CNE/122/2004

D1

Interfaces

Working Document

Part D1 Interfaces Working Document

Page: i

TABLE OF CONTENTS
TITLE

PAGE

GENERAL.................................................................................................................................. 1

SCOPE....................................................................................................................................... 1

INTERFACE POINT IDENTIFICATION CODE.......................................................................... 1

INTERFACE POINTS ................................................................................................................ 3


4.1

MECHANICAL INTERFACES........................................................................................ 3
4.1.1 General Guidelines ........................................................................................... 3
4.1.2 List of Mechanical Interfaces within L Station Phase II............................... 3
4.1.3 List of Mechanical Interfaces between L Station Phase II and
Phase I................................................................................................................ 4
4.1.4 List of Mechanical Interfaces between L Station Phase II and
External .............................................................................................................. 5

4.2

ELECTRICAL INTERFACES ......................................................................................... 5


4.2.1 General Guidelines ........................................................................................... 5
4.2.2 List of Electrical Interfaces .............................................................................. 5

4.3

INSTRUMENTATION AND CONTROL INTERFACES.................................................. 6


4.3.1 DCS Cubicles in Package D scope and Man-Machine
Interface in the CCR .......................................................................................... 6
4.3.2 Interfacing with Phase I .................................................................................... 8
4.3.3 Maintenance Telephone System...................................................................... 8
4.3.4 Water RTU.......................................................................................................... 8

4.4

CIVIL INTERFACES....................................................................................................... 8
4.4.1 General Guidelines ........................................................................................... 8
4.4.2 List of Civil Interfaces....................................................................................... 9

D1_Interfaces_II_WD

Part D1 Interfaces Working Document

Page: 1

GENERAL

Each Package shall co-ordinate his work in every phase of his activity like design, engineering,
workshop testing, construction, erection, site testing and commissioning directly with all other
Package(s).
During the design period, the concerned Package shall contact directly other Package(s) in all
matters concerning required data for his detailed technical design to get the necessary information.
The other Package is obliged to provide timely all necessary information as may be required by the
concerned Package(s). Copy of the correspondence shall be submitted to the Employer/Engineer.
The concerned Package may arrange for technical meetings with other Package(s) for the same
reason. The timing and agenda shall be submitted to the Employer/Engineer in due time before the
meeting for information and decision whether or not to attend the meeting. In case of nonattendance a copy of the Minutes of Meetings shall also be distributed to the Employer/Engineer.

SCOPE

This specification part D1 'Interfaces' describes the interfaces of the Package D - Desalination of
the Jebel Ali L Station, Phase II with the power package of Phase II, L Station Phase I and
External.
(Remark: Although Phase I is 'External' to the Phase II scope, the classification still contains this
category for better understanding.)
The number of interfaces shall be minimised, i.e. wherever possible, there shall be common
interface points for a system and sub-distribution in a package shall be done be the Contractor
responsible for that package.
To determine which package contractor has the lead responsibility for an interface, the following
order of priority shall be used:
P>D
The contractor who has the lead responsibility for the interface will be responsible for the coordination and for the physical completion of the interface. This includes providing the necessary
material (such as bolts, gaskets, flanges, weld rods, cable shoes and clamps, etc.) except the
cable and carry out the necessary work (such as aligning pipes, welding, tightening bolts, attaching
the cable shoes, connecting to the junction box, etc.) except pulling the cable.

INTERFACE POINT IDENTIFICATION CODE

Each interface shall be clearly identified by a unique identification code. Since every interface point
appears in the interface list of both involved systems, the interface shall use the exact same
identification code in both systems.
The following numbering system for interface points has been used in the tables below:
Xx-n/Yy-n-z
with
X, Y

Package Letter
P = Power, D = Desalination, S = 400kV Substation Phase I, E = External
The package letter shall always be in the following order: P>D>S>L>E

x, y

System Number, as given in the table on the following page

D1_Interfaces_II_WD

Page: 2

Part D1 Interfaces Working Document

(The number is the same as used for the Particular Technical Specification X2.x
e.g. System P8 as specified in Part P2.8 - Condensate and Feedwater System)
n

