Beruflich Dokumente
Kultur Dokumente
Dialog
1
Introduction -- #1
Title bar of Costbook Window
says: National Estimator 32
[National Construction
Estimator] and shows page 17 of
the NCE. To create a costbook
without a year visible, remove
2000 from the header on the
2000 version. Then click Utilities
and Import to create the new no
year costbook.
The Index -- #2
I'll use the index to search for sand fill under a slab base.
I'll double-click.
We've got a choice here. Let's try the first one.
This isn't what we want. I'll move down the page a little.
Here it is.
Split Screen. -- #3
I'll split the screen in two so the costbook is at the top and our
estimate is at the bottom. Let's put a name on this estimate.
I'll open up a little space by pressing Enter.
Ill press tab to get to the center.
Here's a good name for our estimate.
How's that?
I'll press Enter once more to open up a little space.
Here's the line I want to copy to our estimate. I'll select it.
Then I'll click the Copy button.
And the Paste button.
Notice the blinking cursor in the Quantity box.
I'll type a quantity of 100 because this slab is 100 square feet.
I'll press tab and check the estimate. This column shows costs
per unit, . . .for each square foot.
The column over here has extended costs for all 100 square
Action
Dialog
1
feet.
These lines explain what's getting installed. You can change
anything that needs correction. Just click and start typing.
It looks fine to me. So I'll click OK.
There! How's that?
Markup -- #5
Let's add some overhead and profit to this job. I'll click the
markup button.
I'll type percentages for overhead and profit. 15% for
overhead.
10% for profit
And I'll click OK.
That looks about right.
Changing Markup -- #6
We're about done. Let's check the estimate. I'll click the
Estimate Window button.
It looks OK to me. But you can change anything you want. To
change overhead or profit, click the markup button.
To change any cost, click on the line. Then click the Change
Cost button.
To change any words, just click and start typing.
Printing -- #7
Just one more thing you're sure to need. Let's save that
estimate to disk. I'll click the save button.
I'm going to save to the My Documents folder.
And the file name is Estimate Two.
I'll click on Save.
It should be saved. Let's see if it really happened.
I'll close Estimate Two.
Action
Dialog
1
Then click File . . .
And Estimate Two.
Here it is.
Getting Help -- #9
Click the question mark.
This is the end of the short
version of Show Me.
Action
Dialog
1
Here's the new cost.
Were done here.
Now the estimated labor cost for placing 15 anchor bolts is
54.45.
Changing the hourly wage for any craft code changes the rate
for that craft code everywhere in this estimate.
Changing Cost Estimates - #13
Estimate window. Stillwel estimate
with "Foundation" at top of screen.
Action
Dialog
1
Adding a Cost Estimate Line #16
Estimate window. Stillwel estimate
with "Foundation" at top of screen.
Cursor is at left just below the new
line, "Reinforced corners."
You can add or change lines in the costbook the same way
you add or change lines in an estimate. I'll switch to the
costbook window.
Some of our jobs require 8 mil polyethylene. There isn't any in
the costbook.
So let's add a line. I'll add it right here.
And click to insert a cost.
This is 8 mil polyethylene.
Square foot is OK for the measurement and I'll use the craft
code of BL for building laborer. Manhours are the same as for
6 mil poly.
Material price is a nickel a foot.
The labor cost is filled in automatically, so I'm done.
There. How does that look?
Action
Dialog
1
It's in red to show that this is a line I added. You can put all
kinds of notes in the costbook -- such as price quotes and
phone numbers.
To remove anything you added, just select it and press the
delete key.
It's gone!
Insert a Subtotal -- #18
Continuing from the prior screen,
NCE page 71.
Let's put some sales tax in this estimate. Tax goes at the end,
so I'll drag the scroll bar to the bottom.
I'll right-click and select tax rate.
Action
Dialog
1
set at 10% and profit should be
set at 15%.
Our tax rate here is seven point two five percent on materials.
There. How's that?
You can display an estimate on screen just the way it will look
when printed on paper. I'll click on the Print Preview button.
I can go to the Next Page or Previous Page to turn pages.
Or click on Two Page to see two estimate pages side by side.
Click on Zoom In to get a closer look.
Click on Close when you've seen enough.
Action
Dialog
1
Show Pictures #24
Stillwel estimate at the last lines.
Construction costbook on page 71
with Slab Membrane at the top of
the page.
Also Open: None
Most estimators like to see what theyre doing. Until you get
comfortable copying and pasting, keep both the costbook
window and the estimate window open.
But copying and pasting works just as well when youre in the
full costbook window.
Just for practice, let's do a little blind pasting. I'll open a new
estimate.
The next takeoff item is 15 foundation bolts. Lets try some
blind pasting.
Ill type bolts
And double click on foundation
I'll get the Index window out of the way.
