Beruflich Dokumente
Kultur Dokumente
Design Manual
List of Figures
Figure 3.8.1-1 Prestress Beam Protection. .....................................................................................2
Figure 3.8.3-1 Kinematic wave formulation Chart #1 ....................................................................9
Figure 3.8.3-2 Scupper Requirement Nomograph ........................................................................10
Figure 3.8.3-3 Bridge Deck Drainage (8" x 6" Scuppers) ............................................................15
Figure 3.8.4-1 Chart #2 - Velocity in triangular gutter sections ...................................................19
Figure 3.8.4-2 Chart #7 - Grate inlet frontal flow interception efficiency ...................................20
Figure 3.8.4-3 Chart #8 - Grate inlet side flow interception efficiency ........................................21
Figure 3.8.4-4 P-1-7/8 and P-1-7/8-4 grates .................................................................................22
Figure 3.8.4-5 Example #2 - Grate Inlet Capacity ........................................................................24
Figure 3.8.4-6 Bridge Deck Drainage (1x 3 Grates) ..................................................................25
Figure 3.8.5-1 Inlet detail showing formed blockout under inlet box ..........................................27
Figure 3.8.5-2 Example: Grate Inlet on Steel Girder Bridge ........................................................28
Figure 3.8.5-3 Example: Grate Inlet on Steel Girder Bridge ........................................................29
Figure 3.8.5-4 Example: Grate Inlet on Steel Girder Bridge ........................................................30
Figure 3.8.5-5 Example: Grate Inlet on Prestressed Girder Bridge ..............................................31
Figure 3.3.5-6 Example: Scupper on Steel Box Girder Bridge ....................................................32
Figure 3.3.5-7 Example: Scupper on Prestressed Bridge .............................................................33
Figure 3.3.5-8 Example: Scupper on Steel Girder Bridge ............................................................34
Figure 3.3.5-9 Example: Scupper on T-Girder Bridge .................................................................35
Figure 3.3.5-10 Typical Drainage System Details ........................................................................36
Bridge Section
3 - 8 - i
Design Manual
Disclaimer:
Disclaimer:ThisdocumentisprovidedforusebypersonsoutsideoftheKansasDepartmentof
Transportationasinformationonly.TheKansasDepartmentofTransportation,theStateofKansas,its
officersoremployees,bymakingthisdocumentavailableforusebypersonsoutsideofKDOT,donot
undertakeanydutiesorresponsibilitiesofanysuchpersonorentitywhochoosestousethisdocument.
ThisdocumentshouldnotbesubstitutedfortheexerciseofapersonsownProfessionalEngineering
Judgement.Itistheusersobligationtomakesurethathe/sheusestheappropriatepractices.Any
personusingthisdocumentagreesthatKDOTwillnotbeliableforanycommercialloss;inconvenience;
lossofuse,time,data,goodwill,revenues,profits,orsaving;oranyotherspecial,incidental,indirect,or
consequentialdamagesinanywayrelatedtoorarisingfromuseofthisdocument.
U
TypographicConventions:
Thetypographicalconventionforthismanualisasfollows:
NonitalicreferencesrefertolocationswithintheKDOTBridgeDesignManuals(eithertheLRFDorLFD),
orHyperlinksshowninred,asexamples:
x
x
Section3.2.9.12Transportation
Table3.9.21DeckProtection
ItalicreferencesandtextrefertolocationswithintheAASHTOLRFDDesignManual,forexample:
x
Article5.7.3.4
ItalicreferenceswithaLFDlabelandtextrefertolocationswithintheAASHTOLFDStandard
Specifications,forexample:
x
LFDArticle3.5.1
Bridge Section
3 - 8 - ii
Design Manual
Bridge-deck drainage systems are a continual maintenance problem; therefore, the designer
should eliminate drains on bridges when they are unnecessary. A drain-free bridge may be
achieved by using open bridge rails. Where curbs are required, the designer can take advantage of
the shoulder section provided on most of todays bridges by using it as a gutter. If the runoff coming to the bridge is removed before it runs onto the bridge, the hydraulic capacity of the shoulder
may be great enough to eliminate the need for bridge drains on short bridges.
Inlet structures located immediately off the end of the bridge should be designed in collaboration
with the road section to determine when and where they are needed. This coordination also helps
to avoid conflicts with other bridge or roadway structures such as guard fence posts which could
interfere with the drainage flow.
Short continuous span bridges, particularly overpasses, may be built without inlets on the bridge
and the water carried downslope by a flume or inlet structure near the end of the bridge. An open
flume down the sideslope or foreslope is preferred because the concrete flume is more accessible
for maintenance and repair.
On long bridges, drainage should be provided by scuppers or grates of sufficient size and number
to adequately drain the gutters and limit the encroachment of water in the driving lanes.
On bridges containing open-type expansion devices, drains should be located to pick up as much
drainage as possible before it crosses the device. Glands shall be placed in finger devices to carry
drainage; however maintenance cleaning of these troughs and other inlets and grates may be
limited. Drainage design and details should provide the necessary hydraulic capacity with a
minimum of required maintenance. Conservative assumptions of hydraulic capacity is encouraged to provide drainage operation based on limited maintenance. (50% inlet efficiency is a good
rule.)
