Sie sind auf Seite 1von 2

WEST BENGAL STATE ELECTRICITY DISTRIBUTION COMPANY LIMITED

(A Government of west Bengal Enterprise)


Office of the Regional Manager
Birbhum regional Office
:: Suri : Birbhum ::
Name of the work: Sub-Surface Soil investigation works at the proposed JOYDEB 33/11 KV
sub-station under Bolpur division in the District of Birbhum.
Sl
N
o

ITEMS OF WORK

Mobilization charges of all tools & plants along


With accessories,Labour supervision etc, at site
with necessary shifting etc, complete &
demobilization after completion of work.
Labour for sinking nominal 150-mm.dia casing
pipes in soil except rock for collection of soil
samples as per relevant IS Code upto a depth of
10-mtr.for 3(Theree) nos. boreholes and 30mtr. For one no. borehole below ground level
for bore holes as marked in the actual site
including cost of labour and materials involved
thereof as per direction of the Engineer-inCharge.
a) For 4 nos. bore hole 10 m depth.
Collection of disturbed & undisturbed soil
samples in seem less thin tube as per relevant
IS Code (latest revision) With necessary
precaution as per direction of the Engineer inCharge including labour and cost of all
materials.
a) Un-disturbed samples
b) Disturbed samples
Conducting standard penetration test in all bore
Holes by split spoon samples.
Conducting laboratory tests on the soil samples
obtained from the boreholes at the contractors
laboratory at his cost and expenses for the
determination of the following as per relevant
IS Code (latest revision) and submission of
detailed report thereon.
a)particle size distribution .
i)By sieve analysis
(for disturbed samples)
ii) By hydrometer analysis

4
5

Quantity Unit

L/S

One
job

40

Metre

16-Nos
16-nos

No
No

16-Nos.

No.

16-Nos

No

Rate per
Unit(RS)(To
be quoted)

Amount(RS)

(for undisturbed samples)


b) Natural moisture content.
c) Specific gravity, degree of saturation &
relative density.
d) Bulk density and dry density.
e) Void ratio.
f) Liquid limit and plastic limit, shrinkage
limit & degree of shrinkage.
g) Unconfined compression test of undisturbed
clayey sample.
h) Tri-axial shear tests (un-consolidated
Undrained).
i) Consolidation test and evaluation of
settlement.
j) permeability test.
k) Chemical test of soil.
l) Chemical test of water(PH, Chloride,
Sulphate & Others as necessary).
m) Differential free swell index.
n) Free swell index test.
o) Swelling Pressure test.

16-Nos
16-Nos

No
No

16-Nos
16-Nos
16-Nos

No
No
No

16-Nos
16-Nos

No
No

16-Nos

No

16-Nos
16-Nos
16-Nos

No
No
No

16-Nos
16-Nos
16-Nos
16- Nos

No
No
No
No

Submission of test results & reports in 6 (Six)


complete sets including drawings as required
and providing therein discussions on different
test results, the types of soil deposits and
recommending foundation different
structure/building etc. and also including the
type of foundation selection, including
swelling, pressure.
Topographical survey of the land marked for
JOYDEB 33/11 kv sub/station and preparation
of drawing showing all permanent structures
/building and existing roads .

L/S

One
job

L/S

One
job

Total (In figures) Rs. =


(In words) Rupees :