Beruflich Dokumente
Kultur Dokumente
LIST OF TABLES
Table 1.2.1 Classification of Terrain .......................................................................... 5
Table 1.2.2 Traffic data for Palugama-Boralanda-Haputale road............................... 7
Table 1.2.3 Relationship of the Design Speed related with the Road Classification,
Terrain and the Design Volume. .................................................................................... 9
Table 1.3.1 Minimum width of sealed pavements of undivided roads ..................... 13
Table 1.3.2 Design Level of Service ......................................................................... 14
Table 1.3.3 Adjustment factors for directional distribution (f d) .............................. 16
Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and
restricted shoulder width (f w) ...................................................................................... 16
Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane
Highways over Different Terrain Segments ................................................................ 16
Table 1.4.1 - Recommended Cross-falls on Straight for Different Surface Types ...... 23
v
LIST OF FIGURES
Figure 1.1.1 Location Map of Palugama-Boralanda-Haputale road. .......................... 4
Figure 1.4.1 Typical cross section of a road ............................................................. 20
Figure 1.7.2 - Edge profile for a Circular curve .......................................................... 49
Figure 1.7.3 - Edge profile for Reverse curve ............................................................. 50
Figure 1.7.4 - Edge profile for Compound curve......................................................... 51
Figure 1.7.5 Development of superelevation in sealed shoulder .............................. 52
Figure 1.7.6 Development of superelevation in unsealed shoulder .......................... 52
Figure 1.8.1 Basic Elements of a typical vertical curve ........................................... 54
Figure 1.8.2 Crest vertical curves ............................................................................. 55
Figure 1.8.3 Sag vertical curves ................................................................................ 61
Figure 2.2.1 Traffic Data at the intersection from 7.00 to 19.00 hrs ........................ 76
Figure 2.4.1 Geometric Elements of a Roundabout .................................................. 89
Figure 2.5.1(a) Traffic turning volumes in Morning Peak hour (9.15-10.15) .......... 99
Figure 2.5.1(b) Traffic turning volumes in Mid day Peak hour (11.00-12.00)....... 100
Figure 2.5.1(c) Traffic turning volumes in Evening Peak hour (17.00-18.00) ....... 101
Figure 2.5.2 Required No. of Circulating and Entry lanes ................................... 102
Figure 2.5.3 Proportion of vehicles stopped on a multi lane entry roundabout ....... 115
Figure 2.5.4 Definitions of the terms used in Table 2.5.11(a) and 2.5.11(b).......... 118
Figure 2.5.5 Alternative 1 ....................................................................................... 125
Figure 2.5.6 Alternative 2 ....................................................................................... 126
Figure 2.5.7 Alternative 3 ....................................................................................... 127
Figure 2.5.8 Alternative 4 ....................................................................................... 128
Figure 2.5.9 Alternative 5 ....................................................................................... 129
Figure 2.7.1 Derivation of turning roadway width on curves at intersection ......... 132
Figure 3.2.1 Rainfall Intensity Duration Curves.................................................. 142
Figure 3.2.2 Coefficient of Run-off ........................................................................ 149
Figure 3.3.1 Flow in Triangular Gutter ................................................................... 151
vii
viii
REPORT
ON
GEOMETRIC DESIGN
OF
PALUGAMA-BORALANDA-HAPUTALE ROAD
(B 353) FROM 0+000 TO 27+200
(SECTION FROM 2+800 TO 5+450)
1.1 INTRODUCTION
1.1.1 GENERAL
Geometric design is an important aspect of Highway Design dealing with the visible
dimensions of a roadway. To produce a well balanced design, all geometric elements
such as
Horizontal alignment
Vertical alignment
Sight distances
Cross-section components
Lateral and vertical clearance
Intersection treatment
Control of access
A well designed highway has to be consistent with the economy. There are some
other factors influence the geometric design are the availability of funds and the
adjacent land use. If design is carried out improperly it may result in early
obsolescence of the new highway with considerable economic losses.
Carriageway is not divided into lanes and no built up drains are provided. Bends are
not met with geometric standards. The travelers those who are going visit the
Adisham Bungalow which is a historic place popular among the locals and foreigners
have to go along the this particular road. If the mobility had been improved in this
road it will be helpful for the tourism industry. These factors had been inspired to
improve this road.
The other factors lead to improve the above road is the poor vertical alignment,
narrow carriageway width, poor sight distance and humpy road surface.
This report describes the general principles of the geometric design and its
application to the detailed design of Palugama-Boralanda-Haputale road from
chainage 2+800 to 5+450.
1.2.1. TOPOGRAPHY
Terrain type is one of the main factors which govern the vehicular speed. Terrain also
has a significant effect on the costs of achieving high geometric standards. Therefore
terrain can be considered as one of the main element used in selecting the design
criteria. In geometric design, roads are divided into sections with uniform terrain
characteristics, i.e. Flat, Rolling, Mountainous. Table 1.2.1 gives the classification of
terrain based on its representative slope.
Code
Corridor Slope %
Flat
10
Rolling
10-25
Mountainous
>25
The topography of the section from 2+800 to 3+500 and from 4+750 to 5+450 of
Palugama-Boralanda-Haputale road can be considered as flat. The remaining section
is a Rolling terrain.
1.2.2. TRAFFIC
The geometric design of roads is mainly based on the traffic data. Traffic data is
classified as follows.
I. Volume of Traffic.
A road should be designed so that it will accommodate, or can be readily
changed to accommodate, the number of vehicles which is estimated will be
using at the end of its service life with a desired level of service. The traffic
volume is usually the Annual Average Daily Traffic (AADT) and number of
traffic lanes required is a function of traffic volume. The number of vehicles
using a road in a given time determines the number of traffic lanes required.
Traffic data given by the Traffic & Planning Division of Road Development Authority
in Palugama-Boralanda-Haputale road is tabulated in Table 1.2.2.
Vehicle Composition
Percentage %
Motor Cycle
28.99
Three wheel
31.39
Car
8.15
Van
5.66
Medium Bus
0.69
Large Bus
7.89
5.49
6.17
Large Lorries
2.49
Farm Vehicles
3.09
The design vehicle is a motor vehicle whose weight dimensions and operating
characteristics are used to establish design controls. For this purpose vehicles are
classified into following groups.
I.
II.
P design vehicle
SU design vehicle
III.
IV.
1.2.3. SPEED
Speed maintained by a driver for a given road section depends upon following
conditions.
I. Type of terrain.
II. Weather.
III. Volume of traffic.
IV. Speed limitations.
Design speed applies to individual geometric elements and is the speed that is used to
co-ordinate sight distance, curve radius, super elevation and friction demand for
elements of the road so that the driver negotiating each element at its design speeds.
The design speed for this particular road is 40km/h. But the topographic constrains
limit the design speed to 30km/h in some sections.
Table 1.2.3 gives the design speed values corresponding to the road class, terrain type
and design volume.
Table 1.2.3 Relationship of the Design Speed related with the Road Classification,
Terrain and the Design Volume.
Type of
Road
Road Class
R0
R1
Design
Design Speed
Volume
Km/h
PCU/day
Rural
Urban
80
70
80
70
70
60
80
70
70
70
60
60
70
60
60
60
50
50
60
50
50
50
40
40
50
40
40
40
30
30
Terrain
F
F
R
72,000108,000
40,000-72,000
F
R2
R3
R4
R5
A,B
A,B
C,D
D,E
25,000-40,000
18,000-25,000
300-18,000
<300
1.2.4. SAFETY
Whatever design standard is adopted, safety is the major element to be improved for
both vehicle users and pedestrians.
With the increase of number of decisions required to take the driver, number of
crashes increases. Therefore a Highway should be designed to minimize making
decisions while driving and to reduce unexpected situations. To reduce the number of
decision making, highways shall be design in uniform manner & accommodate proper
9
The existing trace is having poor geometric features such as inadequate sight
distances at the bends and inadequate carriageway and shoulder width. As these sub
standard will tend to promotes accidents, in designing new trace adequate amounts
were provided for above.
10
1.3.1. GENERAL
Width of traffic lane influence the safety, comfort of driving and Level Of Service of
that particular road. With the increase of lane width vehicles could be driven freely in
a broaden width. Hence it provides safety and comfort of driving. The width of
carriageway is determined in terms of the number of traffic lanes and width of a
traffic lane. Number of lanes to be provided depends on the present and future
anticipated traffic volume. Shoulder is the portion traveled adjoining to the outer edge
of the traffic lane. Wider shoulder will be provided emergency stops for the vehicles.
11
12
Speed
volumes(AADT)
Km/h
1-140
141-300
301-1100
1101-2200
Over 2200
40
3.7
5.6
6.2
50
3.7
5.6
6.2
6.8
7.4
60
3.7
6.2
6.8
6.8
7.4
70
3.7
6.2
6.8
6.8
7.4
80
3.7
6.2
6.8
7.4
7.4
90
3.7
6.2
6.8
7.4
7.4
100
3.7
6.8
6.8
7.4
7.4
110
3.7
6.8
7.4
7.4
7.4
120
3.7
6.8
7.4
7.4
7.4
The concept of Level Of Service (LOS) is the different operational qualities of the
traffic flow. Level Of Service is a qualitative measure of speed and travel time,
freedom to maneuvers, traffic interruption, driving comfort, convenience, safety and
operating cost.
Six Level Of Service are categorized from A to F and it cover entire range of traffic
condition which may occur.
Level Of Service A Free flow with high speed and low volumes. Drivers can hold
their desired speeds without delays.
13
Level Of Service B Reasonably free flow. Stable flow and drivers have reasonable
freedom to select their speed.
Level Of Service C Stable flow. Most drivers are restricted in their freedom to select
their own speed, change lanes, overtake etc... But operating speeds are still
reasonable.
Level Of Service D Approaches unstable flow with nearly all drivers restricted.
Comfort and convenience are low but may be tolerated for short periods. Fluctuations
in conditions cause substantial drops in speed. As this service volume corresponds to
what is referred as tolerable capacity, this level of service should be used to determine
the upper limit of traffic demand which should be tolerated.
Level Of Service E Unstable flow and there may be momentary stoppages. This
LOS is obtained with traffic volumes with near or at capacity.
Level Of Service F Forced or breakdown flow operating at low speed caused by the
demand exceeding capacity. There is stop-start operation with large queues and
delays. In the extreme both speed and volume can drop to zero.
New roads are normally designed for LOS C or even D. The design level of service
may be as in the Table 1.3.2.
Design
Design Level Of
Volume/Capacity
speed(km/h)
Service
ratio
70 or more
0.6-0.8
60 or more
0.8-0.9
C,D,E
50 or more
>0.9
Road Class
14
The capacity is the maximum hourly rate at which vehicles can reasonably be
expected to traverse a point or uniform section of a lane at LOS E.
The service flow rate is the maximum hourly rate of a lane or roadway under
prevailing roadway, traffic and control conditions while maintaining a designated
level of service. To calculate the service flow rate, equation 1.3.1 and 1.3.2 is applied.
( c) * f
SF i = 2800 * v
* f w * f HV
. (1.3.1)
. (1.3.2)
Where:
SFi
= Total service flow rate in both directions for prevailing roadway and
Traffic conditions, for level of service i, in vph
(v/c)i = Ratio of flow rate to ideal capacity for level of service i, obtained from
Table 1.3.2
fd
fw
= Adjustment factor for narrow lanes and restricted shoulder width, obtained
from Table 1.3.4
fHV
= Adjustment factor for the presence of heavy vehicles in the traffic stream
PT
PB
ET, EB = Passenger car equivalent for trucks and buses obtained from Table 1.3.5
15
90/10
80/20
70/30
60/40
50/50
0.71
0.75
0.83
0.89
0.94
1.00
Adjustment Factor, fd
Table 1.3.4 - Adjustment factors for the combined effect of narrow lanes and
restricted shoulder width (f w)
Usable
Shoulder
Width
(m)
>=1.8
1.2
0.6
0
3.7 m Lanes
3.4 m Lanes
3.0 m Lanes
2.7 m Lanes
LOS
A-D
LOS
E
LOS
A-D
LOS
E
LOS
A-D
LOS
E
LOS
A-D
LOS
E
1.00
0.92
0.81
0.70
1.00
0.97
0.93
0.88
0.93
0.85
0.75
0.65
0.94
0.92
0.88
0.82
0.84
0.77
0.68
0.58
0.87
0.85
0.81
0.75
0.70
0.65
0.57
0.49
0.76
0.74
0.70
0.66
Table 1.3.5 - Average Passenger Car Equivalent for Trucks and Buses on Two Lane
Highways over Different Terrain Segments
Vehicle Type
Trucks, ET
Buses, EB
Level Of Service
Type of Terrain
Level
Rolling
Mountainous
2.0
4.0
7.0
B and C
2.2
5.0
10.0
D and E
2.0
5.0
12.0
1.8
3.0
5.7
B and C
2.0
3.4
6.0
D and E
1.6
2.9
6.5
16
= 1399(In 2009)
= 10% of ADT
= 140
fd
fw
(v/c)I
PT
=17.24% (5.49%+6.17%+2.49%+3.09%)
PB
=8.58% (0.69%+7.89%)
ET
=5.0
EB
=2.9
= 0.54
= 875
Traffic growth rate is 5% and assuming the road will reach to its capacity after n
years.
