Beruflich Dokumente
Kultur Dokumente
b1
PROPOSED
SHAFTS +
KITCHENER
FACILITY
PIT TOP
#1 SHAFT
Vent + 2nd Egress
#3 and #4
VENT
SHAFTS
MINING AREA
WHERE
REPAIRS
OCCURRED
PROPOSED WORKINGS
OLD ABANDONED WORKINGS
#2 SHAFT - Flooded
Slide 3
b1
bmckay, 3/11/2010
Repair Background
Recently, an incident occurred on the longwall face, where damage was
caused to two of the 6 legged tailgate shields (Number 122 and 123). The
shield clevises were subjected to excessive tensile forces resulting in a
ductile failure when the shield canopy was raised to the roof in a localised
cavity.
Due to the unique operation of the shields, the middle two hydraulic
cylinders (legs), were raised by the outer legs extending them into this
cavity. This caused severe damage to the shield canopy middle clevises.
A decision was made by Austar management to repair as soon as
possible. The ongoing operation of these shields and possibly the
adjacent shields, was definitely not sustainable. This was due to an
estimated 50% reduction in roof support density (estimated by OEM
Design Engineer) above any one shield that was not operating as it was
designed.
Longwall Equipment
Methodology
Identification of Repair Options and Risk Assessment
A group of employees including mine workers, tradesmen,
engineers, management, OEM representatives and a local
check inspector were involved in an options evaluation. A risk
assessment to determine the best options available to repair the
shield, included the following 1.
2.
3.
4.
5.
6.
Considerations
Adherence to and compliance with relevant guidelines, standards and
legislation were considered throughout the process, with particular
focus on:
Considerations
Audit check lists were developed for MDG25 and were included in all
site Safe Work Procedures
Major Advantage
Major Disadvantage
2/ Install a bolt on
fork clevis
Eliminated the
welding process from
hot work activities
Major Advantage
Major Disadvantage
Major Advantage
Major Disadvantage
4/ Continue to
operated with the
damaged clevis
No underground
repairs required
Uncontrolled canopy
movement during
operation
Reduced support
density
Shield operation
slower
5/ Remove the
shields for
workshop repairs
6/ Replace the
No hot work required
shield with a similar underground
unit
A very complex
operation
Evaluation Outcome
The group believed with the appropriate controls in place,
welding on the LW face had the lowest level of risk.
Exemption
Austar Coal Mine applied for an exemption under
CMHSR2006 clause 19 (1) (c). Specifically this was for the use
of non Gazetted electrical equipment in the hazardous zone.
The exemption was time limited therefore Austar could not
allow for any major delay during the repair process. A detailed
time line was developed which included contingencies.
Consequence
Damages hydraulic hoses which
could lead to high pressure fluid
being released
Electrical equipment damaged
Gas Ignition
Ineffective welding
Dust
Explosion
Further Details
The Mig welder powered from a 1000 to 415 volt transformer. The
primary welding machine was a MIG Kempi Master 5001.
This transformer was powered via a 50mm squared cable from the
longwall substation.
WELDING
SITE
415v TO
1000v
TRANSFORMER
AIR
FLOW
A3 Block
Retreat Direction
WELDING POINTS
124
X
X
X
OXY ACETYLENE BOTTLES
MINIMUM 3m APART
DCB
TX
0.9
LnL
MIG GAS
T/G
WELDING POD
BRATTICE WINGS
AIR
FLOW
5m
0.9
LnL
0.9
LnL
GOAF
0.9
LnL
0.9
LnL
9ct
EXISTING
QUIKSEAL
PARTIALLY
REMOVED
FOR
VENTILATION
PERMANENT GOAF
STREAM SAMPLE POINT
TUBE BUNDLE POINT No 5
Instruction
#124
Prop Setters
x 2 off
Link n lock
packing
CST DRIVE
Special Preparation
The Boilermakers and equipment needed to meet Austar and
OEM competency requirements. A trial welding programme using
these people and equipment was undertaken in the OEMs
workshop.
Welding equipment and compliance to MDG25 & AS 1674.2.
Non Destructive Testing personnel competence Australian
Institute for Non Destructive Testing.
Site preparation had to be audited prior to hot work commencing.
This was undertaken by the MME, MEE & MME.
I&I instructed the Austar MME, MEE & MME or their nominated
delegates to audit the site every 24 hours.
I&I randomly audited the welding site during the project.
Continuous monitoring of the atmosphere was undertaken by a
mine official.
Application of the
Hierarchy of Controls
During the hot work repairs
The OEM designed and supplied a shear pin to be installed on
the bottom leg clevis. This was rated at 33.6 tonnes and was
designed to fail, prior to any structural damage occurring.
During the subsequent longwall relocation
The capabilities of the top clevis were increased during the
longwall relocation. This still incorporated the shear pin.
Longer Term
Continued mechanical and structural improvements with the six
legged shields.
Replace the six legged shields with four legged types