MICROHYDRO DESIGN AIDS 2010 for Microsoft Excel 2003

Small Hydropower Promotion Project (SHPP)/GTZ


By Mr. Pushpa Chitrakar

Worksheets

Collaboration Partmers

Conductivity
Hydrology
Weir
Side Intake
Bottom Intake
Headrace Canal
Headrace Pipe
Settling Basin
Penstock & Power
Loads on Anchor
Anchor Block Stability
Turbine
Electrical
Machine Foundation
Transmission Line
Loads and Benefits
Costing & Financial Analyses
Utilities
Version: 2010.04

SHPP/GTZ, Nepal

Email
Web
Entec AG, Switzerland

Email
Web
Feedback
Pushpa Chitrakar

pushpa.chitrakar@gmail.com
Help

Online Manual
Drawings
List of Reference

Small Hydropower Promotion Project 2006

Kathmandu, Nepal

Discharge Measurement by Conductivity Meter


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

06-Apr-2016

2006.05
Golmagad SHP
Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

Project
Developer
Consultant
Designed
Checked
Meter
Salt
Given k

HANNA Instruments (HI 933000)

Iyoo Noon

Salt Const. (k)


Wt. of Salt
Nr of data
Baseline conductivity
Sum of readings
Effective Area
Discharge

Water temp:
1.8 Time intervals

11 deg C
5 sec

1.8000
1580 gm
1795 gm
91
106
24
24
3433
3997
6245
7265
455 l/s
445 l/s
Average Discharge

400 gm
70
25
2062
1560
462 l/s

0 gm
1
0
0
0
0 l/s
454 l/s

Discharge Measurement by Conductivity Meter: Golmagad SHP


80
70

Salt
Salt
Salt
Salt

60
Conductivi
ty
50

=400gm, A ef f =1560
=1580gm, A ef f =6245
=1795gm, A ef f =7265
=0gm, A ef f =0

mS

40
30
20
10
0

Discharge Measurement by Conductivity Meter: Golmagad SHP


0

50

100

150

200

250

rge = 453.89 l/s

300
350
400
450
Time(sec)
Salt =400gm, A eSalt =1580gm,
Date= 2010/10/5, 11de g C, HANNA Ins trum e nts (HI 933000), Iyoo Noon, k =1.8, Ave . Dis charge = 453.89 l/s

500

550

600

A efSalt =1795gm,0gm, A eff =0

HYDROLOGICAL CALCULATIONS FOR UNGAUGED MHP RIVERS


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances:2,2,4, 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project:

Upper Jogmai SHP

Developer
Consultant
Designed
Checked

Kankai Hydropower P Ltd


EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

06-Apr-2016
2006.05

INPUT
River name :
Location :
Measured flow for MIP method l/s:
Month and day of flow measurement:
MIP region (1 -7) :
Area of basin below 3000m elevation A3000 km2 :

Chhyota Khola
Barand, Sertung VDC 2, Dhading
80
March
23
3
1.5
80
5%
10%

Turbine discharge Qd l/s:


Water losses due to evaporation/flushing/seepage % of Qd :
Downstream water release due to environmental reasons % of Q lowest :

OUTPUT
MIP monthly average discharge
Month
@ river
To plant
January
#NAME?
#NAME?
February
#NAME?
March
#NAME?
April
#NAME?
May
#NAME?
June
#NAME?
July
#NAME?
August
#NAME?
September
#NAME?
October
#NAME?
November
#NAME?

Hydest Flood Flows


Return Period (yrs)

December
Annual av

Q exceedence (month)

#NAME?

2
20
100
Discharges (l/s)
Qturbine (Qd)
Q diverted Qd+Qlosses
Q losses 5% of Qd
Q release 10% of Qlow
Q min required @ river

#NAME?
#NAME?

Flood Discharge (m3/s)


Daily
Instantaneous
1.952
4.197
5.747
16.334
8.987
28.669
Designed
80.000
84.211
4.211
#NAME?
#NAME?

As per MGSP
#NAME?
#NAME?
#NAME?
#NAME?
#NAME?

12

12

Long Term Average Annual Hydrograph of Chhyota Khola river, Upper Jogmai SHP
12

10
MIP Flows

Q design =80 l/s with 12-month exceedence

#NAME?

8
Discharge (l/s)

0
Jan

Feb

Mar

Apr

May

Jun
Months

Jul

Aug

Sep

Oct

Nov

Dec

Design of Stone Masonry Weir


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

06-Apr-2016

2006.05
Upper Jogmai, Ilam
Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

Project
Developer
Consultant
Designed
Checked

Weir Section & Forces @ Normal Condition

4.0
3.5
3.0
2.5

Height ZZ (m)

2.0
1.5
1.0
0.5

0.0
-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

-0.5

XX (m)

-1.0

Foundation and Soil


Foundation on

Soil Coeff of soil at active state (ka)

Allowable bearing capacity Pall (kN/m2)


Coeff of soil at rest (ko)

180 Soil Density (kN/m3)


1 Friction coeff between block and soil m

0.33
20.000
0.5

Weir Geometry
Length L1 (m)
Length L2 (m)
Length L3 (m)
Length L4 (m)
Total length L (m)
Material

0.25
2
1
0.5
3.75
Concrete

Height H1 (m)
Height H2 (m)
Height H3 (m)
Density (kM/m3)
Head above crest during flood, hf (m)

3
1.5
1
22
0.500

OUTPUT
Weight Wi
(kN)

Forces

LA along XX (m)

Moment (kN-m)

Weir
G1
G2
G3
G4

5.500
132.000
16.500
49.500

3.625
2.500
0.833
0.750

19.938
330.000
13.750
37.125

W1
W2
W3
U1

5.000
45.000
5.000
84.375

3.625
-1.000
0.500
-2.083

18.125
-45.000
2.500
-175.781

W1
W2
W3
U1

6.250
61.250
11.250
103.125

3.625
-1.167
0.667
-2.045

22.656
-71.458
7.500
-210.938

S1
S2

1.650
11.250

-0.333
0.500

-0.550
5.625

Normal
205.731
124.125
30.400

Flood
153.648
106.625
40.400

Water (normal conditions)

Water (flood conditions)

Soil

Summantion forces
Sum of moments M (kN-m)
Sum of vertical forces V (kN)
Sum of horizontal forces H (kN)

Overturning: Equivalent distance at which SM acts from critical point


d (m)
1.657
Eccentricity e, (m)
0.218
Allowable eccentricity e all (m)
0.625
Comment on overturning moment
Ok
Bearing
Pressure at base, Pmax
Pressure at base, Pmin
Comments on bearing
Sliding
Factor of safety against sliding, FS sl
Comment of sliding

1.441
0.434
0.625
Ok

44.621
21.579
Ok

48.177
8.690
Ok

2.042
Ok

1.320
Not Ok

Design of Orifice Side Intake


Spreadsheet developed by Mr. Pushpa Chitrakar, Engineering Advisor, SHPP/GTZ

06-Apr-2016
2006.05
Ankhu HEP
Ankhu Hydropower P Ltd
HSEC P Ltd
Neeraj Shrestha
Pushpa Chitrakar

Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project
Developer
Consultant
Designed
Checked

Wall Geometry
Design
Flood Level

Coarse Trashrack
Min 100 thick & 1000 wide
walkway Rcc slab

Orifice (H*B)

Normal
1
river level 3
.

