Answer and Explanation:
The correct answer is A.
Unknown risks are handled by applying risk reserves.
Last update: Feb 11, 2016
A content writing firm established a productivity figure of 10 pages/hour. This figure was
identified by a benchmarking firm specializing in the test engineering industry.
Every quarter the companys senior management conducts a management review of the
productivity figures. The latest productivity figures show that projects using word processing
software installed on the users PC were able to beat the target with a productivity of 15
pages/hour, while web-based content writing projects are at 5 pages/hour.
Senior management is not satisfied with the performance of the web-based projects and requests
an investigation with the help of the quality department. The goal is to understand why webbased content is missing the mark. After a detailed analysis the quality assurance department
issues a report illustrating the reason why some projects are exceeding the goal while others are
not.
Based on your understanding of benchmarking what are possible reasons for the above scenario?
A.) The benchmarking figures utilized were derived from a different industry
B.) The original benchmarking was done only for projects using locally-installed software and did
not include web-based development
C.) Project managers lack monitoring tools for project metrics in order to meet organizational
goals
D.) Benchmarking never works in a creative production environment
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: A)
Benchmarking is an activity performed within the organization or across organizations to
compare data from similar projects/parameters. The content writing firm should have taken data
for the type of projects that it executes rather than picking up industry benchmarks on
productivity for a testing firm. Therefore The benchmarking figures utilized were derived from a
different industry is the best explanation of what is going on here.
The second best option to select would have been that The original benchmarking was done
only for projects using locally-installed software and did not include web-based development.
However, there are two problems with this answer: The scenario does not give us any indication
that the original benchmarking had indeed been performed like this and the fact that The
benchmarking figures utilized were derived from a different industry is a more generic and
therefore the better answer here.
The answer Project managers lack monitoring tools for project metrics in order to meet
organizational goals can obviously not be correct because the scenario discusses that we know
exactly what the actual results are, therefore the monitoring is in place.
Last but not least, Benchmarking never works in a creative production environment is not a
good answer, because it contains the word never. Always be wary of absolutes in answers.
Answers with always, never and other absolutes are usually incorrect, because project
management is never black and white.
HINT: The Project Management Plan contains the Communications Management Plan.
Answer and Explanation:
The correct answer is B.
October 2015:
Question: Sandra is the vice president for a large software development company. She
has recently proposed a new game development project which has been strongly opposed by
another vice president. Which of the following conflict resolution techniques that conforms to the
PMI Code of Ethics and Professional Conduct should Sandra use to resolve the conflict?
A.) Forcing
B.) Collaborating
C.) Withdrawal
D.) Avoiding
August 2015
July 2015:
You are managing a construction project. You have outsourced the labor workforce to a contractor
using a Time and Materials contract. As per the contract, your contractor is claiming $10 per hour
for labor and an average of 10 hours a day per each labor resource provided. You know that on
average only 8 of these 10 hours per day were actually productive time spent on the project.
However, your contract doesnt state anything specifically about not charging for unproductive
time. You now have a hold on all of the contractors invoices until you reach a resolution. Which of
the following might be a factor contributing to this situation?
A.) Your contractor is being unreasonable
B.) You are being unreasonable towards the contractor
C.) You have not drafted the contract properly
D.) You should never use a T&M contract on a construction project
Answer & Explanation
Correct Answer: C)
Dont get distracted by the scenario. The scenario may put you in the shoes of the project
manager, but it does not mean that you are always right! Assume that you are not the project
manager for a moment. In that case you cannot resolve this dispute in any partys favor just with
the information given. However, you can easily spot the weakness in the contract since it should
have clauses regarding issues such as these. A T&M contract can be used in this type of
project however the terms of the arrangement should be clearly specified within the agreement
to avoid potential disputes.
Reference: PMBOK Guide 5th Edition, page 364
May 2015:
April 2015
Question
You are a project team member on a project being managed by one of the senior project
managers in your company. You are responsible for the Quality Assurance of the project. You have
found some serious issues with the procedures the project team is following. If these problems
are not corrected, the project may end up being a disastrous failure. What is the best way for you
to deal with this situation?
A.) Do nothing as its the project managers responsibility to rectify problems
B.) Issue a change request for the recommended changes to these processes
C.) Talk to the project manager in confidence and ask him to rectify the situation
D.) Informally report your findings to the project sponsor
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: B)
As you are currently responsible for the Perform Quality Assurance process, it is your
responsibility to officially report your findings and recommendations to the concerned authorities.
In this case, you must officially issue a change request for Change Control Board (CCB) review.
Reference: PMBOK Guide 5th Edition, page 247
Because you were able to identify the defects, you have performed the Monitor and
Control Project Work process.
Similarly, as you were able to remove the defects, you have performed the Integrated
Change Control process as well.
As you have performed both processes, you have followed the change control system.
allows the commissioning and testing team to start their activities on the newly installed site. The
reporting structure is such that each of the teams has five engineers and a separate team lead.