Coat the top of Prestressed Beams with Substructure Waterproofing Membrane where the deck
drains are located to prevent leaks from compromising the member.
Bridge Section
3 -8 - 1
Design Manual
Bridge Section
3-8- 2
Design Manual
3.8.2 Design/Procedures
3.8.2.1 Design Spread and Rainfall Frequency
The purpose of the bridge-deck drainage system is to remove rainfall-generated runoff from the
bridge deck before it encroaches onto the traveled roadway to the limit of the design spread, (T).
For Kansas Interstates and Freeways (A and B routes) with two or more lanes in one direction,
drains may be spaced so the top width of flooding (T) is preferably not more than 10 feet but in no
case shall encroach more than one half of a thru lane. For urban areas where high volume rush
hour traffic must be considered, the designer should consider a design spread (T) which will
exclude all lanes from flooding. For two lane B, C, D and E routes, the traffic lanes in each
direction should not be restricted to less than 10 feet. On superelevated bridges, the depth of flow
in the gutter should be restricted to 9 inches.
The design of A and B routes should be based on a 10 year frequency storm. ForC, D
andE routes, a 5 year frequency storm is adequate.
Use a 50-year frequency storm for all bridges located in the sag vertical curve where ponded
water can be removed only through the storm-drain system.
cia
Q
c
i
a
=
=
=
=
The rainfall intensity used in the Rational Equation is selected for a duration equal to the time of
concentration for a particular drain. The time of concentration ( t c ) is the time required for the
runoff to reach the drain from the furthest point of the drainage area.
To estimate t c , apply the Kinematic Wave equation:
0.6 n 0.6
t c = 56L
-------------------------i 0.4 S 0.3
Bridge Section
3 -8 - 3
Design Manual
Where:
tc
L
n
i
S
=
=
=
=
=
The solution is one of trial and error. Estimate the location of a drain to get L and select i for an
assumed 5 minute storm from the Rainfall Intensity Tables for Kansas. (If Kansas Rainfall Intensity Tables are not available, refer to Appendix A of HEC 12 (1984) for development of intensityduration-frequency curves using NWS HYDRO-35 maps.) Reiterate until the assumed storm
duration equals the computed t c . If t c is less than 5 minutes it is KDOT policy to use the 5 minute storm for the design of bridge drains. The maximum intensity need not exceed 6 inches per
hour. (Experience has shown when the intensity of rainfall exceeds 6 inches per hour, a drivers
vision becomes substantially obscured because the capacity of the windshield wipers is exceeded.
Operational speed is therefore voluntarily reduced and the probability of hydroplaning is
less.)(Ref.1)
Bridge Section
3-8- 4
Design Manual
1/2
8/3
K Sx S T
Q = ----------------------------------------n
Where
K
Sx
S
T
n
Q
=
=
=
=
=
=
a constant (0.56)
cross slope (road crown slope), ft./ft.
road grade, ft./ft.
top width of flow, feet
0.016
flow rate, cubic feet/second
and
nQ
T = -------------------------------5/3 1/2
K Sx
S
3/8
References:
For additional information on pavement drainage refer to:
1)
2)
3)
4)
Bridge Section
3 -8 - 5
Design Manual
2)
Problem:
Design scuppers in Area I for a 500-foot interstate bridge located in Johnson County, Kansas, based upon the following information:
Bridge Section
3-8- 6
1.
Design Manual
Find the distance from the PC to the high point of the curve.
a)
b)
k (a constant) =
A- = ------------1.5 - = 0.075
-----2L
2 ( 10 )
(L in stations)
c)
d)
A
---- = 1.5
------- = 0.150
L
10
g
+ 1.00 - = 6.667 Sta.
Location of high point: xt = -----1- = -------------------2k
2 ( 0.075 )
P.C. Sta. =
95 + 00
+ 6 + 66.7
101 + 66.7 = Sta. of high point
Allowable spread:
= + 10 - (0.150)(97.50 - 95.0)
= 0.625% = .00625 ft./ft.
Bridge Section
3 -8 - 7
2.
Design Manual
Need to determine Rainfall Intensity (i) which depends on the storm duration
(which is equal to the time of concentration) and to the recurrence interval.
The time of concentration may be estimated from Chart 1, Figure 3.8.3-1 Kinematic wave
formulation Chart #1or from the Kinematic Wave Equation:
0.6 n 0.6
t c = 56L
-----------------------i 0.4 s 0.3
Assume tc = 5 min., then for Johnson Co. and a 10-year storm, i = 9.11 in/hr. (from Kansas
Rainfall Intensity tables. 1981)
@EWS:
0.6
0.6
L=
=
=
24393.6
------------------Cn
Sx S T
--------------------------------iw
1.67
0.5
2.67
( 0.0156 ) ( 0.00625 ) ( 10 )
------------------------------------------------------------------------------6(35.33)
Bridge Section
3-8- 8
Design Manual
Bridge Section
3 -8 - 9
Design Manual
Bridge Section
3 - 8 - 10
3.
Design Manual
2.67
2.67
Find distance to first scupper from high point (where spread reaches 10-0).
