Beruflich Dokumente
Kultur Dokumente
1. Introduction
* Director, Legal Affairs, EFTA Secretariat. Opinions expressed are those of the
author.
1. Since 1 Sept. 1991 the Member States of the European Free Trade Association
(EFTA) are Austria, Finland, Iceland, Liechtenstein, Norway, Sweden and Switzerland.
1172
Norberg
The EEA has, since 1986, and during the negotiations as well as in
the Agreement, been characterized as both dynamic and homogeneous,
which obviously leads to considerable political and legal consequences.
The basic idea behind this ambitious and cumbersome work, which in
practice might be looked upon as a kind of widening of the internal market, can only be realized if the same legal rules are applied in a uniform
manner throughout all the 19 countries concerned. It is only thereby
that it will be possible to achieve equal treatment and non-discrimination of the some 380 million inhabitants in these countries.
In the areas covered by the Agreement the results shall thus, in principle, be the same whether Community rules or EEA rules are applied.
If the individuals and economic operators cannot be guaranteed that
that will be the case, it would seem that a primary objective behind this
work could be jeoparidized. The word homogeneous therefore does not
only concern homogeneity as to the application of the EEA rules as such
and the relationship between the EFTA and the EC states, but also
homogeneity between these rules and corresponding EC rules. Furthermore, homogeneity should not only prevail at the entry into force of the
Agreement, but also during the dynamic development of the Agreement, in step with the development of the Community in corresponding
areas. Obviously, it has been a major challenge for the negotiators to
secure this in the Agreement, while at the same time quaranteeing the
independence and decision-making autonomy of the Parties. It should
also be underlined that the result could hardly be the intended one, if
the Contracting Parties had not seen to it that in the Agreement itself
this objective is very clear.
Although there formally thus will be two separate legal orders, the
EC law and the EEA law, the two could, in practice, be said to form
a common European legal system.
The Agreement has 21 Contracting Parties, the European Economic
Community (EEC), the European Coal and Steel Community (ECSC),
the twelve EC Member States and the seven EFTA States. It is applicable between the EC and its Member States, on the one hand, and the
EFTA States, on the other, but also between the EFTA States.
As to the substantive scope of the Agreement, this may, in general
terms, be described as covering all EEA-relevant primary and secon-
EEA agreement
1173
1174
Norberg
VIII (Articles 115- 117) the financial mechanism for the less developed
EC countries and, finally, Part IX (Articles 118- 129) general and final
provisions. In all areas where this has been possible, the provisions of
the Agreement have been formulated as closely as possible to corresponding provisions of EC law, in particular the EEC Treaty, as one
of the means of securing that the interpretation can be the same.
The main part of the Agreement2 is followed by 49 Protocols and 22
Annexes to the Agreement. While the Protocols contain rules on more
particular questions, such as the origin of goods, customs matters, trade
in fish or transitional periods, the Annexes provide for the integration
into the Agreement of around 1,600 legal acts of secondary EC legislation, which have been identified as relevant so-called "acquis communautaire". This is done through a technique of reference to the publication of these legal acts in the Official Journal of the Communities,
which is published in the nine EC languages. The complete text of these
legal texts is not reproduced in the Agreement itself, but the Annexes
mainly contain the headlines of the legal acts with certain technical
adaptations to the text. To this end, references to EC institutions, for
instance, are replaced by references to corresponding EEA organs, etc.
In each Nordic EFTA country, however, these texts will also be published in an authentic translation in the respective national language.
The total volume of these texts is around 14,000 pages.
The Final Act of the Agreement contains, inter alia, 29 Joint Declarations by all Contracting Parties, two Declarations by the EC Member
States and the EFTA States (on faciliation of border controls and on a
political dialogue on foreign policy issues) and 39 Declarations by one
or more Contracting Parties. In addition, the Final Act contains Agreed
Minutes and certain arrangements for the interim period.
It is the intention in this article to focus upon the institutional provisions of the EEA Agreement and thus not to describe the substantive
ones, which could also merit a special presentation.
EEA agreement
2. Legal and institutional issues
2.1 The legal technique and structure of the Agreement
1176
Norberg
suring that these rules in the EEA are interpreted in the same way as they
are in the Community. Any attempt to "codify" case law would otherwise risk jeopardizing the whole exercise and risk freezing the development of case law. Obviously, rules on transitional periods in the EC
which are no longer relevant have not been kept.