Weir Crest

Gravel Flushing Gate

hbot

h -h
.

h sub

Canal

LS

Fb

River bed

hr

h rf

Gravel trap (if needed)


1:30
Compacted earth/200mm
stone soling

Trashrack calculations
Input

Output
Trashrack coeffieient kt
Bar thickness t mm
Clear spacing of bars b mm
Approach velocity Vo m/s
Angle of inclination from horizontaldeg
Flow deviation deg
Design Discharge Qd cumec
Height of trashrack bottom from river bed ht
Canal invert level (m)

2.4
15.00
75.00
1.00
75.00
90.00
33.670
1.250
890.65

2.4

Headloss due to friction hf m


236.091
Headloss due to bends hb m
0.051
Headloss coeff K 4633.103
Total headloss ht m
236.142
Trashrack coeff, K1 0.8
0.8
Surface area A surface m2
52.287
Vertical height h m
2.250
Trashrack width B m
22.447

Orifice Calculations for (B = 2H or provided) rectangular canal downstream of orifice


Input
Orifice

roof-sha

River
Velocity coeff of orifice c 0.800
0.800
Velocity through orifice Vo m/s
1.5

Crest length L m
Provided Q flood m3/s
Q flood m3/s (Q20 for MHP with Qd>100)

Manning's coeff of roughness 0.012


0.012
Downstream submergence depth hsub m
0.100
Used Q flood
Orifice height H m
1.100 Canal & Spillway
Height of orifice from canal bed h bot m
1.250
Spillway crest height above NWL m
Provided water depth in the river hr (m)
3.500
Spillway discharge coeff
Provided canal width (m)
21.000
Provided Freeboard h fb1 m

35.000
976.100
16.334
976.100
0.100
1.600
3.000

Output
Normal Condition
Canal witdth d/s of orifice
1/Slope of canal immediately d/s of orifice
Depth of water in canal hc m
Free board in canal h fb m
Area of orifice A m2
Width of orifice B m
Actual velocity through orifice Vo act m/s
Canal width Wc m
Water level difference dh m
Water depth in the river hr = hc + dh m
Height of weir (hw = hr+0.1) m
Spillway overtopping height h overtop m

Flood
21.000
40492
2.450
3.000
22.447
20.406
1.500
21.000 Spillway
0.179
3.500
3.600
2.600

Critical depth of water at crest yc m


1/Slope of canal immediately d/s of orifice
Flood head at river hf r = hw+yc m
Head difference dhf
Velocity through orifice Vof m/s
Q intake Qf cumec
Depth of water at canal (hc f) m

4.296
#NAME?
7.896
#NAME?
#NAME?
#NAME?
#NAME?

Ls1 for Qf w/o d/s Obs m


Ls2 for Qf-Qd w/o d/s obstruction m
Ls3 for Qf with d/s Obs m
Ls4 for Qf-Qd with d/s obstruction m

#NAME?
#NAME?
#NAME?
#NAME?

Design of Bottom/Drop Intake


Spreadsheet developed by Mr. Pushpa Chitrakar, Engineering Advisor, SHPP/GTZ

06-Apr-2016
2006.05
Sarbari SHP
Kullu, Himanchal Pradesh, India

Referances: 6,7,8,12,13

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project
Developer
Consultant
Designed
Checked

Pushpa Chitrakar
Pushpa Chitrakar
Critical Depth Considered
Critical Depth Not Considered

##
##
##
##
##
#
#

Weir Geometry

#
#
#
#
#
#
#
#
#
#
#
#

Input

1
River Width (Br) m =
Head/Critical Depth of u/s water (ho)m =
Upstream water velocity (vo) m/s =
River gradient (i) degrees =
Trashrack gradient () deg =
Contraction coeff () =

River Width flood (Brf) m =


20
8
ho flood m =
3.000
0.226
vo flood m/s =
4
1.494
Design Discharge (Qd), m 3/s =
2.7
9.462
Trashrack witdth/diameter (t) mm =
60
36
Trashrack clearance (a) mm =
30
0.85
Invert level of crest (masl)
500
Aspect ratio (Length across the river/Breadth along the river) = 3.5464682

Output
c/c distance of trash rack bars d mm =
Total head (he) m =
kappa () =
velocity head (h) m =
Correction factor ( c) =
Length of intake (L) m =
Length (L' ) m =
Intake length across the river (b) m =
Area of intake (A=L' *b) m2 =

90
0.340
0.749
0.170
0.146
2.249
1.819
7.975
17.935

Qo u/s of intake (m3/s) normal =


Qu d/s of intake (m3/s) normal =
h d/s normal (m)
h flood u/s=
h d/s flood (m)
Qof u/s of intake = Br * hof * vof (m 3/s) =
Q in flood m3/s =
Quf d/s of intake (m 3/s) =

2.700
0.000
0.000
1.906
1.864
325.497
7.318
318.178

Side Intake
Spreadsheet

0
0
500
500
800
800
1800
1800
2100
2100
3100
3100
0
1550

Orific =1,1x20,41
0
300
300
1550
1550
300
Top =899,05
300
1800
2650
1550
1800 8695.9694
1550
2100 8695.9694
300
2100
2650
300
1800
2650
0
Canal =890,65
0
3100
300
3500
300
3100

WALL GEOMETRY
10000
9000
8000
7000
WALL (m m )
6000

0
1800

Crest =894NWL =894,HFL =898,55


3900
3800
8196
3900
3800
8196

2100
3100

NWL =893,
2750
2750

#NAME?
#NAME?
#NAME?

5000
4000
3000
2000
1000
0
0

1000

Bottom Intake

3000

4000

Weir Geometry

Top =500
0
500
1000
1300
1300

Top =498,68
NWL =500,HFL =501,9Trashrack
Width =1,82
0 3119.3444
0
0 2048.2735
4822
1300 1821.831
1300
0 3119.3444
500
1300 2048.2735
3728 3119.3444
500 3119.3444
1821.831 3419.3444
500 3119.3444
500 2363.5406
1821.831 3719.3444
0 3419.3444
500 2363.5406
0 3919.3444
0 3719.3444
500 2363.5406

2000
BASE ( m m )

0
0

5500

4500

3500
WALL (m m )
2500

1500

500

-500
0

1000

2000
BASE ( m m )

3000

4000

5000

Canal Design: Proposed design and optimum canal sections


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Project
Developer
Consultant
Designed
Checked

06-Apr-2016

2006.05
Sisne Small Hydropower Project
Gautam Buddha Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar
Revision

Input
Type and Name
Flow (m3/s)

Intake Canal
Tailrace
0.185

Roughness coefficient (n)

0.02

0.017

0.02

0.02

Sectional Profile

Rectangular

Trapezoidal

Semicircular

Triangular

Side slope N (1V:NHorizontal)

0.02

Main2

0.017

Main3

0.145

0.145

0.02

0.5

0.5

0.145

0.02

0.5

Length of the canal (m)

20

40

150

1/Canal slope (s)

77

200

30

120
72

Channel Depth/diameter D (m)

0.300

0.525

0.300

0.300

Freeboard FB (m)

0.300

0.250

0.150

0.150

Channel Width (B) m

0.500

1.000

0.400

0.400

Channel Drops di m

0.000

0.000

0.000

0.000

Channel Drops Horizontal length hi m


Desired velocity Vo (m/s)

0.000
1.000

0.000
1.500

0.000
1.500

0.000
1.500

Output
Side slope d (degrees)
Canal slope S
Total depth H (m)

0.000

63.435

0.000

63.435

0.01299

0.00500

0.03333

0.01389

0.600

0.775

0.450

0.450

20.000

60.000

210.000

330.000

Area A m2

0.150

0.663

0.035

0.060

Top Width T (m)

0.500

1.525

0.400

0.400

Wetted Perimeter P (m)