Heres what were looking for. Ill click on the 5/8 by 12 line.
And press the F8 key. F8 is the same as copy and paste.
Ill type a quantity of 15
And click on OK.
Youre probably wondering where those bolts got pasted. The
screen isnt split. So you cant see the estimate. I'll explain in
the next frame.
Action
Dialog
1
Screen
Beginning Screen: Costbook
Window, Construction.ubk with
Foundation Bolts on page at the
top.
Also Open: Estimate1 which
shows the cost for 15 foundation
bolts.
Action
Dialog
1
Undo #27
See also: Cut, Copy, Paste, Insert
a Text Line, Insert a Cost Line,
Insert or Edit Subtotal Line,
Commands Grayed Out
Beginning Screen: Estimate
Window, with Estimate1
Also Open: Construction.ubk
Cut #28
See also: Copy, Paste, Undo,
Gray Commands and Buttons
Beginning Screen: Estimate
Window, with Estimate1, including
cost for 15 foundation bolts.
Also Open: Construction.ubk
When you know what page you need, its easy to get
there. I know bevel siding is on page 458 of the
Insurance costbook. So lets open that costbook and go
to page 458.
Theres a button here with P A G E on it.
But thats not what we need. We need costbook page, not
estimate page.
This is the one. Ill click and type the page number, . page
458. . .
and click on OK.
All right. Im on 458
But I dont see any bevel siding at the top of the page. So Ill
scroll down a little.
Its s right here
10
Action
Dialog
1
Beginning Screen: Costbook
Window at INSUR.UBK page 458
with mouse cursor on the Save
button.
Also Open: Estimate1 and
Construction.ubk
11
Action
Dialog
1
Using the Slide Bar #31
See Also: Copy, Paste
Beginning Screen: Estimate
Window with Just Testing.est on
page 1.
Also Open: Estimate1 and
Construction.ubk and
Insurance.ubk
12
Action
Dialog
1
Its gone.
13
Action
Dialog
1
Pasting and Inserting #33
See also: Paste, Copy. Beginning
Screen: Split Window at
Insurance.ubk page 393 and Just
Testing.est at page 1
Also Open: Construction.ubk
Any time you copy and paste costs, you have to type a
quantity. While youre in that estimating box, you have a
chance to make changes before pasting. Ill click on the
remove line again. Then copy and paste it to the estimate.
And paste.
I'll type the quantity of 1.5 in the quantity box.
If I clicked on OK now, these costs would be copied to the end
of estimate. Weve done that already. Ill press Tab and then
take a second to look at the changes we could make here.
I could make changes in the - - Measurement, - - - Craft
Code, - - - Hourly Wage, - - - Man-Hours, - - - Material Cost, - - Labor Cost, - - - Equipment Cost - - - Title - - - or
Description. And if you havent entered a cost in any other
box, you can type a figure in the Total Cost box.
The total gets filled in automatically if you have any labor,
material or equipment costs. But if you have only a lump sum,
like a quote from a contractor, all cost boxes are empty and
you can fill in the total box.
This is the Extended Costs column.
Its the cost for all units. The cost each times the number of
units.
Ill click on Cancel because weve already pasted these costs
to our estimate.
Most of the time youll have just one estimate on the screen.
When I click on the Estimate Window button, Just Testing is
all you see.
14
Action
Dialog
1
Reorganizing the Screen
Beginning Screen: Split Window
Just Testing.est , Stillwel.est is
also open. Construction.ubk and
Insurance.ubk
But you can open several estimates at once. There are good
reasons to have several estimates open. Ill show you that in
the next frame. In this frame, Ill open a second estimate.
Right now, only Just Testing is on the screen.
To open another estimate, click on File and Open.
Now Ive got a two estimates open. But only one is on the
screen.
This is the Pollard estimate. To see a list of open estimates,
even those not displayed, click on Window on the menu bar.
We have three estimates and two costbooks open.
Lets switch back to the Stillwel estimate.
OK. Heres Stillwel again.
Now Ill go back to Pollard.
And now back to Just Testing.
Switching back and forth between estimates is easy. Now lets
do some copying in the next frame.
15
Action
Dialog
1
Copy from Estimate to Estimate
#36
See also: Copy, Paste, Open
Several Estimates, Changing a
Cost Line
Beginning Screen: Estimate
Window Just Testing at page 1
Also Open: Stillwel.est ,
Construction.ubk and
Insurance.ubk
Were going to copy about fifty lines of costs from the Stillwel
bid to Just Testing. That saves lots of time. I'll select the
Stillwel estimate.
The first step is to select what we want to copy. Ill find the
beginning of the rough carpentry section.
Now Ill click at the left end of the first rough carpentry line we
want to copy.
Holding the shift key down, Ill press the down arrow key until
Ive selected all the rough carpentry costs in the Stillwel job.
