Sie sind auf Seite 1von 129

The Construction Manager:

The Contractor:

King Abdulaziz International Airport Development Project


(J-10-421-PF-00 and J-10-422-PF-00)

Compliance with CM Comments


Submittal Tittle:

MST For Steel Structure Installation (421-DCS-MST-S-00850)

Sub-Contractor :

Saudi Binladin Group

Sl.No.

CM Comments

Rev.

Facility Code:

F100

Area of Appliacation:

F100-PTB

Contractor's Reply

Logistics of access to the working areas.

A separate logistic plan for zone A&E will be submitted with coordination with the main contractor.

Method of lining and leveling required.

Please find section 13 Survey scheme.

421/422-SBG-CCM-010-00

THE ENGINEER:

King Abdulaziz International


Airport Development Project
(Phase I)

THE CONTRACTOR:

Jeddah, KSA
Contractor: Saudi Binladin Group
Doc. Ref. No.: 421-DCS-MST-S-00850 Rev.04
Contract No.: J-10-421-PF-0
Date Issued: 31 Jan 2013
Method Statement for Installation of Steel Structure

List of Contents
1 Preface ................................................................................................................... 4
2 Scope of Work ........................................................................................................ 5
2.1 Pier .................................................................................................................................................. 5
2.2 Terminal Processor ....................................................................................................................... 5
2.3 International Hub........................................................................................................................... 8
2.4 Boarding Bridge ............................................................................................................................ 9
2.5 Reference Standards: ................................................................................................................ 10

3 Personnel Roles and Responsibilities ............................................................... 10


4 General Construction Introduction .................................................................... 10
4.1 Schedules .................................................................................................................................... 10
4.2 Site Plan ....................................................................................................................................... 10
4.3 Manpower plan .............................................................................................................................. 11
4.4Mechanical and Equipment............................................................................................................. 11
4.5 General Work Procedures .............................................................................................................. 12

5 AESS requirement................................................................................................ 14
6 Site Welding ......................................................................................................... 15
7 Bolting Tightening ............................................................................................... 15
8 Touch Up Painting Procedure ............................................................................. 15
9 Installation Method for Pier ................................................................................. 17
9.1 Shipping Unit ............................................................................................................................... 17
9.2 Erection Units .............................................................................................................................. 18
9.3 Detailed Erection Unit and weight ............................................................................................ 18
9.4 Crane Analysis and Selection ................................................................................................... 20
9.5 Temporary Supports ................................................................................................................... 24
9.6 Detail erection method ............................................................................................................... 25

10 Erection Method for Terminal Processor ......................................................... 34


10.1 Shipping units ............................................................................................................................ 34
10.2 Erection Weight and Selection of Cranes ............................................................................. 35
10.3Temporary support..................................................................................................................... 38
10.4 Detailed Erection Method for Terminal Processor ............................................................... 39

11 Erection Method for International Hub ............................................................. 44


11.1 Shipping Unit ............................................................................................................................. 44
11.2 Erection Units ............................................................................................................................ 45
11.3 Erection Weight and Crane Analysis...................................................................................... 48

Page 2 of 82

THE ENGINEER:

King Abdulaziz International


Airport Development Project
(Phase I)

THE CONTRACTOR:

Jeddah, KSA
Contractor: Saudi Binladin Group
Doc. Ref. No.: 421-DCS-MST-S-00850 Rev.04
Contract No.: J-10-421-PF-0
Date Issued: 31 Jan 2013
Method Statement for Installation of Steel Structure

11.4 Temporary supporting............................................................................................................... 56


11.5 Detailed Erection Method for International Hub ................................................................... 57

12 Erection Method for Boarding Bridge .............................................................. 62


12.1 General Dimension................................................................................................................... 62
12.2 Transportation Units ................................................................................................................. 63
12.3 Erection Units ............................................................................................................................ 64
12.4 Crane Selection ........................................................................................................................ 64
12.5 Erection Method ........................................................................................................................ 65

13 survey schemes ................................................................................................. 66


13.1 Analysis of difficulties ............................................................................................................... 66
13.2 Survey idea and control method............................................................................................. 67
13.3 Accuracy control of anchor bolts ............................................................................................ 67
13.4 Accuracy control of Zone A Banana trusses ......................................................................... 68
13.5 Installation position for banana truss ..................................................................................... 69
13.6 Positioning accuracy of PIER ................................................................................................. 69
13.7 Assembly and installation surveying for boarding bridge ................................................... 78

14 Logistic Plan....................................................................................................... 79
14.1 Storage Yard .............................................................................................................................. 79
14.2 Master Schedule ....................................................................................................................... 79
14.3 Manpower Plan ......................................................................................................................... 79
14.4 Equipment Plan......................................................................................................................... 80

15 Health and Safety ............................................................................................... 82


16 Attachment: ........................................................................................................ 82
Appendix A Risk assessment
Appendix B Insert for temporary support layout
Appendix C Insert for temporary support detail
Appendix D Interface TC and processor
Concrete floor calculation see RFI
Site assembly yard plan dwg
Banana truss erect plan see attachment dwg

Page 3 of 82

1 Preface
PTB contains four main structural parts: Piers, Terminal Processor, International Hub, and Boarding
Bridge. The installation method for space frame roof in the terminal processor and international
hub is not stated in this document.
The total PTB covering area is about 220,000m2, with a length 1500m and width 1000m.
Piers contain columns and space truss roof. This statement applies to both of them.
Terminal processor contains support columns, space frame and shed framing, and this statement
only applies to the support columns and shed framing.
International hub contains support columns, gills truss, perimeter beams and space frame roof.
This statement only applies for the support columns, gills truss and perimeter beams.

Page 4 of 82

2 Scope of Work
According to project specs, drawings and contract, this statement describes the installation method
for the following steel parts:
2.1 Pier
Structure Introduction
Pier is also named as concourse and could be described by single pier at zone B, C, E and double
pier at Zone F, G and D. The steel structure covering the 2nd civil floor is composed of cranes
(240PCS), H section roof, catwalk (only for double pier) and casting foot joint.
The supports columns composed of curved arch columns and the webs welding on it. Their
sections are CHS101.6X10~CHS475X14, UB127X76X13~UB838X292X14, CUB686X191X67,
UC254X254X132 and UC305X305X240.

Single pier

Double pier

2.2 Terminal Processor


Structure Introduction
The terminal processor covers the 3rd civil floor and covering an area of approximately 66000m2. It
contains south facade, tree and tripod, north columns, space frame and shed framing.
JGS will erect all steel structures of terminal processor except space frame. The following
paragraphs give an introduction to each part of terminal processor

Page 5 of 82

Shed Framing

South faade head

Soffit
Tree
and
tripod

North Column

South facade

Detail at Level 3

Tree bottom 24pcs

Detail at Level 1

South facade
South faade is made up of 64 banana trusses and 826 transoms. Banana truss is connected with
space frame by bolts sphere joints, and welded with transom. There is a third segment between top
and bottom tusk. The length of the bottom segments is 11m, while the top segments range from
14m to 25m. The tusks range from 5.3ton to 19.5ton, and the total weight is about 1661 ton. Each
banana truss is constituted of front chord, rear chord and web member. The section of chord
ranges from CHS 219.1x10 to CHS244.5x25. The section of web ranges from CHS 168.3x12.5 to
CHS 193.7x16. The typical section dimension of transom is CHS 168x10, CHS 193.7x12.50.
Drawings below are for detail connection of tusk:

Top connection

Interface with concrete +14.9m

Page 6 of 82

Base plate

88 trees and 6 tripods


Tree columns with length ranging from 9.8m to 22.3m and weight ranging from 3.6 ton to 8.2 ton
for each tree. There are 6 tripod columns with length ranging from 26 to 30m, weight ranging from
9.6 to 10.9ton for each tripod.
The sections of tree and tripod column are CHS762x20.

Tripods column

Tree support

North column
There are 54 North columns. Their sections are CHS 457x16, and their lengths are 7.5m~14.1m
with their weight ranging from 1.6 ton to 2.5 ton. The whole weight is about 100 tons.

Page 7 of 82

North column

Shed frame:
Shed frame is made up of about 11800 beams, weighting total 1633 tons with length 3.3m to
28.3m, and typical section dimension CHS140x6.3,UB250*250*16, RHS203.2*203.6*7.2*11. The
weight of the heaviest beam is 0.7 ton.

2.3 International Hub


Structure Introduction
International hub roof covers the 2nd civil floor and covering an area approximately 50000m2. It
contains arches, sloped columns, gill columns, gill trusses, perimeter beams and space frame.
JGS will do the installation of the steel structure except for the space frame.

Page 8 of 82

Arch
Gills Truss
Sloped Column

Gills Columns
Perimeter Beam

GC20
There are 18 piece of Arches and 9 pieces of Sloped Columns in International HubArches and
Sloped columns are on the second floor .Their length is 29 m and 16.5 m ; The section is RHS
600x40 (arches) and CHS 559x25 (sloped columns), and the weight is 20ton and 5.4 ton
There are 54 pieces of Gill Columns distributed on Level 2 and Level 3 except GC20s that are on
Level 0, so their length are 10.6m, 14.9m, 25.9m respectively. Their section is different from CHS
406x16 to CHS508x50, and the weight is from 2.59 t to 6.08 t.
The gills trusses have a curved shape and are the key to make the project successful.
There are 15 pieces of Gills Trusses having 5 pieces of South Gills Trusses and 5 pieces of
Northwest Gills Trusses and 5 pieces of Northeast Gills. The weight of South Gills is from
12.6~70.38 ton and North Gills are from 14.5~63.8 ton. Both of their Height is from 4.5~7.7 m .The
section is as follow:
CHS193.1X10, CHS219.1X12.5~20, CHS273X20, CHS323.9X12.5~25CHS457X25, CHS457X40
2.4 Boarding Bridge
Totally 46 boarding bridges will be installed on site. The members are mainly H section and Box
section. Connections will be bolted on site and requires high erection accuracy.

Page 9 of 82

2.5 Reference Standards:


The reference of standards to be made in accordance with the following:

Project specification Section 051200 Structural Steel Framing


IBC2006 International Building Code
AISC "Manual of Steel Construction", 13th Edition.
AISC 303-05 "Code of Standard Practice for Steel Buildings and Bridges"
AICS/ RCSC-04 "Specifications for Structural Joints Using ASTM A 325 A490 Bolts"
AWS D1.1-08 "Structural Welding Code"

3 Personnel Roles and Responsibilities


The overall responsibility of KAIA PTB Steelwork as below:
SBG (Main Contractor)
Saudi Binladin Group
RSS (Steel Subcontractor)
Roots Steel
JGS (Steel Supplier & Erector)
Jinggong Steel
4 General Construction Introduction
4.1 Schedules
The total schedule duration is 16 months, starting from the project commencement to the time of
steel structure erection completion.
Before the site erection, it requires at least 6 months for the following process:
Detailing drawing, procurement, fabrication, trail assembly, delivery.
1st Aug 2012 assumed as commence on site work, totally 10months for site installation
The main contractor is follow the submitted base line Schedule and meet the mentioned date for
the steel structure delivery to site and installation works.
4.2 Site Plan
Site assembly yard see attachment
storage yard shall be 610mx86m, 52460m2;

Page 10 of 82

4.3 Manpower plan


The maximum manpower on site shall be 292.

4.4Mechanical and Equipment

All tower cranes to be used by steel contractor shall complete the handover a month before
steel installation. During the installation, steel contractor shall have the priority to use the
cranes.
Piers:
8 railed tower cranes
Terminal Processor: 9 fixed tower cranes
International Hub: 6 fixed tower cranes

Mobile crane 400t will be used for erection of piers in the cross zone between Zone B and
Zone D

Page 11 of 82

4.5 General Work Procedures

The concrete works handover sequence is assumed in this statement. The handover shall
be 1 week prior to steel structure installation commencement. Accurate surveying report for
the concrete works to be provided to the erector prior starting erection, to ensure the entire
structure conformity. The above mentioned report shall be provided to the erector for action
and to CM for information. In case of any site modifications are required due to unconformity
between the concrete works and steel erection works a detailed report is to be submitted for
CM approval.

All tower cranes that are to used by steel contractor shall be taken over a week prior to steel
installation. During the steel installation, steel contractor has the priority to use the cranes.

The shed framing installation commences after the space frame execution is finished in
terminal processor, the temporary supports and scaffolding shall remain for JGS use.

4.5.1 Pier

The members will be transported to site as members in bulks.

Trial assembly will be executed to ensure the accuracy for fabrication.

The erection units named crane will be assembled on the ground in the pre-assembly area
and then lifted by the railed tower cranes to 2nd civil floor. Total nos. of crane for erection is
240.