1.100

2.174

0.471

0.671

Hydraulic Radius r (m)

0.136

0.305

0.075

0.089

0.226 high

1.249 high

0.057 low

0.071 low

Chainage L (m)

Present canal

Calculated flow (m3/s) & remarks


Comment on freeboard
Velocity V m/s
Critical Velocity Vc m/s & Remarks
Headloss hl (m)
Total headloss Hl(m)
Critical dia of sediment d crit (mm)

ok

low

ok

ok

1.233

0.219

4.103

2.417

1,72 Ok

2.06 Ok

0,93 Not Ok

1,21 Not Ok

0.260

0.200

5.000

1.667

0.260
19.481

0.460
16.769

5.460
27.500

7.126
13.665

0.1850
0.6022
1,74 Ok
0.1505
0.301
0.150
0.451
0.602
0.0050
0.100
0.100
8.271

0.0967
0.7636
1.11 Not Ok
0.1180
0.236
0.263
0.498
0.528
0.0112
0.449
0.549
14.584

0.0967
0.9949
0,98 Not Ok
0.1244
0.497
0.150
0.647
0.995
0.0145
2.175
2.724
19.834

0.0967
0.4867
1.4 Not Ok
0.1088
0.218
0.150
0.368
0.487
0.0173
2.079
4.803
20.736

Optimum canal
Area Ao m2
Top Width T (m)
Critical Velocity Vc m/s & Remarks
Hydraulic Radius ro (m)
Channel Depth/diameter Do (m)
Freeboard Fbo (m)
Total depth Ho (m)
Channel Width Bo (m)
Canal Slope
Headloss hlo (m)
Total headloss Hlo(m)
Critical dia of sediment d crito (mm)

HEADRACE PIPE CALCULATIONS


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 2,4, 6,12,13,15,16


SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Project:

Upper Jogmai SHP


Location:
Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

Developer
Consultant
Designed
Checked

Date

06-Apr-2016

Revision

2006.05

Jogmai

INPUT
Economic life (years)

15

0.160

U/S Invert Level (m)

1950.00

0.160
7.000

% head available or headloss hlt (m)


Entrance Type
Bending radius (r/d)

Hydraulics:
Diversion flow Qd (m3/s)
Flow in each pipe Qi (m3/s)
Gross headHg (m)

95.00%
0.8
0.3

0.80.3

Headrace pipe
HDPE

Exit (Yes/No)

Yes

NA
NA

No of pipes
Bending angle 01

1.00
20.00

NA
Burried
0
0
282
260
NA
3.0

Bending angle 02
Bending angle 03
Bending angle 04
Bending angle 05
Bending angle 06
Bending angle 07
Bending angle 08
Bending angle 09

4.00
6.00
20.00

140.000

Bending angle 10

Pipe Material
Welded / Flat rolled if steel
Rolled if steel
Type if steel
Burried or exposed
Type of valve
Non standard ultimate tensile strength (UTS) N/mm2
Estimated pipe diameter d(mm)
Provided pipe diameter d(mm)
Min pipe thickness t (mm)
Provided pipe thickness t (mm)
Pipe Length L (m)
Trashrack
t
6.00

b
20.00

Vo
1.00

60.00

0.00

Q
0.160

H
3.00

Tmax (deg)

T installation

Tmin

1st Pipe length(m)

2nd Pipe L (m)

3rd Pipe L (m)

4th Pipe L (m)

5th Pipe L (m)

40

20

50.00

100.00

150.00

200.00

250.00

hf
0.0213

hb
0.0000

H coeff
0.4174

H
0.0213

S
0.8006

B
0.23

2.40

k
2.40

Expansion Joints

OUTPUT
Trashrack
Min Submergence

1.39

CGL=1.5v^2/2g

0.69

Turbulent loss coefficients


K inlet

0.80

K bend 05

0.00

K bend 10

0.00

K bend 01
K bend 02
K bend 03
K bend 04

0.16
0.13
0.13
0.16

K bend 06
K bend 07
K bend 08
K bend 09

0.00
0.00
0.00
0.00

K valve
K exit
K others
K Total

0.00
1.00

Hydraulics
Pipe Area A (m2)
Hydraulic Radius R (m)
Velocity V (m/s)
Pipe Roughness ks (mm)
Relative Roughness ks/d
Reynolds Number Re = d V /Vk
Type of Flow
Friction Factor f
Expansion Joints (mm)

0.053
0.07
3.01
0.06
0.00023
687032
Turbulent
0.0153

U/S Invert Level (mAOD)


D/S Invert Level (mAOD)
Is HL tot < HL available
Friction Losses hf (m)
Fitting Losses hfit (m)
Trashracks and intake loss (m)
Total Head Loss htot individual (m)
% of H.Loss of individual pipe
0.0E+00

EJ number

dL theoretical

dL recommended

dL for expansion

dL for contraction

2.37

1950.000
1943.000
OKAY
3.82
1.10
0.02
4.94
70.56% Ok

Settling Basin Design


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 2,4, 6,9,12,13,15,16

Date

06-Apr-2016

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project:

Location:

2006.05
Jogmai

Upper Jogmai SHP


Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

Developer
Consultant
Designed
Checked

Q flood
Manning's number M (m 1/3/s) 1/n=
Design discharge Qdesign (m3/s) =

0.000
50.000

Sediment swelling factor S =


Volume of sediment storage V (m3) =

0.421

Sediment depth Hs (m) = V/Asi

0.63

Flushing discharge Qflush (m /s) =

0.034

Inlet approach conveyance Canal/Pipe =

Canal

Total discharge Qbasins (m3/s) =

0.455
0.300
85%
15
0.037
2
8
24.000
0.241
2600

1/Bottom slope of SB Sf (1:50 to 1:20) =


Outlet approach conveyance Canal/Pipe =
Water level at inlet NWL (m) =
h flush below the base slab (L<6m)
Number of basins N
Spillway crest height above NWL m
Spillway discharge coeff
Provided Freeboard h fb1 m
Discharge coeff for pipe as orifice (2.76 if L <6 m)
Drawdown discharge % of design discharge

50.00
Pipe
1950.00
1.70
1.00
0.05
1.60
0.30
2.76
1.00

Max section width for hydraulic flushing B (m) =


Width used B (m) =
Inlet canal width /canal diameter Bc1 (m) =

0.455
3.258
2.500
1.000

Water depth of inlet canal hc1 (m) =


Outlet canal width /canal diameter Bc2 (m) =
Water depth of outlet canal hc2 (m) =
Provided Length of the basin Lact (m)=

0.50
0.50
0.30
0.00

Length of basin L (m) (Idel L = 9,6) =


Aspect ratio (4<=AR<=10)
Min. water depth Hi (m) =
X-sectional area / basin Ai (m2) =
Wetted perimeter / basin Pi (m) =
Hydraulic radius Ri (m) =
Normal WL @ basin h b m =
Straight inlet transition length at 1:5 (m) =
Straight approach canal length (m) =

10.000
4.000
0.755
1.888
4.010
0.471
1.385
3.750
10.000

Particles to settle d (mm) =


Trapping efficiency n (%) =
water temperature t (oC) =
Fall velocity w at 15 deg C (m/s) =
Sediment concentration Cmax (kg/m3) =
Flushing Frequency FI (hours) =
Surface area / basin Asi (m2) 85 % =
Basin transit velocity Vt (m/s) =
Bulk Sed density G (kg/m3) =
Discharge per basin Qbasin (m3/s) =