One element of the technique used has also been to make the objectives of the Contracting Parties very clear and thereby to assist and
guide the interpretation of the rules of the Agreement.
In the Preamble the Contracting Parties have expressed in sixteen recitals certain main principles and objectives on the creation of the EEA.
In these recitals, certain principles are emphasized regarding the positive effects of the EEA, the privileged relationship between the Contracting Parties, the further development of the EEA, the importance
of the EEA to individuals, the importance of the flanking policies, such
as environment, the social dimension, consumers' interests, the
strengthening of the scientific and technological basis of European industry. Of particular interest in this context may be mentioned the
fourth recital emphasizing, inter alia, the objective of establishing a dynamic and homogeneous European Economic Area, based on common
rules and equal conditions of competition and providing for the adequate means of enforcement, including at the judicial level. The eighth
recital addresses the important role that individuals will play in the European Economic Area, inter alia, through the exercise of the rights
conferred on them by the Agreement.
Another recital in the Preamble recalls that the conclusion of the
Agreement shall in no way prejudge future accession to the EC by any
EFTA State.
In the second but last recital, which was added to the text after the
first opinion of the EC Court of Justice of 14 December 1991,3 the
Contracting Parties emphasize the objective to arrive at and maintain
3. Opinion 1/91, O.J. 1992, C 110/Annotated by Schermers in this Review at
991-1009.
EEA agreement
1177
1178
Norberg
nity itself as Contracting Parties) may with regard to the EC side have
different meanings depending upon the respective competences of the
Community and the EC Member States under Community law.5 It can
thus, depending upon the status of EC law, either mean the Community
and the EC Member States, or the Community, or the EC Member
States.
The Contracting Parties have also undertaken a corresponding obligation to that under Article 5 of the EEC Treaty, an Article which has
been the subject of numerous judgments of the EC Court of Justice.
Thus under Article 3 the Contracting Parties are obliged to take all appropriate measures, whether general or particular, to ensure fulfilment
of the obligations arising out of the Agreement. They shall abstain from
any measure which could jeopardize the attainment of the objectives of
the Agreement. Moreover, they shall facilitate co-operation within the
framework of the Agreement.
A general prohibition regarding discrimination on grounds of nationality corresponding to Article 7 of the EEC Treaty is contained in Article 4.
Article 5 lays down the important principle that any Contracting
Party at any time may raise a matter of concern at the level of the EEA
Joint Committee or the EEA Council. This principle, which during the
negotiations has been referred to as "droit dyevocation" is also expressed in Articles 92(2), as to the EEA Joint Committee, and 89(2), as
to the EEA Council.
One of the most difficult and delicate issues to negotiate concerned
the question of how to ensure that provisions of the EEA Agreement,
which in their substance are identical to provisions of EC law, are also
given such an interpretation. With regard to the interpretation of such
provisions on the date of signature of the Agreement it was natural for
the Contracting Parties to agree that the interpretation should be in conformity with that given until then by the EC Court of Justice. The particular difficulties refer, however, to the interest, on the one hand, to
keep future interpretations of corresponding EC and EEA rules as uniform as possible, while at the same time preserving the autonomy of the
5. A corresponding definition is also contained in the Fourth LomC Convention.
EEA agreement
1179
EFTA States and their judicial systems. The solution chosen and laid
down in Article 6 of the EEA Agreement is inspired by corresponding
solutions in the 1988 Lugano Convention on jurisdiction, recognition
and enforcement of judgments in civil and commercial matters. The
problems in connection with that Convention were similar in relation to
the corresponding 1968 Brussels Convention, and the solutions then
worked out are contained in Protocol 2 to the Lugano Convention.
As can be seen from Article 6 of the EEA Agreement, the Contracting
Parties have, first of all, declared that on the date of signature of the
Agreement all provisions of the AgreementY6in so far as they are identical in substance to corresponding EC rules shall in their implementation and application be interpreted in conformity with the relevant rulings of the EC Court of Justice. With regard to developments in the
future, the provision makes a reservation in the sense that what is said
should be without prejudice to future developments of case law. This
is an expression of the need to avoid "freezing" in the interpretation at
the state as of the date of signature. In order, nevertheless, to emphasize
the objective of the Contracting Parties, also for the future, to maintain
homogeneity, Article 6 is supported by further language in the Agreement. In particular, mention should here be made of the second but last
recital of the Preamble, which was mentioned above, and of Section 1
of Chapter 3 of Part VII which will be commented upon later.'