875
= 140 x (1.05)n
=37.5
The road will maintain the LOS D for 37 years from 2009.
17
The width of shoulder should be chosen in relationship to the traffic and topography
after due consideration of the following
a) Provision of space for
Emergency operations
A lane width of 2.5 m is needed to allow a passenger vehicle to stop clear of the
traffic lane. A width of 3.0 m allows a passenger vehicle to stop clear of the traffic
lanes and provides an additional clearance to passing traffic. It also allows a
commercial vehicle to stop clear of the traffic lanes.
18
1.4.1. GENERAL
The cross section of a road consists of the following items. (Refer Figure 1.4.1)
I. Carriageway.
II. Shoulder.
III. Median.
IV. Platforms.
V. Cross fall.
VI. Drains.
VII. Batters.
VIII. Parking Strips.
IX. Right Of Way.
19
20
1.4.2. CARRIGEWAY
The carriageway is the surface on which the vehicles are expected to run.
Carriageways are classified as single-lane, two-lane or multi-lane. A traffic lane is
defined as the width used for single line of traffic operation. The desirable lane width
is taken as 3.7m. The absolute minimum lane width shall be 3.1m. For multi-lane
roads carriageway is divided into two parts by introducing a median. Then vehicles
are moving in opposite direction at each part. Such carriageway is called a duelcarrigeway.
1.4.3. SHOULDER
Shoulder is the portion traveled adjoining to the outer edge of the carriageway that
accommodates stopped vehicles, emergency use and lateral support of sub base, base
and surface course. In the absence of foot walk, shoulders could be used for
pedestrians also. It may be of compacted earth or gravel. In some cases shoulders may
be totally or partly sealed. The desirable width of shoulder is 3.0m and minimum
shoulder width may be 2.4m and absolute minimum width may be 1.8m.
1.4.4. MEDIAN
Median is the land of dividing the carriageway in order to avoid the collision of
opposing vehicles. Normally center median accommodate for 4-lane or multi-lane
roads. To clearly identify the centre median from the carriageway, median may be
raised, flush or provide small humps at regular intervals. The main advantages of
providing the centre median are to separate opposing traffics, provide refugee area for
21
1.4.5. PLATFORM
Carriageway and shoulder on either side when taking together is called as the
platform.
1.4.6. CROSSFALL
1.4.6.1. GENERAL
The carriageway crossfall is the slope of the carriageway measured at right angles to
the horizontal alignment and shoulder crossfall could be similarly defined. The main
purpose of introducing crossfall is to ensure sufficient drain the road surface.
Generally shoulder crossfall is steeper than the carriageway crossfall and should be
varied with the surface material.
22
Recommended Crossfall
2.0%
Asphalt Concrete
2.5%
Surface Seals
3.0%
Unsealed Gravel
4.0%
The recommended crossfall values for the shoulder are tabulated Table 1.4.2.
Recommended Crossfall
3-4%
Gravel
4-5%
1.4.7. DRAINS
Drains are provided for collecting and conveying of water from the road surface. The
selected cross section of drain should have the sufficient capacity to dispose the rain
water collected from the road platform.
23
No intercepter drains are provided for this particular section on PalugamaBoralanda-Haputale road since embankment cut height is always less than 6m.
Cross Shoulder Drains were not provided in the design of Palugama-BoralandaHaputale road.
1.4.8. BATTERS
25
1.4.9.1. GENERAL
Every vehicle owner wishes to park the vehicle as close as possible to his destination
so as to minimize his walking. Also spaces are required to vehicles to load or unload
goods. This results a great demand for parking spaces in the urban area where bare
land around the road is limited.
In urban areas, parking bays should be provided for commercial vehicles to load and
unload merchandise and customers vehicles. Location of parking bay is important as
it influence the success in attracting motorists.
Generally 3% -4% cross fall is adopted for parking strips in both angle and parallel
parking.
1.5.1. GENERAL
Sight distance in road design is the distance at which a driver of a vehicle can see an
object of specified height on the road ahead of him assuming satisfactory conditions
prevail to ensure visibility. A driver ability to see ahead is of the most importance in
the safe and efficient operation of a vehicle on a road. For safety on road the designer
should provide sight distance of sufficient length that drivers can control the vehicles
to avoid striking an unexpected object on traveled way.
1.05m
Commercial Vehicle
1.80m
1.15m
Stationary Object
0.20m
0.60m
0.75m
1.00deg
Vertical clearance
5.20m
Stopping sight distance has two compartments; the distance traveled during total
reaction time and the distance traveled during breaking time.
t RV
V2
SSD =
+
3.6 254
.. (1.5.1)
SSD
tR
29
The value of Coefficient of Longitudinal Friction () varies with speed, tyre pressure,
tyre condition, type of pavement and whether the surface is dry or wet. The
Coefficient of Longitudinal Friction () values assumed are tabulated in Table 1.5.1.
Friction Factor ()
30
0.40
40
0.38
50
0.35
60
0.33
70
0.31
80
0.30
90
0.30
100
0.29
tR = 2.5s
From Equation 1.5.1,
SSD = 2.5 x 40/3.6 + 402/ (254 x 0.38)
= 44.35 m
By rounding, SSD = 45 m
30
t RV
V2
SSD =
+
3.6 254( 0.01G )
G
.. (1.5.1)
The calculated stopping sight distances for each speed are given in Table 1.5.2.
The overtaken vehicle travels uniformly at one step lower than the
design speed.
With these assumptions, calculated sight distances required for overtaking at various
speeds are also tabulated in Table 1.5.2.
31
As the road is located in mountainous terrain and due to land acquisition problems
overtaking sight distance was not strictly followed.
The design Continuation sight distance values are tabulated in Table 1.5.2
Table 1.5.2 - Design Values for Stopping, Overtaking & Intermediate Sight Distances
on Bituminous and Concrete Pavements
Design speed(kmph)
Stopping Sight
Continuation Sight
Distance(SSD) - m Distance(CSD) - m
Overtaking Sight
Distance(OSD) m
30
30.0
60.0
160
40
45.0
90.0
220
50
65.0
130.0
280
60
85.0
170.0
350
70
115.0
230.0
430
80
140.0
280.0
520
100
205.0
410.0
690
1.05
1.05
1.05
0.20
1.15
1.15
32
1.6.1. INTRODUCTION
The important consideration in determining the horizontal alignment of a road is the
provision of safe and continuation operation for substantial lengths of roadway. The
horizontal alignment of a road is usually a series of straights and circular curves
connected by transition curves.
When introducing horizontal curves, following aspects such as the minimum radii,
transition lengths, pavement widening and superelevation required has to pay special
attention.
From the first principals the following equation could be derived for normal values of
superelevation;
V2
e+ f =
127 R
.. (1.6.1)
Where;
e
= Superelevation.
By rearranging the above formula, a minimum curve radius can be determined using
the maximum values for superelevation (emax) and maximum side friction factors
(fmax) for a given design speed(V).
Rmin
V2
=
127(emax + f max )
(1.6.2)
Therefore maximum values for superelevation and side friction factors have to be
determined. The maximum superelevation used on highways is controlled by many
factors. Those are climate condition, terrain type, type of area and frequency of slow
moving vehicles whose operation might be affected by high superelevation rates.
Consideration of these factors jointly leads to the conclusion that no single maximum
superelevation rate is universally applicable that a range of value should be used.
Therefore the range of values suit Sri Lanka for Maximum superelevation (emax) was
tabulated in Table 1.6.1.
34
emax
Open
Build-up
Flat
6%
6%
Rolling
8%
6%
Mountainous
10%
6%
By considering safety and comfort the maximum values of side friction factor adopted
for the design of horizontal curves for paved and unpaved roads are tabulated in Table
1.6.2.
35
Design speed(kmph)
Gravel Roads
30
0.210
0.140
40
0.190
0.130
50
0.170
0.120
60
0.160
0.110
70
0.150
0.100
80
0.140
0.090
90
0.130
100
0.128
1.6.4.1 GENERAL
Horizontal curvature is a shape to provide for places where change in direction occurs
of the designed centre line. Depending on the changes of the direction, one of the
following curve types could be introduced at the design stage.
I. Simple circular curve.
II. Transition curve.
III. Compound curve (Unidirectional curve).
IV. Reverse curve.
36
37
Design
Speed(kmph)
2.5%
3.0%
4.0%
5.0%
6.0%
7.0%
8.0%
9.0%
10.0%
30
35
30
30
30
30
30
25
25
25
40
60
60
55
55
55
50
50
45
45
50
105
100
95
90
90
85
80
80
75
60
155
150
145
135
130
125
120
115
110
70
225
215
205
195
185
180
170
165
155
80
310
300
280
270
255
240
230
220
210
90
415
400
380
355
340
320
305
290
280
100
515
500
470
445
420
400
380
365
350
In this design the radius selected for two curves and their corresponding
superelevation values are as in the Table 1.6.4
Chainage
Radius of the
Superelevation
Curve (m)
3+272.04 3+327.28
70
2.5%
3+737.00 3+791.99
160
2.5%
Ls is required to
Ls.
The advantages of adopting the transition curve in horizontal alignment are the
following.
I. To provide a natural, easy-to-follow path for drivers, such that the lateral
force increases and decreases gradually as a vehicle enters and leaves a
circular curve.
II. To provide a length over which the super elevation development can be
applied.
III. To provide flexibility in accomplishing the widening of sharp curves.
IV. To improve the appearance of the road by avoiding sharp discontinuities in
alignment at the circular curves.
Transition curves are used when the design speed is higher than 70km/h. Since
maximum design speed used in Sri Lanka is less or equal to 70 km/h use of transition
curve has been limited.
39
This consists of two curves in the same direction formed by a short tangent. Attempt
should be made to avoid this type of alignment by adopting a Simple Curve or a
Compound Curve. When Similar Curves are unavoidable, tangent lengths in the range
of 0.6 V to 3 V should be avoided. (Where V is the Design Speed in km/h for the
particular trace)
40
Table 1.6.5 Design values for pavement widening on open highway curves
6.2 meters
Radius of
Design speed (km/h)
curve (m)
30
40
50
60
70
300
0.5
0.6
0.6
0.7
0.7
250
0.5
0.6
0.7
0.7
0.8
200
0.6
0.7
0.8
0.8
0.9
150
0.8
0.9
1.0
1.1
1.1
140
0.8
0.9
1.0
1.1
130
0.9
0.9
1.0
1.1
120
0.9
1.0
1.1
1.2
110
0.9
1.0
1.1
1.2
100
1.0
1.1
1.2
90
1.1
1.2
1.3
80
1.1
1.2
1.3
70
1.2
1.3
60
1.3
1.5
50
1.6
1.7
40
1.8
30
2.0
41
1.7. SUPERELEVATION
1.7.1. GENERAL
When vehicle travels along a curve it experiences a force called centrifugal force.
Centrifugal force increases when the velocity of the vehicle increases and the radius
of the curvature decreases. To balance the effects of the centrifugal force curves
should be superelevated. The amount of superelevation will depend on the radius of
the curve, design speed and pavement surface characteristics.
