Sr.No
.
Item
Make
Qty.
VFD
Siemens
3(1/2 HP)
PLC
Siemens
MCB
Schneider/Siemens
5 3pole,1
2pole
Contactor
Schneider/Siemens
Relay
Schneider/Siemens
SMPS
Schneider/Siemens
Push Button
Schneider/Siemens
As per design
selector Switch
Schneider/Siemens
As per design
Indicator Lamp
Schneider/Siemens
As per design
10
Panel
11
MCCB
Schneider/Siemens
12
Terminals
Schneider/Siemens
As per design
13
Fan
Schneider/Siemens
14
Tower Lamp
Schneider/Siemens
1-3tier
15
Sensors
Sick
16
Emergency Stop
Schneider/Siemens
Sequence of operation:
1: - Operator will keep the boxes on the power roller conveyor (module 1)
2: - The power roller conveyor (module 2) running at a higher speed will help in
maintain a constant pitch between the boxes
3: - At online weighing machine (Module 3) the weight of the boxes will be measured
and the data will be send to Inkjet Printer (Module 5)
4: - The boxes will be moved to power roller conveyor (Module 4) and the weight will
be stamped on the boxes by the printer
5: - The boxes will be then moved to Strapping machine (Module 6) and the first
strapping will be done. After first strapping the box will move forward and the
second parallel strap will be done on the same strapping machine.
6: - The boxes will be then moved to gravity roller conveyor (Module 7) from where
it will be picked by another operator
7: - In case any of the conveyor is full, then all the equipment behind that conveyor
will stop and will start as soon as the conveyor is cleared.
8: - Cycle repeats from 1 ~ 8.
Integration:
Conveyor Functional Requirements Auto weighing Line
SL.
No.
1
Conveyor
Integration requirement
Functional Requirement
Powered
Roller
Conveyor
1.When
line
is
stop/Error
machine will not be start. Or if
any error (emergency, strap
feed error) in strapping machine
line will stop. After machine in
normal condition line will start
automatically.
2. By Pass Mode also.
Scope of work
1. PlC Programming as per sequence of operation.
2. On site Interlock.
3. Panel design & assembly.
4. Documentation.
Note: - PlC have extra i/o and should be Extra provision of Ethernet.