Another provision with a similar objective is Article 7 which is similar
to Article 189 of the EEC Treaty. Thus acts referred to or contained in
6 . It follows from Art. 2 that the term "Agreement" means the main Agreement,
its Protocols and Annexes as well as the acts referred to therein.
7. In this context particular mention should also be made of Art. 3 of the abovementioned Agreement between the EFTA States on the establishment of a Surveillance
Authority and a Court of Justice. While Art. 3(1) of that Agreement is identical to Art.
6 of the EEA Agreement, Art. 3(2) reads: "In the interpretation and application of the
EEA Agreement and this Agreement, the EFTA Surveillance Authority and the EFTA
Court shall pay due account to the principles laid down by the relevant rulings by the
Court of Justice of the European Communities given after the date of signature of the
EEA Agreement and which concern the interpretation of that Agreement or of such
rules of the Treaty establishing the European Economic Community and the Treaty establishing the European Coal and Steel Community in so far as they are identical in substance to the provisions of the EEA Agreement or to the provisions of Protocols 1 to
4 and the provisions of the acts corresponding to those listed in Annexes I and I1 to the
present Agreement".
1180
Norberg
Part VII Institutional Provisions (Articles 89- 114) is divided into four
chapters, Chapter 1 the Structure of the Association, Chapter 2 the
Decision-making procedure, Chapter 3 Homogeneity, Surveillance procedure and Settlement of disputes and Chapter 4 Safeguard measures.
2.4.1 Chapter 1, The Structure of the Association
This chapter (Articles 89-96), dealing with the structure of the Association is, in its turn, divided into four sections each dealing with one of
the joint organs created by the Agreement, EEA Council, the EEA
Joint Committee, the EEA Joint Parliamentary Committee and the cooperation between economic and social partners, which, inter alia, will
be carried out through the EEA Consultative Committee. In reading
this Part of the Agreement it should be kept in mind that the Agreement
does not foresee any transfer of legislative competence from any Contracting Party to any organ of the EEA.
As can be seen from a comparison between the provisions on the EEA
Joint Committee and those on the EEA Council, the Agreement fore-
EEA agreement
1181
sees that the daily operation of the EEA shall be in the hands of the EEA
Joint Committee. It will be the EEA Joint Committee that adopts the
decisions regarding amendments of the provisions of the Agreement
contained in the Annexes and most of the Protocols. It will also be the
Joint Committee that will be in charge of the management of the Agreement. The Joint Committee will also have an important function with
regard to the settlement of disputes under the Agreement. The role of
the EEA Council will more be a political one, to give the political impetus and to take the political decisions regarding the further development
of the EEA. It may be noted also that, on the Community side, the
presidency in the EEA Council will be held by a member of the EC
Council, while in the EEA Joint Committee it will be the Commission
that will hold the presidency on the EC side.
The tasks of the EEA Council as defined in Article 89, shall, in particular, be to give the political impetus in the implementation of the Agreement and lay down the general guidelines for the EEA Joint Committee.
To this end, the EEA Council shall assess the overall functioning and
development of the Agreement and take the political decisions leading
to amendments of the Agreement. Furthermore, the Contracting Parties may raise, in the EEA Council, any issue giving rise to a difficulty
("droit d'kvocation"). While this normally should first be discussed in
the EEA Joint Committee it may, in exceptionally urgent cases, be
raised directly without such a discussion.
The EEA Council shall consist of the members of the Council of the
European Communities, members of the EC Commission and of one
member of the Government of each of the EFTA States. Decisions by
the EEA Council shall further be taken by agreement between the Community, on the one hand, and the EFTA States, on the other. The office
of President of the EEA Council shall be held alternately, for a period
of six months, by a member of the Council of the European Communities and a member of the Government of an EFTA State. The EEA
Council shall meet at least twice a year.