42
Built-up
30
205
160
40
360
280
50
565
440
60
810
630
70
1105
860
80
1440
1120
90
1825
1420
100
2250
1750
That rotate line is defined as the axis of rotation. Position of the axis of rotation is
depend upon the type of terrain and type of the road. For two lane undivided road
usually the centre line of the road is taken as the axis of rotation. In the case of wide
medians it is general practice to assume the median edge of pavement or shoulder as
the axis of rotation.
Centre line was taken as the axis of rotation for the design of Palugama-BoralandaHaputale road.
A change from normal cross fall to super-elevation occurs as the road changes from a
straight to curved alignment. The length required to develop super-elevation should be
adequate to ensure a good appearance and give satisfactory riding qualities.
Le =
W (e + n )
Gr
Where;
Le
= Superelevation
= Normal crossfall
Gr
.. (1.7.1)
Design
Speed(kmph)
1 Lane
2 Lane
>2 Lane
30
1.00
1.50
2.00
40
0.83
1.25
1.66
50
0.71
1.07
1.42
60
0.63
0.95
1.26
70
0.56
0.84
1.12
80
0.50
0.75
1.00
90
0.45
0.68
0.90
100
0.42
0.63
0.84
The rate of rotation is defined as a change in the crossfall from normal crossfall to full
superelevation over the time, required by a vehicle traveling as the design speed along
the length where the change occurs.
The length of superelevation development is given by following expression.
Le =
( e + n )V
3 .6
.. (1.7.2)
Where;
Le
= Superelevation
= Normal crossfall
45
The rate of pavement rotation is recommended to be 0.035rad/s for design speeds less
than 80kmph and to be 0.025rad/s for design speed greater or equal to 80kmph.
The maximum value given from above two equations is taken as the superelevation
development length by rounding to next highest multiple of three.
Design speed
=40km/h
Lane width
=3.2m
Superelevation
=2.5%
Normal crossfall
=2.5%
Relative gradient
=0.83
Rate of rotation
=0.035
=19.28m
=15.87m
=19.87m
=21.00m
46
e
(%)
2-lane roads
V=40kmph
4-lane roads
2-lane roads
4-lane roads
AC 205
20
20
20
20
360
30
30
30
30
2.5
35
20
20
30
30
60
30
30
30
30
30
20
30
30
30
**
**
55
30
30
40
40
**
**
**
**
**
50
40
50
60
60
25
40
40
40
40
**
**
45
50
60
70
70
10
**
**
V=50kmph
e
(%)
2-lane roads
V=60kmph
4-lane roads
2-lane roads
4-lane roads
AC 565
30
30
30
30
810
40
40
40
40
2.5
105
30
30
40
40
155
40
40
40
40
100
30
30
40
40
150
40
40
50
50
95
30
40
50
50
145
40
40
50
60
90
40
40
50
60
135
40
50
60
60
**
130
50
60
70
70
85
50
50
70
70
125
50
60
80
80
80
50
60
70
80
120
60.
70
80
90
**
115
60
70
90
100
10
75
60
70
90
90
110
70
80
100
100
47
V=70kmph
e
(%)
2-lane roads
V=80kmph
4-lane roads
2-lane roads
4-lane roads
AC 1105
40
40
40
40
1440
50
50
50
50
2.5
225
40
40
50
50
310
50
50
50
50
215
40
40
50
50
300
50
50
60
60
205
40
50
60
60
280
60
60
70
70
195
50
50
70
70
270
70
70
80
80
185
50
60
80
80
255
80
80
80
90
180
60
70
80
90
240
90
90
90
100
170
60
70
90
100
230
100.
100
100
110
165
70
80
100
110
220
110
110
110
120
10
155
70
90
110
120
210
120
120
120
130
a) Tangent to circular.
shows the position of superelevation development length from tangent to circular and
Figure 1.7.2 shows edge profile for a circular curve.
Superelevation development lengths for tangent to circular curves have been designed
according to above method in Palugama-Boralanda-Haputale road.
48
3L
3L
C urve
3L
TC
3L
CT
T a n g e n t p o in t s
b) Reverse curve
For common or closely spaced tangent points, all or most of the development must be
within the circular arc. Typical edge profiles for reverse curves having common and
closely spaced tangent points are shown in figure 1.7.3
49
Superelevation development lengths for reverse curves have been designed according
to above method in Palugama-Boralanda-Haputale road.
c) Compound Curves
For common or closely spaced tangent points (i.e. the tangent points separated by less
than 70% of the total length required to develop super-elevation) position the change
in super-elevation development evenly about common tangent point or tangent points.
(Refer Figure 1.7.4)
50
1. Sealed Shoulder
On the high side of the super-elevation, the shoulder is rotated to match the cross
fall of the adjacent lane and then the whole carriageway is rotated as a plane
surface until the required super-elevation is achieved.
2. Unsealed Shoulders
To prevent length of unsealed shoulders being at level cross fall when the
pavement is level during superelevation development, these shoulders are
superelevated as shown in Figure 1.7.6
51
52
1.8.1. GENERAL
The following general controls for vertical alignment should be kept in view in
designing the vertical profile of a road.
I. The selected grade line shall be smooth with gradual changes, consistent to
class of the road and terrain type.
II. Two vertical curves in the same direction separated by short section of
tangent grade should be generally avoided.
III. On long grades it may be preferable to place the steepest grade at the
bottom and flattern the grade at shorter intervals of lighter grade instead of
uniformly sustained grade.
IV. Hidden type of profile should be avoided as it is hazardous and
aesthetically unpleasant.
53
Various types of curves can be used as the vertical curves of a road. But the
considering of ease of manual computation and a constant rate of change of curvature
along the length, the type of curve used as vertical curve is the simple parabola.
The basic parabolic equation derived to calculate the elements of a vertical curve is
expressed as follows.
Y=
A
X2
200 Lv
.. (1.8.1)
Where;
Y =
X =
A =
Lv =
1.8.3.1.1. GENERAL
The vertical curve having convexity upward is called a crest vertical curve. This curve
develops when an ascending road intersects a descending road or when an ascending
gradient meet descending gradients in convex manner. (Figure 1.8.2)
Minimum length of crest vertical curves based on sight distance criteria, riding
comfort or by appearance requirements.
LV =
Where Lv
AS 2
200( h1 + h2 ) 2
.. (1.8.2)
h1
h2
Since S, h1 and h2 are fixed values and only A is the variable. Therefore above
equation can be expressed as a linear function of Lv = KA, where K (in m per %) is a
constant for each design speed.
The calculated length of vertical curve is rounded up to the next highest multiply of
10m. Table 1.8.1 gives the minimum lengths of crest vertical curves for Sight distance
criteria.
Table 1.8.1 - Minimum Crest Vertical Curve Length Based on Sight Distance Criteria
Continuation Sight
Overtaking Sight
Distance
Distance
Distance
h1=1.05
h1=1.05
h1=1.05
h2=0.2
h2=1.15
h2=1.15
30
2.1
4.1
29.1
40
4.7
9.2
55
50
9.8
19.2
89.1
60
17
33
139.3
70
31
60
210.2
80
45
89
307.4
100
97
191
541.3
Design Speed
(kmph)
Lv = 2 S
200 h1 + h2
A
56
.. (1.8.3)
Where
Lv
h1
h2
The lengths of vertical curve resulting from Equation 1.8.3 are insignificantly less
than those resulting from Equation 1.8.2 for S < L, except for the curves with very
small A values and high Design Speeds.
Therefore it may be argued that if the standard values should be calculated only with
reference to equation 1.8.2, taking also the fact that in normal design practice the
length of vertical curve is rounded up to the next highest multiple of 10m.
Hence, the K values of vertical crest curve given in Table 1.8.1 can be applied to both
cases, whether the sight distance is shorter than the length of vertical curve or not.
Specimen calculations
h2 = 0.2m
1.5.2)
Therefore
K = 4.7
h2 = 1.15m
1.5.2)
Therefore
K = 9.2
57
h1 = 1.05m
h2 = 1.15m
1.5.2)
Therefore
K =55
2. Appearance Criterion
At very small changes of grade, a vertical curve has little influence other than
appearance of the profile and may be omitted. At any significant change of grade,
short vertical curve detract from the appearance. This is particularly evident on high
standard roads.
Table 1.8.2 gives vertical curve lengths on the basis of appearance. Longer curves
may be preferred, where they can be used without conflict with other design
requirements and where they give a better fit to the topography.
Design Speed
Minimum length of
(km/h)
30
1.3
30
40
1.3
40
50
1.0
50
60
0.8
50
70
0.7
60
80
0.6
70
100
0.3
90
58
Minimum curve length for Appearance Criteria was provided on all crest curves in
Palugama-Boralanda-Haputale road.
Curves should be provided at all grade changes exceeding the values shown in Table
1.8.2.
This criterion is not fulfilled in designing of crest vertical curves in PalugamaBoralanda-Haputale road.
4. Comfort Criterion
The resolved component in the vertical direction, of the acceleration normal to the
curve, due to traversing the path of parabolic vertical curve at uniform speed is given
by;
v2 A
v2
a=
=
100 L v 100 K
.. (1.8.4)
The adopted design value for a is 0.03g. Values of K for specific design speed and
vertical acceleration of 0.03g are shown in Table 1.8.3
59
Minimum curve length for Comfort Criterion is provided on all crest curves in
Palugama-Boralanda-Haputale road.
30
2.4
40
4.2
50
6.5
60
9.4
70
13
80
17
100
26
5. Drainage Considerations
60
1.8.3.2.1. GENERAL
The vertical curve having convexity downward is called a sag vertical curve. This
curve develops when an ascending road intersects a descending road or when
ascending gradients meet or descending gradients meet in concave manner(Refer
Figure 1.8.3). There is no restriction to sight distance during day time on sag vertical
curve. But during night time visibility is limited by the distance illuminated by the
head light beam. Therefore in designing sag vertical curve, a head light criterion is the
main criterion. Other criteria are the Appearance criterion, Comfort criterion, Over
Head Obstruction and Drainage Considerations.
Based on the Head Light Criterion, length of sag vertical curve is given by;
AS 2
Lv =
120 + 3.5S
61
.. (1.8.5)
Where
Lv
From the above equation minimum length of sag vertical curve for various design
speed is tabulated in Table 1.8.4.
Table 1.8.4 - Minimum Sag Vertical Curve Length Based on Head Light Sight
Distance Criterion
Design Speed(kmph)
30
4.0
40
7.3
50
12
60
17
70
25
80
32
100
50
Specimen Calculations
S = 45 m for Design Speed of 40 km / h (Refer Table 1.5.2)
K = 452/ (120 + 3.5 x 45)
= 7.3
Minimum curve length for Head Light Criterion is provided on all sag curves in
Palugama-Boralanda-Haputale road.
Based on the Over Head Obstruction, length of sag vertical curve is given by;
62
Lv =
Where Lv
200
AS 2
(H h1 + (H h2 ) )2
h1
h2
.. (1.8.6)
3. Appearance Criterion
Minimum curve length for Appearance Criteria is provided on all sag curves in
Palugama-Boralanda-Haputale road.
5. Comfort Criterion
Minimum curve length for Comfort Criterion is provided on all sag curves in
Palugama-Boralanda-Haputale road.
63
6. Drainage Considerations
Minimum longitudinal grade on kerbed pavement should be 0.30 % for satisfactory
drainage. There is a level point on a sag vertical curve, but no difficulty with drainage
on kerbed pavement experienced if the curve is sharp enough so that the minimum
grade of 0.30 % is reached at a point about 15 m from the crest. This corresponds to a
K value of 45 m per percent change in A.
1.8.4. GRADES
1.8.4.1. GENERAL
The gradient of a line is its longitudinal slope and is expressed as the ratio of the
difference in height, of its two ends, to the length between them. The gradient in the
vertical alignment could be taken different values based on the topography of
particular area. To characterize variations in topography, it is generally separate it into
three classifications according to terrain.
In level terrain, highway sight distances, as governed by both horizontal and vertical
restrictions, are generally long or can be made to be so without construction difficulty
or major expense.
In rolling terrain, natural slopes consistently rise above and fall below the road or
street grade, and occasional steep slopes offer some restriction to normal horizontal
and vertical roadway alignment.
64
(a) GENERAL
The grade adopted should allow the average vehicle to climb mountain in top gear at
the design speed or move down without excessive breaking. Therefore to satisfy
above criteria maximum grade should be defined. Also runoff water should drain
along the road. Therefore in the places where almost flat terrain, minimum grades are
involved.