1.50
15.12

Pipe does not need a straight approach! ***


Head over outlet weir h overtop (m) =
Approach inlet velocity vi1 (m/s) =
Approach outlet velocity vi2 (m/s) =
1/Energy gradient during operation So =
d 50 during operation (mm) =
Depth of water during flushing yfi (m) =
d 50f during flushing (mm) =
Length of an Ideal Basin (m) =

0.23
0.91
3.03
15763.86
0.33
#NAME?
#NAME?
10.00

Spilling of excess water


Vertical Flushing pipe
Diameter for flood d1 m =

0.000

Freeboard m
Spillway overtopping height h overtop m
Spillway length for Qf (flood and non operational)

0.300
0.125
0.000

Combination of vertical flushing pipe and spillway


Vertical flushing pipe diameter d1 m
No of vertical flushing pipe
Spillway length used (m)

0.30
1.00
1.00

Flood and Under Operation (Qf- Qd)


H overtopping
Discharge passing through vertical pipe
Discharge passing over spillway

0.00
0.00
0.00

Diameter for load rejection (u/s flood bypass) d1 m = 2 x 0,43

Spillway
Spillway length for Qd (under operation)
Spillway length for Qd (load rejection & u/s flood bypass)
Spillway length for Qd (d/s obstruction & full hovertop-50)

0.00
6.43
3.18

Flood and non operational (Qf)


Flood discharge passing through vertical pipe
Spillway length for the remaining discharge m

0.000
1.00

Load Rejection (Qd)


H overtopping
Discharge passing through vertical pipe
Discharge passing over spillway

0.262
0.240
0.215

Calculate Gate Rating Curves

Flushing of water and sediment


Flushing pipe and orifice diameter
d for incoming flow and draw down m
d for incoming flow only (empty state) m
d for incoming flow only (empty state & with y flushing) m

Gate
Opening
Hg
0.000
0.033
0.067
0.100
0.133
0.167
0.200
0.233
0.267
0.300
0.333
0.367
0.400
0.433
0.467
0.500

0.35
0.40
#NAME?

Gate
Buoyance weight of the gate W kgf
Gate Opening B, (m)
Gate Opening H (m)
Submerged area of th gate A m2
Water surface to cg of submerged area h m
Coeff of static friction mu
Lifting force F kgf
H. of water (H1)
1.800

300.00
1.00
0.50
0.50
1.14
0.90
810.84
1.39

Designed Cross Section

1.600
1.400
1.200

Penstock diameter m
Penstock velocity m/s
Submergence depth of penstock pipe m
Height of pipe above the base slab m
Min. pond depth m
Effective thickness of penstock mm
FS for air vent (5 burried, 10 exposed)
Young's modulus of elasticity E N/mm2
Penstock inlet gate (Yes/No)
Air vent diameter mm

0.800
0.600
0.400
0.200
0.000

Gradual Expansion of 1:5

half of Gr expansion

0.500
Width 2,5m

Flushing cone/spillway O

L =10

Gradual Expansion 1 in 10 (1:2 for MHP)

Spillway

0.500

Discharge
One basin
Q
0.000
0.128
0.251
0.369
0.484
0.597
0.707
0.816
0.922
1.027
1.129
1.230
1.328
1.423
1.516
1.606

Forebay cum settling basin (one basin)

1.000

1.000

Relative
Gate Openinig
Hg/H1
0.000
0.024
0.048
0.072
0.096
0.120
0.144
0.168
0.193
0.217
0.241
0.265
0.289
0.313
0.337
0.361

Water depths 0,76m & 0,96m


Sediment depth 0,63m

Slope 1:50

0.300

0.41
3.45
0.91
0.30
1.62
3
10
200000
No
Nominal

PENSTOCK AND POWER CALCULATIONS


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances:2,4, 5,6,12,13,15,16
SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Project:

Jhankre mini-hydropower
Himal Power Limited
BPC Hydroconsult
Pushpa Chitrakar
Pushpa Chitrakar

Developer
Consultant
Designed
Checked

Date

06-Apr-2016

Revision

2006.05

Location:

INPUT
General:
Project:
Location:
Hydraulics:
Diversion flow Qd (m3/s)
Flow in each pipe Qi (m3/s)
Gross head (from forebay) Hg (m)
Power:
Turbine type (CROSSFLOW/PELTON)

Jogmai I
0.450
0.450
180.00

Number of units
Penstock pipe:
Pipe Material (STEEL/HDPE/PVC)
Welded / Flat rolled if steel
Rolled if steel
Type if steel (UNGRAGED/IS)
Burried or exposed
No of pipes
Bending angle 01(degrees)
Bending angle 02
Bending angle 03
Bending angle 04
Penstock diameter d=>d estd, d act (mm)
Pipe Length L (m)
Trashrack

Valves (Sperical/Gate/Butterfly)
Taper (Yes/No)

0.3
No

Exit (Yes/No)

No

30.00
3

Non standard ult. tensile strength (UTS) N/mm2

Steel
Welded
Rolled
IS
Exposed

Safety factor for lower pipes (0 for default)


Entrance Type
Entrance with gate and air-vent (Yes/No)
Bending radius (r/d) (1/2/3/5/1.5)
Bending angle 05

1.00
2.00
11.00
4.00
11.00
475 Pipe thickness t=>t min, t act (mm)
Roughness coefficient (ks)

418
550.000

Clear spacing, b
(mm)
20.00

Approach velocity,
Vo (m/s)
1.00

Tmax (deg)

T installation

Tmin

1st Pipe length(m)

2nd Pipe L (m)

40

20

10.00

15.00

Frictional headloss, hf (m)

Bend loss, hb
(m)

0.5
No
0.45
22.00

0.45

Bending angle 06
Bending angle 07
Bending angle 08
Bending angle 09
Bending angle 10
3.0

14.00
0.00
0.00
0.00
0.00
7.0
0.060

Design
discharge, Q
(m3/s)
0.450

Submergence
depth @
trashrack, h (m)
0.70

3rd Pipe L (m)

4th Pipe L (m)

5th Pipe L (m)

20.00

25.00

30.00

Angle of inclination, Flow deviation,


(deg)
(deg)
71.56
0.00

thickness, t(mm)
6.00

2.40

0.3

Yes

Direct Coupling (Yes/No)


Closure time T sec

2.40

10
1213.90
16.00%
79.38%

Pelton
1 10%

No of total jets (nj) & % closure

Trashrack coefficient, kt

Economic life (years)


WL @ forebay or U/S Invert Level (m)
% head allowable headloss hlt (m)
Cumulative knowm efficiency (g,t,tr,others)

Ilam

Expansion Joints

OUTPUT
Trashrack

0.0233
Turbulent loss coefficients
K inlet

Headloss coeff Total headloss, H(m)

0.0000

0.4572

K Total

K bend 01
K bend 02
K bend 03
K bend 04

0.0233

2.79

1.76

0.49

0.50

K bend 05

0.24

K bend 10

0.00

0.18
0.21
0.19
0.21

K bend 06
K bend 07
K bend 08
K bend 09

0.22
0.00
0.00
0.00

K valve
K taper
K exit
K others

0.30
0.00
0.00
0.00

Factor of Safety
Young's modulus of elasticity E N/mm2
Thickness
Diameter (mm)
Net Head (m)
Wave Velocity a (m/s)
Critical time Tc (sec) *2 = Closing time T
Hsurge for 10% closure of one jet
Hsurge for one jet closure of Pelton(m)
Hsurge for instanteneous closure of all unit closure of Pelton (m)
Lengths (max & actual) of the specified pipe (m) & Ok
Power
Turbine efficiency as per MGSP
Available shaft power(kW)
Reqd.'Turbine Capacity (+10%) (kW)