Article 92 establishes the EEA Joint Committee, which shall ensure
the effective implementation and operation of the Agreement. It shall
to this end carry out exchanges of views and information and take decisions in the cases provided for in the Agreement. A reference to the socalled "droit d'kvocation" implies that the Contracting Parties shall
1 182
Norberg
EEA agreement
1183
1184
Norberg
With regard to the decision-making procedure itself, Article 99 provides that as soon as new legislation is being drawn up by the EC Commission in a field which is governed by the EEA Agreement, the Commission shall informally seek advice from experts from the EFTA States
in the same way as it seeks advice from experts of the EC Member States
for the elaboration of each proposal (Article 99(1)). When transmitting
its proposal to the EC Council the Commission shall further transmit
copies thereof to the EFTA States. A preliminary exchange of views will
take place at the request of any of the Contracting Parties in the EEA
Joint Committee (99(2)). All along the very extensive decision-making
procedure in the Community there will then, in parallel within the EEA,
be an intensive information and consultation process between the EC
and the EFTA States in the EEA Joint Committee (Article 99(3)). It
will, however, through the "droit dYCvocation",be possible to raise a
problem to the Ministerial level in the EEA Council. The Contracting
Parties are further under a general obligation to co-operate in good
faith during the information and consultation phase with a view to
facilitating, at the end of the process, the decision-taking in the EEA
Joint Committee (Article 99(4)).
The question regarding the participation of experts from the EFTA
States in EC committees set up to assist the EC Commission, was intensively discussed during the negotiations. In broad terms distinction
could be made between three categories of EC committees, (a) those
assisting the Commission in the exercise of its executive powers, (b)
those assisting the Commission in the management and development
of particular Community programmes where EFTA States contribute
financially and (c) other committees. In accordance with the provisions
laid down in Article 100, the EC Commission will with regard to
category (a) ensure experts of the EFTA States as wide a participation
as possible in the preparatory stage of draft measures to be submitted
subsequently to the committees. The Commission will hereby refer to
experts of the EFTA States on the same basis as it refers to experts of
the EC Member States. This is of the utmost importance since thereby
it will be possible for the Commission, already at an early stage, to take
into account views from the EFTA countries.
Special more far-reaching solutions for the association of EFTA ex-
EEA agreement
1185
perts have then been worked out for the category (b) committees, i.e.
those established for the different EC programme activities in which the
EFTA countries will participate financially (Article 81).
With regard to committees under category (c), i.e. other committees
established to assist the Commission, the association of EFTA States'
experts will be guided by the need that might exist in the interest of the
good functioning of the Agreement (Article 101). Protocol 37 contains
already a list of eight such committees. It is envisaged that decisions
concerning such association with further committees will be taken by
the EEA Joint Committee as soon as it starts work.
Article 102 addresses the particular problem that arises from, on the
one hand, the principle of decision-making autonomy of the Contracting Parties and, on the other, the political desire and need to maintain
the homogeneity of the EEA Agreement. It concerns, in other words,
the particular procedures needed for the adoption of amendments to the
Annexes to the Agreement. As explained above, the Annexes contain all
the integrated secondary Community legislation and whenever one of
these legal acts in the Community, normally EEC Regulations or Directives, will be amended, corresponding amendments should also be made
to the Annexes of the EEA Agreement.
Certain general principles regarding the adoption and the entry into
force of such amendments are laid down in Article 102(1). It is thus emphasized that, in order to quarantee the legal security and the homogeneity of the EEA, the EEA Joint Committee shall take a decision concerning amendments of the Annexes to the Agreement as closely as
possible to the adoption by the Community of the corresponding new
Community legislation with a view to permitting a simultaneous application of the latter and of the amendments of the Annexes to the Agreement. From the homogeneity point of view this principle is evidently
very important. There should in other words be no delays in relation to
the entry into force of an amendment of an Annex to the EEA Agreement and the entry into force of the corresponding Community rule. To
this end the Community is under an obligation to inform, as soon as
possible, the other Contracting Parties in the Joint Committee
whenever it adopts an EEA-relevant legislative act.
The Contracting Parties are obliged to make all efforts to arrive at
1186
Norberg
EEA agreement
1187
sions as well as when the decisions concerning new Community rules are
taken. If this is not done there might be a risk that the EFTA States will
not be able to follow the development of EC rules and give their approval to corresponding new EEA rules.
For the EFTA States this would imply that an important part of the
possibilities for initiatives concerning the future development of the
common rules will be in the hands of the Community. The EFTA States
will, however, in various ways have the possibility of injecting their
views both informally and formally and discussing new common rules
with the Community. In the end, they will be able to claim that they will
maintain their freedom not to accept the proposal to an amendment of
the existing EEA rules. In that sense the situation of an EFTA State in
the EEA differs from that of an EC Member State in the Community.
An EC Member State can in most areas be overruled by a majority of
the other Member States and thereby against its own will be bound by
a new rule. In the EEA the principle of consensus prevails. To block a
decision on a new EEA rule may, however, in practice, unless the parties cannot agree on any other solution, as described above, ultimately
have the result that a part of an Annex to the Agreement, which would
be affected by the new rules, can be provisionally suspended.