Indication of Phase Number


I = Phase I, II = Phase II

Sequential number

For example:
P7II/D4II-3
= Interface point number 3 between the system P7 (Steam Systems) of Phase II
and system D4 (Seawater Supply) of Phase II
System Numbers
P Power
P0
Common
P1
GTs Turbine Units and Auxiliaries
including bypass stack
P2
HRSGs and Auxiliaries
P3
Auxiliary Boilers
P4
Fuel Oil storage and supply system for
GTs and Boilers
P5
Gas systems for GTs and Boilers
P6
Steam Turbine Units and Auxiliaries
P7
Steam Systems
P8
Condensate and Feedwater Systems
P9
Closed Cooling Water System
P10 Emergency Power Supply
P11 Instrument and Service Air
P12 Not Used
P13 Steam / Water Sampling System
P14 Steam / Water Circuit Chemistry / Dosing
P15 Demineralised Water Plant
P16 Not Used
P17 Not used
P18 Waste Water Treatment Plant
P19 Sewage Treatment Plant
P20 Sump Pumps
P21 Cranes and Hoists
P22 Not Used
P23 Station Fire Fighting and Fire Detection
Systems
P24 Heating, Ventilation and Air Conditioning
P25 Emission Monitoring System
P26 Electrical Equipment
P27 I&C Systems
P28 Civil Works

D - Desalination
D0
D1
D2
D3
D4
D5
D6
D7
D8
D9
D10
D11

Common
Desalination Plant
Potable Water Pumps Station
Blending Station
Seawater Supply and Screening
Systems
Chemical Stores
Cranes and Hoists
Electrical Equipment
I&C Systems
Civil Works
Seawater Chlorination Plant
Plant Potable Water and Service Water
Systems

E External
E0 Common
E1 Natural Gas Pipeline
E2 Potable Water Pipeline

D1_Interfaces_II_WD

Part D1 Interfaces Working Document

4
4.1

Page: 3

INTERFACE POINTS
MECHANICAL INTERFACES

4.1.1 General Guidelines


The interfacing shall preferably be near the E226 co-ordinate (piperack) or approx. S2000 (south
end road of Phase I) or S2300 co-ordinate (southern perimeter fence).
The identified interfaces have been listed below. Further interfaces, if required for the
completeness of the plant / system, shall be provided by the Contractor with no extra costs.

4.1.2 List of Mechanical Interfaces within L Station Phase II


Interface

System /Medium

D0

Common

P20-II/D0-II-1

Chemical Waste Water Tie-in points at the chemical drains sump pump suction
Drains
lines in the vicinity of the various plant systems

P23-II/D0-II-1

Fire Water

D1

Desalination Plant

P7-II/D1-II-1

LP Steam

At MSF steam inlet valve, nearby pipe rack between P


and D area (E226), 1 per each MSF unit

P7-II/D1-II-2

IP Steam

At MSF steam inlet valve, nearby pipe rack between P


and D area (E226), 1 per each MSF unit

P8-II/D1-II-1

Return Condensate

On pipe rack between P and D area (E226), 1 per each


MSF unit

P11-II/D1-II-1

Service Air

On pipe rack between P and D area (E220), 1 per each


MSF unit

P11-II/D1-II-2

Instrument Air

On pipe rack between P and D area (E220), 1 per each


MSF unit

P20-II/D0-II-1

Chemical Waste Water Tie-in points at the chemical drain sump pump suction
Drains
lines in the vicinity of the various plant systems

P20-II/D0-II-2

Oily Waste Water


Drains

D4

Seawater Supply and Screening Systems

P6-II/D4-II-1

Sea Water Supply to


Condenser

P6-II/D4-II-2

Sea Water Return from At each Condenser siphon pit outlet


Condenser

D1_Interfaces_II_WD

Location / Description
(co-ordinates are approximate)

Tie-in point on common fire water supply ring line on the


north end side (S2000 co-ordinate) or south end side (S
2300 co-ordinate) of the phase II area

Tie-in points at the oily water drain sump pump suction


lines in the vicinity of the various plant systems

At each Condenser motor operated valve inlet counter


flange

Page: 4

Part D1 Interfaces Working Document

Interface

System /Medium

Location / Description
(co-ordinates are approximate)