1
4
9
5
4

2.0555

2.06

Hydraulics
Pipe Area A (m2)
Hydraulic Radius R (m)
Velocity V (m/s)
Pipe Roughness ks (mm)
Relative Roughness ks/d
Reynolds Number Re = d V /Vk
Type of Flow
Friction Factor f

Expansion Joints (mm)


EJ number
dL theoretical
dL recommended
dL for expansion
dL for contraction

Submergence @ Submergence @
trashrack width, penstock, h min penstock, h min
B (m)
(m)
(m)

Surface area, S (m2)

2
6
13
7
6

560.313

0.177
0.12
2.54
0.060
1.263E-04
1057668
Turbulent
0.0137

U/S Invert Level (mAOD)


D/S Invert Level (mAOD)
Is HLtot < HL available
Friction Losses hf (m)
Fitting Losses hfit (m)
Trashracks and intake loss (m)
Total Head Loss htot individual (m)
% of H.Loss of individual pipe

200000

1213.90
1033.90
OKAY
5.23
0.67
0.02
5.93
3.29% Ok

Ultimate tensile strength (UTS) N/mm2

410

7.000

H total for 10% closure of one jet(m)

208.33

475.000

t effective (mm)

4.30

174.074

Minimum t effictive for negative pressure (mm)

4.97

1094.981

Comment on thickness

NA, No gate

1 Ok

Safety Factor (S)

3.57

28.33338
283.334
283.334
550.000

Check on Safety Factor


Air vent diameter d vent (mm)
H total capacity of the specified pipe (m)
H static capacity of the specified pipe (m)

Ok
60.75
212.24
183.91

75.00%
576.34
633.97

Electrical Power as per MGSP GL (kW)


Electrical Power based on Hnet (kW)
Power for known cumulative eff (kW)

397.31
461.07
610.00

Coeff of linear expansion /deg C


2
4
9
11
17
22
10
12
8
10

1.2E-05
5
13
26
14
12

Forces on Anchor Block

Block # & type

Convex

Small Hydropower Promotion Projec Spreadsheet by Mr Pushpa Chitrakar


Referances: 6,12,13,15,16

Date

06-Apr-2016

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

2006.05

Project
Developer
Consultant

Designed
Checked

Pushpa Chitrakar
Pushpa Chitrakar

Golmagad SHP
Kankaimai Hydropower P Ltd
EPC Consult

Input
Particulars

Central

Upstream

Pipe dimensions
Diameter (Di)
Thickness
Shaddle Spacing & number

Downstream

0.39
0.006
4.00

0.39
0.006
4.00

Elevations

Vertical angles, a & b (deg)

2.000

53.712

0.0000

27.7832

Location of Expansion Joint

D/S Expansion Joint :

Vertical angles, a & b (rad)

78.5
9.81
25

0.586
1.172
1.758
3.097

0.000000

0.484908

200
30
20

Heads (m)
Forebay WL
Tot.Transient Length (m)
Tpot Pipe Len (forebay to AB)
Total Surge Head
Static Head
Surge Head
Total (H)
Youngs Modulus of Elasticity (E)

Yes

0.586
1.172
1.758
3.097

22

Bearing capacity (kN/m2)

Yes

Output
Weight of pipe, Wp (kN/m)
Weight of water, Ww (kN/m)
Total weight, W (kN/m))
Velocity, v (m/s)

0.37

Unit Weights (kN/m3)


Mild Steel
Water
RCC
Anchor Block
Soil

818.000

Horizontal Distance (m)

Design Discharge, Q (m3/s)

0.5236

835.000
511
56.388
96.360
17.000
10.63
27.633
2.1E+11

Coefficient of Linear Expansion (a)

12E-06

GENERAL FORCES
1. Perpendicular component of Wt of pipe and water act perpendicular to the pipe CL along the anchor faces

F1=dead weight of half of anchor saddle pipe perp to pipe


3.516
3.516
F1u (kN)=wu*lmu/2*COS():
F1d (kN)=wd*lmd/2*COS()
F1 perpendicular to pipe
3.516
3.110
F1 axial
0.000
-1.639
Fixed end moment = wl^2/8 for proped cantilever FEM.
FEMu (kN-m)= Restoring moment:
FEMd (kN-m)= Overturning moment
FEM

2.

2.344

-2.344

Axial frictional force of pipe on saddle supports transferred to anchor


F2 (kN)= *w*L'*cos

0.25

US Pipe Length, L' (m):

2.00

F2 (kN) =

3.

12.305 +ve for expansion

Hydrostatic Pressure at Bend due to the vector difference of static pressure & acting towards IP
Pu (kN) = F3u =PI/4*dui^2*Ht*

32.38

Pd (kN) = F3d =PI/4*ddi^2*Ht*

32.38

F3 = 2*P*sin((-)/2)

4.

15.549

Component of weight of pipe (wp) along the pipe


F4u= wp*active arm L*sin()

F4d= wp*active arm L*sin()

F4

5.

0.000

F5 (kN)=pi()*Dmean*t*E*a*Dt
Condition
Temp at oC

F5 expansion
F5 contraction

6.

+ Expansion, - Contraction
Tmax
Tinstallation
40
20
0.000

Tmin
4
0.000

0.000

0.000

Axial friction within Expansion joint seal due to the movement against the circumferential pressure
F6=PI()*D*W*H*g*m

0.25 Seal width, W (m)

0.16

Static Pressure at Exp, Ps (m)

17.000

Dynamic Pressure at Exp, Pd (m)

10.256

11.06

Total (AH)

27.256
13.507

28.992
13.939

F6 (kN)

+ Expansion, - Contraction

for rubber packing

7.

0.546

Thermally (expansion/contraction) induced axial force ( if no EJ provided)

17.93

F6

F6
p

Axial hydrostatic pressure on exposed end of pipe in Expansion Joint


F7=PI*D*t*H*g

F7

8.

1.996

F7

2.059

Dynamic pressure at the bend due to the vector difference of momentum


F8 = 2.5*(Q^2/d^2)*sin((-)/2)

P8= mV =Q**Vi

P8 (kN)

1.146

F8

9.

F6

Pipe Movement

1.146
0.540

Axial (small diameter) force on Reducer


F9=PI()*(Dupi^2-Ddni^2)/4*g*H
Reducer:
Location & Diameter:
St. Head
Dyn. Head

No

No
3.00
17.00
10.63

F9 (kN)

0.40

0.000

4.00
18.86
10.98

0.40

0.000

10 Axial drag of flowing Water (friction of flowing water) (not considered in MHP)
F10=g*PI()*Dupi^2/4*DH(Exp to block)
F10 (kN)

0.000 No

0.000 No

11 Axial (u/s slope) force due to soil pressure upstream of the block
F11 =s*hs^2/2*cos *ka*B

F11

ka= (cosi-sqrt(cosi^2-cos^2))/(cosi+sqrt(cosi^2-cos^2))

hs = soil depth = hu
F11

0.333

1.8
21.600 Yes

Width, B(m)
@ 1/3 of hs

0.6

12 Vertical force due to the weight of the block


F12 =block*Vol of block
Vol of block
F12

SUMMARY OF CRITICAL FORCES

16.191

F12

356.202 Yes
Expansion
@ bend

1 Summation of total horizontal forces H (kN)


2 Summation of total vertical forces V (kN)
3 Summation of total moment forces M (kN-m)

Contraction
Total

@ bend

16.551

38.151

-10.41

11.19

-16.554

339.648

-3.56

352.64

0.000

0.00

Total

F7

Anchor Block Stability


Small Hydropower Promotion Proje Spreadsheet by Mr Pushpa Chitrakar
Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project
Developer
Consultant
Designed
Checked

