MONTHLY PROGRESS MEETING NO.

15
(ENDING AUGUST 2015) 03 SEPTEMBER 2015

THE CONSTRUCTION AND COMPLETION OF PROPOSED AMPANG-KUALA


LUMPUR ELEVATED HIGHWAY (AKLEH) PHASE 2 EAST BOUND FROM
JALAN JELATEK INTERCHANGE (KM 4.6) TO
ULU KELANG INTERCHANGE (KM 6.0) FOR PROJEK LINTASAN KOTA SDN BHD

PROJECT: AKLEH PHASE 2


CONTENTS
1. EXECUTIVE SUMMARY
2. PROJECT OVERALL LAYOUT
3. SUMMARY OF PHYSICAL PROGRESS FOR MONTH OF AUGUST 2015
4. WORK DONE IN MONTH OF AUGUST 2015
5. QA / QC SUBMISSIONS
6. WORKS PROGRESS PHOTOS
7. STATUS OF PROGRESS CLAIM
8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
9. MAIN CONTRACTORS CONCLUSION

PROJECT: AKLEH PHASE 2


1. EXECUTIVE SUMMARY
Day Lapsed

378 / 443 scheduled workdays

Weeks Lapsed

67 / 79

Physical Progress (Planned)

92.35 %

Physical Progress (Actual)

92.74 %

Physical Variance

+ 0.39 % (2.98 % in July 2015)

Financial Progress (Planned)

90.67 %

Financial Progress (Actual)

89.05 %

Financial Variance

- 1.62 %

Average Manpower on Site

106 nos.

Total Mandays Worked

398 days

Total Manhours Worked

398,360 manhours

Cumulative

PROJECT: AKLEH PHASE 2


1. EXECUTIVE SUMMARY
200

180

160

140

120

100
Planned
80

Actual

60

40

20

PROJECT: AKLEH PHASE 2


2. PROJECT OVERALL LAYOUT
AMPANG
INTERCHANGE
KM6.0

JELATEK
INTERCHANGE
KM4.6
SECTION 1
(P1 ~ P19)

SECTION 2
(P20 ~ P31)

SECTION 3
(P32 ~ P44)

PROJECT: AKLEH PHASE 2


3. SUMMARY OF PHYSICAL PROGRESS FOR AUGUST 2015

PROJECT: AKLEH PHASE 2


3. WORK DONE IN MONTH OF AUGUST 2015
Component

%
Completion

Activity / Description

A. Design

1) Construction drawings currently issued up to design


of Parapet.

B. Physical
Works

2) Bridge Structure Works


a)

Casting of Deck Slab 45 spans out of 45 spans


completed.

Status

Info

100.00 %

2 nos. (July)
4 nos. (August)

b) Fabrication of Precast Parapet Panels in SPC


Industries 1,822 nos. out of 1,857 nos.
completed.

98.1 %

1,658

89.3 %

389 nos. (July)


835 nos. (August)

d) Casting of Road Kerbs 39 nos. out of 45 spans


completed.

86.7 %

11 nos. (July)
22 nos. (August)

c)

Installation of Precast Parapet Panels


nos. out of 1,857 nos. completed.

PROJECT: AKLEH PHASE 2


3. WORK DONE IN MONTH OF AUGUST 2015
Component
C. Authorities
Requirements

Activity / Description

%
Completion

Status

3) Tenaga Nasional Berhad (TNB)


a)

Completed TNB Pylon Relocation Works which


includes the following:i.
Erection of two (2) new towers;
ii. Stringing Works (conductors, earthwire and
optical ground wire)
iii. Sagging of Conductors
iv. Installation of Jumpers, Vibration Dampers
& Aircraft Warning Sphere
v. Final Inspection by TNB

100.0 %

Taking Over
Certificate
(TOC) signed
by TNB on 11
August.

4) JPS Selangor
a)

Continued construction of Gabion Mattress in


Section 1 (between piers P3 ~ P19).

55.0 %

b) Continued construction of GeoBags (Softrock


Formation) in Section 3 (between piers P33 ~
WE91).

80.0 %

PROJECT: AKLEH PHASE 2


5. STATUS OF QA / QC SUBMISSIONS
No

Item

Submitted

Approved (or
Reviewed with
Comments)

Under
Review

Comments

Method Statement

34

29

17 nos. approved;
3 nos. (No. 1, 14 & 19) withdrawn
from submission.

Material Submission

122

119

109 nos. approved

Concrete Tests for the following Structural Elements:3

Bored Pile

347

347

Pile Cap

74

74

Column

71

71

Crossbeam

111

111

RC Plinths

63

63

TM Beams

310

310

T-Beam

14

14

10

Diaphragm Beams

135

119

16

11

Deck Slab

195

174

21

12

Parapet

1,656

1,656

13

Kerb

75

38

37

100 % COMPLIANCE WITH


SPECIFICATIONS UP-TO-DATE

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
July 2015

View of Increasing Chainage from pier


P4 Completed Parapet and Kerb
Casting from Span 5 ~ Span 7.

August 2015

10

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
July 2015

View of Increasing Chainage from pier


P11
- Completed Parapet and Kerb Casting
from Span 11 ~ 14.

August 2015

11

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
July 2015

View of Increasing Chainage from pier


P14
- Completed Parapet and Kerb Casting
from Span 14 ~ 18.