2.4.3 Chapter 111, Homogeneity, Surveillance Procedure and Settlement of Disputes
2.4.3.1 General
With regard to the need to securing a uniform interpretation of the EEA
rules themselves as well as in relation to corresponding EC rules, reference is made to the above comments to the Preamble as well as to the
general rule of interpretation contained in Article 6 of the Agreement.
The question of uniform interpretation is, however, also intimately
linked to the question of how to arrange for dispute settlement between
the Contracting Parties. As to both of these questions it was already
clear during the exploratory talks preceding the negotiations that in order to secure legal homogeneity within the EEA some kind of a special
mechanism must be established.
1188
Norberg
The EFTA side thus suggested already at the beginning of the discussions that an independent EEA Court should be established to function
in conjunction with the EC Court of Justice. A solution to that end was
worked out and adopted at the Joint Ministerial Meeting in May 1991.
It implied the creation of an independent EEA Court as well as a Court
of First Instance, both functionally integrated with the EC Court of
Justice. However, in an opinion delivered by the EC Court of Justice
on 14 December 1991,9 the Court declared that solution not to be compatible with the EEC Treaty. During the following two months a new
system for settlement of disputes was worked out and finally adopted
by the negotiators on 14 February 1992. In a second opinion delivered
by the EC Court of Justice on 10 April 1992,1 the Court declared the
new solution compatible with the EEC Treaty.
The finally-agreed system emphasizes in particular the questions of
preserving the homogeneity of the Agreement and the settlement of disputes between the Contracting Parties. The section regarding the surveillance procedure under the Agreement underwent, apart from
changes regarding the judicial mechanism, no amendment. As to the
question of guaranteeing and preserving homogeneity in the EEA, the
idea of having a joint EEA Court and Court of First Instance had to
be abolished. Instead, the EFTA States will establish for their part an
EFTA Court. In order to ensure uniform interpretation a number of
different elements have already been mentioned above. Chapter I11 of
Part VII adds thereto important provisions, especially regarding the
role of the EEA Joint Committee. It shall keep under constant review
the development of the case law of the Court of Justice of the European
Communities and the EFTA Court, as far as provisions of the EEA
Agreement which are identical to provisions of Community legislation
are concerned. The EEA Joint Committee may, in this context, take the
necessary action to preserve the homogeneous interpretation. If a
difference in the case law of the two Courts has been brought before the
Joint Committee and the Joint Committee has not succeeded within two
months to preserve the homogeneous interpretation, the dispute settle9. See note 3 supra.
10. Opinion 1/92 O.J. 1992, C 136/1. Annotated by Schermers, supra note 3.
EEA agreement
1189
1190
Norberg
EEA agreement
1191
for the EFTA States and the ESA before the EC Court of Justice. The
ESA-EFTA Court Agreement contains provisions granting the EC
Commission and the Community corresponding rights to intervene in
cases before the EFTA Court.
2.4.3.3 Surveillance Procedure
The general rules regarding the surveillance procedure under the EEA
are laid down in Articles 108- 110. Article 108 states the obligations for
the EFTA States to establish an independent surveillance authority (the
EFTA Surveillance Authority, hereinafter referred to as ESA) and a
Court of Justice (EFTA Court). With regard to the surveillance authority it is further laid down that the EFTA States shall establish procedures
similar to those existing in the Community, including procedures for
ensuring the fulfilment of obligations under the Agreement and for
control of the legality of acts of the ESA regarding competition. From
this, it follows that the ESA, with regard to its surveillance activities,
will have competences corresponding to those of the EC Commission.
Further details regarding this are laid down in various other parts of the
EEA Agreement, e.g. in Protocols 21 and 26, which, inter alia, deal
with the powers and functions of ESA in the fields of competition and
State aid.
As to the EFTA Court, it is also stated that it shall, in accordance
with a separate agreement between the EFTA States, with regard to the
application of this agreement be competent, in particular, for: (a) actions concerning the surveillance procedure regarding the EFTA States;
(b) appeals concerning decisions taken by the EFTA Surveillance
Authority in the field of competition; and (c) settlement of disputes between two or more EFTA States.