OK. Ive got all rough carpentry selected. Now Ill click on
copy.
OK, all these carpentry costs are in the Windows clipboard.
The next step is to find where they belong in the Just Testing
estimate. Ill click on Window - - - and then on the Just Testing
job. .
Now Im in the Just Testing estimate.
Ill paste these rough framing costs at the end of the estimate.
When I right-click and select Paste at Estimate End, the whole
section gets copied. .
Ive just pasted about 50 lines from the Stillwel estimate into
Just Testing.
That can save hours of estimating time. But theres one more
step. Adjusting the quantities. The framing quantities on most
jobs will be different. And thats our subject in the next frame.
16
Action
Dialog
1
paste, like we've just done. Even better, create a template
estimate that includes all the work you do most often.
That way you never have to start from scratch. Open the
template, make a few changes, save under a new name and
print it out again.
Template estimates are like having a cookie cutter. You can
stamp out new estimates one after another.
17
Action
Dialog
1
File Type for Estimates #38
See also: Open an Estimate,
Open an Estimate Backup, Save
As
Beginning Screen: Stillwel Also
Open: Construction and
Insurance.ubk
Be ready to show the following
backup estimates:
18
Action
Dialog
1
Other options in the Print dialog box depend on the printer
youve got. Click on Properties to see other printers installed
and the options available.
We dont need that now, so Ill click on OK to print the Stillwel
estimate.
19
Action
Dialog
1
Printed Estimates #41
See also: Print the Current
Estimate, Make Estimates Easier
to Read, Print Preview, Print
Setup, Percent Changes,
Examples, Double Space Lines,
Show Unit Costs, Markup, Tax
Rates
Beginning Screen: Estimate
Window with last 20 lines of
Stillwel.est Be sure to set the
following:
Overhead 15%
Profit 10%
Tax 7.25% on material only
Also Open: Construction.ubk and
Insurance.ubk
20
Action
Dialog
1
Stillwel.est page 8.
Also Open: Insurance.UBK
21
Action
Dialog
1
Show Unit Costs #44
See also What Is Not Pasted,
Options
Beginning Screen: Estimate
Window Stillwel.est at page 9.
Also Open: Construction.UBK.
Save As #45
See also: See File Type for
Estimates, Search for Help on,
Save Every 10 Minutes, Save
With a New Name, Save to a
Different Disk, Exporting an
Estimate.
Beginning Screen: Estimate
Window with Stillwel.est page 8
Also Open: Construction.ubk and
Insurance.ubk
22
Action
Dialog
1
The A drive has a disk with no
estimates.
Also Open: Construction.ubk and
Insurance.ubk
23
Action
Dialog
1
Save in a Different Format #47
See also: Exporting an Estimate,
Export to Word Processing, Export
to a Spreadsheet, Export & Import
With the Clipboard
Beginning Screen: Estimate
Window with Stillwel Upgrade.est
at page 8. Excel is on the C drive.
Also Open: Construction.ubk and
Insurance.ubk
24
Action
Dialog
1
Note that National Estimator puts numbers, not formulas, in
spreadsheet cells.
If you revise costs after exporting to a spreadsheet, add
formulas that compute new row and column totals.
25
Action
Dialog
1
Export to Word Processing #50
See also: Save As, Export to a
Spreadsheet, Exporting an
Estimate, Export & Import With the
Clipboard, Search for Help on.
Beginning Screen: Estimate
Window with Stillwel.est page 1.
Word 6 is also running.
Also Open: Construction.UBK
and Insurance.UBK
26
Action
Dialog
1
Switch User Costbooks #52
See also: Default Costbook, Open
a Second Costbook, Changing a
Costbook, Migrating User
Costbooks, New User Costbook,
User Costbooks
Beginning Screen: Costbook
Window with Room Additions at
softwood flooring. Default name
UBK files for all 6 of Craftsman's
major costbooks should be on My
Documents. Construction,
Insurance, Paointing, Plubming,
Electrical, Repair.
Also Open: Stillwel.est and
Insurance.ubk
27
Action
Dialog
1
Updates #54
See also: New User Costbook,
Migrating User Costbooks, Switch
User Costbooks, Changing a
Costbook, User Costbooks..
Beginning Screen: Costbook
Window with Construction.UBK.
Also Open: Stillwel.est and
Insurance.UBK
Options #55
See Also: Default Costbook
Beginning Screen:
Construction.UBK and
Insurance.ubk
28
Action
Dialog
1
Then click on File, Print Topic and Print.
Delete an Estimate #58
See also Deleting Other File
Types
Beginning screen:
Construction.UBK
29
Action
Dialog
1
starting this event:
Craftsman Construction
251 Ashdale Avenue
Box 6500
Fairfield, FL 33456
567-558-1557
http://CraftsConst.Com
These settings are in Print Setup,
Company Info. Set your computer
date to todays date in the year
2003. The form title is set to
Estimate in Print Setup. Zoom to
75% so the form fills the screen.