The roof members will be installed after the crane is in its position.

The welding work will be done on the ground for the cranes to be assembled. All other
erection work is by bolt.

Totally 8 railed tower cranes are required, 4 of 8 have the capacity of 17.9t @ 27m and the
other four have the capacity of 12t @ 34m.

Page 12 of 82

4.5.2 Terminal Processor

All the columns, soffit steel, shed framing steel will be transported to site in bulks with
maximum a length of 17m, the south facade will be divided to 3 units as a truss segment.

A crawler crane will be used to lift the south facade units and then to be assembled as a
complete truss on the ground in the designated pre-assembly area.

Transom will be erected by tower cranes and the welding done with the brackets.

The tree columns, north faade columns will be erected by 9 fixed tower cranes, which have
the capacity 5.7t @ 50m.

The shed framing shall be installed with space frame erection unit prior to lifting

4.5.3 International Hub


All the columns, perimeter beams will be transported to site in bulks with maximum length of
17m. The gill trusses also will be in bulks and assembled on the civil floor to be a complete
erection unit.
Trial assembly will be done to ensure the accuracy for fabrication.
Total 6 fixed tower cranes will be used for lifting the steel having capacity of 8.8t @ 35m.
Any area inaccessible by tower cranes shall be managed by a 35T mobile crane.

Page 13 of 82

5 AESS requirement
For the architecturally exposed steel structure quality in the project should comply with the AESS
requirements:
2.4m
2.4~6m
6m

first level
second level
third level

Level one and level two are the visible and the appearance on these levels is critical. A glossy
finish completed with grinding is required.

Page 14 of 82

6 Site Welding

Field welding shall be carried out as per the approved Welding procedure specification
(WPS)

Due to the significant number of site welding joints, an independent testing and
inspection agency will be engaged to perform site testes and inspection. The attendance
and numbers of the agency inspectors shall be according to the welding inspection
requirements and will not hinder the erection schedule.

Welding plan shall be prepared and updated daily by the assigned independent testing
and inspecting agency.

Welding shall be carried out in good climatic and environment condition. In case of
damp climatic condition, additional protection shall be provided to cover the weld area.
All joints are to be dried before welding in damp climatic condition.

In the case of multi layer welding, slag and spatters on each completed bead shall be
removed prior to weld the following layer.

7 Bolting Tightening

Bolt storage: All fastener set shall be delivered in a sealed box, it shall be stored into a
dry space, the sealed box shall be put away from ground. No such box is allowed to be
open before it to be fixed at site.

Bolt tightening shall be carried out after completion of alignment to the specified area. All
bolts / nuts and washers shall be used as per shop drawings and project specification.

Mobile Access Platform or scaffolding platform shall be used during Erection, Bolting
tightening and inspection.

Bolted connection shall be tested and inspection by the independent testing and
inspecting agency according to RSCCS Specification for structural joints Using ASTM
A325 or A490 Bolts.

8 Touch Up Painting Procedure

Site Painting for site welding area.


The welding shall be cleaned by using electrical sand disc or wire brush. Surface
profiles check shall be completed on the ST3 finish using testex tape.

Prior to the application, foreign material adhering to the surface shall be removed by
using hand / Mechanical clean by sand disc and dry cotton cloth to maintain SSPC-SP2
or SSPC-SP3 surface preparation.

Paint (Primer to top coat) shall be applied as per project specification by using hand
brush / roller. (As per below flow chart).

The following painting system shall be used.

Page 15 of 82

S/No Applicable Area Location

Coating
layer
Structural
Steel
painting Primer
system As per the specification Intermediate
051200:
Structural
steel Coat
framing clause 3.3.N. & 3.6 Final Coat
repairs and protection

Paint Type

epoxy
epoxy

Painting
DFT
125m
155m

polyurethane 80m

Touch-up painting shall be carried where the paint surface is damaged during transit.

Only approved paint shall be used for touch up painting work.

Prior to the application, foreign material adhering to the surface shall be removed by
SSPC-SP 2 hand-tool cleaning or SSPC-SP 3 power-tool cleaning.

Touch up painting (primer and top coat for deep damage & top coat for small depth
scars & minor paint scars on top coat) shall be carried out by using hand brush / roller.
(see below flow chart for site painting)

Flow chart for Site Painting Touch-up (Repair) & Paint Work (Welds)

Identify the Location of Painting touch (Repair) work & Painting work (weld)

Check the Atmospheric Condition & Type of Painting System

Clean the painting damage area / Weld joint by:


1. Wire brush cleaning
2. Mechanically surface preparation to level ST3 (SSPC SP-3) by sanding disc for weld
joint area & major paint damaged area, the surface profile shall be test accordingly.
3. Hand sanding with 80 grade sand paper feathering back the existing coating to revel a
tight edge. The repair overlap distance on the existing coating shall be minimum 5mm
4. Solvent cleaning with approval Thinner with lint free cloth and allow to fully dry
before proceeding with the original coating system.

After check the cleaning surface (Ref: Painting System table):


1. 1st Applied Strip coat paint at corner/holes/bolts/welds by brush.
2. All splice plate edges, fasteners edges shall be sealed with paint during strip coating.
3. After Strip coat all touch up area shall be paint by brush / roller uniformly as required paint thickness.
4. Top coat, before top coat paint application the first coat paint should dry minimum 2-3hours
5. Strip coating with top coat to sharp edges shall also be applied for the top coat.
6. Before applied top coat, the surface shall be clean by Cloth / brush
7. Applied top coat paint as required thickness

Check the Painting DFT / Visual Inspection

Page 16 of 82

9 Installation Method for Pier


9.1 Shipping Unit
The structure of pier shall be transported as illustrated considering the transportation, size
condition, connection type, appearance, etc.
For double Pier (Zone D, F & G), the shipping unit is as indicated below:

For Single Pier (Zone B, C, E), the shipping unit as indicated below:

For Roof Beams: Secondary Trusses are shipped in two pieces as shown in the picture while the
other beams are to be delivered in bulk.

Page 17 of 82

9.2 Erection Units


The erection unit shall consider the crane capacity, critical weight to minimize the installation work
mid-air.
The piers (green) could be erected by tower crane as complete unit. The piers (yellow) shall be
broken by one beam. The (red) one shall be installed by 400t mobile crane as a a complete set.

Zone B, C 52 PCS(12.01t@29m<16.5t@29.5m)
9.3 Detailed Erection Unit and weight

Conclusion:
Total Amount240 PCS
Complete Units: 118 PCS, 50%
Part Assembly:102 PCS, 42%,by 25t mobile
crane on the floor and 8033.16
Mobile Crane:20 PCS, 8%, by 400t mobile
crane

Page 18 of 82

Zone E 60 PCS (25t mobile crane)

THE ENGINEER:

King Abdulaziz International


Airport Development Project
(Phase I)

THE CONTRACTOR:

Jeddah, KSA
Contractor: Saudi Binladin Group
Doc. Ref. No.: 421-DCS-MST-S-00002 Rev. 00
Contract No.: J-10-421-PF-0
Date Issued: 02 February 2012
Method Statement for Installation of Steel Structure

Zone F, G
76PCS (15.9t@29m<16.5t@29.5m)

Zone D
32PCS (14.78t@31m<15.48t@31m)

Zone H
20 PCS (20.4t@27m<25.3t@27m)

Page 19 of 82

9.4 Crane Analysis and Selection


9.4.1 Crane selection and site position
Railed Tower Crane position: The railed tower crane shall be located at a distance from the
concrete as detailed below:

Page 20 of 82

Page 21 of 82

Page 22 of 82

9.4.2 Crane Capacity Analysis


(Green) Denotes means erected by 16t tower crane.(see crane plan)
(Red) Means erected by 400t mobile crane of zone H, by 25t mobile crane on the floor of zone
BCE . Concrete floor calculation see attachment.
Burden
%

AXES

New Rev
Weight

Radius
for RTC

NE56

15.9

29m

16.5

96%

NE54NE26

15.54

29m

16.5

94%

NE24

15.7

29m

16.5

95%

NE2022

16

29m

16.5

97%

NE18

19.7

29m

16.5

119%

N26S33

14.9

29m

16.5

90%

S31S29

15.7

29m

16.5

95%

S27

16.1

29m

16.5

98%

SE47

25.37

29m

16.5

154%

SE4543

22.55

29m

16.5

137%

SE41SE3

21.84

29m

16.5

132%

12

S1S5

21.84

29m

16.5

132%

13

N24N20

17.4

29m

16.5

105%

14

N18

19.7

29m

16.5

119%

15

N1614

20.3

29m

16.5

123%

16

N1210

23.9

29m

16.5

145%

17

N8N2

24.4

29m

16.5

148%

NE2NE10

24.4

29m

16.5

148%

NE12NE18

20.4

29m

16.5

124%

20

NW246

24.4

29m

16.5

148%

21

NW810

24.1

29m

16.5

146%

22

NW12

20.48

29m

16.5

124%

23

NW1416

20.3

29m

16.5

123%

24

NW18

19.7

29m

16.5

119%

25

S25S21

18.45

35m

30

62%

S19

24.1

35m

30

80%

S15S17

25.2

35m

30

84%

S13S7

21.84

35m

30

73%

No.

Zone

FG

10
11

18
19

26
27

BC

28
Remark

Crane Capaciy

WOLLF
8033.16

mobile
crane 400t

Contain Tool 0.5t

Page 23 of 82

9.5 Temporary Supports


9.5.1 Temporary Supports layout
A. Assembly yard plan see attachmentKAIA zone pier assembly yard plan:
B. Setting temporary supporting using by expansion bolt.

Temporary
supporting

20dia expansion bolt


to fix the support
Please ref to attachments appendix B embedded parts layout and appendix C embedded detail.
9.5.2 Ground Hardening Measurement
The floor under the assembly support should take the measurements as follow:

Page 24 of 82

9.5.3 wind rope


Insert the embedded for fix wind rope during concrete pouring.
All temporary support and completed steel structure should be using wind rope as safety
required.
9.6 Detail erection method
9.6.1 Pier Erection Sequence
The Pier Erection sequence is illustrated in the picture below.
Procedure: crane assembly on the ground, crane erection, roof beam, side walk and some
other ancillary facilities
Start from F, G, B, C, with the railed tower crane and move towards Zone D and Zone E.
Eight railed tower cranes are required in total.

Page 25 of 82

9.6.2 Erection Sequence For Double Pier


Step1: Loft & deploy supports

Step 2: Erect the curve column

Step 3: Erect the crane

Step 4: Erect the roof truss

Step 5: Completing the joint

Page 26 of 82

Step 6: Erect the other beams

Step 7: Final Touches

9.6.3 Erection Sequence For Single Pier


Concrete floor calculation see attachment.
Step 1: Loft & deploy supports

Step 3: Erect the crane

Step 2: Erect the curve column

Step 4: Erect the sword and column

Page 27 of 82

Step 5: Erect the Curve part connection

Step 7: Web member assembly

Step 6: Erect the Low span truss

Step 8: Final touches

Step 9: Erection the roof truss

Step 10: Erect other beams

Page 28 of 82

9.6.4 Erection Sequence For International Pier


Step 1: Casting& deploy supports

Step 2: Erect the Dome

Step 3: Erect the High span Truss

Step 4: Erect the web member

Step 5: Erect the sword

Step 6: Erect the Curve part connection

Page 29 of 82

Step 7: Erect Low span Truss assembly

Step 8: Erect the web member

Step 9: Erection the roof truss

Step 10: Erect other beams

Workers are
on the
movable
scaffolding
platforms
to erect the
beams

Page 30 of 82

9.6.4 Assembly on the ground


Double pier assembly
Step 1: Assembly the crane truss

Step 1: support setting assembly

Step 2: Casting assembly

Step 3: Sword and Dome assembly

Step 4: Middle Connection assembly

Page 31 of 82

Step 5: Curve part connection assembly

Step 6: Crane truss assembly

Step 7: Web member assembly

Step 6: Final Touches

Page 32 of 82

Single pier assembly


Step 1: Assembly support setting and truss
Step 2: Assembly casting

Step 3: Dome assembly

Step 4: High span Truss assembly

Step 6: A-frame and web member

Step 6: Half crane finish

Page 33 of 82

10 Erection Method for Terminal Processor


10.1 Shipping units
The structural elements of terminal processor building shall be transported as detailed below,
considering transportation size condition, connection type, appearance, etc.
10.1.1 South facade
Length of element is 12m.
Detail division method is as follow: lower segment 11.5m, middle segment 12m~16m, upper
segment 5~13m. The lower segment and the middle segment is naturally separate. Drawing
below is its detail method.

