Rev.
No.
Date
Data
Description
Descriere
Prepared
Intocmit
Checked
Verificat
Approved
Aprobat
Projects &
Engineering
Dept.
Project no.
ROA09134227
266
Rev.: 01
Pag. no.:
1 of 13
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
2 of 13
TABLE OF CONTENTS
1. INTRODUCTION
3
4
4
3. SCOPE OF WORK
5
6
6
6
6
6
7
7
8
8
8
8
9
9
10
10
10
10
10
11
11
11
12
12
12
4. TIMELINE
13
13
13
5. ANNEXES
13
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
3 of 13
1. INTRODUCTION
OMV PETROM S.A. Member of OMV Group (the COMPANY), is the largest Romanian oil and
gas group, with activities in the business segments of Exploration & Production (E&P), Gas & Power
(G&P) and Refining & Marketing (R&M).
Munteni Gas Conditioning Facility is located in Petrom Asset IX Moldava South, Galati County,
Romania.
Existing Gas Conditioning Facility consists of a Dehydration unit based on molsieve technology and a
compressor station.
Starting with 1st of September 2014 instead of mol-sieve adsorbent silica gel adsorbent is used for
gas dehydration and HCDP control. This was a part of pilot project, in which only the adsorbent was
changed without changing rest of facilities.
In order to ensure sustainable performance of silica gel adsorbent, OMV Petrom intends to perform a
EPCM contract to retrofit the existing gas conditioning facility in line with requirements of Silica Gel
adsorbent (based on attached BASF studies).
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
4 of 13
Gas flow for burning is around 40Nm3/day and gas flow for regeneration is 1900Nm3/h. Regeneration
is done at low pressure 3-4barg.
Gas that is used for regeneration is sent back to suction of compressors being prior cooled in the
existing heat exchangers.
Water and condensate obtained during regeneration on the bottom of adsorbers are sent to existing
atmospheric tank.
Actual unit is manually operated; no PCS and ESD systems are in place.
Petrom perform condition assessment of existing Adsorbers. Attached to this ITB are the results.
2.2 UTILITIES
Power supply is made from existing power transformer station having following main supply level of
voltage: 0.5kV, 0.4kV and 0,23kV.
Instrument air: Not available.
Water: well water.
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
5 of 13
3. SCOPE OF WORK
3.1 DESIGN REQUIREMENTS
Contractor shall design new equipment according to applicable standards and legislation
requirements, accommodate the existing ones according to legislation requirements, and fit them with
new process requirements.
Any modification required in the existing plant shall be highlighted by the Contractor and approved by
OMV Petrom.
Main changes for unit upgrade are modification of regeneration temperature from 160degC to
290degC (as required by Silica Gel adsorbent), the addition of supplementary cooling system due to
higher regeneration temperature and implementation of condensate recovery package.
Actual cycle time for operation is 8 hours. In order to reach HCDP a shorter cycle time will be
required, therefore implementation of actuated valves (Motor Operated Valves) for cycles change are
required. New valves shall be controlled via one PLC.
Contractor shall coordinate with silica gel absorbent supplier (BASF Germany) clarifications regarding
process parameters required to operate the unit with silica gel (regeneration temperature, cooling
temperature, cycle times for operations etc.).
Contractor shall consider a turndown ratio of 10:1 in design and that pressure can vary up to 30 barg.
Design pressure for new items shall be determined by Contractor to allow gas delivery at 40barg
pressure at delivery point.
Design life of the unit shall be for 15 years.
Corrosion allowance for new items (equipment, pipes etc.) shall be in accordance to OMV Petrom
standards.
Energy efficiency and fit for purpose design concept shall be implemented during detail design.
Resolution of design changes during fabrication and construction shall be in scope of engineering
Contractor.
Contractor shall prepare repairing project for existing adsorbers in accordance to condition
assessment reports and getting recertification from authorities (ISCIR).
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
6 of 13
Wet gas stream: from outlet flanges of existing horizontal separators at inlet of dehydration unit;
Dry gas: inlet of Gas Metering Station;
Regeneration stream: inlet of compressors suction, flanges from first heat exchangers battery;
3.2.2
Electric
Distribution board from existing power transformer substation, equipped with 2 transformers 1000kVA
20/0,5kV and one transformer 250kVA, 20/0,4kV.
3.2.3
Instrumentation
Documentation required to obtain all the permits and approvals from authorities, including
construction permit;
Documentation for civil constructions: foundations for new equipment, steel structures, piping
systems, access ways, sewage system;
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
7 of 13
Process engineering
Construction management (HSSE coordination and supervision; supervision of site works for
all disciplines during construction, pre-commissioning, commissioning, start-up and close out;
coordination of daily activities, daily reporting of site activities status and next steps).
For engineering activities (where is applicable) every document will be submitted to Petrom for
approval, at following phases:
As built.