Maximum gradient mainly depend on the type of terrain, speed and class of road.
With the gradient up to 10% satisfactory level of service can be provided. But
gradient over 10% can cause problems of very slow climbing speeds and high
downhill speed for heavy vehicles. In such situations climbing lanes may be provided
to increase capacity and decrease delay & accidents.
Table 1.8.5 illustrate the relevant maximum gradients corresponding to the class of
the roads and terrain type.
65
Terrain type
Maximum gradient
Flat
Rolling
Mountainous
Flat
Rolling
Mountainous
Flat
Rolling
Mountainous
10
Flat
Rolling
10
Mountainous
10
Flat
Rolling
10
Mountainous
10
Gradients steeper than general maximum have to use because of the existing
topography of the section.
Drainage is the main consideration where minimum grades are involved. On flat
terrain the gradient can be flat provided that normal cross fall is available and length
of level gradient to be as small as possible. In rural areas a minimum gradient of 0.5%
should be maintained and in urban areas where pavements are kerbed, minimum
gradient should not be flatter than 0.3%.
66
67
Grade %
480
330
250
200
170
150
140
10
135
12
120
1.9.1. GENERAL
Economics factors often apply the predominant influence and the final result is
usually a compromise between aesthetic considerations and economics.
I. The design speed of the road in both the horizontal and vertical directions
should be of the same order.
68
II. Sharp horizontal curves should not be introduced at or near the top of a vertical
curve as a driver may not identify the change in the alignment, especially at
night. This situation is avoided if the horizontal curve leads the vertical curve.
III. Reverse horizontal curve with crest vertical curves are undesirable if horizontal
curves are short, since the reverse curvature of the alignment is difficult to
understand to the driver by the crest.
IV. It is undesirable to provide a crest of a vertical curve near or at a road
intersection or rail crossing.
V. Short humps in the grade should be avoided.
VI. Adequate visibility should be provided when transitioning from undivided to
divided roads.
I. It is desirable that the horizontal curve is longer than the vertical curve and that
the start of the horizontal curve should ideally lead the start of the vertical curve.
II. A sag vertical curve should be located on the horizontal curve rather than on the
tangent close to the start of the horizontal curve.
III. A short vertical curve on a long horizontal curve looks unpleasantly.
IV. Rolling grades on isolated straights between curves looks unpleasantly.
V. A short tangent in the grade line between sag curves has a poor appearance.
VI. A broken back crest or sag curves has a poor appearance.
VII. A short sag curve on a straight is unsightly, although functionally adequate,
whereas a long sag curve provides continuity and is aesthetically pleasing.
69
1.10. REFERENCES
1. Road Development Authority Geometric Design Standards of Roads 1998
3. National
Association
of
Road
and
Traffic
Authorities
in
Australia
70
.
CANDIDATE
(Eng. P.C.I. Kumaratunga)
..
SENIOR DESIGNS ENGINEER
.
DEPUTY DIRECTOR / HIGHWAY DESIGNS
.
DIRECTOR / HIGHWAY DESIGNS
71
ON
GEOMETRIC DESIGN
OF
INTERSECTION
OF
COLOMBO-GALLE-HAMBANTOTA-WELLAWAYA
ROAD AND HAMBANTOTA BY PASS ROAD
AT
2.1. INTRODUCTION
2.1.1. GENERAL
1.
2.
3.
Channelised
4.
Signalised
The aims of the intersection design are to improve traffic flow and reduce likelihood
of accidents. This is achieved controlling vehicle manoeuvres and reducing the
number of points of conflict. At the same time optimum balance between following
factors has to be achieved.
1. Capacity
2. Delay
3. Safety
4. Cost
5. Environmental Quality
6. Pedestrian Delay and Safety
7. Cyclist Safety
8. Drivers Comfort
73
Although the present traffic movements across the junction is less, it is expected that it
will be increased considerably with the start of functioning of Hambantota Harbour
and Airport.
Traffic movement through Hambantota- Tangalle road was became almost zero with
the construction of Hambantota bypass road through Hambantota saltern. Therefore
in designing the roundabout, Hambantota-Tangalle road was connected to the
Gonnoruwa road before the junction. With this alteration four leg intersection was
become an intersection having only three legs.
74
Traffic indicates the service for which the improvement is being made and directly
affects the geometric features such as widths, alignments and grades.
The traffic data required for the design include the traffic volumes for days of the year
and times of the day, as well as the distribution of vehicles by type. The data also
include information on trends of traffic growths in the future.
The traffic data required for design of this intersection was collected by the Traffic &
Planning Division of the Road Development Authority. (Refer Figure 2.2.1)
The traffic pattern on any highway shows considerable variation in traffic volumes
during the different hours of the day and in hourly volumes throughout the year. It
must be determined which of these hourly traffic volumes should be used in the
design.
It would be wasteful to predicate deign on the peak hour traffic of the year, yet the use
of the average hourly traffic would result in an adequate design. The hourly traffic
volume used in design should not be exceeded very often or by very much. On the
other hand, it should not be so high that traffic would rarely be great enough to make
full use of the resultant facility.
On guide in determining the hourly traffic best fitted for use in design is a curve
showing variation in hourly traffic volume during the year. These curves lead to the
75
conclusion that the hourly traffic used in design should be the 30th highest hourly
volume of the year. It is abbreviated as 30 HV.
However traffic studies in our country has shown that there is not much significant
variation in hourly volumes and hence the peak hour traffic volume is used for the
design purposes. In addition to peak hour traffic volume, their turning movements
were also collected and analysed for the designs.
The peak hour traffic volumes and turning movements relevant to Gabada junction
collected by the Traffic & Planning Division of the Road Development Authority on
08.01.2009 are shown in Table 2.2.1(a) Table 2.2.1(b), Table 2.2.1(c).
Figure 2.2.1 Traffic Data at the intersection from 7.00 to 19.00 hrs
Table 2.2.1 (a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 1015 Hrs) at Gabada Junction (in Veh / h)
LEG
LEG1
LEG2
LEG3
TOTAL
MOVE
MCL
TW
CAR
VAN
MBU
LEG2
30
10
11
LEG3
11
LEG1
22
LEG3
44
13
14
LEG1
15
LEG2
37
159
MENT
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
21
92
16
56
10
10
108
26
13
86
39
41
34
24
25
25
33
384
77
Table 2.2.1 (b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 1200 Hrs) at Gabada Junction (in Veh / h)
LEG
LEG1
LEG2
LEG3
TOTAL
MOVE
MCL
TW
CAR
VAN
MBU
LEG2
31
11
LEG3
LEG1
15
10
LEG3
39
10
13
LEG1
13
LEG2
33
140
MENT
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
10
15
12
97
23
60
13
84
22
17
12
11
91
53
45
34
25
20
32
22
377
78
Table 2.2.1 (c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 1800 Hrs) at Gabada Junction (in Veh / h)
LEG
LEG1
LEG2
LEG3
TOTAL
MOVE
MCL
TW
CAR
VAN
MBU
LEG2
29
15
LEG3
LEG1
30
14
15
LEG3
37
11
LEG1
10
LEG2
46
160
MENT
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
11
86
20
12
97
11
84
20
12
83
41
40
45
29
22
29
16
390
79
Equivalent Factor
Motor cycle
0.4
Three wheeler
0.8
Passenger car
1.0
Van
1.1
Mini Bus
1.8
Large Bus
2.4
1.5
MG1
2.0
MG2
2.5
HG3
3.0
AG3
3.5
AG4
4.0
AG5
5.0
AG6
6.0
FVH
6.0
80
To cater the pedestrian traffic, 2.4 m wide foot-walks are provided within the
intersection limits.
Parking of vehicles near an intersection obstructs the free flow of traffic. Kerb side
parking also affects the capacities of an intersection by narrowing the carriageway
available for moving traffic. However, assessment of the present and future demands
should be made in order to make adequate provision in the intersection design.
Bus halts should be located at places, where its interference on circulating and
through traffic is absolutely in minimum.
At present, there is one bus halt on Weerawila leg of the intersection and, two bus
bays are introduced in places, where their effect on smooth functioning of the
intersection is minimum.
81
The location and design of an intersection will be affected by many factors including
the introduction of new highway, the alignment and the grade of the approach roads,
the neediness of providing drainage, the extent of interference with public utilities,
property access and the local features, both manmade and natural. Some sort of
compromises in design is generally necessary as it is seldom possible to satisfy each
and every requirement.
In designing alignments all attempt should be made to not to disturb features such as
culturally, historically, religiously important.
Overhead and underground utility services which are close enough to the intersection
to be affected, together with any future planned amplification of these services should
be determined in the preliminary stage of the design.
At Gabada junction, there are electrical posts to be shifted and relocated out of the
Right Of Way limits. Water Supply manholes also have to be shifted, wherever it will
be needed.
82
Acquisition problems may be arise with the location of intersection, access to the
property and presence of local features both manmade and natural.
At Gabada Junction, there are no such right of way problem since already acquired
up to sufficient extent.
The design of an intersection should make provision for vehicle of legal dimensions
to carry out turning movement under acceptable operating conditions with adequate
clearance to features such as kerbs and road furniture.
Selection of design vehicle is necessary for the design of minimum turning radius,
pavement widths, turning lane widths etc. The turning path of the design vehicle
selected is used to determine the maximum width to be maintained. Selection of
design vehicle depends upon the location of the intersection, traffic volume and the
percentage of vehicles of each classification likely to use the intersection.
Table 2.3.1 shows the percentage of each classification of vehicles in Hambantota
Intersection.
83
Evening Peak
No of
% of
No of
% of
No of
% of
Vehicles
Vehicles
Vehicles
Vehicles
Vehicles
Vehicles
Motor cycle
159
41.41
140
37.14
160
41.03
Three wheeler
39
10.16
53
14.06
41
10.51
Passenger car
41
10.68
45
11.94
40
10.26
Van
34
8.85
34
9.02
45
11.54
Mini Bus
0.26
0.00
1.03
Large Bus
24
6.25
25
6.63
29
7.44
25
6.51
20
5.31
22
5.64
MG1
25
6.51
32
8.49
29
7.44
MG2
33
8.59
22
5.84
16
4.10
FVH
0.52
0.53
0.51
Heavy Vehicles
0.26
1.10
0.51
2.3.2.
ANALYSIS
OF
DATA
FOR
SELECTION
OF
TYPE
OF
INTERSECTION
84
GIVE WAY signs on the minor roads. However, regulatory signs are not a
substitute for channelisation.
Speed changing lanes allow left or right turning vehicles to reduce or increase
speed when leaving or entering the through road without affecting the speed of
through traffic adversely.
Passing lanes permit through vehicles to pass on the left of another vehicle
waiting to complete waiting to complete a right turn at an intersection.
3. Channelised Intersections
Roundabouts generally provide for safer and more efficient operation than
traffic signals owing to the restricted crossing speed and the reduced lost time.
4. Signalised Intersection
85
Local conditions and the cost of right of way often influence the type of intersection
selected as well as many of the design details. The alignment and grade of the
intersecting roads and the angle of intersection may make it advisable to channelise or
use auxiliary pavement areas, regardless of the traffic densities.
86
2.4. ROUNDABOUTS
Depending on the size of the central island and the arrangement of vehicle
movements, roundabouts are categorised as follows.
Mini roundabouts have central island diameter less than 4.0 m and single lane
circulating carriageway. Adequate deflection is not achieved and drivers face
difficulty in deciding appropriate gaps in the traffic flow. These types of roundabouts
are constructed at low traffic intersections. Also a provision has been made to pass
over the central island for heavy vehicles by keeping the central island 50 mm above
the road surface.
When central island diameter is less than 10.0 m, the roundabout is considered as
small. These may have a circulating carriageway of single or two lanes. Small
roundabouts are appropriate for three or four legs intersections with moderate traffic
movements. Most of the roundabouts in Sri Lanka fall into this category.
Large roundabouts are those with central island diameter more than 10.0 m. Drivers
have to cover more distance in executing a manoeuvre. These are recommended for
large new junctions or major improvements to existing intersections. For construction
of this type of roundabout requires large area and high installation cost.
87
Depending on the site conditions and availability of right of way and the effect of
possible traffic growth, a large roundabout is selected for Hambantota Intersection.