Since S is variable;
L = (16.94 x
105 )
1.67
2.67
(------------------------------------------------0.0156 )
( 10 ) - 0.5
S
212
L = 3,590 S0.5
Use trial and error to get distance from high point equal toL from formula.
Station
100+66.7
100+16.7
99+66.7
Distance from
High Point
100
150
200
Computed L
0.0015
0.00225
0.0030
139
170
197
0.0028
190
(Close enough)
187
Bridge Section
3 -8 - 11
Where:
c=
i=
a=
Design Manual
0.9
6.0 in./hr.
WL----------------= drainage area in acres
43, 560
35.33 (L + l 1 )
0.9 (6.0) x ---------------------------------- - 0.14 cfs
43, 560
0.56
also, QR2 = ---------- Sx 1.67 S2 0.5 t2.67
n
=
0.56
------------- (0.0156)1.67 S2 0.5 t2.67
0.016
29.745Q R2
solving for t = -------------------------0.5
S2
0.375
0.375
Bridge Section
3 - 8 - 12
Design Manual
0.375
0.375
The number of scuppers required by the above procedure should be considered a minimum. The final scupper spacing still requires some engineering judgement.
Allowance should be made for the inevitable clogging of scuppers with debris. A factor of
safety of two has been suggested. Scuppers should also be spaced to clear piers and facilitate construction.
Bridge Section
3 -8 - 13
Design Manual
Drainage from scuppers in the end span would fall on the berm so the berm are to be
protected by slope paving, dumped rock or drain troughs.
If drainage cannot be discharged thru vertical downspouts, and a drainage system is
required, it may be more economical to use grates located near piers supporting the downspouts.
Drainage off the end of the bridge needs to be picked up by a grate inlet or by a concrete
flume directing the flow down the side slope.
See Bridge Deck Drainage (8" x 6" Scuppers) sheet, Figure 3.8.3-3 Bridge Deck Drainage
(8" x 6" Scuppers) for final scupper spacing.
Bridge Section
3 - 8 - 14
Design Manual
Bridge Section
3 -8 - 15
Design Manual
Compute Eo:
Eo
Eo
Qw
Q
W
T
=
=
=
=
=
=
for
b)
Qw / Q = 1 - (1 - W/T) 2.67
ratio of frontal flow (flow passing over the grate) to total gutter flow.
flow in width W, cfs
total gutter flow, cfs
width of depressed gutter or grate, ft.
total spread of water in gutter, ft. (max. 10)
W = 2,
W = 3,
W = 4,
Eo = 0.449
Eo = 0.614
Eo = 0.744
Find Rf factor, which is the ratio of frontal flow intercepted to total frontal flow.
Rf = 1 - 0.09 (V - Vo)
V = Velocity of flow in gutter
Bridge Section
3 - 8 - 16
Design Manual
Vo = 3.0
Vo = 3.8
Vo = 4.7
Find Rs factor, which is the ratio of side flow intercepted to the total side flow.
Rs =
1
1 + 0.15 V1.8
Sx L2.3
L = 1,
L = 1.5,
L = 2.0,
Rs = 0.043
Rs = 0.102
Rs = 0.180
Bridge Section
3 -8 - 17
Design Manual
Compute efficiencies for the various grate sizes listed below: E = Rf Eo + Rs (1 - Eo)
L
1
1
1.5
1.5
2
2
x
x
x
x
x
x
Rf
2
3
2
3
2
3
1
1
1
1
1
1
Eo
Rs
0.449
0.614
0.449
0.614
0.449
0.614
0.043
0.043
0.102
0.102
0.180
0.180
0.473
0.631
0.505
0.653
0.548
0.684
Due to the rather flat grades with resulting low gutter velocities, the more efficient grates
are wider, narrow ones. Even though the chart shows the 2 x 3 grate to be the most efficient for this particular example, the 1 x 3 grate appears to be the most cost effective since
reducing the inlet size by 200 percent, only decreases the grate efficiency by 8 percent.
Bridge Section
3 - 8 - 18
Design Manual
Bridge Section
3 -8 - 19
Design Manual
Bridge Section
3 - 8 - 20
Design Manual
Bridge Section
3 -8 - 21
Design Manual
Bridge Section
3 - 8 - 22
2.
Design Manual
Bridge Section
3 -8 - 23
Design Manual
Bridge Section
3 - 8 - 24
Design Manual
Bridge Section
3 -8 - 25
Design Manual
Bridge Section
3 - 8 - 26
Design Manual
Figure 3.8.5-1 Inlet detail showing formed blockout under inlet box
Bridge Section
3 -8 - 27
Design Manual
Bridge Section
3 - 8 - 28
Design Manual
Bridge Section
3 -8 - 29
Design Manual
Bridge Section
3 - 8 - 30
Design Manual
Bridge Section
3 -8 - 31
Design Manual
Bridge Section
3 - 8 - 32
Design Manual
Bridge Section
3 -8 - 33
Design Manual
Bridge Section
3 - 8 - 34
Design Manual
Bridge Section
3 -8 - 35
Design Manual
Bridge Section
3 - 8 - 36