The scope of work includes, but is not limited to the following activities
3.3.1
General
Operation and maintenance manual (including update of the manual for As-built);
SOW preparation for next phase (PCC contract);
RFQ for all equipment and materials to be developed as per OMV Petrom requirements.
3.3.2
Project management
Project coordination (bi-weekly meetings, MoMs, etc.) during engineering, procurement,
construction, pre-commissioning, commissioning and start-up;
Project planning and reporting (time schedule level III, including basis of schedule, monthly
reports, cost control, PSP updated);
Document control;
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
8 of 13
Authority engineering
Preparation of documentation to obtain urbanism certificate (including OCPI visa) and
submission of documents to authorities (including tax payments by Contractor);
Preparation of documentation to obtain all permits required by urbanism certificate and
submission of documents to authorities (including tax payments by Contractor);
Preparation of documentation to obtain construction permit and submission of documents to
authorities, including General deviz.
Obtain new ATR (Aviz tehnic de racordare) Electric agreement (including tax payments by
Contractor), if required.
Preparation of documentation for demolition permit submission of documents to authorities
(including tax payments by Contractor);
Release Acceptance protocol after completion works according to HG 444/2014.
3.3.4
Process engineering
Process and plant description;
Heat and mass balance, simulation;
Preparation of PFD, PID;
Perform HAZOP Study, however HAZOP leader will be provided by Petrom, therefore
contractor shall not quote for third party HAZOP leader;
Sizing and calculations reports;
Hazardous area documentation;
PID for demolition.
3.3.5
Civil engineering (including concrete, steel structure, sewage and access ways)
Technical memorandum and calculations;
Detail design drawings and MTO/BoQs;
Foundations plot plan and specifications.
3.3.6
Mechanical engineering
Engineering for static equipment (specifications (if applicable) and datasheets);
Engineering for rotating equipment (specifications (if applicable) and datasheets);
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
9 of 13
Piping engineering (tie-in list, line list, isometrics, stress calculations, datasheets, supports,
valves, MTO/BoQ etc.);
Plot plans and piping layouts (including existing facilities).
Engineering for adsorbers repairing works according to condition assessment reports.
Plot plan and layout for demolition;
3.3.7
3.3.8
Electrical engineering
Technical memorandum for electric system;
Calculations, specifications and datasheets for electrical equipment (including but not limited
to panels, UPS, motors, cables, lighting, lightening protection, grounding);
Consumers/loads list;
Single line diagrams;
Wiring diagrams;
Lighting layout;
Lightening protection and grounding layout;
Cable routing and cable list;
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
10 of 13
MTO/BoQs.
3.3.9
Firefighting
Technical memorandum;
Equipment list and specifications;
Preparation of documentation to update the existing firefighting scenario;
3.3.10
HSSE
HSSE Coordination, supervision and reporting, according to Romanian legislation and OMV
Petrom requirements;
General HSSE Plan for Engineering and Construction phases;
SIMOPS and constructability review workshop;
3.3.11
Quality
Project quality plan and Inspection test plan for all works (fabrication, construction, precommissioning, commissioning and start-up);
Quality assurance and quality control during fabrication, construction, pre-commissioning,
commissioning and start-up);
Participation at FAT and SAT, checking of FAT and SAT reports.
3.3.12
GIS
Procurement activities
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
11 of 13
Site activities
Site visit and collection of necessary data as input for BoD (Gas Composition bulletin will be
provided by Petrom after contract award);
Check of actual conditions to integrate new and old facilities (visual inspection);
On site review meeting for P&IDs and layout drawings;
Topographical survey;
HSSE Coordination and supervision;
Coordination and supervision of site activities during construction, pre-commissioning,
commissioning, start-up and close out;
3.4 WARANTIES
Contractor shall be responsible to provide and assure process warranty for design of this project.
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
12 of 13
3.5.2
OMV Petrom documentation review is maximum 10 working days for 1st documents submission & 5
working days for next submissions. These activities shall be highlighted separately in the Time
schedule.
3.6 EXCLUSIONS
Engineering for fire and gas systems, SIS (ESD) system, security systems, PAGA systems,
telecommunications are excluded from Contractor SOW, as these systems are not being installed in
this project.
Condition assessment of existing equipment or piping. Only visual inspection to be performed by
Contractor for gathering of data.
Work permits will be issued by OMV Petrom.
Placing of purchase orders for procurement packages.
OMV PETROM
Doc.
no.:
PE-D- A09134227266-GESOW-003-01-E
EXPLORATION&
PRODUCTION
Rev.
no.:
01
Projects &
Engineering
Page
no.
13 of 13
4. TIMELINE
4.1 OFFER PREPARATION
A joint site visit and clarification meeting will be performed before submission of offer, after 3-4
working days from issuance of ITB.
5. ANNEXES
Item Document title
Document number/name
Plot plan
compressors
Hazardous area plan dehydration
unit
Basis of design
List of deliverables