P9-II/D4-II-1

Sea Water Supply to


CCW

At each intercepting valve inlet counter flange

P9-II/D4-II-2

Sea Water Return from At each intercepting valve outlet counter flange
CCW

P18-II/D4-II-1

Treated Waste Water

P18-II/D4-II-2

Cooling Sea Water


At the main sea water supply header Main Water Sea
Supply to Waste Water Water Cooling Pump delivery side to Steam Condensers
Cooling and Monitoring
Basin

D11

Plant Potable Water and Service Water Systems

P0-II/D11-II-1

Potable Water &


Service Water

Tie-in points on common potable / service water supply


line approx. at crossing (E220 / S2000 co-ordinates)

P9-II/D11-II-1

CCW Supply

nearby CCW cooler / pumps, on ground level

Into the seawater outfall structure

4.1.3 List of Mechanical Interfaces between L Station Phase II and Phase I


Interface

System /Medium

Location / Description
(co-ordinates are approximate)

D0

Common

P19-I/D0-II-1

Sewage Waste Water

D1

Desalination Plant

P15-I/D1-II-1

Distillate Water

Connection in the Demineralisation Plant, at the Phase I


buffer tank and the Phase I suction header of the
distillate booster pumps

P15-I/D1-II-2

Acid for Demister Pad


Cleaning from Demin
Plant

At the acid storage tank of the Demin Plant

P15-I/D1-II-3

Effluent from Demister At the Neutralisation Tank of the Demin Plant


Pad cleaning to Demin
Plant

D2

Potable Water Export System

D2-II/D2-I-1

Potable Water

D3

Blending Plant

Connection between Phase II sewage water piping with


Phase I sewage water ring line at the Phase I ring line

Connecting the new potable water export pumps to the


existing suction and discharge headers

D1_Interfaces_II_WD

Part D1 Interfaces Working Document

Page: 5

Interface

System /Medium

Location / Description
(co-ordinates are approximate)

P15-I/D3-II-1

Supply of Caustic
Solution to
Demineralised Water
Plant

Connection flange at the Demin Plant caustic soda tank


(if required)

D3-I/D3-II-1

Water, Caustic Soda,


Hypochlorite solution

Connections between the new blending train of Phase II


and the common equipment of Phase I

D3-I/D3-II-2

Blending Seawater

At the blending chamber of Phase I

D4

Seawater Supply and Screening Systems

P18-II/D4-I-1

Treated Waste Water

At the seawater outfall structure

D4-II/D4-I-1

Cooling Seawater,
discharge

At the flange of the discharge pipes provided under


Phase I

D10

Seawater Chlorination Plant

D10-I/D10-II-1 Seawater and


Hypochlorite solution

Connections between the new electrochlorination trains


of Phase II and the common equipment of Phase I

D10-I/D10-II-2 Hypochlorite solution

Connection of the new chlorination trains to the holding


&and dosing tanks and from the tanks to the new dosing
pumps (new dosing pumps are not really new, they have
been used for make up under Phase I)

4.1.4 List of Mechanical Interfaces between L Station Phase II and External


Interface

System /Medium

D2

Potable Water Pumps Station

D2-II/E2-1

Potable Water

4.2

Location / Description
(co-ordinates are approximate)

At tie-in point on water pipeline in the south-east corner


of the plant

ELECTRICAL INTERFACES

4.2.1 General Guidelines


The bulk of interfaces are between the 11 kV unit Auxiliary Supply of Package P and the 11 kV
sub-distribution boards of Package D.
Generally all 11 kV-Power cables and all related control, pilot wiring protection and interlocking
cables connecting any 11 kV unit SWG with any other 11 kV SWG of the entire Plant shall be part
of Package P. The same is applied for all connections between the 11 kV station service SWG and
any 11/0.4 kV auxiliary transformer of other Packages.

4.2.2 List of Electrical Interfaces


In the same way, the LV power cables and control cables from the Main Emergency Distribution
board in Package P to the 0.4 kV Emergency Distribution Board in Package D shall be provided.

D1_Interfaces_II_WD

Page: 6

Part D1 Interfaces Working Document

No.

