Beruflich Dokumente
Kultur Dokumente
GONDOLA
Shifting plan
Total gondola = 6
Total shifting = 6
Average time needed for one gondola shifting = 2days
Safety issues for gondola
a) told the gondola operator to check every 3 day
b) all gondola has numbering
c) all gondola has clearance to work on
d) overrall conclusion from Jangho's HSE department and IJM HSE
is good
2
SCISSORS LIFT
Quantity = 2
Location = ground floor
Safety issues for scissors lift
a) all is good to go
b) constant monitoring
c) needs to be barricaded
d) Training given
e) PMA cleared
SCAFFOLDING
Page 1
Sheet1
a) Aluminium scaffold
1 high tower at rooftop to be used during abseiling works
b) IJM scaffolding
* currently erection of scaffolding for stick wall is underway ,
* next would be collumn for glass installation
Safety issues for scaffoldings
a) all tagged and erected as planned
b) minor adjustment done from time to time
Materials are being calculated and will be returned
This formula
(material borrowed) (material being used) = (material to be returned)
WELDING MACHINE
Quantity = 4 ( 3 electrical and 1 oil)
Location = all at GROUND FLOOR
* all permits are done and tagged
* safety equipments such as fire blanket
and fire extingiushers are placed
near the workplace
* oxy tanks are equiped with new metres
and flashback arrestor.
* IJM safety personal is satisfied with it
* ONLY the electrical ones are being used
FORKLIFT
* our forklift drivers has been given training
by the IJM Safety Officer
* we are given checklist for the drivers to
inspect on daily basis starting next week
* I have gone through the checklist & make
necessary arrangements
* checklist will be needed to send to IJM
Page 2
Sheet1
on weekly basis
PROGRESS REPORT
1
WINDOW CLEANING
Target dates
Currently at level
No of workers
Internal
External
:
22th floor
Comments :
GLASS REPLACEMENT
see atachment for details
Comments :
COLUMN CLADDING
C10 = to be finished by 12th Jan
Issues = sillicons haven't arrive
Comments :
GOAL POST
Page 3
Sheet1
CYLINDER SPRAYING
21 completed
11 incompleted
* on hold , awating paint to arrive
* mean while the supervisor is checking for defects that needs painting starting
Level 11
Comments :
ADDITONAL INFORMATION
TOWER B
- glass replacement must be done by 30th Jan , 10 glass
- sunshade alignment to be checked
-15th Jan material arriving for Twr B sliding door
Stainless Steels
- the welder is expected to come today
Comments :
Prepared by,
MATHAN CHANDRAN
(Safety Coordinator )
Approved by ,
Page 4