Beruflich Dokumente
Kultur Dokumente
PROJECT OVERVIEW:
Name: POSIE Project
Steering Committee Names: Bill Smith, Director, IT, Julie Compton, VP Manufacturing, Pete Stein, VP
Technology, Tejah Singh, VP Finance, James Carmen, President & CEO
Steering Committee Approvers: Bill Smith, Julie Compton, Tejah Singh
Project Owner: Bill Smith, Director, IT
Executive Sponsor: Julie Compton, VP Manufacturing
PROJECT DESCRIPTION
The merger of three well-established supermarket chains, Alpa, Beta and Gamma resulting in the
formation of Supersave, calls for a major project to be implemented. Supersave stores are in need of a new
system that enables the organization to carry out business in various parts of the world, specifically Europe
and Russia. Subdivided into five categories, the project coined POSIE, incorporates the development of the
system to be installed in each Supersave store location, development of systems within the server locations
(Europe), revamping 119 existing stores, constructing 21 new stores and the roll out of a store system to 140
store locations.
The project, when complete will allow real-time stock and item movement data to streamline essential
information from its store operations to its distribution and manufacturing centers. In addition, both back-end
and front-end applications (electronic point of sale) through the development of a new store system will create
effective and efficient customer service as well as timely execution of administrative procedures. With the
timeline set to its target, the project will ultimately place the Supersave brand in markets around various parts
of the world with a competitive edge through its innovative technology.
Objective
Number of resources
required
1
1
Duration (months)
Salary
24
20
$350 000
$180000
22
$240000
15
$170000
5
3
12
3
$140000
$60000
Estimate
d
Register
cost
($300)
Estimated
cost of
scanner
($100)
Estimated
upgrade
back end
system to
UNIX
platform
($100 per
store)
Estimate
d cabling
costs
($200
per
store)
Labor costs
(including
analysis,
equipment
installation
costs, testing
and
enablement)
Alpha
Register
cost:
345*$30
0
=$1035
00
Scanner
cost:
345*$100
=$34500
UNIX
upgrade
cost:
20*$100
=$2000
Cabling
cost:
20*$200
=$4000
$285000 (Sum
of labor
divided by 4)
Register
cost:
3160*$3
00
=$9480
00
Scanner
cost:
3160*$100
=$316000
UNIX
upgrade
cost:
100*$100
=$10000
Cabling
cost:
100*$20
0
=$20000
$570000 (Sum
of labor
divided by 4
multiplied by
2*)
17 stores
(approx. 15
lanes)
Total
$429000
3 new stores
(30 lanes)
Number of
lanes: (17* 15)
+
(3*30)=255+9
0
=345 lanes
Beta
92 stores
(approx. 30
lanes)
8 new stores
(50 lanes)
Number of
lanes: (92* 30)
+
(8*50)=2760+
400
=3160 lanes
*Multiplied by
2 because
Beta requires
more work
$1864000
Gamma
10 stores
(approx. 30
lanes)
Register
cost:
800*$30
0
=$2400
00
Scanner
cost:
800*$100
=$80000
UNIX
upgrade
cost:
20*$100
=$2000
Cabling
cost:
20*$200
=$4000
$285000 (Sum
of labor
divided by 4)
$611000
$129150
0
$430500
$14000
$28000
$1140000
$2904000
10 new stores
(50 lanes)
Number of
lanes: (10* 30)
+
(10*50)=300+
500
=800 lanes
Total
MAJOR RISKS
The major risks of any given project can be both external and internal. External risks include
governmental laws and market conditions. Internal risks pertain to the company and project proposal. The
probability and impact of these risks have the potential to terminate the project and thus, a risk assessment is
completed at the start of the project by the steering committee approvers while risk management is completed
throughout the duration of the project in the form of monthly status reports from the director of IT.
Internal Risks
Probability
(High, Medium,
Low)
Impact
(High, Medium,
Low)
Budget
-Economic conditions
Medium
High
Schedule
-Managing scope creep (Gantt charts, Critical path method)
-Penalty: late installation = CAD $20,000 per day
Medium
High
Employee Resistance
-Providing training courses
-Utilizing techniques such as phased/parallel adoption
Medium
Medium
Technology Requirements
-Implementing a companywide system of up to 50 checkout lanes in 1
store; efficiency/speed
-Capability of adding on additional checkouts 50 +
Medium
Medium
Store Capacity
-Ceiling/walls/floor space for cables and power for present and
potential future checkout expansions
Low
Low
Management
Employee Resistance
Technology Requirement
Schedule
Budget