The elements of a roundabout are shown in Figure 2.4.1 and brief descriptions of each
element are given below.
In general a large central island provides greater separation between adjacent conflict
areas and makes it easier for entering drivers to determine whether vehicles, already
on the circulating carriageway, are exiting or continuing on around the circulating
carriageway. Larger diameter central islands are usually necessary for roundabouts in
high- speed areas at multi-leg intersections.
89
The diameter of the circle that may be inscribed within the outer kerb line of the
circulating carriageway is denoted by inscribed diameter. This may not always be
truly circular.
The carriageway around the central island on which, circulating vehicles travel in a
clockwise direction.
A broken line, marked across the entry carriageway, where it meets the circulating
carriageway and at which, vehicles should wait if necessary for an acceptable gap in
traffic to enter the circulating carriageway.
90
In the design of Hambantota Intersection, Give Way Lines are inserted in all three
legs of the intersection.
The left edge of pavement curve of the entry carriageway, which leads vehicle into
the circulating carriageway, is known as entry curve.
Radii of each entry curves of each approach of Hambantota Intersections are given in
Chapter 2.7 under Geometric Design Calculations.
The left edge of pavement curve of the exit curve carriageway, which leads vehicle
out of the circulating carriageway, is known as exit curve.
Radii of each exit curves of each approach of Hambantota Intersections are given in
Chapter 2.7 under Geometric Design Calculations.
The one-way width of the carriageway on the approach to the roundabout is known as
the approach width.
The width of the carriageway at its entry / exit point to / from the circulating
carriageway is known as entry / exit width.
91
The one-way width of the carriageway on the departure from the roundabout is known
as departure width.
The radius of the corner kerb between adjacent entry and exit roadways is known as
corner kerb radius.
Splitter islands should be provided on all roundabouts in rural and urban areas. They
provided shelter for pedestrians, assist in controlling entry speed, guide traffic into the
roundabout and deter right turners from taking dangerous wrong way short cut
movements through the roundabout.
The splitter island should be of sufficient size to shelter a pedestrian (at least 2.4 m
wide) and be a reasonable target to be seen by approaching traffic. A minimum area
of 8 to 10 m2 should be provided on any major road approach.
The areas of splitter islands provided in the design are given in Section 2.7.
92
The Follow-up time is the minimum headway between minor steam vehicles, which
enter in the longer gaps in the circulating traffic. In both cases, the units are in
seconds.
In the theory, it is assumed that all drivers will accept a gap greater than Critical
Acceptance Gap. It is also assumed that drivers are consistent and behave exactly the
same each time a gap is offered.
As the drivers in each entry lanes behave differently, each entry lane will be given
different Critical Gap and Follow-up Headway parameters.
The procedure for capacity analysis for each approach by this method is as follows.
1. Assemble Traffic Data.
2. Determine the number of entry and circulating lanes.
93
The second type use analytical techniques based on Gap Acceptance Theory and
Traffic Control Theory. Both types of packages have their uses and limitations.
STEP 1:
Table 2.2.1(a), 2.2.1(b) and 2.2.1(c) give the summary of Turning Movement Survey
Carried out at Hambantota intersection in different peak hours of the day. Turning
volumes are in vehicles / hour.
94
Turning Volumes given in Table 2.2.1(a), 2.2.1(b) and 2.2.1(c) were converted into
Passenger Car Units by multiplying with the Equivalent Factors given in Table 2.2.2
and tabulated in Table 2.5.1(a), 2.5.1(b) and 2.5.1(c).
Figure 2.5.1(a), 2.5.1(b) and 2.5.1(c) illustrate the turning movements diagram
corresponding to the values in Table 2.5.1(a), 2.5.1(b) and 2.5.1(c).
95
Table 2.5.1(a) - Summary of Peak Hour Turning Moments in Morning Peak (0915 1015 Hrs) at Gabada Junction (in PCU / h)
LEG
MOVE
MENT
MCL
TW
CAR
VAN
MBU
LEG1
LEG2
LEG3
12
4
8
2
11
1
9
1
2
0
0
0
LEG2
LEG1
LEG3
9
18
2
10
5
14
8
11
0
0
LEG3
LEG1
LEG2
6
15
3
6
3
7
2
7
64
31
41
38
TOTAL
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
5
0
14
0
52
3
0
0
0
0
0
0
0
0
0
0
6
0
119
11
2
24
7
13
12
14
18
3
0
0
0
0
0
0
0
0
0
0
0
0
63
107
0
0
0
31
2
10
0
10
0
7
0
0
3
0
0
0
0
0
0
0
0
6
19
99
57
37
50
83
12
418
96
Table 2.5.1(b) - Summary of Peak Hour Turning Moments in Mid day Peak (1100 1200 Hrs) at Gabada Junction (in PCU / h)
LEG
MOVE
MENT
MCL
TW
CAR
VAN
MBU
LEG1
LEG2
LEG3
12
4
6
4
7
2
12
4
0
0
2
0
LEG2
LEG1
LEG3
6
16
8
8
8
13
9
3
0
0
LEG3
LEG1
LEG2
5
13
3
14
3
12
0
9
56
43
45
37
TOTAL
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
15
2
30
2
30
2
0
0
4
0
4
0
5
0
0
0
0
0
127
20
0
31
8
2
14
6
12
2
0
0
0
0
0
4
0
0
0
0
12
0
77
85
0
0
0
26
2
3
0
12
2
5
0
0
0
0
0
0
0
0
0
0
0
0
15
94
59
32
64
53
12
418
97
Table 2.5.1(c) - Summary of Peak Hour Turning Moments in Evening Peak (1700 1800 Hrs) at Gabada Junction (in PCU / h)
LEG
MOVE
MENT
MCL
TW
CAR
VAN
MBU
LEG1
LEG2
LEG3
12
3
6
2
7
1
16
5
5
0
10
0
LEG2
LEG1
LEG3
12
15
11
5
9
11
17
9
0
0
LEG3
LEG1
LEG2
4
18
2
6
4
8
1
2
64
32
40
50
TOTAL
LBU LGV
MG1
MG2
HG3
AG3
AG4
AG5
AG6
FVH
TOTAL
11
0
22
6
5
0
0
0
0
4
0
0
0
0
0
0
0
0
94
21
2
26
10
6
16
8
30
5
0
0
4
0
0
0
0
0
0
0
0
6
111
91
0
2
2
29
2
4
0
6
0
0
0
0
0
0
0
0
0
0
0
0
0
6
15
81
69
33
58
40
12
413
98
99
Figure 2.5.1(b) Traffic turning volumes in Mid day Peak hour (11.00-12.00)
100
101
STEP 2:
The required number of entry and circulating lanes can be obtained from Figure 2.5.2.
For the Hambantota roundabout, all the points given by plotting circulating flow
against entry flow were below the lower shaded bands. Therefore single-lane
roundabout is suitable for present traffic data. But by considering future traffic
growth due to the development of Hambantota harbour and air port two-lane
roundabout was selected.
From the trial geometric layout of the intersection, number of entry lanes and
approach lanes for each leg is as in Table 2.5.3.
102
Leg
STEP 3:
Gonnoruwa leg
Weerawila leg
Hambantota leg
Geometric Values
Average approach lane widths and entry lane widths taken from geometric layout of
the roundabout were as follows.
Table 2.5.4 Widths of entry lanes and approach lanes in Hambantota intersection
Leg
STEP 4:
Gonnoruwa leg
3.5m
4.0m
Weerawila leg
3.5m
3.8m
Hambantota leg
3.4m
3.8m
All the specimen calculations were carried out considering Morning Peak Traffic
Values of Gonnoruwa Leg of Hambantota Roundabout (LEG 1). Similarly,
calculations were carried out for other legs in same manner and results are indicated
in Table 2.5.13 & Table 2.5.14.
103
The entry lane flows are a function of the turning volumes and the portion of through
traffic in each entry lane. In roundabout having four legs, it is assumed that the left
lane will carry the traffic turning left and half of the through traffic. But three leg
roundabouts traffic flows was divided according to the existing traffic movement
pattern.
= 119*0.65
= 77
= 11 + 119*0.35
= 53
Therefore for the particular approach, the left hand lane is the dominant lane and
right hand lane is the sub-dominant lane.
STEP 5:
Gap Acceptance parameters are affected by the geometry of the entry. Geometries,
which offer an easier entry path, give lower gap acceptance values. These parameters
are also a function of the circulating flow. At higher circulating flows, the circulating
speeds are lower and drivers are more willing to accept smaller gaps. Also the higher
circulating flows, more circulating drivers slow and allow entering drivers to move in
front of them. This leads to priority sharing or even reversal of priority.
The Critical Gap Parameters are evaluated for each entry lane. Table 2.5.5 gives the
Dominant Stream Follow-up times.
104
Table 2.5.5 - Dominant- Stream Follow-up Headways (tfd) (Initials Values) in seconds
Circulating Flow
(veh/h)
Inscribed
Diameter
(m)
0
500
1000
1500
2000
2500
20
2.99
2.79
2.60
2.40
2.20
2.00
25
2.91
2.71
2.51
2.31
2.12
1.92
30
2.83
2.63
2.43
2.24
2.04
1.84
35
2.75
2.55
2.36
2.16
1.96
1.77
40
2.68
2.48
2.29
2.09
1.89
1.70
45
2.61
2.42
2.22
2.02
1.83
1.63
50
2.55
2.36
2.16
1.96
1.76
1.57
55
2.49
2.30
2.10
1.90
1.71
1.51
60
2.44
2.25
2.05
1.85
1.65
1.46
65
2.39
2.20
2.00
1.80
1.61
1.41
70
2.35
2.15
1.96
1.76
1.56
1.36
75
2.31
2.11
1.92
1.72
1.52
1.33
80
2.27
2.08
1.88
1.68
1.49
1.29
The values given in Table 2.5.5 are adjusted if the number of entry lanes differs from
the number of circulating lanes. The adjustment values are given in Table 2.5.6.
105
Table 2.5.6 - Adjustment Times for the Dominant Stream Follow-up Headway
Number of Circulating
Lanes
1
2
3
0.00
0.39
-
-0.39
0.00
0.39
-0.39
0.00
Note: Add or subtract these factors from the initial values from Table 2.5.5.
(Source: AUSTROAD Part 6 Roundabouts)
Table 2.5.7 gives the Sub-dominant Follow-up time.
Table 2.5.7 - Sub-dominant Steam Follow-up headway tfs
Dominant steam
follow-up
headway tfd
(s)
1.0
1.5
1.6
1.7
1.8
1.9
2.0
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
3.0
2.05
2.10
2.15
2.20
2.25
2.30
2.35
2.41
2.46
2.51
2.56
2.61
2.70
2.80
2.90
3.00
106
1.94
2.05
2.15
2.25
2.35
2.46
2.56
2.66
2.76
2.87
2.97
3.07
3.17
3.28
3.38
3.48
1.89
2.02
2.15
2.28
2.40
2.53
2.66
2.79
2.92
3.05
3.17
3.30
3.43
3.56
3.69
3.82
1.84
1.99
2.15
2.30
2.46
2.61
2.76
2.92
3.07
3.23
3.38
3.53
3.69
3.84
4.00
4.15
For a Circulating Flow of 99 PCU/h and Inscribed Diameter of 33.0 m, the Dominant
Steam Follow-up time, tfd is 2.82 s.
According to the Table 2.5.6, Adjustments Value for the particular leg was 0.00.
Therefore Dominant Stream Follow-up Headway after adjustment was 2.82s.
For Hambantota Roundabout, the ratio of the dominant entry lane flow to the subdominant entry lane flow was equal to 77/53 = 1.45.
Using this value and the dominant Stream Follow-up time, tfd, Sub-dominant Followup time was 3.00 s. (Refer Table 2.5.7)
Table 2.5.8 indicates the ratio of the Critical Acceptance Gap to the Follow-up time.