Upper segment

Middle segment

Upper and middle segment division


10.1.2 Tree and tripod
Shipping of Tree and tripod is classified to two kinds. Red one is erected by two pieces and
black one is erected by one piece.

(Red) ones are divided into two units, (Black) ones are shipped as one unit
Type one: (>17.8m)
T1T2T5T6 and tripod (total 38 pieces) is divided to two segments to transport, T6
(16.8m) is divided for weight as it cannot be lifted up by fixed tower crane.

Page 34 of 82

Type 2: (17.8m) T3,T4,T7,T8,T9,T10,T11 (total 56 pieces) shipped as one unit.

10.1.3 North column shipped as one unit

10.1.4 Shed frame shipped in bulk.


10.2 Erection Weight and Selection of Cranes
10.2.1 South Faade and Tripod
The weight of south faade tusk and tripod column is about 23 tonso we consider to
use 500ton crawler crane erect.
analysisloading capacity of 500t crawler crane at boom length 102m and working radius
75m is 47ton > 23 ton+0.4 tonlifting hook and sling

500t crawler crane


Banana truss erect plan see attachment dwg

Page 35 of 82

10.2.2 Lifting of tree columns on slabs

Tree columns of T1, T2, T6 as lifted by tower in two pieces after being shipped to site, other
tree columns should be pre-assembled before lifting. Drawing below is about the location of
tower cranes, each color and circle represents one tower.
(Green)T36, T37 70m Wolf7532.12
(Red)T41 60m Wolf7532.12
(Blue)T40, T 42 70m Wolf7532.12
(Pink)T39, T43 60m Wolf7532.12

Location of tower cranes


Analysis of lift sequence for tree columns (same crane location above drawing)

Page 36 of 82

NO.

T1-1
T1-2
T1-3
T1-4

LIST OF ERECTION UNIT AND CRANE CAPACITY


characters
crane
lifting lgth of
crane
wt*1.2(T crane
radius(m
burden
capactiy
lgth(m) wt(T)
weight(t main
)
number
)
rate(T)
)
boom
(T)
22.3
8.2
9.8
T41
4.9
60
39.0
7.5
65.3%
21.5
7.9
9.4
T41
4.7
60
42.4
6.6
71.5%
21.1
7.7
9.3
T41
4.6
60
52.9
5.1
90.8%
21.9
8.0
9.6
T41
4.8
60
50.4
5.1
94.3%

T2-1

20.0

7.3

8.8

T36

4.4

70

58.3

4.2

104.6%
[95.8%(10
% safty
ratio)]

T2-2
T2-3
T2-4
T3-1
T3-2
T3-3
T3-4
T4-1
T4-2
T4-3
T4-4
T5-1
T5-2
T5-3
T5-4
T6-1
T6-2
T6-3
T6-4
T7-1
T7-2
T7-3
T7-4
T8-1
T8-2
T8-3
T8-4
T9-1
T9-2
T9-3
T9-4
T10-1
T10-2
T10-3
T10-4
T11-1
T11-2
T11-3
T11-4

19.3
18.9
19.3
17.8
17.1
16.8
17.5
15.8
15.1
14.9
15.5
18.9
18.2
17.3
18.0
16.8
16.1
15.4
16.0
15.2
14.5
13.8
14.5
13.0
12.4
12.0
12.4
14.2
13.5
12.6
13.2
12.5
11.9
11.1
11.6
10.9
10.4
9.8
10.2

7.1
6.9
7.1
6.5
6.3
6.1
6.4
5.8
5.5
5.5
5.7
6.9
6.7
6.3
6.6
6.1
5.9
5.6
5.9
5.6
5.3
5.1
5.3
4.8
4.5
4.4
4.5
5.2
4.9
4.6
4.8
4.6
4.4
4.1
4.2
4.0
3.8
3.6
3.7

8.5
8.3
8.5
7.8
7.5
7.4
7.7
6.9
6.6
6.5
6.8
8.3
8.0
7.6
7.9
7.4
7.1
6.8
7.0
6.7
6.4
6.1
6.4
5.7
5.4
5.3
5.4
6.2
5.9
5.5
5.8
5.5
5.2
4.9
5.1
4.8
4.6
4.3
4.5

T36
T36
T36
T36
T36
T36
T36
T36
T36
T36
T36
T42
T42
T42
T42
T42
T42
T42
T42
T36
T36
T36
T36
T36
T36
T36
T36
T43
T43
T43
T43
T43
T43
T43
T43
T35
T35
T35
T35

4.2
4.2
4.2
2.9
2.7
2.7
2.8
2.5
2.4
2.4
2.5
3.0
2.9
2.8
2.9
3.7
3.5
3.4
3.5
2.4
2.3
2.2
2.3
2.1
2.0
1.9
2.0
2.3
2.2
2.0
2.1
6.6
1.9
1.8
1.9
1.8
1.7
1.6
1.6

70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
60
60
60
60
60
60
60
60
60
60
60
60

49.3
53.4
54.5
32.3
27.0
18.5
23.0
27.7
31.0
24.5
20.0
24.0
28.7
30.6
26.2
55.5
61.0
61.8
56.4
39.8
37.3
48.2
39.8
37.3
39.8
47.5
45.6
22.6
25.0
19.5
16.3
52.6
47.0
48.2
53.7
19.7
14.6
17.8
22.2

5.3
4.7
4.7
8.0
9.6
11.8
11.8
9.6
8.0
11.8
11.8
11.8
9.6
8.0
9.6
4.2
3.8
3.8
4.2
6.9
6.9
5.3
6.9
6.9
6.9
5.3
5.3
12.0
12.0
12.0
12.0
5.1
5.8
5.8
5.1
12.0
12.0
12.0
12.0

80.0%
88.3%
90.2%
35.8%
28.6%
22.9%
23.8%
26.5%
30.3%
20.3%
21.1%
25.7%
30.5%
34.8%
30.1%
87.8%
93.0%
89.0%
83.7%
35.4%
33.8%
41.8%
33.8%
30.3%
28.9%
36.4%
37.6%
19.0%
18.1%
16.9%
17.7%
39.4%
33.0%
30.8%
36.6%
14.6%
13.9%
13.1%
13.7%

Page 37 of 82

10.3Temporary support
10.3.1 Temporary support layout

Insert plate during concrete pouring 300*300*16


Temporary support weld to the plate
Please ref to attachments appendix B embedded parts layout and appendix C embedded
details

Tack welding
10.3.2 Head & Bottom Connection

Page 38 of 82

10.3.3 Wind rope


Insert the embedded for fix wind rope during concrete pouring.
All temporary support and completed steel structure should be using wind rope as safety
required.
10.4 Detailed Erection Method for Terminal Processor
10.4.1Erection Sequence

Erection tree column start from center to both side.


Space frame will installed follow the steel structure schedule.
The roof frame will install after space frame completed.
Remove the temporary support when work is completed, space frame and steel structure using
separately.

Page 39 of 82

10.4.2 Erection process


South facade
Step 1: Erect the lower segment of tusk of
south faade

Step 3: Erect transom between tusk for


south facade

Step 2: Erect upper segment of south facade

Step 4: Weld transom

Page 40 of 82

Tree

Shed frame
Shed frame Installation in location after Space frame are installed.
Temporary catwalk will be installed on space frame to help installation of shed frame. See
picture below.
Soffit purlins installation use boom length 26m man lift . 26m man lift 2pcs.

Page 41 of 82

Step 1Erect the first beam and short beam


component

Step 2:

Step 3:

Step 4

Step 5: Erect from axis G0 to axis G11

Step 6: Erect from center to side

Step 7: Erect from axis NS to axis TWTE

Step 8: Erect from axis NS to axis TWTE

Page 42 of 82

Page 43 of 82

11 Erection Method for International Hub


11.1 Shipping Unit
Shipping Units should satisfy the capacity of transportation and easy to assembly. Its better to
being segmented at the different sections:
11.1.1 Arches and Sloped Columns
Arches: Total length is 29m and divided into 2 with 14.5m length36units, 8.5t for each

14.5m

14.5m

Sloped Columns: (9 units5.4t per piece)

25m

11.1.2 Gills Columns


Type 1: 10.6m~14.9m, delivered in one piece50 units, From 2.28 to 6 t

Type 2: 25.9m, deliver in two pieces4 Units, 3 t per piece

11.1.3 Arches Connection


Arches(Sloped Column) Space Connection and Base Connection(9 units,14tper Space
Connection, 2.7 t per Base Connection)
Both of them are delivered as single piece

11.1.4Gills Trusses
Gills trusses are delivered as single pieces, the length of web member is 4~7m. We should
control the chord member in 9~15m as the following illustration:

Page 44 of 82

11.1.5 Perimeter Beam


The perimeter beams are delivered as single units. If the length is shorter than 12.5m we
deliver it as one unit, the others are delivered in two pieces. There are 84 straight pieces and
6 arc pieces in total:

12.5m

11.2 Erection Units


The tower crane type and position are unchangeable, the Erection Units should meet the
followed principle
A. Under the capacity of tower crane
B. Easy to set temporary supporting
C. Easy to transport and raise up
D. Control the single pieces, improve the progress
11.2.1 Arches and Sloped columns
The arches shall be erected as two pieces, the sloped one shall be as one piece.

Page 45 of 82

H: 14.85m

11.2.2 Gills Columns

11.2.3 Connection units as shipping unit


11.2.4 Gills Truss
Gills 1 (8 Erection Units)

Gills 2 (6 Erection Units)

Page 46 of 82

Gills 3 (4 Erection Units)

Gills 4 (3 Erection Units)

Gills 5 (3 Erection Units)

Page 47 of 82

11.2.5 Perimeter Beam

25m

11.3 Erection Weight and Crane Analysis


11.3.1 Tower Crane Layout:

Some units weight is above the Tower Crane capacity. In such cases, we will use 35t mobile
crane to raise them.

Page 48 of 82

11.3.2 Tower Crane and Mobile Crane capacity analysis:

M 35tmobile crane

TW1

TW1

TW14

TW17

TW1
6

TW18

Page 49 of 82

Crane capacity analysis of Sloped Columns and Arches


List of Erection Units & Crane Capacity
No.

PCS

Characters
Light

Weight

Kg/m

Wt*1.2

Crane

Light of
Main
Boom
(m)

Radius
(m)

Crane
Capacity(t)

Burden
Rate

SC1

16.5

5.4

327

6.48

TW15

60

40

7.5

86%

AR1a
AR1b
AR1c
AR1d
SC2
AR2a
AR2b
AR2c
AR2d
SC3
AR3a
AR3b
AR3c
AR3d
SC4
AR4a
AR4b
AR4c
AR4d
SC5
AR5a
AR5b
AR5c
AR5d
SC6
AR6a
AR6b
AR6c
AR6d
SC7
AR7a
AR7b
AR7c
AR7d
SC8
AR8a
AR8b

1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1

14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4
14.4
14.4
16.5
14.4
14.4

8.5
8.5
8.5
8.5
5.4
8.5
8.5
8.5
8.5
5.4
8.5
8.5
8.5
8.5
5.4
8.5
8.5
8.5
8.5
5.4
8.5
8.5
8.5
8.5
5.4
8.5
8.5
8.5
8.5
5.4
5.4
5.4
5.4
5.4
5.4
8.5
8.5

590
590
590
590
327
590
590
590
590
327
590
590
590
590
327
590
590
590
590
327
590
590
590
590
327
590
590
590
590
327
375
375
375
375
327
590
590

10.2
10.2
10.2
10.2
6.48
10.2
10.2
10.2
10.2
6.48
10.2
10.2
10.2
10.2
6.48
10.2
10.2
10.2
10.2
6.48
10.2
10.2
10.2
10.2
6.48
10.2
10.2
10.2
10.2
6.48
6.48
6.48
6.48
6.48
6.48
10.2
10.2

MC
MC
TW15
TW15
TW15
TW15
TW15
TW15
TW15
TW15
TW15
TW15
TW15
MC
MC
MC
MC
MC
MC
TW16
TW16
TW16
TW16
TW16
TW16
TW16
TW16
TW16
TW16
MC
TW16
MC
TW17
TW17
TW17
TW17
TW17

14.4
15.6
60
60
60
60
60
60
60
60
60
60
60
19.5
14.4
19.5
14.4
14.4
19.5
60
60
60
60
60
60
60
60
60
60
14.4
60
14.4
60
60
60
60
60

6
6
30
19.4
20
12
12
11
9
35
17
25
30
6
6
6
6
6
6
19
25
17
12
12
22
13
15
21
27
6
37
6
43
35
16
25
12

17.2
15.6
10.4
12
12
12
12
12
12
8.8
12
12
10.4
15.6
17.2
15.6
17.2
17.2
15.6
12
12
12
12
12
12
12
12
12
11.2
17.2
8.3
17.2
7
8.8
12
12
12

59%
65%
98%
85%
54%
85%
85%
85%
85%
74%
85%
85%
98%
65%
38%
65%
59%
59%
65%
54%
85%
85%
85%
85%
54%
85%
85%
85%
91%
38%
78%
38%
93%
74%
54%
85%
85%

Page 50 of 82

AR8c
AR8d
SC9
AR9a
AR9b
AR9c
AR9d

1
1
1
1
1
1
1

14.4
14.4
16.5
14.4
14.4
14.4
14.4

8.5
8.5
5.4
8.5
8.5
8.5
8.5

590
590
327
590
590
590
590

10.2
10.2
6.48
10.2
10.2
10.2
10.2

TW17
TW17
TW17
TW17
TW17
TW17
TW17

60
60
60
60
60
60
60

10
15
24
16
17
23
30

12
12
12
12
12
12
10.4

85%
85%
54%
85%
85%
85%
98%

Crane capacity analysis of Gills Column


List of Erection Units & Crane Capacity

No.

