Beruflich Dokumente
Kultur Dokumente
The size of the cable has been varied from 250 MCM to 1500
MCM. Figure 1 shows the results for single-point and twopoint bonding.
600
I. INTRODUCTION
F. de Len is with CYME International T&D, 1485 Roberval, Suite 104, StBruno, Quebec, Canada, J3V 3P8 (e-mail: info@cyme.com).
Ampacity [A]
500
Single-Point
Bonded
400
Two-Point
Bonded
300
200
100
0
0
250
500
750
1000
1250
1500
1750
600
500
Ampacity [A]
Directly
Buried
400
6%
Duct
Bank
300
200
100
0
0
250
500
750
1000
1250
1500
1750
reductions.
TABLE 1. VARIATION OF AMPACITY FOR TREFOILS WITH DIFFERENT BONDING
Bonding Arrangement
Single-Point
Two-Point
Cross Bonding
464
455
441
416
800
800
Ampacity
600
Ampacity [A]
Ampacity [A]
464
394
400
600
Two P o int (no t trans po s ed)
400
200
1000 MCM
Standing Vo ltage / km
0
0
200
500 MCM
0
0
0.1
0.2
0.3
0.4
0.5
Distance be twe e n phase s [m]
0.6
1000
Steel
1000 MCM
1000
Single-Point Bonding
800
Two-Point Bonding
600
400
200
0
0
250
500
750
1000
1250
1500
1750
600
1200
400
500 MCM
200
0
0
100
200
300
400
0 .2
0.4
0 .6
0 .8
1000
PVC
500
600
Ampacity [A]
Ampacity [A]
800
1200
Ampacity [A]
800
600
400
200
0
0
250
500
750
1000
1250
1500
1200
Ampacity [A]
1000
800
600
400
200
0
Figure 9. Standardized arrangements for cables in air
0.1
1033
838
714
772
772
947
910
544
0.5
0.6
0.5
0.6
1000
Ampacity [A]
Ampacity [A]
800
600
400
200
0
0
0.1
0.2
0.3
0.4
Separation [m]
Arrangement
Number
1
2
3
4
7
8
9
10
0.2
0.3
0.4
S eparation [m]
800
Vented Ends
Vented
Top
600
400
Not Vented
200
0
100
200
300
400
500
Inte rnal Diame te r of Duct [mm]
Figure 12. Varying the internal diameter of the conduit for different
V. CONCLUSIONS
1400
Ampacity [A]
1200
1000
Vented Ends
800
600
Not Vented
400
200
0
0
0.2
0.4
0.6
0.8
1400
Ampacity [A]
1200
1000
Vented Ends
800
600
400
NotVented
200
0
0
500
1000
1500
B. Cables in Air
For cables in air the three major factors affecting cable
ampacity are: conductor size, the cable grouping and the
distance to the wall. Doubling the conductor cross-sectional
area does not double the ampacity, but the "reduction effect"
is smaller than that of underground cables. Ampacity is less
sensitive to the bonding type and somehow dependent on the
intensity of solar radiation especially for large values of the
absorption coefficient of solar radiation. However, ampacity
is very much dependent on the distance from the cable to the
wall and on cable groping; see table 2 and Figures 10 and 11.
2000
2
VI. REFERENCES
Figure 15 shows a plot of ampacity versus wind speed. The
ampacity increases with an increase of wind speed. However,
the ampacity increase is larger at the lower end. Thus
increasing the wind speed form 0 to 5 m/s has a large effect
than increasing it from 15 o 20 m/s. The length of the riser
pole was varied from 1 to 20 meters and the ampacity did not
show any significant variation (results are not shown).
800
Ampacity [A]
700
600
500
400
300
200
100
0
0
10
15
Wind Speed [m/s]
20
[1]
1
2
3
4
5
6
-6
Figure 16. Construction and dimensions of the concentric neutral
cable used for most simulation
-4
-2
0
Ambient temp = 25C
2
Figure 16. Construction and dimensions of the concentric neutral cable used for
most simulations
Size
[MCM]
Shield
Insulation
Screen
C. Wires
Jacket
250
Conductor
0.5748
0.6148
1.6384
1.7927
1.9541
2.1510
500
0.8129
0.8629
1.8866
2.0409
2.2023
2.3992
750
0.9980
1.0480
2.0716
2.2417
2.4448
2.6417
1000
1.1519
1.2119
2.2355
2.4056
2.6088
2.2805
1250
1.2889
1.3489
2.3726
2.5426
2.7458
2.9426
1500
1.4118
1.4718
2.4954
2.6655
2.8686
3.0655
-3
Figure 19. Flat formation for the parametric study of cable separation (distances
in feet)
1
2
3
4
5
6
Native Soil = 1.00 C-m/W
-4
-1
-6
-2
-2
Figure 17. Duct bank installation of a 2X2 duct bank with four trefoils (distances
in feet)
VIII. BIOGRAPHY
Francisco de Len (S86, M92, SM02) was
born in Mexico City in 1959. He received the
B.Sc. and the M.Sc. (summa cum laude) degrees in
Electrical Engineering from the National
Polytechnic Institute (Mexico), in 1983 and 1986
respectively, and obtained his Ph.D. degree from
the University of Toronto, Canada, in 1992. He
has held several academic positions in Mexico and
has worked for the Canadian electric industry.
Currently working with CYME International T&D
in St. Bruno (Quebec, Canada), he develops
professional grade software for power and
distribution systems and is the leading technical support of CYMCAP, CYME's
cable ampacity program. He has published over a dozen papers in refereed
journals (IEEE/IEE), which have been cited over 100 times in journals listed in
the Science Citation Index.