUOUS
MONITOFUNG
General
The test methods mentioned thus far are the most common
techniques used for machine insulation testing. Most of these
methods are best applied to large rotating machinery or on
motors at critical locations. Although each method has many
strengths in detecting incipient failures, they all have limita-
997
(7)
If the negative-sequence impedance of the motor is significantly larger than the impedance of the cable from the source
to the fault, which is usually the case in cable-connected motors, i.e.,
. ,
l z
L,
ru,
W
OO
LEAKAGE CURRENT, A
(a)
't
then
and
LEAKAGE CURRENT, A
where I, is the fault current, A. In other words, the negativesequence current will equal one-half of the measured fault
current. This result has also been tested experimentally on
cable-connected motors.
With circuit models such as those shown in Figs. 2 and
3, many relationships between negative-sequence current and
fault current, fault impedance, etc., can be derived; however,
these relatively simple models do not exist for motors with
internal winding faults. Nonetheless, the basis for negativesequence monitoring has been developed from this foundation,
and relationships between fault current and negative-sequence
current have been discovered on internal motor faults. The
ideas have been developed mostly through experimentation on
a motor which allows access to the stator coils. This machine
allows various stator coil connections, and it also allows the
insertion of fault paths within the windings.
Tests performed on this motor have indicated that negativesequence current is a good indicator of winding fault severity.
In addition, for points of known fault potential, the negativesequence current can be used as an estimate of the internal
fault current, just as it could for the cable-connected model.
A summary of results is shown in Fig. 4. This figure illustrates the relationship between negative-sequence current and
fault current at three different fault potentials for several fault
impedances. It is noted here that many different types and locations of the faults were simulated. In addition, both wyeand delta-connected windings were used. Despite these differences, there is a direct relationship between the measured
negative-sequence current and the fault current at a constant
fault potential.
Of course, internal fault potentials cannot be measured;
therefore, the relationships illustrated in Fig. 4 cannot be
used directly. However, if fault severity is determined by the
fault potential and current (because these values represent the
power consumed by the fault) then the negative-sequence current should reflect the increasing fault severity with potential. This effect is clearly represented in Fig. 4. The level of
negative-sequence current increases with potential for constant
values of leakage current.
The motivation behind this work is to find a single parameter that can be used to help evaluate motor-winding integrity.
(b)
W
'Z
00
LEAKAGE CURRENT, A
(C)
998
This has been done in the lab using a waveform analyzer, and
in the field using an oscilloscope; clamp-on CTs and resistive voltage dividers were used in both cases. The use of a
scope requires great care to accurately determine the phase
angles for the current and is probably not practical for use in
an extensive test program, although it would be fine for evaluating a few motors. The use of a commercial instrument that
directly measures the negative-sequence component would be
far more desirable for everyday application.
The efficacy of the negative-sequence current as an early
predictor of motor deterioration was discovered during the
development of a continuous monitoring system for predicting incipient failure. This system measures the voltages and
current phasors, and as such, determination of the negativesequence component is trivial. The negative-sequencecomponent will be an important predictor in the continuous monitoring system, but equally important, it can and should be used
in a periodic test program as well. Admittedly, the user will
have to locate or construct a device that is convenient to use,
since that aspect was not investigated by the authors.
It is well-known that voltage unbalances can induce the
flow of negative-sequence current because induction motors
have low negative-sequence impedance. In many installations,
unbalanced supplies may not be present. However, in some
cases, voltage unbalances will exist. This is problematic because the measured negative-sequence current may be a result
of the voltage unbalance and not a sign of deterioration in the
motor. Both experimental and mathematical evidence suggest
that a voltage unbalance factor of 0.1 percent could obscure
significant levels of deterioration within a motor.
The effect of the source unbalance on the magnitude of the
negative-sequence current must be separated from the contribution, which is due to deterioration, if sensitivity to low
levels of deterioration is not to be lost. A method of doing this
has been developed and uses linear superposition to identify
the portion of the measured negative-sequencecomponent that
is due only to deterioration within the motor [20]. Unfortunately, this method requires an in-depth knowledge of motor
parameters; these parameters may be difficult to obtain from
the motor manufacturer. However, there is reason to believe
that it will be possible to simplify the method with an acceptable loss of sensitivity such that the user will not require
detailed motor design parameters.