System

Voltage
[V / kV]

Location

P26II/D7-II-1

11 kV Power Supply
Desalination Units

11 kV

Switchgear buildings of desalination


units

P26II/D7-II-2

380 V Emergency Power


Supply Desalination Plant

+ Protection,
control and
interlocking

380 V
+ Control and
interlocking

P26II/D7-II-3

Earthing system

D7-I/D7II-1

11 kV, 380 V
Power Supply from
Potable Water Pump Station

P26II/D7-II-1

4.3

Switchgear building Seawater


pumphouse,
Incoming feeders of 380 V
Emergency Sub-distribution Board
Desalination Plant,

Earthing system of the desalination


plant

Cross connections to the


earthing loops of power plant

+ Protection,
control and
interlocking

11 kV Power Supply
Seawater Supply and
Screening Systems

Incoming feeder of 11 kV Switchgear


of the desalination units

+ Protection,
control and
interlocking

Switchgear building Potable water


pump station
Extension of the existing 11 kV SWG
and LV SWG as required for the
additional potable water pumps.
Switchgear building Seawater pump
house
Incoming feeders of 11 kV Seawater
Intake Switchgear.

INSTRUMENTATION AND CONTROL INTERFACES

The following interfacing with other Packages and others shall be considered for Package D

4.3.1 DCS Cubicles in Package D scope and Man-Machine Interface in the CCR
Interface / System
P27/D8 I&C

Provisions made for interfacing and interfacing work to be performed


By Package D

By Package P

DCS Cubicles

DCS cubicles in the local


electronic rooms in the
Desalination plant, Seawater
switchgear, etc. buildings for all
Package D process systems

Extension and laying of the DCS


plant/highway bus from Package P
electronic room DCS up to the
Package D DCS cubicles

Plant/Highway Bus
connection

DCS cubicles communication /


coupling modules for the plant /
highway bus

Connection of the DCS plant / highway


bus to the Package D DCS cubicles

D1_Interfaces_II_WD

Part D1 Interfaces Working Document

Page: 7

CCR MMI
(Hardware)

Installation of CCR MMI hardware


components for the Package D
portion.

Provision of CCR furniture for the


Water Control Desk and cladding /
fixation for Package D large screen
device.

CCR Terminal / LAN


bus

CCR terminal/LAN bus for


Package D scope and connection
to highway bus and to the
Package D Water Control Desk
operator stations and peripheries
in the CCR

Connection and integration of the


Package D CCR terminal / LAN bus
to the Package P portion of the CCR
terminal/LAN bus

MMI Software

CCR MMI software, database,


Integration CCR MMI hardware,
configuration, etc., for Package D software and database for Package D
portion
portion

Documentation,
information and data

Provision of documentation and


information and data for common
and overall tasks 1) for Package
P, preparation of screen pictures
with refreshed values and operator
controls for Package D portion,
provision of calculations and
balances for the Plant
Management system

Remark

Integration of Package D control


tasks into the Plant control and
supervision including, bot not limited to
shared control tasks, Plant Coordinator and Plant Master control,
screen representations, logs and
protocols, with acquired and calculated
data

1)

The following documentation / information shall be timely delivered by Package D to P in a form


as required by package P:

List of all measurements (local and remote), including setpoints, alarms, etc.

Functional diagrams (logic and control diagrams with functional descriptions in clear text

P&I diagrams

MMI screen mimics for the Desalination Plant and proposal for common shared systems

Data for the plant management system, ready to use calculation routines, heat balance
calculations, correction curves, etc.

Layout drawings showing the location of the cubicles and other interfacing points, if any;

Equipment specification relevant for the interfacing;

All necessary engineering data and any other data as required by package P to perform
their specified tasks
Whenever required, the exchanged data shall be provided on PC data carrier.
For the duration of DCS programming by Package P for Package D tasks the latter shall
delegate to Package P one competent process engineer familiar with all necessary
instrumentation and control aspects of their package.

Package D shall further support all Package P tasks as far as Package D systems /
constructions are concerned (e.g. proposing and releasing locations for Loudspeaker system, etc.).

