15
(ENDING AUGUST 2015) 03 SEPTEMBER 2015
Weeks Lapsed
67 / 79
92.35 %
92.74 %
Physical Variance
90.67 %
89.05 %
Financial Variance
- 1.62 %
106 nos.
398 days
398,360 manhours
Cumulative
180
160
140
120
100
Planned
80
Actual
60
40
20
JELATEK
INTERCHANGE
KM4.6
SECTION 1
(P1 ~ P19)
SECTION 2
(P20 ~ P31)
SECTION 3
(P32 ~ P44)
%
Completion
Activity / Description
A. Design
B. Physical
Works
Status
Info
100.00 %
2 nos. (July)
4 nos. (August)
98.1 %
1,658
89.3 %
86.7 %
11 nos. (July)
22 nos. (August)
c)
Activity / Description
%
Completion
Status
100.0 %
Taking Over
Certificate
(TOC) signed
by TNB on 11
August.
4) JPS Selangor
a)
55.0 %
80.0 %
Item
Submitted
Approved (or
Reviewed with
Comments)
Under
Review
Comments
Method Statement
34
29
17 nos. approved;
3 nos. (No. 1, 14 & 19) withdrawn
from submission.
Material Submission
122
119
Bored Pile
347
347
Pile Cap
74
74
Column
71
71
Crossbeam
111
111
RC Plinths
63
63
TM Beams
310
310
T-Beam
14
14
10
Diaphragm Beams
135
119
16
11
Deck Slab
195
174
21
12
Parapet
1,656
1,656
13
Kerb
75
38
37
August 2015
10
August 2015
11
August 2015
12
No.
July 2015
August 2015
August 2015
Mattress
in
16
Amount
Claimed
(RM)
Cumulative
Amount
(RM)
Certified
Amount
(RM)
Cumulative
Certified
(RM)
Amount
Received
(RM)
Date
Payment
Received
29/01/2015
6,166,849.93
49,646,249.93
6,166,000.00
49,645,400.00
6,166,000.00
13/02/2015
10
25/02/2015
7,565,766.29
57,211,166.29
7,565,000.00
57,210,400.00
7,565,000.00
18/03/2015
11
27/03/2015
8,894,880.84
66,105,280.84
8,894,000.00
66,104,400.00
8,894,000.00
16/04/2015
12
27/04/2015
3,184,099.14
69,288,499.14
3,184,000.00
69,228,400.00
3,184,000.00
20/05/2015
13
28/05/2015
4,924,954.88
74,213,354.88
4,924,000.00
74,212,400.00
4,294,000.00
25/06/2015
14
24/06/2015
6,661,898.05
80,874,298.05
6,661,000.00
80,873,400.00
6,661,000.00
09/07/2015
15
29/07/2015
3,857,505.93
84,731,803.98
3,850,000.00
84,723,400.00
3,850,000.00
21/08/2015
16
01/09/2015
2,422,060.80
87,153,864.78
2,422,000.00
87,145,400.00
17
A.
Physical Works
Activity / Description
1.
a)
P21 ~ P22
P22 ~ P23
P26 ~ P27
P25 ~ P26
P24 ~ P25
P23 ~ P24
02 September 2015
04 September 2015
05 September 2015
07 September 2015
09 September 2015
11 September 2015
Span 22
Span 23
Span 27
Span 26
Span 25
Span 24
Pavement Works
a)
b)
c)
B.
Authorities
Requirements
Activity / Description
3.
JPS Selangor
a)
C.
Other Works
4.
Drainage Works
a)
5.
a)
19
Areas of Improvement as commented by Consultants:1) Contractor advised to pay special attention to concrete finishes especially now that the works
are limited to parapet and kerb.
2) Defects Listing as part of Handover and LLM requirement for SKPL should be commenced as
soon as practical and rectification works should be targeted to complete prior to completion of
new bridge deck.