Each team member interacts with each other but only the team leads interact with you. Both
team leads also interact with each other to synchronize their operations. How many
communication channels do you have on your project?
A.) 33
B.) 23
C.) 42
D.) 78
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: A)
This was a difficult question wasnt it? Lets analyze the scenario to calculate the answer.
> We have two independent teams. Each team has six members (five engineers and one team
lead). Each team member is interacting with each other so communication channels for each
team are (6)*(6-1)/2=15. And because we have two teams like this, the total is 2*15=30.
> Both team leads are communicating with you so there are two communication channels for this
interaction.
2.Question
A project has the CPI of 0.73 and SPI of 1.1. Two programmers on your project team are in conflict
over the best approach to take now. A junior programmer wants to re-use some of the software
components your company developed from a similar software application in the past. She
supports her idea by claiming that this approach would save at least 1,000 hours of team effort.
The opposing senior programmer wants to follow the current development plan because the new
proposed approach would require major design changes.
As the project manager, what is the best way for you to proceed?
A.) Tell both programmers to work out the problem between themselves
B.) Consult the project management plan for guidance
C.) Tell them to follow the original design
D.) Analyze the idea and issue a change request if appropriate
Since the CPI is 0.73 and SPI is 1.1 we can infer that the project is over budget but slightly ahead
of schedule.
Accepting the idea will reduce the project duration. Dont get carried away by the fact that
because the SPI is greater than 1 that time is not an issue. A point to be considered here is that if
we can reduce the total project time by 1,000 man-hours of team effort, we can significantly
reduce the project cost as well. Although this benefit is not highlighted in the junior
programmers claim, it is very obvious. It seems that taking her advice is a good idea.
But in order to weigh all the pros and cons we need to first analyze it further and then issue a
change request.
Reference: PMBOK Guide 5th Edition, page 283 and page 82
3
A content writing firm established a productivity figure of 10 pages/hour. This figure was
identified by a benchmarking firm specializing in the test engineering industry.
Every quarter the companys senior management conducts a management
review of the productivity figures. The latest productivity figures show that projects using word
processing software installed on the users PC were able to beat the target with a productivity of
15 pages/hour, while web-based content writing projects are at 5 pages/hour.
Senior management is not satisfied with the performance of the web-based projects and requests
an investigation with the help of the quality department.
The goal is to understand why web-based content is missing the mark. After a detailed analysis
the quality assurance department issues a report illustrating the reason why some projects are
exceeding the goal while others are not.
Based on your understanding of benchmarking what are possible reasons for the above scenario?
A.) The benchmarking figures utilized were derived from a different industry
B.) The original benchmarking was done only for projects using locally-installed software and did
not include web-based development
C.) Project managers lack monitoring tools for project metrics in order to meet organizational
goals
D.) Benchmarking never works in a creative production environment
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: A)
4
Each time you perform the Validate Scope process with your customer he points out changes to
the design that are nice and often useful but which he hadnt really asked for. You are annoyed by
all of this undetected gold plating. Which process are you not performing that would have
detected it earlier?
A.) Collect Requirements
B.) Define Scope
C.) Control Scope
D.) Perform Integrated Change Control
Question provided by The PM Exam Simulator: www.pm-exam-simulator.com
Answer & Explanation
Correct Answer: C)
Collect Requirements and Define Scope are processes that are performed early on in the project,
usually a long time before the deliverables are worked on. These processes were performed and
completed as a basis for your scope. They wont help you detect gold plating.
Perform Integrated Change Control is the process of reviewing and approving change requests.
Gold plating is applied without formally filling in a change request and asking for approval. This
process wont help you either.
The Control Scope process on the other hand might help you detect gold plating before you show
the deliverables to the customer. In this process we monitor the status of the project scope. In
particular we compare the original requirements with the work performance information. Gold
plating will show up as a variance between the planned and actually produced features of a
deliverable.
Reference: PMBOK Guide 5th Edition, page 137
5.
Your company provides specialized IT support services for firmware upgrades. Your countrys
government has passed regulations stating that firmware of all telecommunication equipment
must be upgraded to support IPv6. The government has approached your company to upgrade
the firmware of all installed equipment at the major airports in the country. For your company,
this project is a result of which of the following:
A.) Market demand
B.) Strategic opportunity
C.) Customer request
D.) Legal requirement
Answer & Explanation
Correct Answer: C)
This is a tricky scenario and the answer is at first a bit surprising. Lets look at this from the point
of view of both the government and your company: The government approached your company
to do this project because they are bound by their own regulations. So for the government, this
project was initiated as a result of their own legal requirement For your company, however, the
project is initiated by a customer request. Remember that you dont own the airports nor the
equipment installed there so you dont have a legal requirement to update the firmware. The
government, on the other hand, owns the airports/equipment and is therefore asking you
to perform this update. In this case, the government is a customer like any other customer and
you are doing