D1_Interfaces_II_WD

Page: 8

Part D1 Interfaces Working Document

4.3.2 Interfacing with Phase I


Interface

System /Medium

Location / Description

D2.8-I/D8-II-1

Potable Water Export System

Interfacing between Phase I and II control


systems establishing common control for the
whole system with supervision and selected
control from each Phase CCR operator stations.

D2.8-I/D8-II-2

Blending Plant

Interfacing between Phase I and II control


systems for full scale monitoring from both,
Phase I and II CCR operator stations and for
exchange of signals from/to existing equipment
for common tasks.

D2.8-I/D8-II-2

Seawater Chlorination Plant

Interfacing between Phase I and II control


systems for full scale monitoring from both,
Phase I and II CCR operator stations and for
exchange of signals from/to existing equipment
for common tasks.

4.3.3 Maintenance Telephone System


(P27/D8)
The interfacing point between the Plant Maintenance telephone system in Package P scope and
the network provided in the Package D scope shall be in the local electronic room of the
desalination unit closest to the central switchgear and control building of Package P.
Package D shall provide one delivery point for electrical and a separate one for I&C network in
their marshalling cabinet.
Package P shall provide the cable and cable laying from their central marshalling place of the
Maintenance Telephone System up to the common interfacing point and connect.

4.3.4 Water RTU


The interfacing of the Water RTU to the Employers Water SCADA System shall be done at the
existing multiplexer of the Employer at Jebel Ali G Station through armoured copper UG cables.
The connection to the Employers multiplexer is still in the Package D scope.
The interfacing may also be done via the link provided already by Phase I., subject of Employer/
Engineer's approval.

4.4

CIVIL INTERFACES

4.4.1 General Guidelines


As the scope of works of the Jebel Ali Power and Desalination Station L Phase II has been
divided in to two (2) packages, the civil works required by each packages will be divided
accordingly.
For the buildings, structures, equipment foundations, piperack / busduct foundations, and pipe and
cable trenches required for mechanical/electrical plants and equipments, the interfaces for the civil

D1_Interfaces_II_WD

Part D1 Interfaces Working Document

Page: 9

works are defined by the interfaces of the mechanical/electrical plants and equipments for which
the civil works are required. Reference is made to the relevant Clauses of mechanical/electrical
interfaces above.
Further interfaces for civil works not related directly to any of those plants, equipments, pipe and
cable racks/trenches, works such as roads, drainage and sewage etc., which need to be defined
area-wise i.e. to be shared by Packages, will be defined below in the Clause 4.4.2
Works for all of the Station to be executed by a certain Package will be defined accordingly.
Otherwise works of general nature mentioned in the scope of works below are limited to the
concerned packages only.

4.4.2 List of Civil Interfaces


4.4.2.1 General
Interfaces between Package D and P are defined below by physical co-ordinates cover civil
works of general nature. Some other works of general nature such as Employer/Engineers Site
office, first aid station for the whole construction site are included in the scope of works for
Package P and thus not specifically stated in the interfaces. In case of different civil contractors
are employed at Site for each Package, the co-ordination between them shall be undertaken by
the responsible contractor of the area.
In case of disputes about the scope of works of other civil contractor in his area, area contractor is
responsible for the completeness and functionality of all civil works in his area.

4.4.2.2 Interfaces between Package D and Package P


For works and services as roads, drainage lines, cable trenches if utilised by both packages,
landscaping, levelling and other works of similar nature area west of the co-ordinates
approximately E 226 (limits of walkway) will be in the scope of supply of the civil works for Package
D

4.4.2.3 Interfaces to the existing Station Phase I


For the buildings, structures, equipment foundations, piperack / busduct foundations, and pipe and
cable trenches required for mechanical/electrical plants and equipment, the interfaces for the civil
works are defined by the interfaces of the mechanical/electrical plants and equipment for which the
civil works are required.
Further interfaces for civil works not related directly to any of those plants, equipment, pipe and
cable racks/trenches, works such as roads, drainage etc., which need to be defined area-wise,
following shall apply:

Storm Water Drainage lines along the roads are to be connected at manholes at the defined
limits for the roads

For general limits of the roads reference is made to General Plant Layout and to Part D2.9 of
the Sepcification

D1_Interfaces_II_WD