Table 2.5.8 - Ratio of the Critical Acceptance Gap to the Follow-up Headway (tad/tfd)
Number of Circulating
Lanes
Average Entry Lane
Width
(m)
Circulating Flow
(Veh/h)
0
200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
2600
One
2.32
2.26
2.19
2.13
2.07
2.01
1.94
1.88
1.82
1.98
1.92
1.85
1.79
1.73
1.67
1.60
1.54
1.48
1.64
1.58
1.52
1.45
1.39
1.33
1.26
1.20
1.14
2.04
1.98
1.92
1.85
1.79
1.73
1.67
1.60
1.54
1.48
1.41
1.35
1.29
1.23
1.70
1.64
1.58
1.51
1.45
1.39
1.33
1.26
1.20
1.14
1.10
1.10
1.10
1.10
1.36
1.30
1.24
1.18
1.11
1.10
1.10
1.10
1.10
1.10
1.10
1.10
1.10
1.10
107
For single lane circulating carriageways, if the critical gap calculated from Table 2.5.5
and 2.5.8 is less than 2.1 s, use 2.1 s.
For multi-lane highways, the minimum value of critical gap should be 1.5 s.
Note: Values of the ratio may be interpolated for intermediate widths of entry lane.
For Gonnoruwa Leg of Hambantota Roundabout, Average entry lane width, Number
of circulating lanes and Circulating flow were 4.61 m, 2 and 99PCU/h respectively.
Therefore the ratio of the Critical Acceptance Gap to the Follow-up Headway was
1.47. (Refer Table 2.5.8)
The Critical Acceptance Gap for the sub-dominant stream was 1.46 x 3.00 = 4.38 s.
STEP 6:
The greater the number of circulating carriageway lanes, the shorter will be the
average headway between bunched vehicles of all lanes. The average headways of
bunched vehicles are given in Table 2.5.9.
Table 2.5.9 - Average headway between bunched vehicles in the circulating traffic ()
and the number of effective lanes in the circulating carriageway.
Circulating
Flow
Less than 10 m
Number of
Headway between
Number of
Headway between
effective
bunched vehicles
effective
bunched vehicles
lanes
() (s)
lanes
() (s)
<1000 veh/h
>1000 veh/h
1 (or 2)
2 (or 1)
108
For Hambantota Intersection, the circulating carriageway width was greater than
10.0 m and it was considered to be function as a two-lane roundabout. Therefore the
Average Headway between the vehicles for circulating flow carriageway was 1 s.
(Refer Table 2.5.9)
One
2.0
1.0
0.250
0.250
300
0.375
0.313
600
0.500
0.375
900
0.625
0.438
1200
0.750
0.500
1500
0.875
0.563
1800
1.000
0.625
vehicles, , (s)
2000
0.667
2200
0.708
2400
0.750
2600
0.792
109
STEP 7:
The absorption capacity of each entry lane is calculated from the entry lane Gap
Acceptance parameters (ta and tf) applicable to the dominant lane and sub-dominant
entry lane and the circulating flow characteristics. (Qc, and )
C=
3600(1 )qc e (t a )
(1 e )
t f
. (2.5.1)
Where,
C = the absorption capacity of an entry lane in veh/h
= The proportion of bunched vehicles in the circulating steams
qc = The flow of vehicles in the circulating streams in veh/h
ta = The critical acceptance gap relevant to the dominant or sub-dominant lanes
tf = The follow on headway relevant to the dominant or sub-dominant lanes
= The minimum headway in the circulating steam and these are related by
(1 )q c
(1 q c )
= 0.271,
=1s
tad = 4.13 s
tfd = 2.82 s
Qc = 99
110
=0.021
From equation 2.5.1, C= 3600 (1-0.271) x 0.0275 e 0.021 (4.131 )/ (1 e- 0.021 x 2.82)
= 1197
The entry lane capacity for the dominant stream lane was 1197.
= 0.271,
=1s
tas = 4.38 s
Qc = 99
tfs = 3.00 s
From equation 2.5.1, C = 3600 (1-0.271) x 0.0275 e 0.021 ( 4.381 )/ (1 e- 0.021 x3.00)
= 1123
The entry lane capacity for the sub-dominant stream lane was 1123.
The degree of saturation of an entry lane is the arrival divided by the entry
(absorption) capacity of the lane.
Qm
X =
C
..(2.5.3)
Where,
Qm
Qmd = 77
Cd = 1197
= 77 / 1197
= 0.064
Qms = 53
Cs = 1123
= 53 / 1123
= 0.047
111
Qm = 77 +53 = 130
CT = 1197+1123
= 2320
= 130 / 2320
= 0.06
Delays at Roundabout
There are two components of the delays experienced at roundabouts, namely queuing
and geometric delay.
Queuing delay is the delay to drivers waiting to accept gap in the circulating traffic.
Geometric delay is
1. The delays to drivers slowing down to the negotiation speed, proceeding
through the roundabout and then accelerating back to normal operating
speed; or
2. The delay to drivers slowing down to stop at the end of the queue and,
after accepting a gap, accelerating to the negotiation speed, proceeding
through the roundabout and then finally accelerating further to reach
normal operating speed. It excludes the time to wait for an acceptable gap.
Queuing Delay
To calculate the average queuing delay, minimum delay should be calculated using
following equation for the conditions when the entering traffic flow is very low.
2 2
e (t a )
1
Wh =
ta +
(1 )qc
2( + 1 )
112
(2.5.4)
Where the gap acceptance parameters ta, , and are as in equation 2.5.4 and the
circulating flow qc is in veh/s.
For all practical purposes, the average queuing delay per vehicle is given by;
(Z
Wm = Wh + 900T Z +
+ mx CT
)]
(2.5.5)
Where,
Wm
Wh
= Minimum delay in seconds when the entering traffic is very low (from
equation 2.5.4)
= Duration of the flow period in hours, i.e. the time interval during which an
average arrival demand Qm persists (use 1 h or 0.5 h)
=x1
Using the gap acceptance parameters for each entry lane and circulating flow
parameters, the average queuing delay per vehicle can be calculated using equation
2.5.4 and 2.5.5.
Wh
=0.58
113
Wm
Wh
=0.61
Wm
Therefore the average queuing delays per vehicle were 0.23 s and 0.26 s for the
dominant and sub-dominant streams respectively.
The approach queuing delay was related to the lane flows and it was (0.23 x 77 +
0.26 x 53) / (77 + 53) = 0.24 s.
The geometric delay for vehicles differs depending on whether the vehicles have to
stop or not.
d g = Ps d s + (1 Ps )d u
.. (2.5.6)
Where,
Ps
ds
(1- Ps) = The proportion of entering vehicles which need not stop
du
The proportion of entering vehicles, which must stop, Ps can be estimated using
Figure 2.5.3.
ds and du can be obtained from Table 2.5.11 (a) and 2.5.11 (b).
115
Table 2.5.11 (a) - Geometric Delay for Stopped Vehicles (Seconds per Vehicles)
Approach
Distance
Speed
Around
Va
Roundabout
(km/h)
D (m)
20
25
30
35
40
45
50
40
40
40
40
40
20
60
100
140
180
10
19
8
15
22
7
12
17
7
9
13
18
7
7
10
14
18
60
60
60
60
60
20
60
100
140
180
13
23
11
18
26
10
15
21
10
13
18
22
10
10
15
19
23
10
10
12
15
19
10
10
10
12
15
10
10
10
10
10
80
80
80
80
80
20
60
100
140
180
17
26
15
22
29
13
19
25
13
17
21
26
13
14
19
23
27
13
13
16
19
23
13
13
13
16
19
13
13
13
13
16
100
100
100
100
100
20
60
100
140
180
20
30
18
25
33
17
22
28
17
20
25
30
17
18
22
26
30
17
17
20
23
27
17
17
17
20
24
17
17
17
17
20
116
Table 2.5.11 (b) - Geometric Delay for Vehicles, Which Do Not Stop (Seconds per
Vehicles)
Approach
Distance
Speed
Around
Va
Roundabout
(km/h)
D (m)
20
25
30
35
40
45
50
40
40
40
40
40
20
60
100
140
180
7
17
4
11
19
2
7
13
1
4
8
13
0
0
4
8
12
60
60
60
60
60
20
60
100
140
180
11
20
8
15
22
5
11
17
4
8
13
17
3
4
9
13
17
2
2
5
8
12
1
1
1
4
7
1
1
1
1
2
80
80
80
80
80
20
60
100
140
180
14
24
11
19
26
9
15
20
7
11
16
21
6
8
13
17
21
5
5
9
13
16
4
4
5
9
12
3
3
3
4
7
100
100
100
100
100
20
60
100
140
180
18
27
15
22
29
12
18
24
10
15
20
25
9
12
16
20
25
8
9
13
17
20
7
7
10
13
16
6
6
6
12
Geometric delay is different for each traffic movement left turn, right turn and
through, at each approach and should be calculated separately.
117
Figure 2.5.4 Definitions of the terms used in Table 2.5.11(a) and 2.5.11(b)
From the geometry of the Hambantota Roundabout, the distance D for Gonnoruwa
Leg, for through traffic and right turning traffic were 30.0 m and 60.0m respectively.
The geometric delay values for the same leg obtained from Tables 2.5.11 (a) &
2.5.11. (b) are as in table 2.5.12.
Movement
7.50
9.00
1.75
4.00
Through
Right
= 2.33 s
The average geometric delays for all movement of particular approach are shown in
Table 2.5.13.
The total delay per vehicle for a movement is the summation of average geometric
delay per vehicle and total average queuing delay per vehicle.
The total delays for all movement of particular approach are shown in Table 2.5.13.
Table 2.5.13 - Geometric Delay and Total Average Delay Values for Movements of
Gonnoruwa Leg of Hambantota Roundabout.
Movement
Through
Right
Turning Volumes
(Veh/h)
Geometric Delay
for Movement
(s)
Total Average
Delay for
Movements
(s)
119
11
2.33
4.50
2.57
4.74
The average delay per vehicle on the approach is the weighted average of the total
movement delays.
=2.75 s
(119 + 11)
Capacity calculations and Delay calculations for each approach for all peak hours
are given in Table 2.5.14, Table 2.5.15 and Table 2.5.16.