PCS

Characters

Wt*1.2

Light

Weight

Kg/m

Crane

Light of
Main
Boom(m)

Radius (m)

Crane
Capacity(t)

Burden
Rate

Outcapacity

GC1

10.6

3.15

297

3.78

TW18

70

35

47%

GC2

10.6

2.28

215

2.74

TW17

70

15

11.8

23%

GC3

10.6

3.97

375

4.76

TW17

70

22.5

11.8

40%

GC4

10.6

4.88

460

5.86

TW18

70

15

11.8

50%

GC5

10.6

3.97

375

4.76

TW18

70

30

9.6

50%

GC6

14.9

2.59

174

3.11

TW18

70

10

11.8

26%

GC7

10.6

5.97

563

7.16

TW18

70

12.5

11.8

61%

GC8

10.6

5.97

563

7.16

TW18

70

32.7

8.8

81%

GC9

14.9

2.59

174

3.11

TW18

70

35

39%

GC10

14.9

2.29

154

2.75

TW18

70

57

4.5

61%

GC11W

9.9

2.63

266

3.16

TW14

70

35

39%

GC11E

9.9

2.63

266

3.16

TW13

60

55

5.1

62%

GC12W

9.9

2.63

266

3.16

TW15

60

53

5.8

54%

GC12E

9.9

2.63

266

3.16

MC

22

10

7.9

40%

GC13W

14.9

4.43

297

5.32

MC

22

12.6

42%

GC13E

14.9

4.43

297

5.32

MC

22

12.6

42%

GC14W

9.9

3.71

375

4.45

TW14

70

20

11.8

38%

GC14E

9.9

3.71

375

4.45

TW13

60

35

8.8

51%

GC15W

9.9

3.71

375

4.45

TW14

70

34

9.6

46%

GC15E

9.9

3.71

375

4.45

TW13

60

58

4.8

93%

GC16W

9.9

4.56

461

5.47

TW14

70

10

11.8

46%

GC16E

9.9

4.56

461

5.47

TW13

60

20

12

46%

GC17W

9.9

5.57

563

6.68

TW14

70

17

11.8

57%

GC17E

9.9

5.57

563

6.68

TW13

60

32

9.6

70%

GC18W

9.9

4.56

461

5.47

TW14

70

33

8.8

62%

GC18E

9.9

4.56

461

5.47

TW13

60

21

12

46%

GC19W

9.9

5.57

563

6.68

TW14

70

32

8.8

76%

GC19E

9.9

5.57

563

6.68

TW13

60

27

11.2

60%

GC20W

25.9

6.08

235

7.3

MC

30.4

81%

GC20E

25.9

6.08

235

7.3

MC

30.4

81%

Page 51 of 82

11.3.3 Gills Trusses

Page 52 of 82

Crane capacity analysis of Gills Trusses:


List of Erection Units & Crane Capacity
No.

PCS

SG1a

Characters

Wt*1.2

Crane

Light of Main
Boom(m)

Radius
(m)

Crane
Capacity(t)

Burden
Rate

846

11.58

TW17

60

20

12

97%

8.51

1064

10.21

TW17

60

14

12

85%

Light

Weight

Kg/m

11.4

9.65

SG1b

SG1c

16.4

8.68

529

10.42

TW17

60

17

12

87%

SG1d

16.3

8.83

542

10.6

TW17

60

29

10.7

99%

SG1e

16.3

6.89

423

8.27

MC

24.7

12.6

66%

SG1f

16.4

8.68

529

10.42

MC

24.7

12.6

83%

SG1g

8.51

1064

10.21

MC

24.7

12.6

81%

SG1h

11.4

9.65

846

11.58

MC

24.7

12.6

92%

SG2a

9.2

761

8.4

TW17

60

24

12

70%

SG2b

12.5

4.58

366

5.5

TW17

60

31

10.1

54%

SG2c

16.9

8.54

505

10.25

TW18

70

22

11.8

87%

SG2d

16.9

6.38

378

7.66

TW18

70

35

96%

SG2e

12.5

4.58

366

5.5

TW18

70

48

5.6

98%

SG2f

9.2

761

8.4

MC

24.7

10.2

82%

SG3a

12.5

7.14

571

8.57

TW18

70

32

9.2

93%

SG3b

15.2

6.85

451

8.22

TW18

70

2.6

11.8

70%

SG3c

15.2

4.76

313

5.71

TW18

70

18

11.8

48%

SG3d

12.5

7.14

571

8.57

TW18

70

32

9.2

93%

SG4a

9.4

6.83

727

8.2

TW18

70

16

11.8

69%

SG4b

13.9

4.9

353

5.88

TW18

70

13

11.8

50%

SG4c

9.4

6.83

727

8.2

TW18

70

16

11.8

69%

SG5a

7.7

3.7

481

4.44

TW18

70

30

9.6

46%

SG5b

8.2

4.86

593

5.83

TW18

70

34

8.3

70%

SG5a

7.7

3.7

481

4.44

TW18

70

30

9.6

46%

NWG1a

11.4

9.8

860

11.76

MC

24.7

12.6

93%

NWG1b

875

8.4

TW15

60

26

11.7

72%

NWG1c

16.4

8.78

535

10.54

TW15

60

25

12

88%

NWG1d

16.3

8.83

542

10.6

TW15

60

26.7

11.5

92%

NWG1e

16.3

6.66

409

7.99

TW15

60

35

8.8

91%

NWG1f

16.4

8.78

535

10.54

MC

24.7

12.6

84%

NWG1g

875

8.4

MC

24.7

12.6

67%

NWG1h

11.4

9.8

860

11.76

MC

24.7

12.6

93%

NWG2a

9.1

6.66

732

7.99

TW14

60

34

9.1

88%

NWG2b

15.8

4.29

272

5.15

TW15

60

40

7.5

69%

NWG2c

13.7

5.97

436

7.16

TW14

70

36

7.8

92%

NWG2d

13.7

4.5

328

5.4

TW14

70

34

8.3

65%

NWG2e

15.8

6.66

422

7.992

MC

24.7

10.2

78%

NWG2f

9.1

4.29

471

5.15

MC

24.7

10

7.9

65%

NWG3a

7.14

6.3

882

7.56

TW14

70

35

95%

NWG3b

6.6

943

7.92

TW14

70

17

11.8

67%

NWG3c

4.57

5.67

1241

6.8

TW14

70

17

11.8

58%

Page 53 of 82

NWG3d

7.14

6.3

882

7.56

TW14

70

29

10

76%

NWG4a

10.3

6.45

626

7.74

MC

24.7

10

7.9

98%

NWG4b

16.4

305

TW14

70

14

11.8

51%

NWG4c

10.3

6.45

626

7.74

TW14

70

37

7.6

102%

NWG5a

7.7

4.3

558

5.16

TW14

70

30

9.6

54%

NWG5b

8.2

4.9

598

5.88

TW14

70

33

8.6

68%

NWG5c

7.7

4.3

558

5.16

TW14

70

30

9.6

54%

NEG1a

11.4

9.8

860

11.76

TW16

60

20

12

98%

NEG1b

875

8.4

TW16

60

15

12

70%

NEG1c

16.4

8.78

535

10.54

TW16

60

20

12

88%

NEG1d

16.3

8.83

542

10.6

TW16

60

27

11.5

92%

NEG1e

16.3

6.66

409

7.99

MC

24.7

12.6

63%

NEG1f

16.4

8.78

535

10.54

MC

24.7

12.6

84%

NEG1g

875

8.4

MC

24.7

12.6

67%

NEG1h

11.4

9.8

860

11.76

MC

24.7

12.6

93%

NEG2a

9.1

6.66

732

7.99

TW16

60

25

12

67%

NEG2b

15.8

4.29

272

5.15

TW16

60

33

9.6

54%

NEG2c

13.7

5.97

436

7.16

TW16

60

35

8.8

81%

NEG2d

13.7

4.5

328

5.4

MC

24.7

10

7.9

68%

NEG2e

15.8

6.66

422

7.99

MC

24.7

10.2

78%

NEG2f

9.1

4.29

471

5.15

MC

24.7

10

7.9

65%

NEG3a

7.14

6.3

882

7.56

MC

24.7

10

7.9

96%

NEG3b

6.3

900

7.56

TW13

60

35

8.8

86%

NEG3c

4.57

5.67

1241

6.8

TW13

60

42

7.1

96%

NEG3d

7.14

6.3

882

7.56

MC

24.7

10

7.9

96%

NEG4a

10.3

6.45

626

7.74

TW13

60

19

12

65%

NEG4b

16.4

305

TW13

60

22

12

50%

NEG4c

10.3

6.45

626

7.74

TW13

60

35

8.8

88%

NEG5a

7.7

4.3

558

5.16

TW13

60

15

12

43%

NEG5b

8.2

4.9

598

5.88

TW13

60

23

12

49%

NEG5c

7.7

4.3

558

5.16

TW13

60

27

11.5

45%

11.3.4 Perimeter

Page 54 of 82

Crane capacity analysis of Perimeter


List of Erection Units & Crane Capacity
No.

PCS

S1

Characters

Wt*1.2

Crane

Light of Main Radius


Boom(m)
(m)

Crane
Capacity(t)

Burden
Rate

OutCapacity

Light

Weight

Kg/m

8.7

1088 10.44

MC

19.5

18.4

57%

S2

8.7

1088 10.44

MC

19.5

18.4

57%

S3

16.5

11.4

691

13.68

MC

19.5

18.4

74%

S4

13

3.9

300

4.68

TW18

70

47

5.6

84%

S5

10

5.36

536

6.43

TW18

70

37

7.5

86%

S6

25.3

9.1

360

10.92

TW18

70

25

11.8

93%

S7

33

5.9

179

7.08

TW18

70

25

11.8

60%

S8

36

2.24

62

2.69

TW18

70

45

45%

S9

40

2.47

62

2.96

TW18

70

50

5.3

56%

NM1

8.7

1088 10.44

MC

19.5

18.4

57%

NM2

8.7

1088 10.44

MC

19.5

18.4

57%

NM3

16.5

11.4

691

13.68

MC

19.5

18.4

74%

NM4

13

3.9

300

4.68

TW14

70

47

5.7

82%

NM5

10

5.36

536

6.43

TW14

70

40

6.9

93%

NM6

25.3

9.1

360

10.92

TW14

70

25

11.8

93%

NM7

33

5.9

179

7.08

TW14

70

27

10.7

66%

NM8

36

2.24

62

2.69

TW14

70

41

6.7

40%

NM9

40

2.47

62

2.96

TW14

70

45

49%

Page 55 of 82

NE1

8.7

1088 10.44

MC

19.5

18.4

57%

NE2

8.7

1088 10.44

MC

19.5

18.4

57%

NE3

16.5

11.4

691

13.68

MC

19.5

18.4

74%

NE4

13

3.9

300

4.68

35

8.8

53%

NE5

10

5.36

536

6.43

45

6.6

97%

NE6

25.3

9.1

360

10.92

MC

19.5

18.4

59%

NE7

33

5.9

179

7.08

TW13

60

30

10.4

68%

NE8

36

2.24

62

2.69

TW13

60

25

12

22%

NE9

40

2.47

62

2.96

TW13

60

38

7.2

41%

TW16/M
60
C
TW16/M
60
C

(Red) stands for 35t mobile crane in the illustration. It means that the unit are lifted by mobile
crane. The other colors stand for different tower cranes in the illustration and forms. As shown
in the form, there are 264 units (including 57 single pieces in Gills Trusses). Mobile crane
erects 68 of them. A tower crane erects 74.2% of the unit which makes full use of tower crane.