Job name is Room Addition, job
number is 547, markup is "At End"
I could print this estimate and send it to Bill just the way it is.
But your customers dont need to know the cost of every nut
and bolt in the job.
And they certainly dont need to know your markup.
Job Cost Wizard lets me show and hide what I want and
prints a nice looking bid or invoice. So I'll click on File and
Send to JCW.
Here's the Stillwel estimate in Job Cost Wizard. I'll push the
page up so you can see more.
The format is a little different. Instead of material, labor and
equipment in columns, costs are in rows.
All the descriptions are here.
These costs are subtotals from the estimate.
Otherwise, its about the same as our Stillwel estimate.
If the estimate in Job Cost Wizard doesn't fit your screen, set
the percentage of zoom. For 640 x 480 resolution, 75% in the
zoom window is about right.
Click and drag the vertical slide bar at the right of your screen
to scroll down the page.
This is page 1 of a ten-page estimate.
Turn pages by clicking on the Previous Page or Next Page
buttons.
To go to any page, just type the number and press Enter.
This is the last page, 10 of 10.
Here's overhead and profit in the job.
I'll drag the slide bar to the bottom of the page.
30
Action
Dialog
1
Jasmine Creek Homes
Box 22917
417 River Road
Fairfield, FL 33456
You can change the title of this form and your company name.
That looks OK to me.
You've got a couple of choices here for the title.
Click on Custom and you can type in any title for this form.
Now this is an Alternate Bid. [Pointing].
31
Action
Dialog
1
Details: Show All #64
See also: Details: Subtotals Only,
Stillwel estimate in Job Cost
Wizard with Subtotals only
displayed
On some jobs you may want the invoice to show every cost
rather than just subtotals. Job Cost Wizard can do that. Here
we're showing only subtotals.
To make a change, Ill click on the Detail button.
Subtotals Only is checked for all four cost categories.
Let's change that to show all material, labor and equipment
costs.
Can you see the difference? All the costs are right there for
everyone to see.
And if you export to QuickBooks, every material cost will be
on the QuickBooks item list. That's going to be overkill for
most jobs. I'm going back to "Subtotals only"
That's better.
32
Action
Dialog
1
Mark Up Every Cost Item #66
Beginning Screen: Stillwel page 2
in Omit Work descriptions mode.
Markup is "Every Cost Item."
QuickBooks lets you use nearly any account names. Job Cost
Wizard does the same. You select account namesin the
Account Names dialog box.
Were using the default account names. These are fine for us.
But you can enter any account name. If you want account
names used in Contractors' Guide to QuickBooks Pro, click
the big button.
I'll reset to the defaults.
33
Action
Dialog
1
Box 6500
Fairfield, FL 33456
567-55-1557
http://CraftsConst.Com
Details should be "Subtotals Only"
with no check mark beside "Show
Subtotals Only" and Markup
should be "At End of Estimate."
lots of time. I'll show you. First, let's go back to Job Cost
Wizard.
I'll reset to show work descriptions.
Notice that this is our estimate number 547. Let's save this
estimate to QuickBooks Pro. I'll click on the Save File button.
Notice that I'm already in the QuickBooks Pro folder.
I'll export as an estimate because I'm using QuickBooks Pro.
And click on Save.
OK. We're done. Now let's open this estimate in QuickBooks.
34
Action
Dialog
1
Notice that the amount on the first cost line got filled in when I
clicked on the second cost line.
I added a penny to the last item, so I'll subtract a penny this
time.
I'll continue clicking and changing by a penny until every cost
is extended to the Amount Column.
Filling in the Amount column isn't essential. But it guarantees
that reports show estimated costs correctly.
I'll show you this report a little later.
Progress Billing in QuickBooks
#71
Begins at: Estimate 547 in
QuickBooks -- Amount column
filled in throughout the estimate.
Opens at the top of the Stillwel
estimate. Progress Billing should
be turned off at the beginning. Use
the Craftsman Construction
QuickBooks company file.
We've sent out the first invoice in the Stillwel job. Let's see
35
Action
Dialog
1
Begins at: QuickBooks Navigator.
The date is 2003
36
Action
Dialog
1
item described.
I'll click on the down triangle under Customer:Job and select
Bill Stillwel's job.
This amount is not billable to your customer. So click on the
icon representing an invoice to put a red X over the icon.
One check can cover items in several cost categories and
even costs on several jobs. But I'm done here so I'll click on
Save and Close.
Creating Payroll by Cost
Category #76
In QuickBooks Craftsman
Construction Company showing
estimate 547Job Estimates vs.
Actuals Detail .
37
Action
Dialog
1
1
38