August 2015

12

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
July 2015

Newly Erected TNB Tower


(located off Jalan Enggang)

No.

July 2015

Newly Erected TNB Tower No. 4 (located in


JPS SMART Kg. Berembang Catchment
Area)
13

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
July 2015

View of Increasing Chainage from pier


P25
- Installation of formwork and rebar for
deck slab at Span 26 & 27 in progress
by end of July 2015.
August 2015

View of Increasing Chainage from existing


pier P25
- Casting of Span 27 on 11 August 2015.
14

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
August 2015

View of Span 31 towards Increasing


Chainage (from existing AKLEH)
- Completed Parapet and Kerb Casting
from Span 31 ~ 34.

August 2015

View of Span 38 towards Increasing


Chainage (from existing AKLEH)
- Completed Parapet and Kerb Casting from
Span 38 ~ 42.
15

PROJECT: AKLEH PHASE 2


6. WORK PROGRESS PHOTOS
August 2015

JPS Selangor Requirements


- Installation of Geobags in Section 3.

August 2015

JPS Selangor Requirements


- Construction of Gabion
Section 1.

Mattress

in

16

PROJECT: AKLEH PHASE 2


7. STATUS OF PROGRESS CLAIM
Date
No
Claim
Submitted

Amount
Claimed
(RM)

Cumulative
Amount
(RM)

Certified
Amount
(RM)

Cumulative
Certified
(RM)

Amount
Received
(RM)

Date
Payment
Received

29/01/2015

6,166,849.93

49,646,249.93

6,166,000.00

49,645,400.00

6,166,000.00

13/02/2015

10

25/02/2015

7,565,766.29

57,211,166.29

7,565,000.00

57,210,400.00

7,565,000.00

18/03/2015

11

27/03/2015

8,894,880.84

66,105,280.84

8,894,000.00

66,104,400.00

8,894,000.00

16/04/2015

12

27/04/2015

3,184,099.14

69,288,499.14

3,184,000.00

69,228,400.00

3,184,000.00

20/05/2015

13

28/05/2015

4,924,954.88

74,213,354.88

4,924,000.00

74,212,400.00

4,294,000.00

25/06/2015

14

24/06/2015

6,661,898.05

80,874,298.05

6,661,000.00

80,873,400.00

6,661,000.00

09/07/2015

15

29/07/2015

3,857,505.93

84,731,803.98

3,850,000.00

84,723,400.00

3,850,000.00

21/08/2015

16

01/09/2015

2,422,060.80

87,153,864.78

2,422,000.00

87,145,400.00

17

PROJECT: AKLEH PHASE 2


8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
Component

A.

Physical Works

Activity / Description

1.

Bridge Structure Works

a)

To complete installation of Precast Parapet Panels and Kerb Casting for


the following spans:i.
ii.
iii.
iv.
v.
vi.

P21 ~ P22
P22 ~ P23
P26 ~ P27
P25 ~ P26
P24 ~ P25
P23 ~ P24

02 September 2015
04 September 2015
05 September 2015
07 September 2015
09 September 2015
11 September 2015

Span 22
Span 23
Span 27
Span 26
Span 25
Span 24

Cumulative total of 45 / 45 spans to be completed by 11-Sept 2015.


2.

Pavement Works

a)
b)
c)

To commence premix works by 10 Sept 2015.


To commence installation of traffic signs on 21 Sept 2015.
To commence installation of directional signages and gantry works by
25 Sept 2015.
18

PROJECT: AKLEH PHASE 2


8. MONTHLY LOOKAHEAD (1 SEPT 2015 ~ 30 SEPT 2015)
Component

B.

Authorities
Requirements

Activity / Description

3.

JPS Selangor

a)

To complete installation of gabion mattress in Section 1 by 30 Sept


2015.
b) To complete installation of GeoBags in Section 3 by 21 Sept 2015.

C.

Other Works

4.

Drainage Works

a)

To complete reconstruction of drainage services by 30 Sept 2015.

5.

Defects Listing (as part of Handover Process)

a)

To commence listing of Defects on completed structural elements at


each pier and span by 07 Sept 2015.

19

PROJECT: AKLEH PHASE 2


9. MAIN CONTRACTORS CONCLUSION
 Overall progress achieved in Month of August 2015 has been satisfactory due
to the following reasons:1) Regression on Overall Physical Progress compared to previous month (+0.39 % compared to
+2.98 % in July 2015 and +6.00 % in June 2015) ahead by 2 days in overall activities and no
longer recording delays on critical path.
2) Regression in % ahead is due to the reduced manpower over Hari Raya Aidilfitri period (which
affected the parapet installation works and kerb casting) and the requirement to complete
current ongoing activities prior to commencement of the next milestone works i.e. Pavement
works on new bridge deck.
3) We positively note that TNB Pylon Relocation Works were completed as scheduled, with zero (0)
HSE related incidents and within approx. one (1) year from official communication with TNB on
22 July 2015.

 Areas of Improvement as commented by Consultants:1) Contractor advised to pay special attention to concrete finishes especially now that the works
are limited to parapet and kerb.
2) Defects Listing as part of Handover and LLM requirement for SKPL should be commenced as
soon as practical and rectification works should be targeted to complete prior to completion of
new bridge deck.

20

THANK YOU FOR YOUR TIME