11.4 Temporary supporting


11.4.1 The temporary supporting layout
Arches and Sloped Columns are inclined and they need temporary supports to resist the
horizontal forces. Arches are divided into two pieces as shipping unit and Gills Trusses are
divided into many units as the erection units shown before. The break position needs
temporary support to resist self weight and horizontal force. Based on the erection units.
11.4.2 Temporary Supporting
Insert plate during concrete pouring
Temporary support welding to the plate
Please ref to attachments appendix B embedded parts layout and appendix C embedded
details

Page 56 of 82

11.4.3 Head & Bottom Connection

11.4.4 Wind rope


Insert the embedded for fix wind rope during concrete pouring.
All temporary support and completed steel structure should be using wind rope as safety
required.
11.5 Detailed Erection Method for International Hub
11.5.1 General
International Hub is erected from inside to outside. While erecting the inner part, the
outside place can be used for assembly. The Gills Trusses is erected from middle to
side outwards. The single part is erected after both side units have been erected and
fixed. The man lift is used to reach and weld the single piece into position.
The space frame install will follow the steel structure erection schedule.
Using temporary support is separately and removed when work is completed.
The erection sequence show as following:

Page 57 of 82

11.5.2 Erection of Lens


Step 1: Position Fix and Base Connection erection

Step 2: Temporary support fixing

Page 58 of 82

Step 3: Lens arches erection

Step 4: Space Connection erection

Page 59 of 82

11.5.3 Erection of Gills column


Gill Columns are upright which can be fixed on the floor without temporary supporting directly.
But every steel column needs four cables to improve the stability.

11.5.4 Gills trusses erection


Step 1: Loft & deploy supports

Step 2: Erect the middle unit

Step 3: Erect the other middle unit

Step 4: Adding the single units

Page 60 of 82

Step 5: Erect from middle to side

Step 6: The second Gills Trusses erection

Step 7: Erect piermeter beam

Step 8: Permeter beam butt joint

Step 9: From inside to outside

Step10: Final touches

Page 61 of 82

11.5.5 Gills trusses assembly


Step 1: Chord fixing

Step 2: Adding the web member

12 Erection Method for Boarding Bridge


12.1 General Dimension
Boarding Bridge: 46 PCS
Weight: 46 ton for each
Size: H*B*L=3275mmx5000mmx37000mm
Height: 6m~10m
Section: UB for chords, Box for webs

Page 62 of 82

level
10m
Width: 5000

Height: 3275

level6m

12.2 Transportation Units


The transportation method of boarding bridge shall be as side truss, other members in bulk.

Page 63 of 82

12.3 Erection Units


The erection weight of bridge shall be less than 23ton.

12.4 Crane Selection


Apply: 150 t mobile crane, 25.2m (boom)@11m, 35 ton >23 ton + 0.4 ton (hook)

Page 64 of 82

150t mobile crane


12.5 Erection Method
Step 1: Assemble on ground

Step 2: Erect the first unit

Step 3: Erect the second unit

Page 65 of 82

Step 5: Adding the single piece on the manlift

13 survey schemes

The structure of this project is complicated, with large construction and so much bolt connection
joints. And high accuracy requirement make survey work of KAIA PTB Steel structure work
very difficult. Installation accuracy control is an important and difficult work on site. So we
need to solve many problems in survey work.
13.1 Analysis of difficulties

(1) Survey process is more; high elevation locating is difficult.


According to the construction scheme we should first assemble most of components on the
ground, then hoist them integrally. In construction process the survey work and process
would be increased, so that the accuracy control became very difficult.
(2) The weather is bad; the view condition is very poor.
In Jeddah, the weather is very hot and the sunshine is too strong. BetweenAM9:00
toPM4:00 the air temperature is above 40,the air current is very uneven and the target is
too fuzzy. We cant view the aim directly by the Total station, because the construction area
is too large with a cover of about 1312m941m, None of the tall building to be used as the
survey location, this cause the aims and control points can't be view directly one another.
Lots of extra work has to be done to grantee the survey accuracy.
(3) To control the accurate of curve members is difficult.
In structure system the sword in Piers and the gill truss in Hub are belongs to the curved
tubes. Controlling the curve is a technical difficulty. As the gill truss had lots of joints
connect with it, the components cant be installed successfully if the installation dimensions

Page 66 of 82

exist any mistake.


(4) To control the welding deformation is difficult.
There are great deals of welding works in this project; control of the welding deformation is
an arduous work. The deviation of deformation dimension will impaired the dimension
accuracy directly. So we should control the deviation of deformation dimension both in
assembly and installation process. How to solve these difficulties, and ensure the project
quality are two vital points the survey work must take into consideration.
13.2 Survey idea and control method

We adopt the survey principle that first whole then part, use high accuracy control point
and instrument to make sure small allowance to measure these survey work difficulties in
this project. First we should measure and lay the First class survey control network
according to the control points provided by special surveying Institute, then measure the
local placement, that is to say first the whole engineering were controlled by the high
accurate measurement and advanced technology, then every parts and local were controlled .
In whole measurement work, we should keep to the principle that is "to control installation
accuracy from entirety to part, fabrication precision is small than installation accuracy and
eliminate the error in the every survey process, ensure the installation precision to meet the
standard. In measurement process the coordinate system should be set up and adjust
according to the design and position principle. All measurement data is based on the design
drawing and sections. Site positioning drawing as below:

In observation time, we adopt the method of direction observation in round to measure;


we usually using 2 direction observations to measure them. To the place of high precision,
we adopt the method of more direction observations to raise the accuracy, the same Total
station, survey station and the measurement data are used as the calculate basis, and then
the adjustment program is used for ensuring the precision. We main adopt the method of
measuring the truss open-location and terminal point to control the whole dimension during
the course of assembly and installation. To strictly control the error of every measurement,
to prevent the error is accumulating reached the maximum value.
13.3 Accuracy control of anchor bolts

To position the anchor bolts, the axis and elevation should be setting-out on reinforcing
steel or template by the Total station, and then adopt the method of supporting-wire and
bracing wire to position them. The leveling would be used for measure the elevation of
anchor bolts; first the leveling points must be measured and marked on the template or
reinforcing steel from the nearest elevation control point as the leveling basis. The Total
station was used for checking the top of anchor bolts location when the anchor bolts were
installed. Finally, all measurement data should be controlled within allowable deviation.

Page 67 of 82

The tolerances see AISC 303-5 section7.The location of measurement points as below:

Setting-out the
axis and elevation

Position
Measurement
point
After concrete placement,
location of every bolt should
be check by the Total station

13.4 Accuracy control of Zone A Banana trusses

Banana trusses are cut into pieces in shop, and assemble on site at the assembly yard, and
then lift up integrally. In construction process, we should consider how to control the
assembly accuracy on the ground firstly. We adopt the method of mould bed to control the
assembly accuracy that is according 1:1 scale to stake out the axis and control line on
assembly yard, and make the control lines, joints and position line. The leveling is used for
measuring the elevation of adjustable plate.
The leveling was used for
measure the elevation of
corresponding location

To control the accuracy of assembly dimension, we mainly adopt the method of supporting
wire to do it, just ensure the whole dimension and every joints relative position, the diagram
as below:

Page 68 of 82

We main adopt the


method of supporting
wire to control it

Lastly, the Total station is used for checking the whole dimension and relative position
of every joint. The accurate must be controlled within allowable deviation. The detail
tolerances see AISC 303-5 section7.
13.5 Installation position for banana truss

To position the banana truss, we usually adopt the method of measure the 3D coordinate to
control them that are tube center or forth point of open-location.
Just to ensure the measurement points in consistent with work points in design drawing. The
measure diagram as below:

Measure point)

Measure point (the fourth


point of pipe openl ti )

Measuring points
not less than 2)

In installation process, the measure data must be satisfied with allowable deviation,
every point should be controlled within tolerance value. We need stake-out the line and
elevation on the temporary support before lifting, then wending the limiting plate. The
components need to connect the ropes when lifting, and alignment the axis on the
temporary supports. After that, we use the wind ropes and hydraulic jack to correct the axis
and elevation reached to the allowable deviation. At last, we use the Total station to check
the coordinated of control points, if all dates are OK, fix the rope and limiting plate. The
detail tolerances see the AISC303-5 section7.
13.6 Positioning accuracy of PIER

Pier can be divided into 3 types: double pier, Single pier and International pier.
Most of components adopt the bolts connection; to install Pier we should assemble truss,
and then hoisting them integrally. So the assembly accuracy must be controlled. During
the course of installation, the steel standard and code should be execute and check whole
dimension before welding the truss. The truss must be corrected when we found the

Page 69 of 82

dimension accuracy overstep the allowable deviation.


The principle and base of survey position
To control the Crane accuracy is the key of Pier accuracy control, the accuracy of assembly
and installation control were base on 3D model and situation plan. The critical is to control
the key joint and location. The model position drawing as below:

During the course of installation, the open location and terminal location should be controlled.
The Total station is used for measure the 3D coordinates of truss open-location; all
measurement value is base on design value.

Page 70 of 82

1Temporary supports
To design the temporary supports first the assembly yard should be considered, whether
the temporary support can satisfy the geometry linear and concrete height of truss.
(Assembly yard must be hardening before installing temporary support) the diagram as
below:

The allowable deviation table of temporary support (mm)


Item
Allowable deviation
Check method
axis
elevation

3
(0, +10)

Using the steel ruler


Using the Total station

2Positioning the casting


The axis and control lines should be staked-out on the assembly yard by the Total station,
and the casting base plate should be positioned before assembling the Crane. To position
the casting we usually measuring the pipe orifice centre or fourth points by the Total
station. The rope and hydraulic jack were used for moving the casting to control the
Tolerance.The diagram as below:

Page 71 of 82

Survey point

Survey point
(the pipe center
or fourth point)

During the course of assembly, we need considered the wending shrinkage and settlement. So
we usually let the position value more than or less than design value 5mm.Lastly, the
dimension accuracy can reached the allowable deviation.The requirement and accuracy see
the AISC303-5 section7.

3Positioning accuracy of the curved pipe


To position curved pipe, we adopt the method of combined of supporting wire and plane
right angle coordinates to accurate position, first one point should be moved as the survey
station from the nearest place, and then the Total station is set up on this point and we
adopt the method of measuring the curved pipe center or fourth point 3d coordinate to
accurate position. All survey points must be controlled less than tolerance. The detail
allowable deviations see the AISC303-5 section7.The diagram as below:

(4) Assembling main truss of double pier on the ground


Main truss is first assembled on the ground, and then lift up integrally. To control the
dimension accuracy we should set up a new coordinate system according the truss
dimension and linear, and then staking-out the axis, elevation and contour lines. During the

Page 72 of 82

course of assembly, the dimension accuracy should be controlled by the method of


supporting wire and measuring steel ruler. The whole dimension and every key joint
position must be checked when truss assembly finished by the Total station.
Measurement
Measurement
point
point
Measureme
nt point

Measureme
nt point

The allowable deviation see the AISC 303-5 section7 7.13.

(5) Assembly accuracy control of double pier


To position the main truss, we adopt the method of measuring the Flange plate center point of
H section steel 3D coordinates to accurate position by the Total station. First the main truss
were controlled within the 20mm, and then fixed the rope and wending the limited plate on
the support. After control the accuracy within the allowable deviation. We can use the ropes
to correct the error. The survey control points diagram as below:
Measurement
point

Measure point
(The center
i t)

Measure point
(The center point
of H section)

During the course of survey, the coordinates should be translated in the light of actual
conditions.

(6) To control the whole dimension of double pier


The whole dimension and key location of double pier must be checked; all error was strictly
observed according the standard and code of steel structure. The measuring diagram as
below:

Page 73 of 82

Measurement point (The flange


plate center point of H section)

Measurement point
Survey
point
(center
point)
Measurement point
(roof hanger)

To measure the
key location

All control accuracy seeing the Code of Standard Practice for Steel Building and Bridge
(AISC303-5)
Assembly surveying for Single pier

(1) Temporary supports


Survey method of temporary supports layout and installation the same to double pier. The
diagram as below:

2Single pier assembly surveying process and method


Step1: To position the casting

Page 74 of 82

measurement point1pipe
center or fourth point

measurement point2
pipe center or fourth
point

Step2: Assembly positioning for curved pipes

Step3: Assembly positioning for section 1

Survey point A
(Flange plate center
of Cantilever beam

Step4: To position the joint

Page 75 of 82

measurement
pointpipe
center or fourth
point

Control

Step5: Assembly positioning for section 2


To couple

Flange plate
center of cantilever
Step6: To install the joints

Step8: To check the whole dimension

Page 76 of 82

To loft the location of web


member before installing

The key location must be


checked

The whole dimension must be checked and measured when all components have finished, the
detail requirement and allowable deviation see AISC303-5 section7 Erection. The unqualified
location must be corrected again. We can weld them when the error of every survey location
should be controlled within allowable deviation.
Installation surveying for Pier.
measure point
cantilever beam of
truss

Measure point (open


Location)

Survey point cantilever


beam of truss

Page 77 of 82

Installation
finished
Installing for second

13.7 Assembly and installation surveying for boarding bridge


Totally 46 boarding bridge will be installed on site. The members are mainly H section and Box section.
Connection will be bolted on site and requires high erection accuracy.