06-Apr-2016

2006.05

Golmagad SHP
Mansarawar Hydropower P Ltd
EHS
Pushpa Chitrakar
Pushpa Chitrakar

Input
Anchor
Upstream depth, Hu (m)
Downstream depth, Hd (m)
Width, W (m)
Length, L (m)
anchor (kN/m3)

Output
3.3
2.25
2
3
22
0.5

Concrete volume of Anchor Block


Weight of block, Wb (kN)
Centre of gravity XX
3.5

16.191
356.199
1.405

Anchor Block Se ction

3.0
2.5

Penstock
Bend at (X), (m)
Bend at (Y), (m)
Diameter, d (m)
Upstream angle, (deg)
Upstream angle, (deg)

2.0

1
2.15
0.458
13
25

1.5

0.5
Length X (m) '
0.0
-0.5

Foundation
Upstream depth hfu (m)
Soil friction , (deg)
soil (kN/m3)
Bearing Capacity, SBC (kN/m2)

1.8
30
20
200

Forces (with soil pressure and block weight)


Yes
Forces with earthpressure & anchor
Expansion
H (kN)
V (kN)

Contraction
H (kN)
V (kN)

Height Y (m) '

1.0

0.0

0.5

1.0

1.5

2.0

Active earth pressure coeff, Ka

2.5

Overturning

3.5

4.0

0.3715
F Pa

Soil force
Acting at (m)

3.0

Fx
23.455
0.6

Fy
22.853

Bearing

5.276

Sliding

Net Forces @
SM @ O
bend
53.180
30.327 d
345.260
-16.215 eccentricity e, Ok
e allowable

563.303 P max
1.632 P min
0.132
0.500

72.681
172.63
42.4057 Ok
Ok

SM @ O
-6.19 d
-41.03 eccentricity e, Ok

473.281 P max
1.477 P min
0.023

55.8664
160.22
50.9469 Ok
Ok

16.66
320.44

Turbine Selection
Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

06-Apr-2016
2006.05
SMALL HYDROPOWER PROMOTION PROJECTRevision
Project
Upper Jogmai SHP
Kankaimai Hydropower P Ltd
Developer
EPC Consult
Consultant
Designed
Pushpa Chitrakar
Checked
Pushpa Chitrakar
Referances: 6,7,8,12,13

Date

Input
Discharge (l/s)
Gross head (m)
Hydraulic losses
Max turbine output kW
Turbine rpm
Cd

150 Gear ratio at turbine


69 Gear ratio at generator
15.94% No of turbines/generators
67.89 Total number of jets if Pelton n
750 Specified turbine
0.96 Cu

Output
Net head m
No Gearing
Sp speed of runner rpm (no gearing)
Pelton (12-30) => (Ns 17-42)
Turgo (Ns 20-70) => (Ns 28-99)
Crossflow (Ns 20-80)
Fracis (Ns 80-400)
Propeller or Kaplan (Ns 340-1000)
Jet velocity Vj (m/s)
Nozzle diameter, Dn (mm)
Pitch circle diameter, PCD (mm)

58.001 Generator with gearing rpm

**
Turgo
Crossflow
**
**

With Gearing
46 Sp speed of turbine
Pelton (12-30) => (Ns 17-42)
Turgo (Ns 20-70) => (Ns 28-99)
Crossflow (Ns 20-80)
Fracis (Ns 80-400)
Propeller or Kaplan (Ns 340-1000)
32.38
54.85
395.15

1
2
1
2
Pelton
0.46

1500

23
Pelton
**
Crossflow
**
**

Selection of Electrical Equipment


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

06-Apr-2016
2006.05
SMALL HYDROPOWER PROMOTION PROJECT/Revision
Project
Upper Jogmai SHP
Kankaimai Hydropower P Ltd
Developer
EPC Consult
Consultant
Designed
Pushpa Chitrakar
Checked
Pushpa Chitrakar
Referances: 6,7,8,12,13

Date

INPUT
Discharge (m3/s)
Gross head (m)
Overall plant efficiency (%)
Temperature (oC)
Altitude (m)
ELC correction factor
Frequency of the system (Hz)
Capacity of used generator (kW)
Capacitor configuration

0.08 Power factor


50.968 Safety factor of generator
50% Phase
45 Type of Generator
1500 Over rating factor of MCCB
0.83 Over rating factor of cable

Delta

50 No. of poles
0 Rated rotor speed if induction generator N (rpm)
Efficiency of motor at full load

0.8
1.3
1
2
1.25
1.5

4
1450
89%

OUTPUT
Pe Electrical output (active power) (kW)

20.00 Use of 3-phase generator is mandatory

Generator
Temp.factor
Capacity (kW)
Synchronous rotational speed Ns (rpm)

0.96 Altitude factor


28.25 Actual available capacity (kW)
1500 Rotational speed of the generator (rpm)

IGC capacity (kW)

Rated Voltage (V)

20.00 Calculated Ballast capacity 1.2*Pe (kW)


Excitation Capacitance (micro F)
220 Irated for Cable & MCCB (A) at Generator side

Rating of MCCB (A)

113.64 Calculated size of MCCB (A)

Cable
Rating (A)

255.68 Size of 2-core cupper armoured cables

0.96
30.00
1550
24.00
123.16
170.45
142.04

150

Turbine and Generator Machine Foundation


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 6,12,13,15,16

Date

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Project
Developer
Consultant
Designed
Checked

06-Apr-2016

2006.05
Upper Jogmai, Ilam
Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar
Machine Foundation Plan

Machine Foundation Section


2.8
2.6
2.4
2.2
2.0
1.8
YY (m1.6
)
1.4
1.2
1.0
0.8
0.6
0.4
0.2
0.0

1.8
1.6
1.4

Height
1.2ZZ (m )
1.0
0.8
0.6
0.4
0.2
0.0

0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 3.2 3.4

0.0 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6 2.8 3.0 3.2 3.4

XX (m )

XX (m )

INPUT
Gross head hg (m)
Surge head hs (m)

51.00 Design Discharge Qd (m3/s)


50.00

Foundation

0.150

Penstock
Foundation on

Allowable bearing capacity Pall (kN/m2)


Friction coeff between block and soil m
Length L (m)
Bredth B (m)
Height H (m)
Material of foundation

Soil

Diameter dp (m)

0.300

180
Material
0.5
Centreline above PH floor hp (m)
3.2 Turbine Pit
2.5
Length of opening Lo (m)
1.5
Bredth of opening Bo (m)
Concrete
Height of opening Ho (m)

mild steel
0.300
0.450
0.500
1.000

22

Height of tailrace canal Htr (m)

0.500

2.943
3.434

XX (m)
0.625
2.025

YY (m)
1.250
1.250

Weight Wi
(kN)
70.036

Lever Arm LA (m)


LA along XX
1.800

LA along YY

33.000
27.225
193.875

3.000
2.575
1.175
282.455
260.477

1.25
1.25
1.25
199.530
260.477

Overturning
Equivalent distance at which SM acts from critical point
d (m)
Eccentricity e, (m)
Allowable eccentricity e all (m)
Comment on overturning moment

LA along XX
1.084
0.516
0.533
Ok

LA along YY
0.766
0.484
0.417
Not Ok

Bearing
Pressure at base
Pmax
Pmin
Comments on bearing

LA along XX
64.038
1.081
Ok

LA along YY
70.379
-5.260
Not Ok

LA along XX
1.860
Ok

LA along YY
1.860
Ok

Density of foundation (kM/m3)