The implementation of negative-sequence monitoring into a
maintenance program should not preclude the use of other test
procedures. For example, megohmmeter tests, if properly run
and interpreted, can be very useful for detecting weaknesses in
a motors major insulation system. However, they are not very
useful for detecting phase-phase or turn-turn problems, which
usually occur before the major insulation fails. Surge testing,
which could detect these problems, is difficult to employ in
some locations such as in an underground mine and should be
reserved for surface facilities. Negative-sequence monitoring
could be very useful for detecting problems in advance of
failure so that more complete tests could be run or repairs
could be scheduled. In addition, negative-sequencemonitoring
will not interfere with the normal operation of the motor.
CONCLUSION
The mining industry, like many of the process industries,
places severe demands on electric motors. The ability to detect failures in advance would make scheduled repairs possible; however, traditional motor insulation tests are not practical in many cases and have severe limitations in most cases.
Negative-sequence monitoring is seen as a viable approach to
monitoring motor performance. This method does not interfere with normal operations and is continuous. In laboratory
experiments, it has proven to be a sufficient indicator for detecting electrical deterioration within a squirrel-cage induction
motor. Despite the effects of an unbalanced voltage supply on
the measurement and the present uncertainty over how to compensate for these effects, negative-sequencemonitoring can be
a significant and powerful addition to a plants motor testing
program.
REFERENCES
E. B. Curdts, Insulation testing by dc methods, Technical Fublication 22Tlb, Biddle Ins, 1984.
A Stitch in Time.. ., Biddle Instruments, 1984.
Recommended Practice for Testing Insulation Resistance of Rotating Machinery, IEEE Standard 43-1973, IEEE, 1974.
J. L. Kohler, F. C. Trutt, and J. Sottile, Performance and Condition Monitoring of Electrical Machines, Internal Report on Bureau
of Mines Contract No. J0338028, The Pennsylvania State University,
University Park, Mar. 1987.
C. W. Ross and E. B. Curdts, The recognition of possible measurement errors in dc dielectric testing in the field, AZEE Tmns., paper
no. 55456, 1955.
E. B. Curdts, The Field Testing of Electrical insulation by dc methods, reprint included in Technical Publication 2 I-PSa, Biddle Ins,
1984.
J. L. Kohler, Corona: mechanisms and applications for underground
coal mines, in Conf. Rec., IEEE-ZAS I975 Ann. Meeting, Oct.
1975, pp. 77-80.
R. F. Field, The basis for nondestructive testing of insulation, AIEE
Trans., vol. 60, Sept. 1941, pp. 890-895.
A. T. Nestor, Determining insulation quality by power factor testing, Plant Eng., vol. 38, no. 20, Aug. 1984, pp. 46-48.
Anon., Recommended Practice for Maasuring Tip-Up of Rotating
Machinery Stator Coil Insulation, IEEE Standard 286-1975, IEEE,
1975, p. 1 1 .
D. E. Shump, Applications of surge comparison testing, presented
at the 48th Annual Convention, Elec. Appar. Ser. Assoc., Toroto,
ON, Canada, June 23, 1981, p. 2 .
G. L. Moses and E. F. Harter, Winding-Fault Detection and Location
by Surge-Comparison Testing, AIEE Trans., vol. 64, July 1945, pp.
499-503.
I . A. Oliver, H. H. Woodson, and J. S. Johnson, A Turn Insulation
Test for Stator Coils, ZEEE Trans. Power Appar. Syst., vol. 87,
Mar. 1968, pp. 669-678.
R. L e k v r e , Vice President Sales, Baker Instrument Company, personal
communication, Nov. 1986
M. T. Wright, S. J. Yang, and K. McLeay, General Theory of FastFronted Interturn Voltage Distribution in Electrical Machine Windings, IEE Proc., vol. 130, pt. B, no. 4, July 1983, pp. 245-256.
Guide for Testing Turn-to-TurnInsulation on Form- Wound Stator
Joseph Sottile, Jr., (M86) received the B.S. degree in mining engineering, with highest distinction, and the M.S. degree in mining engineering,
both from The Pennsylvania State University, University Park, PA, in 1984 and 1986, respectively.
He has worked in both production and engineering for the Barnes and Tucker Company from 1977
to 1983, and he also worked for Consolidation Coal
Company in 1987. He is currently a Graduate Research Fellow at the Penn State Mine Electrical Laboratory, where he is pursuing the Ph.D. degree in
mining engineering.
999
Mr. Sottile is a member of Tau Beta Pi and the Society of Mining Engineers.