119
Peak
Hour
Leg
Movem
ent
Turning
Volume
Circula
ting
Flow
Entry
Flow
No of
Entry
Lanes
No of
Circul
ating
Lanes
Average
Entry
Lane
width
(m)
(Veh/h)
LEG1
Morning
LEG2
LEG3
LEG1
LEG2
MidDay
LEG3
LEG1
LEG2
Evening
LEG3
Leg 2
Leg 3
Leg 1
Leg 3
Leg 1
Leg 2
119
11
63
107
19
99
Leg 2
Leg 3
Leg 1
Leg 3
Leg 1
Leg 2
Leg 2
Leg 3
Leg 1
Leg 3
Leg 1
Leg 2
99
130
02
02
4.61
11
170
02
02
4.17
63
118
02
02
4.48
127
20
77
85
15
94
94
147
20
162
77
109
94
21
111
91
15
81
81
115
21
202
111
96
120
Morn
ing
Leg
LP
LF
LT
tf
ta
Xl
Xa
Wh
Wm
LG 1
L
R
L
R
L
R
77
53
91
79
44
74
D
S
D
S
S
D
2.82
3.00
2.79
2.85
2.91
2.81
4.13
4.38
4.57
4.67
4.42
4.26
0.271
1.0
1.0
0.263
1.0
0.06
0.05
0.07
0.06
0.04
0.06
0.06
0.252
1197
1123
1281
1253
1184
1229
0.22
0.24
0.03
0.03
0.15
0.16
0.23
0.26
0.03
0.03
0.15
0.16
L
R
L
R
L
R
83
64
85
77
48
61
D
S
D
S
S
D
2.82
2.93
2.79
2.83
2.92
2.81
4.13
4.30
4.56
4.63
4.42
4.26
0.270
1.0
1.0
0.266
1.0
0.07
0.06
0.07
0.06
0.04
0.05
0.06
0.254
1202
1152
1271
1252
1169
1215
0.21
0.22
0.05
0.05
0.19
0.18
0.22
0.24
0.06
0.06
0.20
0.19
L
R
L
R
L
R
66
49
91
111
39
57
D
S
S
D
S
D
2.81
2.95
2.88
2.79
3.00
2.83
4.13
4.33
4.71
4.56
4.52
4.25
0.267
1.0
1.0
0.273
1.0
0.05
0.04
0.07
0.09
0.04
0.05
0.05
0.254
1214
1155
1230
1270
1108
1182
0.18
0.19
0.06
0.05
0.29
0.26
0.19
0.20
0.06
0.06
0.30
0.27
LG 2
LG 3
LG 1
MidDay
LG 2
LG 3
LG 1
Eveni LG 2
ng
LG 3
0.07
0.05
0.06
0.05
0.08
0.04
Notations:
LG 1 - Gonnoruwa
LT
- Lane Type
LG 2 - Weerawila
tf
LG 3 - Hambantota
- Right Lane
- Left Lane
ta
- Dominant Flow
- Sub-Dominant Flow
- Lane Capacity
Xl
LP
- Lane Position
Xa
LF
121
Table 2.5.16 (a) - Geometric Delay Calculations & Total Delay Calculations
Morning Peak
Leg
Wma
(s)
Proportion
of Vehicles
Ps
(1-Ps)
LEG 1
0.24
0.10
0.90
LEG 2
0.03
0.04
0.96
LEG 3
0.16
0.08
0.92
dg
(s)
Total
Delay
(s)
Through
Geometric
Delay
ds
du
(s)
(s)
7.50
1.75
2.33
2.57
Right
9.00
4.00
4.50
4.74
Left
7.50
1.75
1.98
2.01
Through
8.50
3.25
3.46
3.49
Left
7.00
1.00
1.48
1.64
Right
9.00
4.00
4.40
4.56
Delay for
Approach
(s)
2.75
2.56
4.09
Table 2.5.16 (b) - Geometric Delay Calculations & Total Delay Calculations MidDay Peak
Leg
Wma
(s)
Proportion
of Vehicles
Ps
(1-Ps)
LEG 1
0.23
0.10
0.90
LEG 2
0.06
0.04
0.96
LEG 3
0.19
0.08
0.92
dg
(s)
Total
Delay
(s)
Through
Geometric
Delay
ds
du
(s)
(s)
7.50
1.75
2.33
2.55
Right
9.00
4.00
4.50
4.73
Left
7.50
1.75
1.98
2.04
Through
8.50
3.25
3.46
3.52
Left
7.00
1.00
1.48
1.67
Right
9.00
4.00
4.40
4.59
122
Delay for
Approach
(s)
2.85
2.74
4.19
Table 2.5.16 (c) - Geometric Delay Calculations & Total Delay Calculations
Evening Peak
Leg
Wma
(s)
Proportion
of Vehicles
Ps
(1-Ps)
LEG 1
0.19
0.10
0.90
LEG 2
0.06
0.04
0.96
LEG 3
0.28
0.10
0.90
dg
(s)
Total
Delay
(s)
Through
Geometric
Delay
du
ds
(s)
(s)
7.50
1.75
2.33
2.52
Right
9.00
4.00
4.50
4.69
Left
7.50
1.75
1.98
2.04
Through
8.50
3.25
3.46
3.52
Left
7.00
1.00
1.60
1.88
Right
9.00
4.00
4.50
4.78
Wma
Ps
Delay for
Approach
(s)
2.92
2.71
4.33
dg
1.
2.
3.
4.
5.
Finalised solution was taken after trying out six alternatives for the Hambantota
roundabout. The drawings of the finalised solution (sixth alternative) were submitted
along with this report. The reasons to reject each alternative are described below.
Rejected five alternatives are shown from Figure 2.5.5 to Figure 2.5.9.
124
V = 127 R (e + f
.(2.7.1)
Where,
V
= Speed in km/h
= Radius in m
= Super-elevation in m/m
It is usually necessary with small roundabouts to grade the pavement away from the
central island for drainage.
The value of e may range from a maximum of 0.00 at the centre line of each
intersecting roads to minimum of 0.025. The latter figure will control the speed of
circulating vehicles.
With the smaller diameter roundabouts, the path traverses by passenger vehicles is
closer to the inscribed circle than the central island. So the maximum speed for
circulating traffic on the inscribed circle radius is given by,
V
= 24.44 km/h
.(2.7.2)
Where,
R1
R2
W1, W2
roads
Z = R1 W1 + z
...............(2.7.3)
Where,
Z
Where,
= 31.25 km/h
131
= U1 + U2 + FA + FB + 2C + Z
FA
(2)
U1
(3)
RT1
= R + Z + C/2 + U1
(4)
RT2
= RT1 + FA + C + FB + U2
(5)
U2
(6)
= 6.0 m
..
= 19.68 ft
= 19.68 + 2+2+ U1
132
(1)
U1
= RT1 23.68 ..
(7)
= RT1 23.68
u + 23.68
= (RT12 L2 ) (8)
= 6.0 ft
= RT12 -112
RT1
= 31.6528 ft
(9)
L = 11.0 ft
a = 0.50 ft
FA
= 1.663 ft
For
Bus, u =8.50 ft
(10)
L = 25.0 ft
(11)
= RT2 ( RT1 + FA + C + FB )
(12)
= (RT22 25.02 )
45.816 2
= RT22 25.0 2
RT2
= 52.193 ft
= 6.0+31.653(31.6532 11.02)
= 7.9728 ft
= 8.5+52.193(52.1932 25.02)
= 14.877 ft
= 7.9728+14.877+1.659+0+8+2
= 34.5088 ft
= 10.518m
133
Entry and exit lane widths are governed by the volume of turning traffic and the type
of vehicles to be accommodated. Where there is an approach curve leading up to the
entry curve into the roundabout, it should have the same or a slightly larger radius
than the radius of the curved path, that a vehicle would be expected to travel through
the roundabout.
The exit from roundabout should be as easy to negotiate as practicable. After having
been slowed down by the curved entry path into the circulating carriageway, vehicles
should be able to accelerate on the exit out of the circulating carriageway. Therefore,
the exit radius should generally be greater than the circulating radius.
The entry and exit curve radii adopted in the design of Hambantota Roundabout are
given in Table 2.7.1.
(m)
(m)
Gonnoruwa
100.0
150.0
Weerawila
100.0
150.0
Hambantota
100.0
150.0
Entry and exit curve widths were checked using vehicle - turning templates to ensure
that the swept path of SU Design Vehicle and Semi Trailer Design Vehicle were
properly catered for the turning.
134
Vertical curves are introduced between two consecutive grades in order to increase
sight distance across the junction of grades and provide riding comfort. The vertical
curve usually adopted is a parabola.
Vertical curves are provided as specification given in section 2.8 of Geometric design
of Roads.
135
The minimum splitter island area of 8.0 m2 is adopted in the Highway Designs
Division of the Road Development Authority.
The splitter island areas accommodated in the design of Habmantota Roundabout are
given in Table 2.7.2.
(m2)
Gonnoruwa
95.74
Weerawila
47.41
Hambantota
34.37
136
2.8. REFERENCES
1. National Association of Road and Traffic Authorities in Australia (AUSTROADS)
Guide to Traffic Engineering Practice Part 6 Roundabouts 1993
3. National
Association
of
Roads
and
Traffic
Authorities
in
Australia
137
.
CANDIDATE
(Eng. P.C.I.Kumaratunga)
..
SENIOR DESIGNS ENGINEER
.
DEPUTY DIRECTOR / HIGHWAY DESIGNS
.
DIRECTOR / HIGHWAY DESIGNS
138
ON
FOR
INTERSECTION
OF
COLOMBO-GALLE-HAMBANTOTA-WELLAWAYA
ROAD AND HAMBANTOTA BY PASS ROAD
AT
139
3.1. INTRODUCTION
3.1.1. GENERAL
Highway drainage is the process of removing and controlling excess surface and subsoil water from the Right Of Way. Provision of adequate drainage facilities for a road
or an intersection is essential for its long life and satisfactory service performance.
The primary problem of drainage design is to limit the amount of water flowing along
the gutters or pounding at sags to quantities which will not interfere with the passage
of traffic. This is achieved by placing inlets at suitable intervals to limit the spread of
water on the traveled way to tolerable widths. Grate inlets and depression or curb
opening inlets should be located outside the through traffic lanes to minimize the
shifting of vehicles attempting to avoid to riding over them.
Removal and diversion of surface water from the carriageway and adjoining land is
termed as surface drainage. Diversion or removal of excess soil water or ground water
is termed as sub surface drainage.
New drainage system introduced should have the facility of draining-off the surface
water from all the approaches and transfer same to the side drains and dispose them
at the culverts.
140
Usually regional wise rainfall intensity duration curves for various recurrence
intervals are available and the intensity of rainfall for the selected frequency and for
the time of concentration could be obtained. That chart used by the Highway Designs
Division of the Road Development Authority is given in Figure 3.2.1.
141
The design storm recurrence interval is the probable period of time in which
combination of intensity and duration repeat themselves and is usually expressed in
years.
When determining a recurrence interval for design purpose the following factors
should be considered.
1.
Economic considerations
2.
3.
4.
Maintenance requirements
100 years
10 50 years
1 10 years
Ten years and twenty-five years recurrence intervals are used by the Highway Design
Division at present for road surface drainage and cross drainage structures
respectively.
143
from the most remote point of the catchments to reach the point under consideration.
In the calculation of the design flow which assumes that rain will continue to fall for
the duration of this time of concentration.
Tc = To + Tch + T p
.. (3.2.1)
Where;
Tc
= Time of concentration.
To
Tch
Tp
144
Run-off depends upon a number of factors such as topography, soil type, size and
slope of area, land use and percolation (depending upon the nature of soil and its
absorption qualities). All of which have considerable effect upon the amount of the
total rainfall that infiltrates into the ground.
The success of drainage system design depends on the method adopted to estimate the
peak run- off. The different methods available are listed below with a brief
description.
1.
2.
3.
145
4.
Out of these methods, Rational Method is widely used for the designs.
For the design of drainage system at Hambantota Intersection, Rational Method was
adopted.
Q = FICA
(3.2.2)
Where;
Q
= Mean rate of rainfall for the storm frequency during the time
of concentration.
= Run-off co-efficient
= Area of catchment
146
DISADVANTAGES:-
It is generally accepted that this method overestimates the magnitude of the run-off.
Another shortcoming of the method is the use of constant C, which shows that the
run-off is a fraction of rainfall. The inability to take storage effect in to account is the
other shortcoming.
Most of the catchment areas used in road surface drainage calculations are generally
small enough for the assumption of uniform rainfall to be reasonable. Also most of
the catchments are relatively impervious and hence C values are not greatly
dependant.
147
Run-off co-efficient for urban catchments is given in Figure 3.2.2 which is used for
this design.
3.2.4.3.2 Determination of C
Corresponding to rainfall intensity of 194 mm / h, co-efficient of run-off was 0.92 for
impervious surface. (From Figure3.2.2)
3.2.4.3.3 Determination of A
Topography maps and aerial photographs are widely used in this purpose. Site
inspection may also required in level terrain.
The area catered by inlet, A was estimated by drawing contour lines and flow
patterns.
For Inlet I2, the area estimated from the scaled drawing adopting above method was
83.59m2.
= FICA
= 0.278 x 194 x 0.92 x 83.59 X 10-6
= 4.147 x 10 3 m3 / s
148
The maximum allowable depth of flow on a road surface is 6.5 mm and desirable
maximum allowable depth is 5.0 mm for a recurrence interval of one year and time of
concentration is not less than 5.0 minutes.
1. Introducing crowns
2. Increasing the rate of rotation of super-elevation development
3. Providing drains in the pavement
3.3.1. INTRODUCTION
Kerbs and channels are the intermediate collectors of the run-off water in the
carriageway and they carry the water into suitable out falls.
150
The gutter is formed by the surface of the carriageway and the kerb face. Gutters also
help to reduce the quantity of water entering the pavement or subgrade. The capacity
of the gutter depends on the cross section.
The drainage system at Hambantota Roundabout was designed in such a way, that the
run-off over the carriageway flowed through the kerb inlets to the drain while
overland flow entered directly.
The flow of water in the gutters should be restricted to such a depth, that the
corresponding ponded width may not obstruct or cause a hazard to traffic. The gutter
cross section is triangular in shape and the most common method used to estimate
gutter capacity is Mannings formula.
The formula for depth of flow at kerb can be derived using Mannings formula and
Continuity equation as follows.