Electro-mechanical
Weight of turbine Wt (kN) & cl position
Weight of generator Wg (kN) & cl position
OUTPUT
Forces
Force due to h total of 101 m, Fh (kN)
Foundation
W1
W2
W3
Sum of moments M (kN-m)
Sum of vertical forces M (kN)

Sliding
Factor of safety against sliding, FS sl
Comment of sliding

Transmission and Distribution System:

Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances:2,4, 6,12,13,15,16

Date

06-Apr-2016

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

2006.05
Cable Summary

Project:
Developer
Consultant
Designed
Checked

Upper Jogmai SHP


Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

Power factor
Voltage systems

0.8
11000
400
230

Type
Squirrel

Length(km)
4.50

Gopher

0.00

Weasel

10.00

Rabbit

3.00

Otter

1.15

Dog

5.30

Total Cost(

606600.00

Length of neutral cables (km)

Node name

Reach
name

Reach
Length
(km)

PH-A-B-C-D

Power at
next node
(kW)

Phase
1,3,11

PHA

0.300

AB

0.500

AC

0.500

AD

0.500

T1

PHT1

0.050

T2

T1 T2

1.500

T2 E

0.300

EJ

0.500

EG

0.500

GH

0.200

EK

0.500

KL

LM

PH-T1

T2

V @ next
node (V)

% voltage
drop

400.00

400.00

28.87

6.30

393.70

1.58

5 Rabbit

2500

227.30

27.50

17.60

209.70

8.82

5 Rabbit

2500

227.30

27.50

17.60

209.70

8.82

5 Rabbit

2500

227.30

27.50

17.60

209.70

8.82

37.89

1.60

398.40

1.38

5.00

10995.00

37.89

8.20

38.68

16.20

400.00
21 Otter

1050

11

400.00

400.00

11000.00
21 Squirrel

31500

11000.00

11000.00

400.00

0.05

400.00

6300

7 Dog

3500

7 Otter

3500

226.21

38.68

18.40

207.81

9.65

3 Dog

600

207.81

18.05

3.00

204.81

10.95

7 Dog

3500

226.21

38.68

16.20

210.01

8.69

0.200

3 Dog

600

210.01

17.86

3.00

207.01

10.00

0.200

2 Dog

400

207.01

12.08

2.00

205.01

10.87

E-H (y)

226.21

E-M (b)

400.00

0.40

21 Dog

E-J ( r )
E

Reach Voltage
drop (V)

4800

11

T2-E

V @ prev
node (V) Current (A)
400.00

16 Dog

T1-T2
T1

Load
Momentu
m (kW-m)

PH

PH

ACSR
type

226.21

2.05

226.21

226.21

391.80

210.01

8.69

226.21

226.21

226.21

LOADS AND BENEFITS


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 1,2,3,4, 6,12,13,15,16

Date

Project:

06-Apr-2016

2006.05
Ladagada VDC, Doti

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

Location:

Developer
Consultant
Designed
Checked

Gaddi Gad Khola


Gaddi Gad Khola MHP
Perinial
Pushpa Chitrakar
Pushpa Chitrakar

INPUT
General
Power Output (kW)
Name of the Source

96.1
Gaddi Gad Khola

Beneficiary HH (nos.)
Plant's operating days

471
330

Loads (kWh or W/m)


Domestic
Agro-processing
Bakery
Saw Mill
Herbs Processing
Load 5
Load 6

Operating dTariff (Rs)


330
1.00
330
6.00
320
6.00
300
5.00
180
5.50
330
330

Domestic lighting
Average subscription/household (W/HH)
System loss
10%
time
0
5
load
88
0
440
0
Probable Business Load Expected after 3 years
Operating d/y Tariff (Rs)
Load
Metal Workshop
330
6.00
Photo Studio
320
6.00
Dairy Processing
320
6.00
Cold Store
310
6.00
Load 5
Load 6

Proposed end uses and operting hours


time (hr)
0
Agro-processing
0
time (hr)
0
Bakery
0
time (hr)
0
Saw Mill
0
time (hr)
0
Herbs Processing
0
time (hr)
0
Load 5
15
time (hr)
0
Load 6
12
36
OUTPUT
Summary
Annual Available kWh

4
0
8
9
3
0
3
0
6
0
3
0
0

12
22.5
14
0
16
10
12
25
8
0
5
0
0

16
0
18
0
18
0
17
0
15
0
10
0
0

22
0
22
0
22
0
22
0
22
0
22
0
0

36.00

Annual Income
(Rs)
480,420

85
8
0
0

10
1
8
6

18
91.1
182.2

From (hr) To (hr)


12
16
8
20
8
18
8
18

Daily Energy Demand (Dd) kWh


Yearly Energy Demand (Dy) kWh
Average Load Factor

1037
378578
49.97%

761112
First 3 years
After 3 years
117060
147680
15.38
19.40
42.36
50.40
916,050
1,099,770

Yearly end use load (kWh)


Productive end use load factor (%)
Total load plant factor
Annual total (domestic + end uses) Income (Rs)
End Use

Load
Operation Period
(kW)
Hours/day
Days/year
Domestic Lighting
44.483
13.987
Existing/Committed Business Load
Agro-processing
22.5
4
Bakery
9
6
Saw Mill
10
2
Herbs Processing
25
5
Load 5
15
6
Load 6
12
3
Total
Total Annual Income from sales of electricity

Yearly Load
kWh

LF (%)

330

205326

26.98

330
320
300
180
330
330

29700
17280
6000
22500
29700
11880
117060

3.90
2.27
0.79
2.96
3.90
1.56
15.38

178200
103680
30000
123750
0
0
435,630
916,050

13200
3840
25600
18600
0
0
61240

1.73
0.50
3.36
2.44
0.00
0.00
8.05

79200
23040
153600
111600
0
0
183,720

Probable Business Load after 3 years


Metal Workshop
10
4
330
Photo Studio
1
12
320
Dairy Processing
8
10
320
Cold Store
6
10
310
Load 5
0
0
0
Load 6
0
0
0
Total additional annual income after 3 years
Productive End Use (%)
19.40
Load Duration Chart for the first three years of operation of Gaddi Gad Khola

Load Duration Chart for the first three years of operation of Gaddi Gad Khola
0

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

140

Installed Capacity & Load (kW)


120

Load 6

100

Load 5
Herbs Processing

80

Saw Mill
Bakery

60

Agro-processing
40

Domestic
Installed Capacity

20

0
0

10

11

Tim e (hrs)

12

13

14

15

16

17

18

19

20

21

22

20
0

23

Project Costing and Financial Analyses


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Referances: 1,2,3,4, 6,7,8,12,13

Date

06-Apr-2016

SMALL HYDROPOWER PROMOTION PROJECT/GTZ

Revision

2006.05

Project
Developer
Consultant
Designed
Checked

Golmagad SHP
Kankaimai Hydropower P Ltd
EPC Consult
Pushpa Chitrakar
Pushpa Chitrakar

INPUT
Project size (kW):
Total Project Cost (Rs.)
Subsidy/kW
Headrace
Canal
91500 Rs/kW x 96,1 =
Interest rate i (%)
Payback period n (yr)
Plant life N (yr)
Discount Rate I (%)
Investment Cost (Rs)
Mechanical components
Electrical component
Civil component
Spare parts & tools
Transport.