The assembly
di

For boarding bridge, we adopt the method of assemble them in sections to install them
lying on the ground. To control the assembly accuracy we adopt projection method to do it,
in other words, the axis and contour lines of boarding bridge should be lofted on the
ground, according to the design drawing and model, and then adopt the method of
supporting wire to accurate position.
To install the boarding bridge, the axis and elevation of boarding bridge should be lofted
on the temporary support before hoisting; lastly, the every dimension and key joints
coordinate must be checked by Total station.

Quality accuracy assurance measure for truss


(1) To strict execute the request of assembly technology, and ensured the accuracy of
assembly dimension
Many components would be pre-assembling in the factory; the problem should be found
and solved before leaving the factory that is maybe happening in site. That ensured the
dimension accuracy, section, beveled edges, and making the clearly mark on components.
The assembly quality and progress can be raised by this method. So the key measures of
ensured quality accuracy are adopting the method of Pre-assembly in factory.
(2) To ensure the assembly accuracy of support on site, and ensured the assembly quality
Temporary supports quality will impaired the component of assembly quality, to design the
temporary support we must strict according the technology to do it. The temporary support
must have the enough strength, and cant be rock clearly. The temporary support must have
the web member connection. We should check the position dimension and elevation, to
ensure the temporary support accuracy.
(3)Reinforce the quality management
During the course of assembly, the quality scout and check should be executed strictly; the
disqualification components cant be passed the next process to construct. Insist on
prevention first, wall up the quality accident be happened. Define the inspection item,

Page 78 of 82

inspection standard and method, to demure keep record, date condition and operation staff
etc. The disqualification components should be mark and correct timely.

Construction monitoring
Deformation survey
To monitor the deformation, we adopt the polar coordinates method to do them in this
engineering, to measure the settlement observation we according the observation request
and point to do it. The observation point must be installing securely and be using long time.
When the steel roof have finished, we must set the observation point, the observation cycle
is two months, and the detail plan according the actual conditions to do it. We must call the
project department if found have the big displace.

Uninstall survey
The reflector plates must be stick on the cantilever beam and bottom chord location when the
steel roof structure have finished. During the process of uninstall, all points should be
measured by total station. The construction department must be stopped when we found the
measure data have a big displace of truss and till make a solving scheme. All support points
have uninstalled, we should continue to observation the key points 2 weeks till the data
became stability, and then collecting the survey data.
14 Logistic Plan
14.1 Storage Yard
The storage yard must be as close as possible to the site, and it should be as small as
possible in accordance with the peak necessity. The peak is expected in July and August as
marked in the following table:
The area of the storage yard is 610*86*2=52460 which contains 2 assembly area and 1
check point before unloading, so the remaining area is about 280*86*2=48160. Deducting
the road area ,the pure area is about 31360(>23234 )

14.2 Master Schedule


The total schedule is planned for 16 months, starting from the project commencing date to the
completion of steel structure.
Before the site erection, it requires 6 months minimum for the following processes:
Detailing drawing, procurement, fabrication, trail assembly, delivery.
1st Aug 2012 is assumed as start date and a total of 10months for site installation.

14.3 Manpower Plan

The maximum manpower required is 292 and the welders shall be 60.

Page 79 of 82

14.4 Equipment Plan

Page 80 of 82

14.5Water and Electricity

Page 81 of 82

15 Health and Safety


Site HSE manager will be response to the site safety issues and as a key manager to this
project.
The workers will be made aware of the safety requirements related to this activity through
daily toolbox meeting and safety talk.
Every effort shall be made to assure that employees can accomplish their assigned scope
of work safely.
Carry out provision of the warning sign and isolation requirements on site
Splice joints will be supported by temporary supports and the work platform will also be set.
The movable scaffolding will be the majority facilities for moving.
For the workers, overall equipment will be supplied such as hammer, work suit, safety
harness, safety glass, etc. to guarantee the safety of workers.
Scaffold inspector and erector certifications submit prior start the job.
Fully comply with approved SBGs safety plan. Ref#421-422-DCS-PLN-G-00027-04
16 Attachment:

Risk assessment

Page 82 of 82

Appendix A

RISK ASSESSMENT

Risk Assessment Sheet


FACILITY

421-F100

RISK ASSESSMENT NO:

Pages: 16

Steel structure Installation-001


ACTIVITY

Top coating at site

ASSESSMENT DATE: 7 Nov 2012

ASSESSMENT TEAM:

REVIEW DATE: 7 Nov 2012

JGS

GEOFFREY

RSS

JAYAKUMAR

ASSESSMENT APPROVAL:
Reduced

Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

Inadequate
knowledge of
Project
Requirement
s

Form

Personal injury
Injury to others
Ignorant to site
regulations

Issue 01

20

Attend NDIA Safety Induction for New


Employees
Attend SGW Safety Induction for New
Employees
A qualified person should be
assigned the responsibilities to
ensure all personnel comply with
ES&H Requirements include hygiene
and health sanitation in safety
induction
All areas shall be kept free of
nuisance & safety hazards

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

Moving traffic
in and out of
the lay down
area North
West

Form

Wear proper high visibility vest


Use adequate PPE
Provide shed / covering
Provide cool drinking water
Provide adequate lighting at work
area
Provide signalman
Provide moving equipment with
flasher lights and audible back up
alarm

Hit by moving
vehicle
Hit by moving
truck
Heat stroke

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

Personnel on
ground

Form

Hit by moving
vehicle
Hit by moving
truck
Heat stroke

Issue 01

20

Wear proper high visibility vest


Use adequate PPE
Provide shed / covering
Provide cool drinking water

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

CRANE TO BE LOCATED ON LEVELLED


SURFACE & OUTRIGGERS TO BE FULLY
EXTENDED & PLACED ON PACKING.
PRE LIFT PLAN TO BE FILLED OUT PRIOR OF
EVERY LIFT
LIFTING AREA TO BE BARRICADED AS TO
AND SIGNED (KEEP OUT)
TRAINED, COMPETENT RIGGER SHALL BE
APPOINTED AND MUST BE AWARE OF THE
LIFTING PROCEDURE

TAGLINES WILL BE USED

LOADS SHALL NOT BE LIFTED/SLEWED OVER


PEOPLE - AREA WILL BE ISOLATED.
LIFTING AREA TO BE BARRICADED AS TO
PROHIBIT UNAUTHORIZED PERSONNEL .
OPERATOR SHALL FOLLOW RIGGER
DIRECTIONS - ORDERS
HOT WORKS

Form

ELECTRICITY

ELECTROCUTION, FIRE

Issue 01

16

HOT WORK PERMIT SHOULD BE OBTAINED


PRIOR TO WORK.

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

WELDING UNIT SHOULD BE WELL


MAINTAINED & SHOULD BE CHECKED BY
COMPETENT PERSON BEFORE USING.
COMPETENT & EXPERIENCED OPERATORS
SHOULD HANDLE IT.
THE AREA SHALL BE CLEARED OF ANY
COMBUSTIBLE AND FLAMMABLE MATERIALS
PRIOR TO HOT WORKS COMMENCING. GOOD HOUSEKEEPING
A FIRE EXTINGUISHER OF A SUITABLE TYPE
SHALL BE LOCATED NEARBY.
A FIRE WATCH SHALL BE IN ATTENDANCE AT
THE LOCATION DURING HOT WORK ACTIVITY
AND ALSO 1 HR AFTER THE WORK.
ALL WASTE ELECTRODES SHALL BE
COLLECTED FROM THE FLOOR IN AREAS
WERE WELDING IS TAKING PLACE AND SHALL
BE STORED IN A SUITABLE METAL
CONTAINER.
DCP FIRE EXTINGUISHERS & FIRE BLANKETS
SHOULD BE AVAILABLE ON SITE

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

APPROPRIATE PPE

SHOULD BE WORN

WHICH INCLUDE WELDING HOOD, WELDERS


GLOVES ,COTTON COVERALLS ETC
BEFORE HANDING OUT TOOLS, VISUAL
INSPECTION WILL BE CARRIED OUT, BY
COMPETENT PERSON.
HEARING PROTECTION SHALL BE USED IF
EXPOSED TO NOISE LEVELS OF 85 DB(A) OR
ABOVE
COMPETENT OPERATORS SHALL HANDLE
HAND TOOLS/
POWER TOOL

THE TOOLS & COMPETENT SUPERVISION


HAND TOOLS AND

INJURY TO PERSONNEL, ,

POWER TOOLS

DAMAGE TO MATERIAL.

OPERATION

WILL BE ENSURED.

YES

YES

ALL TOOLS USED WILL BE WELL MAINTAINED


AND DEFECT FREE.
ELECTRICALLY OPERATED TOOLS SHALL
COMPLY WITH OBI / ADCC
REQUIREMENTS-DOUBLE INSULATED /
COLOUR CODED / PROPERLY GROUNDED
APPROPRIATE PPE

GENERAL SITE

SLIPS TRIPS FALLS

CONDITIONS

Form

Issue 01

GOOD HOUSEKEEPING, STARRT TALK FOR


TEAM.

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

USE OF APPROPRIATE PPE ALL TIMES.


WORK ACCESS AREA SHALL BE MAINTAINED
IN A SAFE CONDITION, FREE OF DEBRIS &
MATERIAL THAT WILL POSE A HAZARD.
MATERIALS SHALL BE STORED PROPERLY
ADEQUATE LIGHTING SHALL BE MAINTAINED
AT WORK / ACCESS AREAS WHILE WORKING
AT NIGHT
BARRICADE THE AREA & PLACE WARNING
SIGNS
GRINDING WHEEL MUST BE DRESSED
REGULARLY
GRINDING

GRINDER

FLYING PARTICLES , EYE

INJURY, OTHER INJURIES

GRINDER SHOULD HAVE ITS GUARD

YES

YES

SECURED IN PLACE.
FLAME PROOF SCREENS SHOULD BE USED
TO PREVENT SPARKS FALLING ON
PERSONNEL & OBJECTS.
PROPER PPE FACE SHIELD/GOGGLES
SHOULD BE WORN

WELDING

Form

ELECTRICITY =

ELECTROCUTION, FIRE

Issue 01

20

BEFORE WORK STARTS THE MACHINE WILL


BE CHECKED BY COMPETENT PERSON .

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

THESE MACHINES SHOULD BE HANDLED BY


EXPERIENCED OPERATORS ONLY
COMPETENT SUPERVISION WILL BE
ENSURED.

THE MACHINES SHALL BE WELL


MAINTAINED AND COLOUR CODED. ENSURE
PROPER GROUNDING
THE MACHINES SHALL BE DOUBLE
INSULATED AND THEIR CABLES AND PLUGS
SHALL NOT BE MODIFIED OR CHANGED.
THE WELDING AREA SHALL BE WELL
VENTILATED.
STRICT ADHERENCE TO WELDING PPE
WELDING

FUMES

INHALATION OF FUMES

12
TOOL BOX TALKS WOULD BE CARRIED OUT
AND RISK ASSESSMENT TO BE DISCUSSED
APPROPRIATE PPES TO BE USED
MINIMUM PERSON TO BE IMPLEMENTED ON
WORK

Form

Issue 01

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

SCAFFOLDING
(COLLAPSE OF SCAFFOLD,
FALL OF MATERIAL FROM
WORK ON

STRUCTURAL

SCAFFOLDS

COLLAPSE

HEIGHT ETC. FALL OF MEN


FROM HEIGHT, ACCIDENTAL
MOVEMENT OF MOBILE

VEHICLES NOT TO BE ALLOWED TO DRIVE


5

20

NEXT TO THE SCAFFOLD. AREA TO BE


BARRICADED.

TOWER, TUMBLING OF
SCAFFOLD DURING
MOVEMENT)
ERECTION & DISMANTLLING SCAFFOLD TO
BE DONE BY A CERTIFIED AND COMPETENT
SCAFFOLDER

ONLY.