Mannings formula,
1 23
V = R S
n
151
(3.3.1)
Q = VA
(3.3.2)
Where,
V
= A/
A 2 3 12
Q= R S
n
(3.3.3)
= 1/2 . y . y . z
= y2 z /2
= y (1 + z)
=y.z
= A/W
=y / 2
Therefore,
R
Since z >> 1
1
y = 299 Q S 2 Z
0.375
(3.3.4)
Where, y is in mm.
Highway Designs Division of the Road Development Authority uses the following
maximum ponded widths for 10 years recurrence interval.
= 1.0 m
= 2.0 m
= 4.147 x 10 -3 m3/s
= 40.00
= 21.797 mm
Ponded Width = 21.797 x 40.00/1000
= 0.87 m
153
3.4. INLETS
3.4.1. INTRODUCTION
Inlets are suitably placed to intercept the gutter flow from where water is lead in to the
drains.
Inlet should be provided at all sag points and suitable intervals, so that the gutter flow
will not exceed the gutter capacity for the limited ponded widths. Care should be
taken at road intersections to prevent ponding at radius kerbs and it is therefore
preferable to place inlets just upstream of the tangent point of these kerbs to prevent
surface water flowing across the junction.
1.
Grated inlets
2.
3.
These are typically installed at service stations and other paved areas to
prevent surface flow entering the road.
4. On the road surface in an extended form to intercept sheet flow. These are
commonly called grated drains.
The principal disadvantage in grated inlet is their tendency to clog with debris unless
flow velocity is high enough to clean the grate.
The bars in the grating should be parallel to the direction of flow as experiments
indicate that this minimizes the clogging by small particles of debris and increases the
capacity of grate.
One advantage of kerb-opening inlets over the grated inlets is their ability to self
cleanse. Also kerb-opening inlets are economical and desirable than the grate type.
155
3.4.4.1. GENERAL
Capacity of inlet pits will depend on
1.
Longitudinal grade
2.
Crossfall
3.
Channel discharge
4.
5.
6.
Gutter depression
q=
0.3865
(a + y )2.5 a 2.5
y
156
(3.4.1)
Where,
q
q = 1.7043 (a + y )
1.5
(3.4.2)
If the depth of flow is high, the kerb inlet will be fully submerged. The restriction
imposed on the ponded widths for different locations renders the above.
When deciding the pit spacing, the following factors also should be considered.
1. Pit capacity
2. Allowable ponded width
3. Cleaning requirements
Specimen
: I2
Column 02
: The chainage along the centre line opposite the kerb inlet
Specimen
: 0+049.60
Column 03
Specimen
:R
Column 04
Specimen
: 83.59 m2
Column 05
: The run-off for the drainage area given in Column (4) calculated
using Rational formula.
= 0.278 x 0.92 x 194 x 83.59 x 10 6 = 4.147 x 10 -3 m3/s
Specimen
:Q
Column 06
Specimen
: 1.25 %
Column 07
Specimen
: 0.004147 / (0.0125)1/2
Column 08
Specimen
:Z
Column 09
= 0.037
= 1/e = 1/ 0.025
= 40.00
3.3.4.
= 299 x (0.037/40.00)0.375
Specimen
:y
Column 10
: The water spread (or ponding) width in gutter, when carrying the
discharge Q given in Column (5)
Column 11
: Type of inlet
Specimen
: K1/T1
Column 12
= 21.797 mm
This is the vertical distance from the normal gutter line to the throat of
the Inlet
Specimen
: 0.050 m
Column 13
Specimen
m3/s/m
Column 14
Specimen
: Lreq = 284 mm
Column 15
Specimen
Column 16
Specimen
: 600 / 282
= 2.13
Column 17
Specimen
: 0.00 m3/s
160
Inlet
No
I1
I2
I3
I4
I5
I6
I7
I8
I9
I10
I11
I12
I13
I14
I15
Station
Chainage
R/L
Gonnoruwa
0+057.60
R
0+049.60
R
0+041.70
R
0+032.80
R
0+032.80
R
0+024.00
R
0+016.50
R
0+013.30
L
0+021.50
L
0+029.80
L
0+037.60
L
0+046.00
L
0+057.00
L
0+064.00
L
0+072.00
L
0+080.60
L
10
11
Type
12
13
inlet
14
La=
15
Kerb
16
17
Carry
Area
S in
%
Q/S0.5
Zb
Y mm
PW
of
capacity(qb)
Q/qb
width
L/La
over
Inlet
m3/s/m
L mm
y=
m
8*9
0.66
0.87
0.97
1.33
1.87
1.90
1.38
1.32
1.19
1.25
0.95
0.76
0.96
0.97
0.96
0.93
KI/T1
KI/T1
KI/T1
KI/T1
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.014
0.015
0.015
0.033
0.033
0.015
0.016
0.015
0.014
0.014
0.015
0.014
0.015
0.015
0.015
0.015
173
284
282
141
195
588
414
335
345
529
417
304
538
553
456
403
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
600
m /s
Q=FICA
- Weerawila road
47.39 0.002
1.75
83.59 0.004
1.25
0.95
83.28 0.004
94.63 0.005
0.60
131.02 0.007
0.60
1.00
175.04 0.009
130.84 0.006
0.55
104.03 0.005
0.45
96.27 0.005
1.75
2.30
154.32 0.008
122.59 0.006
2.30
87.09 0.004
2.50
164.63 0.008
2.50
2.50
169.75 0.008
137.94 0.007
2.00
1.80
120.82 0.006
0.018
0.037
0.042
0.061
0.084
0.087
0.088
0.077
0.036
0.050
0.040
0.027
0.052
0.053
0.048
0.045
1/n.c.f
(1/n)*
R2/3S1/3
40.00
40.00
43.48
58.82
83.33
83.33
50.00
50.00
66.67
58.82
43.48
38.46
38.46
38.46
40.00
40.00
16.541
21.797
22.211
22.676
22.482
22.772
27.662
26.356
17.816
21.173
21.754
19.725
25.045
25.335
24.082
23.372
161
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
m3/s
3.48
2.11
2.13
4.27
3.07
1.02
1.45
1.79
1.74
1.13
1.44
1.97
1.12
1.09
1.32
1.49
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
I16
I17
I18
I19
I20
I21
I22
I23
I24
I25
I26
I27
I28
I29
I30
I31
I32
I33
I34
I35
1.70
1.70
1.80
1.40
1.50
3.30
3.30
3.50
3.60
2.40
0.015
0.040
0.036
0.042
0.077
0.038
0.020
0.029
0.023
0.046
76.92
76.92
62.50
55.56
71.43
45.45
41.67
40.00
40.00
40.00
12.296
17.576
18.200
20.099
23.048
21.016
17.028
19.934
18.354
23.637
0.95
1.35
1.14
1.12
1.65
0.96
0.71
0.80
0.73
0.95
KI/T1
KI/T1
KI/T1
KI/T1
KI/T2
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.013
0.014
0.014
0.014
0.015
0.014
0.014
0.014
0.014
0.015
157
379
345
344
636
481
265
384
319
478
600
600
600
600
900
600
600
600
600
600
3.82
1.58
1.74
1.74
1.42
1.25
2.26
1.56
1.88
1.25
0
0
0
0
0
0
0
0
0
0
3.70
3.50
3.30
1.90
0.35
0.75
0.65
0.55
1.20
2.10
1.60
0.023
0.028
0.036
0.036
0.041
0.054
0.100
0.074
0.040
0.027
0.032
40.00
41.67
47.62
66.67
52.63
55.56
66.67
62.50
45.45
50.00
50.00
18.281
19.364
20.138
17.846
20.431
22.116
26.090
23.903
21.395
17.843
18.943
0.73
0.81
0.96
1.19
1.08
1.23
1.74
1.49
0.97
0.89
0.95
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
KI/T1
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.05
0.014
0.014
0.014
0.014
0.014
0.015
0.036
0.034
0.015
0.014
0.014
320
373
455
361
170
317
225
161
303
284
287
600
600
600
600
600
600
600
600
600
600
600
1.87
1.61
1.32
1.66
3.54
1.89
2.67
3.74
1.98
2.11
2.09
0
0
0
0
0
0
0
0
0
0
0
162
KI/T1
KI/T1
KI/T1
3.5.1. INTRODUCTION
The water collected through inlets and overland flow is transported through the drains
to the culvert, bridge and/or bare land depending on the situations. Usually
rectangular drains are used because, it is easy to design, construct and maintain.
The design of a drain to carry the discharge is accomplished in two stages. First a
convenient section is selected with the available slope to carry the design discharge.
Then the degree of protection required to prevent scour in the drainage channel is
determined. Mannings formula is used to calculate the velocity at the design
discharge and is compared with the permissible minimum and maximum velocities
for a given type of channel.
Generally open channel flow conditions are used to design rectangular channels. But
in roadside drainage, there will be cases, where some hydraulic disturbances are
present due to roof run-off, conduit discharge etc.
2.
3.
In order to satisfy above, channel section should be designed first and the slope of the
drainage channel should be decided secondly, conforming to the speed limits of the
flow. This slope may be useful to dispose the muddy material on the drain.
163
3.5.3.1. GENERAL
Capacity of rectangular drain can be calculated from the Mannings formula and
continuity equation.
=bxd
= (b+2d)
= bd / (b+2d)
Q
S1/2
1
0.015
(bd)5/3
(b+2d)2/3
164
Q/S
b = 0.45m
b = 0.60m
0.506
1.340
2.290
3.30
4.33
5.38
6.45
7.51
8.61
9.70
0.710
1.950
3.390
4.940
6.55
8.21
9.89
11.60
13.32
15.05
d (m)
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Description of Table 3.5.2 and Specimen Calculations for drain section I1 to I2.
Column 01
Specimen
: I2
Column 02
: The chainage along the centre line opposite the kerb inlet
Specimen
: 0 + 049.60
Column 03
Specimen
:R
Column 04
Specimen
: From the contour plan, length of catchment along the road surf-ace for kerb inlet I2 was 8.30m.
165
Column 05
Specimen
: Catchment area measured from contour plan for I2 was 83.60 m2.
Column 06
Specimen
Column 07
Specimen
Column 08
Specimen
: Flow time, T was taken as 3 minutes as the length of flow path was
less than 12.0 m
Column 09
Specimen
Column 10
Specimen
Column 11
Specimen
: 0.88 x 498
Column 12
Specimen
Column 13
: Cumulative value of C x A
Column (7) + Column (11)
166
= 515.14 m2
Specimen
: 76.91 + 438.20
Column 14
Specimen
Column 15
: The maximum time taken by water from both road surface and
overland flow to reach the inlet under consideration in minutes.
Higher value of Column (8) and Column (12)
Specimen
: Maximum flow time from Column (8) & (12) was 5.0 minutes.
Column 16
: Time taken for water to travel along the drain section under
consideration in minutes.
Column (14) / Column (28)
Specimen
= 0.14 minutes
Column 17
Specimen
: 5.0 +0.14
= 5.14 minutes
Column 18
Specimen
Column 19
Specimen
: 10 minutes
Column 20
Specimen
Column 21
Specimen
:Q
Column 22
Specimen
: 0.0 x 10 -3 m3 / s
Column 23
= 27.78 x 10 -3 m3 / s
Column 24
Specimen
: 0.010 m/m
Column 25
: The value of ( Q / S )
Specimen
: 43.80 x 10 -3 / (0.010)1/2
Column 26
= 43.80 x 10 -3 m3 / s
= 0.44
It may be selected from the standard sizes, so that the velocity lies
within allowable limits
Specimen
Column 27
Specimen
Column 28
Specimen
:V
Column 29
: Remarks if any
Specimen
168
= 1.00 m/s
169
3.6. REFERENCES
170
.
CANDIDATE
(Eng. P.C.I. Kumaratunga)
..
SENIOR DESIGNS ENGINEER
.
DEPUTY DIRECTOR / HIGHWAY DESIGNS
.
DIRECTOR / HIGHWAY DESIGNS
171
FOR
THE CONSTRUCTION
OF
INTERSECTION
OF
COLOMBO-GALLE-HAMBANTOTA-WELLAWAYA
ROAD AND HAMBANTOTA BY PASS ROAD
AT
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
.
CANDIDATE
(Eng. P.C.I. Kumaratunga)
..
SENIOR DESIGNS ENGINEER
.
DEPUTY DIRECTOR / HIGHWAY DESIGNS
.
DIRECTOR / HIGHWAY DESIGNS
219