Configuring Message Control and understanding how Message Control works

By Krunal Raichura, Accenture Services Pvt. Ltd


Most SD and MM process use Message Control. The concept of Message control is to generate
and manage outputs from an application and control their timing and medium of exchange.
Below are the details for configuring the message control and understanding how message
control works.
Configuring Message control:
Message Control Components:
Communication Structure:
The communication structure passes application information to the Message control. The
communication structure for output determination uses the naming convention as KOMxByy,
where x can be K (header structure) or P (Item structure), and yy is two character application
ID.
The two character application ID can be found from the NACE transaction depending on the
application.

The Procedure

A Procedure defines a set of possible outputs for an application. A procedure is assigned a six
character name. Several procedures can be defined for an application but only one can be
configured as active.
A list of procedure can be seen in NACE transaction for the required application.

A procedure has three main attributes:


- A List of output types set of outputs that are possible for an application
- A Requirement field
- A manual flag

Set of Outputs those are possible for applications are listed in the output types.

Manual Flag is set if the output has to be selected by the user manually instead of selecting
automatically.
For Sales, Procedures can be assigned to Sales document type using V/43 transaction.

Preconditions are captured in Requirements. These conditions are written in VOFM transaction.

We can write the conditions for the Requirement selected from the above list by creating
routine which will start from 900.

ABAP code can be written in the routine for checking the condition.

Output Type:
An Output type defines the characteristics and attributes of the output itself.
Output type can also be selected from the NACE transaction.

Access sequence is the set of business rules for proposing an output type.
If the flag Access to condition is set then the medium and timing are determined from the
condition records using access sequence.
If the flag is not set then the medium and timing data is taken from the customer master.
CannotBeChanged determines whether the output can be edited.
Multiple issuing determines whether multiple outputs are permitted.
Access Sequence:
Access sequence defines a sequence in which the business rules are checked for proposing an
output type. A business rule is checked by comparing the values passed in the application data
with the values defined in the condition records of the condition table. If a match occurs the
business rule is considered satisfied. After a business rule is satisfied the output values from
the condition records are used for the output type.

The exclusive or inclusive strategy specifies whether the system should exit after the first
match of the business rule against the condition record or should continue to process other
business rule in the access sequence.
The reason for an inclusive strategy is to have an output type proposed multiple times.
However, one of the attributes (partner function, partner number or language) must be
different. The system does not allow two output types to have identical values.
Condition Tables:

The condition table specifies the key field for a business rule. You use this key to access the
condition records for output values such as output medium, partner function, partner number,
output language and output time for the message.
If the standard condition tables supplied in the system do not meet your requirements, you can
create new condition tables.
Condition Records:
Condition records are inserted in the condition tables. Condition records contain the actual
business data against which the business rules are checked to propose an output. They are
considered master data maintained by customer.
You can create condition records for the each application in NACE transaction by clicking the
condition record button for the required application.
You will have to select the business rule for which condition record is to be maintained.

Specify the values for the key fields and maintain the output medium, output timing, partner
number and partner function for each record and save the entries.
Message Control is a three step process:
1.
2.
3.

Output proposal
Output editing
Output processing

Output Proposal

When an application is created or changed, after saving the application data the
communication structure is filled and is passed to the Message control along with the
application id and procedure.
The various outputs defined in the procedure are processed one at a time. The output marked
as manual will be processed manually by the user.
The requirement, if specified for an output type is executed to check if the output meets the
requirement. If the requirements are met then further checking continues.
If the conditions are not met then the next output type will be processed from the list.
The short listed output types are checked for the access condition flag. If the flag is not set
then the output medium and timing are determined from the customer master data.
If the access condition flag is set then the processing continues for determining the output
medium and timing. For these output types the access sequence associated is access for
various business rules and determines which of the business rule is satisfied. The values from
the communication structure are checked with the values maintained in the condition tables.
Output Editing:
After the output proposal process is completed, the list of proposed outputs displays on the
output control screen of an application as shown below.

To reach he output control screen we can got for Extras ->Output->Edit for sales order or by
Goto->Messages for Purchase order.
The initial status of these outputs will be 0 (Not Processed) which is displayed as yellow light.
The processed outputs will be displayed as green light.
For EDI, the partner number in the proposed output is validated against the partner profile
entry.
The flow chart below explains the Output proposal procedure.

Output Processing:
After the final selection of the output is done and the application document is saved, entries
are created in the NAST table with application ID, Application document number, output type,
output medium, output timing and Status code.
If the output is not processed the Status code will have values as 0 (Not processed).
The entries in the NAST table are processed by RSNAST00 program. If the entries whose timing
is set to immediately, the program will immediately process those entries. For other entries
you will have to schedule the program RSNAST00.
The RSNAST00 program check the TNAPR table for each entries from NAST table and processes
the program associated with the output medium in the TNAPR table.
For EDI a Standard routine EDI_PROCESSING exist in RSNASTED program.
The EDI_PROCESSING routine reads the Message control record in the partner profile and
determines the process code.
The process code will be having a Function module which will be having the standard interface
for its input and output parameters. The function module will read the application document
data and will format the data into the idoc format.
The idoc data and the control record from the function modules received through the output
parameters will be used by the EDI_PROCESSING program to convert it into physical Idoc.
The complete Outbound process with Message control is as shown below:

The setting of the Output mode field in the partner profile is read to determine the timing for
dispatching the idoc.

If the mode is set to Transfer Idoc immed. then the idoc is immediately passed to the
operating system and if the mode is set to Collect Idoc then the Idoc is not immediately
passed to the operating system until the RSEOUT00 program is executed explicitly.
If the flag for Start subsystem is set then the subsystem program name is read from port
definition and the subsystem program is started.