PROPER ACCESS TO WORKING PLATFORM


AND WORKING AREA
POLES, LEGS, OR UPRIGHTS OF SCAFFOLDS
SHALL BE PLUMB & SECURELY & RIGIDLY
BRACED TO PREVENT SWAYING AND
DISPLACEMENT
BASE TO RATIO TO BE ADHIRED TO

Form

Issue 01

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

ACCESS/EGRESS LADDER TO BE PROVIDED


ACCESS AND EGRESS THROUGH SCAFFOLD
SHOULD BE THROUGH THE INNER SIDE OF
MOPBILE SCAFFOLD
AREA UNDERNEATH SHALL BE BARRICADED,
WHILE SIGNS INDICATING THAT "MEN
WORKING OVERHEAD" SHALL BE PLACED
LATERAL SUPPORTS REQUIRED TO SECURE
LATERAL MOVEMENT OF THE SCAFFOLDING
SCAFFOLDS SHOULD BE CHECKED
REGULARLY BY COMPETENT SCAFFOLDER
AND SCAFFTAG

SYSTEM FOLLOWED.

FALL ARRESTERS SHOULD BE USED AND


SHOULD BE FIRMLY ANCHORED.
MOBILE TOWERS SHALL NOT BE MOVED
WITH PEOPLE ON IT.
CASTOR WHEELS WOULD BE LOCKED TO
AVOID ACCIDENTAL MOVEMENT ON MOBILE
SCAFFOLD.

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

GROUND TO BE FREE OF OBSTRUCTION FOR


LATERAL MOVEMENT OF MOBILE SCAFFOLD.
HANDRAILS, MIDRAILS & TOE BOARD TO BE
INSTALLED AND IF DISMANTELLED FOR
ACCESS OR EGRESS TO BE REPLACED
IMMIDIATELY
SAFE METHODS OF MANUAL LIFTING
SHOULD BE BRIEFED BEFORE THE WORK
MANUAL

MANUAL LIFTING /

LIFTING

MATERIAL HANDLING

MINOR INJURY

YES

YES

STARTS THROUGH STARRT TALK.


MANDATORY PPE SHOULD BE WORN ALONG
WITH THICK GLOVES TO PROTECT FROM THE
EDGES OF CORRUGATED SHEET AND NAILS .
MSDS TO BE AVAILABLE ONSITE. SAFE
HANDLING PRACTICES SHOULD BE BRIEFED

CHEMICAL
HANDLING /

PAINT PRIMER
HANDLING / STORAGE

TO HANDLERS
POISONING, IRRITATION , FIRE

STORAGE

12

GOGGLES ,MASK & GLOVES WILL BE USED


ALONG WITH OTHER PPE
EYE

/ HAND WASH FACILITY & FIRST-AID

FACILITY WILL BE PROVIDED ONSITE.

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

PRIMER SHOULD BE STORED IN


MANUFACTURER

SUPPLIED CONTAINER

ONLY IN WELL VENTILATED AREA AWAY


POISONING, IRRITATION , FIRE

FROM ANY SOURCE OF IGNITION

YES

YES

YES

DRY CHEMICAL / CO 2 / ALCOHOL RESISTANT


FOAM EXTINGUISHERS SHOULD BE
AVAILABLE ONSITE.
WASTE CONTAINERS
ENVIRONMENT

OF

WASTE CONTAINERS SHALL BE COLLECTED


ENVIRONMENT

PAINTS / THINNER

SEPARATELY AND PROPERLY DISPOSED OFF


BY LICENSED AGENT.
DAILY INSPECTION OF EQUIPMENT FOR
LEAKS
PLANT & EQUIPMENT WILL BE CHECKED &
MAINTAINED IN A SAFE CONDITION
MAINTENANCE PERFORMED BY COMPETENT

FLUID SPILLS
OIL SPILLS

FROM VEHICLES &

PERSONS
ENVIRONMENT

EQUIPMENT

DRIP PANS AND SHEETS USED DURING


SERVICE
SPILL

KIT WILL BE AVAILABLE ONSITE IN

ADDITION TO MOP UP ANY ACCIDENTAL


SPILLS TO GROUND
SPILLS TO BE REPORTED IMMEDIATELY

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

DIP TRAYS TO BE PROVIDED AS TO HANDLE


ANTICIPATED SPILLAGE OR CONTAINMENT
REQUIREMENTS
IMPERVIOUS MATERIAL UNDER FUEL TANKS
PERSONNEL AND OR CHERRY
WORKING ON

CHERRY PICKER

MEWPS

("BASKET CRANE'') -

TRAINED, COMPETENT OPERATOR AND

PICKER STRUCK BY VEHICLE


OR THE EXTENDED BOOM,
MATERIALS AND PERSONNEL
FALL FROM HEIGHT

12

RIGGER (FOR HELPING OPERATOR WITH


BLIND SPOTS) TO CONTROL HIM SHALL BE
APPOINTED
LIFTING AREA TO BE BARRICADED AS TO
AND SIGNED (KEEP OUT AND LIFTING IN
PROGRESS)
SAFETY OFFICER IN SITE TO ENSURE DAILY
INSPECTION OF EQUIPMENT, PERIODIC
MAINTENANCE AS REQUIRED
SAFETY HARNESS/FALL ARRESTORS

TO BE

USED BY PERSONNEL ON AERIAL PLATFORM


(BASKET)

Form

Issue 01

Date: 7 Nov 2012

Author REN

YES

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

OPERATOR TO FOLLOW THE EQUIPMENT


LIFTING CHART RESTRICTIONS, MAX. BOOM
RADIUS, PERSONNEL NUMBER AND WEIGHT
TO BE LIMITED ON BASKET ACCORDING TO
EQUIPMENT SPEC. - LIFTING PLAN TO BE
AVAILABLE PRIOR USE
LIFTING AREA TO BE BARRICADED AS TO
PROHIBIT UNAUTHORIZED PERSONNEL .
CHERRY PICKER TO BE LOCATED ON
LEVELLED SURFACE & OUTRIGGERS TO BE
FULLY EXTENDED & PLACED ON PACKING.
HANDRAILS, MIDRAILS & TOE BOARD ON
BASKET (MINIMUM REQUIREMENT FOR
EQUIPMENT USE)
DAILY INSPECTION TO BE CARRIED OUT BY
COMPETENT MECHANIC/OPERATOR
LIGHTING OF 30LUX AND 3.0 FOOT CANDLE
TO BE PROVIDED
TUNGSTEN HALOGEN LIGHTING TO BE USED
WHEREVER POSSIBLE TO MINIMISE FIRE
HAZARDS CAUSED BY TUNGSTEN LIGHTING

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Reduced
Task

Hazard

Hazard effect(consequence)

Risk

Proposed Control Measures

ALARP
Risk

BULB TO BE PROTECTED FROM BREAKAGE


AND ANY BROKEN OR DEFECTIVE BULBS TO
BE IMMEDIATELY REPLACED
LIGHTING FIXTURES TO BE POSITIONED TO
MINIMISE WORKER CONTACT WITH FIXTURES
DURING WORK OPERATIONS
LIGHTING SUPPLY CORDS AND CABLES TO
BE INSTALLED IN CONSISTENCY WITH GOOD
ELECTRIC WIRING PRACTICES.
ALL POINTS OF ACCESS AND EGRESS SHALL
BE CLEARLY ILLUMINATED AND MARKED
PORTABLE GENERATOR TO BE GROUNDED
AT OVER 3.0M DEPTH, METAL CASE SOCKETS
OF BULBS TO BE GROUNDED

Form

Issue 01

Date: 7 Nov 2012

Author REN

Risk Assessment Sheet

Criteria

( C ) Consequence:

Negligible-

Criteria ( L ) Likelihood:

immediate return to work

Risk Calculator,

Conclusions:

Risk level R= C X L

Overall risk - Low/Medium

Improbable- so unlikely that it would not

Minor -

first aid and return to work.

happen.

Moderate-

medical treatment/ lost time

Unlikely-

remote chance of event

Major-

multiple injuries and

Possible-

inattention may cause an

1-4

Acceptable

Are risks reduced to ALARP (as low as

event to happen.

5-8

Tolerable

reasonably practicable), Yes

Probable-

highly likely without control.

9-10

Moderate

Certain-

will happen without

12-15

Substantial

Intervention / control.

>15

Intolerable

RIDDOR reportable
Fatal/Catastrophic-

Death, loss of

installation

Likelihood
Consequence

Improbable

Unlikely

Possible

Probable

Certain

Negligible

Minor

10

Moderate

12

15

Major

12

16

20

10

15

20

25

Fatal/catastrophic 5
Overall risk.

1-4 =Low; 5-10 = Medium; 12-25=High

Form

Issue 01

Date: 7 Nov 2012

Author REN

AppendixB

Insertfortemporarysupportlayout

AppendixC

Insertfortemporarysupportdetail

Appendix D

INTERFACE TC AND PROCESSOR

ConstructionInterface
Between
TransportationCenter422
and
Processor(PTB)421
7August2012

OBJECTIVE
InstallationofStructuralSteelElements(BananaTrusses)at
theFaadeoftheProcessorofPTBOppositeTransportation
CentreWithoutCompromisingCompletionDatesofEither
Facility.

OutlineConstructionSchedule
ofAffectedFacilities/Element
Aug

Sept

Oct

Nov
XX

Processor
ConcreteLevel2

Dec

Jan13

XXXXX

XXXXX

XXXX

TransportCentreRoof

XXXXX

PedestrianBridges
AutomaticWalkway
BridgesfromMSCP

XXXXX

StructuralSteel(Middle)
XXXXX

XXXXX

XXXXX

Mar
13

Apr13

XXXXX

XXXXX

XXXXX

XXX

Processor
ConcreteLevel3

ViaDuctDecks
Zones2&4

Feb13

XXXXX

XXXXX

ConsideredandDiscardedSchemesfor
InstallationofBananaTrusses

Scheme1:CrawlingalongtheFaade

Scheme2:TwoadditionalHeavydutyTowerCranes
OutsidetheTC

Scheme3:FactoryCuttingofBananaTrussesinto23ton
Segments

Scheme1
Crawler CranealongthePeriphery
150tonCrawlerCraneliftsassembleduppertwopartsof
bananaTrusses(16to23tonapprox)andcrawlwiththem
alongtheperipheryoftheFaadetowheretheywillbe
finallyinstalled.

Problem
PostponingmostactivitiesonCurbsideVD,TCandBridgestill
afterFaadeworks.Notacceptablephasing

CrawlingalongthePeriphery

Scheme2
TwoAdditionalTowerCranes
TwoheavydutytowercranesoneithersideofTCtoinstall
bananatrussesoppositetoit.

Problem
ClashwithTowerCranesinProcessor

Scheme2
OperationalClashDiagram

Scheme3
FactoryCutintoShorterSegments
CuttingTrussesinto23tonsegmentsatfactoryand
reassembleatfinallocation(welding)

Problem
Resultin8piecesand7Joints.Eachwillneedtobesupported
individuallyresultinginmassivevolumeoftemporary
support.Involvesmultiplehandlingandonhookholdingfor
longertime.
Moretimeandeffortsaswellasbeingestheticallyinferior.

LoadContoursofTowerCranes
atProcessor

ProposedScheme
InstallTwoAllTerrain500750tonTelescopicCraneoneithersideof
TransportationCentre

TransportassembledTrussfromassemblyyardonspeciallyadapted
flatbedtrailer(26mlong)tobeliftedby500750tontelescopiccrane
toitsfinallocationatthemiddlefaade.