96.10
12,734,865
Total subsidy
8793150

Bank loan
1,890,044
3%
7

Other loan

Cash equity
1,200,000

Kind equity
851,671

Others
0

15
4%
8,516,715
999,040 Installation
2,061,717 Commissioning
1,363,497 VAT
57,550 Contingencies
3,178,800 Others

232,500
0
623,611
0

Cost Summary
Project cost (Rs)
Annual Operation, Maintenance and other Costs (Rs)
Annual Income without probable business loads (Rs)
Annual Income with probable business loads (Rs)
Annual installment for Bank loan
Annual installment for other loan
NPV on equity without probable business load (Rs)+ve
NPV equity with probable business load (Rs)+ve
Cost/Kw =>>Ok
Subsidy/HH

O & M (Rs)
Salary
Spares
Maintenance
Office expenses
Miscellaneous
Others

305,004
114000
0
171,000
20,004

NPV Based on Different Project Costs


NPV
Probable Business Load
Without
With
Total investment cost
(3,543,677)
(2,010,846)
Total Inv Cost-Subsidy
5,249,473
6,782,304
Equity
3,773,038
5,305,869

12,734,865
305,004
916050
1099770
303364
NA
3,773,038
5,305,869
132,517
18,669

Annual Cash Flows


Without Probable Business Loads
Year

Equity

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

O & M costs

Loan repayment

Income

1,200,000
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004
305,004

303,364
303,364
303,364
303,364
303,364
303,364
303,364
0
0
0
0
0
0
0
0

916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050
916,050

Cash flow

With Probable Business Loads


Income

-1,200,000
307,682
307,682
307,682
307,682
307,682
307,682
307,682
611,046
611,046
611,046
611,046
611,046
611,046
611,046
611,046

916,050
916,050
916,050
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770
1,099,770

Cash flow

-1,200,000
307,682
307,682
307,682
491,402
491,402
491,402
491,402
794,766
794,766
794,766
794,766
794,766
794,766
794,766
794,766

Ulitilities and Short Calculations


Small Hydropower Promotion Project (SHPP)/GTZ

Uniform Depth of a Trapezoidal Canal (Y-m)


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05

Design Discharge (l/s):

1,000

1/Mannings Coeff (M):

50.0000

1/Canal Slope (S):

300

Freeboard, FB (m)

0.2

Wall Thickness, t (m)

0.3

Width of Canal, b (m):

1.000
Z= 0.50

Z= 0.50
Top width, T (m)
Uniform Depth (Y-m)

#NAME?
#NAME?
Canal Wall Geometry

Payment of a loan
Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05
Payback

Loan amount (NRs) :


Interest rate (APR):
Yearly payment and No
Yearly Payment

1,800,000 Starting Month


13.00% Starting Year
10
331,721.20

1
2
2006

Actual vs AEPC Power (Pe-kW)


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05

Discharge (l/s):
Cumulative efficiency including head loss (n%)

120
80.00%

Gross Head (H-m)

300.00

Actual Power (Pact-kW)

282.53

Power MGSP-ESAP (Pe-kW)

176.58

Spillway Lengths (m)


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05

Flood discharge (l/s):

2,000

Design discharge (l/s):

500

Overtopping height (ho) mm:

300

Spillway discharge coeff

1.5

L spillway min for Qf m & full height

0.00

Length of spillway Ls1 for Qf m & half height

0.00

Friction Factor (f) & Net head


Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05

Discharge (m3/s)
Gross head (m)
Pipe roughness ks (mm)
Pipe diameter (mm)

0.500 Flow
63 Velocity, v(m/s)
0.010 Reynold's nr, (R )
500.00 Laminar Flow

2.5464790895
1116876.79362734
5.730265000148E-005

Pipe Length (m)

100

9.170E+00

Turbulent headloss factor (K)

1.50

9.170E+00

Friction factor f

0.0119 Transitional Flow &

Headloss hl (m)

1.282

Headloss hl (%)

2.03

Net Head (m)

61.718

0.0118931351

Voltage Drop
Small Hydropower Promotion Project (SHPP)/GTZ

Spreadsheet by Mr Pushpa Chitrakar

Golmagad SHP

Date

06-Apr-2016

Stone masonry canal

Revision

2006.05

Reach length, L (km)


Voltage at 1st node, V1 (V)
Power, P (kW)
ASCR type
Phase at 1st node, (1/3)
Phase at 2nd node, (1/3)

1.000
230
20
6.00
1
1

Current, I (A)

108.70

Impedence, Z (/km)

0.4178

Voltage at 2nd node, V2 (V)

139.17

Power loss P loss (kW)

3.95

Voltage drop, dV (V)

90.83

% Voltage drop

39.49

List of References
Small Hydropower Promotion Project (SHPP)/GTZ
1 Mini-Grid Support Programme, Alternative Energy Promotion Centre, Kathmandu, Nepal
(2002), Peltric Standards
2 Mini-Grid Support Programme, Alternative Energy Promotion Centre, Kathmandu, Nepal
(2003), Preliminary Feasibility Studies of Prospective Micro-hydro Projects
3 Mini-Grid Support Programme, Alternative Energy Promotion Centre , Kathmandu,
Nepal(2001), Technical Details and Cost Estimate
4 Mini-Grid Support Programme, Alternative Energy Promotion Centre , Kathmandu,
Nepal(2003), Guidelines for Detailed Feasibility Study of Micro-Hydro Projects
5 European Small Hydropower Association (1998), Layman's Guidebook on How to Develop
a Small Hydro Site
6 BPC Hydroconsult, Intermediate Technology Development Group (ITDG), Kathmandu,
Nepal (2002), Civil Works Guidelines for Micro-Hydropower in Nepal.
7 United Nations Industrial Development Organization (UNIDO), Report on Standardiztion of
Civil Works for Small Hydropower Plants
8 GTZ/Department of Energy Development, Energy Division, Papua New Guinea, Micro
Hydropower Training Modules (1994), Modules 1-7, 10, 13, 14 & 18B.
9 Americal Society of Civil Engineer (ASCE), Sediment Transportation.
10 KB Raina & SK Bhattacharya, New Age International (P) Ltd (1999), Electrical Design
Estimating and Costing.
11 Badri Ram & DN Vishwakarma, Tata McGraw-Hill Publishing Company Limited, New Delhi
(1995), Power System Protection and Switchgear.
12 Adam Harvey et.al. (1993), Micro-Hydro Design Manual, A guide to small-scale water
power schemes, Intermediate Technology Publications, ISBN 1 85339 103 4.
13 Allen R. Inversin (1986), Micro-Hydropower Sourcebook, A Practical Guide to Design and
Implementation in Developing Countries, NRECA International Foundation, 1800
Massachusetts Avenue N. W., Washington, DC 20036.
14 Helmut Lauterjung/Gangolf Schmidt (1989), Planning of Intake Structures, GATE/GTZ,
Vieweg.
15 Methodologies for estimating hydrologic characteristics of ungauged locations in Nepal
(1990), HMG of Nepal, Ministry of Water Resources, Water and Energy Commission
Secretariat, Department of Hydrology and Meteorology.
16 Design Manuals for Irrigation Projects in Nepal (1990), Planning and Design Strengthening
Project (PDSP), His Majesty's Government of Nepal, Ministry of Water Resources,
Department of Irrigation. United Nations Development Programme (NEP/85/013)/World
Bank.
17 Salleri Chialsa Small Hydel Project (1983), Technical Report, DEH/SATA, ITECO.
18 P.N. Khanna (1996), Indian Practical Civil Engineer's Handbook, 15th Edition, Engineer's
Publishers, Post Box 725, New Delhi - 110001.

Das könnte Ihnen auch gefallen