As mentioned above, the EFTA States, on 2 May 1992 in Oporto,
also signed the ESA-EFTA Court Agreement, which lays down in detail
the rules regarding the functions and competences of the ESA and the
EFTA Court. That Agreement contains, as to surveillance, particular
provisions regarding the general surveillance of the implementation, application and interpretation of the EEA rules by the EFTA States as well
as the special surveillance functions to be carried out in the fields of
competition, state aid and public procurement. All these provisions aim
at ensuring that, for the surveillance procedure, the ESA and the EFTA
1192
Norberg
EEA agreement
1193
1194
Norberg
EEA agreement
1195
at the Joint Ministerial Meeting in May 1991 and laid down in Article
112. The clause may thus be triggered by one of the Contracting Parties
"if serious economic, societal or environmental difficulties of a sectoral
or regional nature liable to persist are arising". Safeguard measures
shall be restricted in their scope and duration to what is strictly necessary in order to remedy the situation. Priority shall be given to such
measures that will least disturb the functioning of this Agreement. The
safeguard measures shall apply with regard to all Contracting Parties.
The use of the safeguard clause is, however, connected to a possibility
for the other Contracting Parties to take proportionate rebalancing
measures if, through the recourse to the safeguard clause, an imbalance
were to arise (Article 114).
1196
Norberg
ments binding the EC, on the one hand, and one or more EFTA States
on the other, "to the extent that the same subject matter is governed by
this Agreement". In practice this will mean that existing Agreements
falling under this Article are neither terminated nor suspended, they are
simply not to be applied. In practice this would mean that, with some
exceptions, the EEA Agreement will be applied instead of the FTAs.
The EEA Agreement does not preclude co-operation in the framework of the Nordic co-operation, of the regional union between Switzerland and Liechtenstein or of the co-operation between Austria and
Italy concerning certain neighbouring regions, to the extent that such
co-operation does not impair the good functioning of the Agreement
(Article 121).
A Contracting Party may withdraw from the Agreement provided it
gives at least twelve months notice (Article 127). The other Contracting
Parties shall then convene a diplomatic conference in order to make the
necessary modifications to the Agreement.
On certain conditions, it will also be possible for other States to become a party to this Agreement. Thus a European State that becomes
a member of the Community shall apply to become a party to the Agreement, while a European State that becomes a member of EFTA may
make such an application.
Finally, according to Article 129 the Agreement shall enter into force
on 1 January 1993, provided that all Contracting Parties have deposited
their instruments of ratification or approval before that date. If these
requirements are not met in time, the Agreement will enter into force
on the first day of the second month following the last notification.
The final date for such a notification is 30 June 1993. If that date is
passed without a decision on the entry into force of the Agreement, the
Contracting Parties shall convene a diplomatic conference to assess the
situation. l 2
In Agreed Minutes to this Article, the Contracting Parties have
agreed that, if any one of them should not be prepared to ratify the
Agreement, the signatories shall review the situation. Furthermore,
12. The ESA-EFTA Court Agreement and the Standing Committee Agreement are
supposed to enter into force after ratification at the same time as the EEA Agreement.
EEA agreement
1197
if any one of them should not ratify the Agreement, the remaining Contracting Parties shall convene a diplomatic conference to assess the effects of the non-ratification for the Agreement and to examine the possibility of adopting a protocol containing the amendments which will be
subject to necessary internal procedures. Such a conference shall be
convened as soon as it has become clear that one of the Contracting Parties will not ratify the Agreement or at the latest if the date of entry into
force of the Agreement is not respected.
1198
Norberg
ment. From this point of view it would also seem that it would hardly
be possible to get any closer to the status of membership in the Community, without becoming a member, than through the present Agreement.
The developments since the beginning of preparations for the negotiations on the EEA Agreement were initiated three years ago have also
been such that four EFTA States, Austria, Sweden, Finland and Switzerland, have presented formal applications for EC membership. At the
meeting of the European Council in Lisbon, at the end of June 1992,
the EC Heads of State and Governments discussed the future enlargement of the Community and decided to initiate formal negotiations
with the EFTA States having applied for membership as soon as the
Maastricht Treaty should be ratified and the future EC budget order
decided upon. It should, however, not be forgotten that no matter when
the next enlargement can take place and which of the EFTA States take
part therein, the EEA Agreement has certainly provided an extremely
good and useful preparation for such a step. At the same time it secures
all EFTA States a participation in the internal market based on equal
treatment and non-discrimination. For those EFTA States which might
not want to take the step towards accession to the EC, the Agreement
could also provide a solution in the longer term.