OR

Transportthetwopartsseparatelyandassembleonadjacentdeckof
KerbsideViaDuct.Lifttolocationasbefore(requireshortertrailer)

NOTE:AddedAdvantage:DismantleTCTowercranesby
theAllTerrainTelescopicCrane

OperationalRadiiforOneSideof
MiddleBananaTrusses(East)

TypicalAllTerrain
TelescopicCrane

AccessandSpaceDetails

OverheadInstallationsandHeadroom
VerificationsaboveAccessRoute
East

OverheadInstallationsandHeadroom
VerificationsaboveAccessRoute
East

NeededSchedulingAdjustments
Aug

Sept

Oct

Nov

cessor
creteLevel2

XX

cessor
creteLevel3

RemoveGarbageSorting
AreaandConcrete
DeliveryStations

Jan13

XXXXX

XXXXX

Feb13

Mar13

Apr13

XXX

XXXX

XXXXX

nsportCentreRoof

estrianBridgesand
kwaysfromMSCP

Dec

ExecutePilesandFootingsONLY
XXXXXXXXXXXXXXX
SuperStructure(Decking)

omaticWalkway
gesfromMSCP

cturalSteel(Middle
sses)

PrepareLiftingPlan
PrepareAccessRoadLayers

DuctDecks

XXXXX

XXXXX

XXXXX

XXXXX

XXXXX

XXXXX

XXXXXXXXXXX

GeneralLayoutaroundProcessor

STAGE4ROOFandFAADESTRUCTURES_REV01_WBS

STAGE4ROOFandFAADESTRUCTURES_REV01_PROPOSAL

EXTRACTFROMMST_rev02STEELROOTS

EXTRACTFROMMST_rev02STEELROOTS

EXTRACTFROMMST_rev02STEELROOTS

~3

A:1

le

145

21

100
00

00
180

W4
6

A:1

804

~3

50

B:4

~6

B:4

NE

Ho

~3

42
W4

le

NW

52

48

0
E4

B:4

~6

46
NE

A:4

NE

~6

B:4

093

10

LF

le
Ho

WO

80

57

NE

NA

56
NE

54

NE

N1

3
497

6
123

52
NE

422

WA

.1

33

Water
tank

00
180

285 ~6 NW44
101 87
53
984

00
505 78
157

~6

NE

~6
N

A:4

B:1

42

A:4

W5
0

B:1

NE

~6
N

858

54

180
00

~3

5
NE

Water
tank

06

Water
tank

~
A:1

44

NE

00

N1

~3N

~3 N

124

W
803 OLFF
3.1
6
NW

B:1
B:1

180

NW
56

W
101 3746 54 A
53
2 :4~6 N
W5
2
101
53
810
8

00
100

NW
57

NW
4

NW

56

747
9

700
0

~3

904

0
700

NA

00

220
0

220

A:1

Ho

50

EA

NE

NW

48

NE
NW

NW
57

57
NE

48

NW
56
NW

le
Ho
41

44

~3

145
21

42

NW

~3

747
9

40

NW

48
NW

34

24

36

Ho

NW

144

NE

804

Water
tank

48

NE

00 1
1

3
NE

263

le

Ho

02

786

498

46
NE

36

NE

le

44

le

8
44

NE

34

NE

NW

34

NW

~6

42
NW

431

A:1
~

32

A:4

~6

NW

804
B:4

NW

~3

285
119 87
53

NW

21

50

~6

20

NW

W24

567
2

220
NW

42

53
384 10
00 153

A:1

38

~3

A:1

NW
4

A:4
~6
A:4

~6

NW
36

28587

30
20

Water
tank

NW

Ho

le

NW

NW18

20

NE18

NW16
NW

26

NW14

NW10

NW6
NW2

NE2

B:1

22

A:1

~3

A:1

~3
N

NW

24

Ho
le

869
5

~6

B:4

793

63
101
00 43
100 370 B:1~3

~3

36

NE

895

32

A:4

~6

A:1

NE

34

~3

28

NE

B:1

NE

7
804
93
130 :4~6

7
504

NE
1

W2
8

~3
NW

18

26

NW

NW

NE

30

NE

B:4

24

~6

NE

Water
tank

Water
tank

84

NW

W2

81

16

30

~6

le
Ho

20

20

3
380 10
48 153
B:1
~3
N

Water
tank

86

22

NE

NW

101
5

80

NE4

3
15
10 184
28 ~6

22

16

NE

38
NE

NE

NE6

NW4

NW

44

NE

24

NE10

22

904

519

26
NE

NE8

NW

B:4
~6

:4~

A
40

0
E3

NE12

NW8

B:4

B:1

~6

A:4

NE16

3664

NW12
24

2
NE

NE14

5650

NW

NE

~3

82 6 4

28

276
3

32

NE

42
NE

445

00
0
47

14

NW

98

14

NE

:1

6B

~3

20

~
B:1

NE

A:4

12
NW

NE
12

2
E2

2
NE

NE
1

10
NW

NE
8

NW

Water
tank

Water
tank

NE
6

NW

38

90
95

00

97
30

3
01

38

15

00

NE

4
NW

00
15

NW
2

NE
2

N2

N2

106
04

N4

N4

Water
tank

380

00

N6

N6

489

N8

N8

03

3800

150
N10

N10

1500

Water
tank

N12

N12
N14

N14
N16

N16

Water
tank

N20

N20

37895

39697

N18

N18

15009

Water
tank

N22

N22

Water
tank

15001

Hole

N24

N24

N26

N26

Hole
4250

5640

6120

11092
11091
49374

S35 A:1~3

11093

S37 B:1~3

8055

S39 A:4~6

8614

S41 B:3~6

9386

N32 A:1~3

49374
11091

N30 B:1~3

11093

N28 A:4~6

8055

N26 B:3~6

S27 A:1~3

N40
S29 B:1~3

N38

N40

S31 A:4~6

N36

N38

S33 B:3~6

N34

N36

N40 A:1~3

Water
tank

Hole

N34

N38 B:1~3

N40 A:1~3

N36 A:4~6

N32 A:1~3

11092

8043

15880

N34 B:3~6

N38 B:1~3

N32

N30 B:1~3

N30

N36 A:4~6

N28

N28 A:4~6

N32

N34 B:3~6

N30

N26 B:3~6

N28

8043

Water
tank

8017

8017

Hole
S39

S37

S37

S35

S35

26000

S41

S39

26000

S41

6474

Hole
Water
tank

8225

11091
49374

11092

11093

49374
11091

8055

11093
8055

4250
5640

15880

6120

4250
6120

15880

5640
S27

S27
WA2

NS

EA2

Water
tank

10083
27164

B:1~3 S21

9039

B:1~3 S25

S23 A:1~3

S19 A:1~3

9039

A:1~3 S19

S21 B:1~3

S25 B:1~3

10083
27164

A:1~3 S23

8041

5548

Water
tank

8042

S27 A:1~3

S29

S35 A:1~3

S31

S29 B:1~3

S33

S37 B:1~3

S29

S31 A:4~6

S31

S39 A:4~6

S33

S41 B:3~6

S33 B:3~6

11092

4818

8043

Hole
Water
tank

12333
2666

Water
tank

956
0

S17

S09

~6

~6

9643

B:4

B:4

100
83

S15

S07

~6

~6
B:4

B:4

48
100 848
83

S13

S05

~3

9039

100
8

9100

~3

A:1

~3
A:1

B:1

S03

S11

B:1
~3

~3

1012

B:1

~3
B:1

S05

S13

S11

~6

6
483266
100

S03

A:4

~6
A:4

A:1
~3

S07

S15

A:1
~3

~6

B:4

1006

~6
B:4

S09

S17

8968

Water
tank

646
2

~6
B:4
5
13

SW
~3

SW

B:1

~3

B:1

10

A:1

~3

A:1

15

SE

08

07

SE

10

~3

08
3

B:1

~3

15

13

B:1

SE

05

SW

SE

1
33
47 083
10

~6

SW

A:4

~6

A:4

11
SE

08

03
SE

10

~6

B:4

~6

41

0
SE

S0

80

B:4

48 B:4~ SW3
10 8486 SW11 B:4
08
~6
3
B:4
S0
~6
1
SW
10
9
08
3
95
59

Water
tank

Water
tank

90

~3

19

39

82

83

58
SE

17

17

~6

SW

B:4
~6

A:4

SW

19

~6
A:4

~6

25

SW

B:4

27

SW

4
16
27 0083
1

Water
tank

42
80

80

41

SE

25

B:4

22 B:4~6
10 731
08
3

~6
SE

19

SE

27

39
90

A:4

~6

A:4
~

46

06
SE

Water
tank

29

41

B:1

~3
B:1

W2

S
~3

A:1

~3
A:1

SW
~3

31

SW

29

SW

64
271 083
10

42

1
804

21

SE

80
21

B:1

B:1

~3

59

SE
23

2 3
10 716
08 4
3

SE

31

A:1

~3

A:1

~3

90
39

26

83

15

00

9
903
213

187
SW
~6

B:4

~6
B:4

35

SW
~6

A:4

43

W
6S

~
A:4

SE
3

33

41

SW

64
271 083
10

Water
tank

Water
tank

1
804

804

SE
4

B:4

~6

1B
:4

~6

2
1007164
83

SE

35

SE
43

A:4

~6

A:4

~6

903

150

00

903

SE

37

804

Water
tank

B:1

39

A:1

~3

Water
tank

45
SW

47

SW

A:1

629

64
2710083
1

45

B:1

~3

B:1

SE

~3

2
1007164
83

39

SE

47

A:1

~3

A:1

~3

903

270

9
903

7
386

1
804

B:1

SW
~3
~3

~3

37
SW

SE

358

98
122

98
122
2

270

00

2
554
00
100

100
195

00

2
554

KAIA PROJECT ASSEMBLY YARD PLAN

00

Remark: Zone F
Zone B

G D each need four water tank,


C E H each need two water tank

195

358

~
A:1

~3

46

NE

3
:1~

NE

le
Ho

Water
tank

NW

577

32

22

50
NE

5
NE

7
804
7
3
804 1609 :4~6
B

34

NE

174
0
506

Water
tank

48
NE

NE

38000

15001

W3

Water
tank

NW

904

40

~3
N

24

15000

22

101

~3
NW

651

NW

le

Ho

36

NE

NE

28587

24

32

15

0
6
E2

125

9
671

38
NE

28

NW

804

36

NE

665

le
Ho
26

2
E4

4
NE

3
NE

Water
tank

NW

B:1

32
NE

804
7

34

904
7

804

Water
tank

36

NW

B:1
~3
NW

554

3N

NW
28

Ho
le

NW

20

38

44

A:4

NE

B:1
B:1
~

30

126

W22

858

NW

NW

NE

93
235 00
100

~6

3N

NW
26

00

B:4

~6

40

7
160 804
93 7

A:4

22

15001

Water
tank

A:1
~

NW
52
6N
W4
6

A:4
~

Ho

634

B:1

40

~3

A:1

953

8
559

NW

~3

A:4
~6

36

NE

~3

400

~3

30
NE

B:1

0
E5

9
747

~3
NW
54

597
6

NE

~3
B:1

NE

Water
tank

46

A:1

56

NE
3

~
B:1

26

NE

39

NW

NW
48

~3

A:1
28

90

A:1

5
NE

4
NE

NW

101
5
3693 1
25 00
B:1
00

NE

21
145

27

~3

NW
3

38

104
A:1

B:1
~3
B:1

N
119 3765 W36 B:4~6 NW
28
6 B:4~6
53
NW
34
100
00
711
6

50

~3

32

W3
8

858

NW
NW

A:1

3.1

54

44
NE

~6

A:4

NE

NW

~3
N

52

A:4

38
93
135 8047
7
554

A:1
A:1

WOL

FF

803

00

220
00

~6

32

NE

NW
NW

220

Ho
le

122

54

456

56
NE

46

NE

46

NW

W
803 OLFF
3.1
363
6
6

0
700

700
0

00
130

120
00

50

9.6t

9.6t

9.0t 15.5t

15.4t

16t

16.5t

22.2t 22.8t

0
71
52
9

51

88

68
686
4
738

68

51

88

13.3t

455

91

50t Crawler crane 2 PCS


500t Crawler crane
Scope of work

71

52

Assembly Yard

Temporary road

44

00
0
R1
5

52410

Temporary road

Assembly Yard

15.5t 9.0t

00
50

Assembly Yard

500t Crawler crane


Scope of work
50t Crawler
crane 2 PCS

55466

11055

50t Crawler
crane 2 PCS

8149

8149

Temporary road

24945
8000

24945
8000

8000

15.4t

16t

16.5t

13.6t

R1

8796

686
738

4629

Temporary road

21096

8000

50t Crawler crane 2 PCS


500t Crawler crane
Scope of work

22.8t 22.2t

16.6t 22.3t
22.3t 16.6t 16.72t 16.8t
10.1t 16.8t 16.72t

17.9t

17.6t 17.7t

10946

91
455

15.3t 15t

Temporary road
35514

500t Crawler crane

8000

15t 15.3t

36000

36000

500t Mobile crane

Temporary road

17.7t 17.6t

50000

52410

17.9t

12.5t

13.9t

2.5t

4583

13.6t

12.7t

14.3t

R1
50
00

13.3t

382652

11.3t

25630

12.7t

11.6t

17308

12.5t

6.7t

9.3t

13.2t

54979

6.7t

52410

11.6t

11209

11.3t

8875

14.3t

7065

13.9t

23660

Assembly Yard

0
50
R1

25000

50000

16425

4583

13.2t

25000

9.3t

9259

2.5t

8000

8796

Das könnte Ihnen auch gefallen