0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
28 Ansichten3 Seiten
If local codes dictate more stringent requirements, then local codes should prevail. Vaporizing propane requires approximately 150 BTU / lb. Tank size and surface area become more important in sizing the tank than how often It has to be refilled.
If local codes dictate more stringent requirements, then local codes should prevail. Vaporizing propane requires approximately 150 BTU / lb. Tank size and surface area become more important in sizing the tank than how often It has to be refilled.
If local codes dictate more stringent requirements, then local codes should prevail. Vaporizing propane requires approximately 150 BTU / lb. Tank size and surface area become more important in sizing the tank than how often It has to be refilled.
Over the past 6 months we have discovered and mostly overcome several problems associated with the dealers propane supplies. To overcome the problems, we have had to do some research and are now prepared to propose some minimum requirements for future propane installations. If local codes dictate more stringent requirements, then local codes should prevail. Propane Supply Tanks Because of our inability to get adequate heat from our 970,000 BTU / hour boiler at Guadalajara, and because Guadalajara installed the smallest propane tank to date (1,671 liters), we searched for a Propane Vaporization Capacity chart which we found at www.elyenergy.com. Vaporizing propane requires approximately 150 BTU / lb. This heat must be conducted through the walls of the tank so tank size and surface area become more important in sizing the tank than how often the tank has to be refilled. 500 Gallon Above Ground Tank (1,893 liters) % of container Propane Vaporization Capacity in BTUs / Hour Filled at 0 F at 20 F 60 426,900 853,800 (less than 970k) 50 383,376 766,752 40 341,120 682,240 30 298,480 596,960 20 255,840 511,680 10 191,880 383,760 Our conclusion is that there is not enough propane vaporizing in the Guadalajara tank at cooler temperatures or as the tank level drops to support a 970,000 BTU / hour boiler. Please note that on the way to drawing this conclusion, we have exhausted several other possibilities, including replacing the regulator on the boiler once, and replacing the shops regulator twice (two different capacities). From the same www.elyenergy.com website we found the following:
1000 Gallon Above Ground Tank (3,785 liters)
% of container Propane Vaporization Capacity in BTUs / Hour Filled at 0 F at 20 F 60 799,500 1,599,000 50 720,000 1,440,000 40 640,000 1,280,000 30 560,000 1,120,000 20 480,000 960,000 10 360,000 720,000 Based on the above, in areas where the temperature is not expected to fall below 20 F we propose that the minimum tank size be specified as 1,000 gallons or 3,785 liters. In areas where the temperature is expected to fall below 20 F we propose that the minimum tank capacity be specified as 2 tanks of 1,000 gallons each (7,570 total liters). It is acknowledged that the tables above were derived for a particular tank of some unknown length and width and that tests on a tank with the same capacity but a different length to width ratio would have somewhat different heat transfer rates, but this is the best information that we have at this time. It is also acknowledged that the heat transfer with a battery of small tanks ( ex. 6 tanks in Hollywood) would add even another variable. All things considered, we still propose the minimum capacity as stated above. Regulators We have also had difficulties with the regulators supplied by the shops. In Hermosillo, the owners contractor installed a regulator that was designed for air, not propane. The regulator failed this month as the propane attacked the internal components. Even after we found the problem and had the shop correct it, the shop still had to deal with nonconforming cures and the hassle associated with them. Accordingly, we ask that all regulators be specified as being designed for propane. In addition, some owners contractors have not been able to translate our BTU / hour and pressure requirements into the correct regulator. Example: the contractor at Astro Llantas installed a regulator with a 10 PSIg inlet pressure rating on a propane system that can have up to 250 PSIg in the system. We propose that the minimum inlet pressure rating be 250 PSIg (17.5 kg / sq cm). We further propose that the minimum of the outlet pressure range be 0 PSIg. The maximum of the outlet pressure range should be between 15 PSIg and 35 PSIg. This is necessary to achieve proper regulation when adjusting at the lower end of the pressure range. In addition, we must have a minimum flow through the regulator. We propose that the minimum inlet and outlet size of the regulator be specified as 1/2 . We also propose that the transition from the outlet side of the regulator to the 1 pipe be completed within 6 of the outlet of the regulator, and that the transition does not have any restriction less than .
Stack Height and Opening Size at the rain cap
Adequate draft is specified by the boiler manufacturer as .02 inches of water when the system is completely cold. This is necessary to keep CO levels in a safe range (<600 ppm absolute maximum and <300ppm preferred) and to keep the combustion gases and flame from being blown down the stack and into the room. Based on our experiences to date, we propose that the stack height be a minimum of 10 above the roof where the stack penetrates the roof, and at least 4 above the highest structure within 30 of the stack. If draft is still less than .02 inches of water with this stack height, we may have to go higher or add a stack fan. The second component of adequate draft is the opening size at the rain cap. We propose that the minimum vertical clearance between the end of the stack and the rain cap be 8. Boiler Size Boiler capacity decreases by 4% per 1,000 feet of elevation. It remains to be seen whether or not we can get enough heat from a 970,000 BTU / hour boiler to support a 25 tire chamber at 5,000 feet of elevation in Guadalajara. The next larger size is 1,140,000 BTU / hour and can be made to fit or retrofit on our existing skid. The additional cost of the boiler is ~ $2,000. Based on whether or not we are eventually successful in Guadalajara with a 970,000 BTU / hour boiler, we will probably need to talk about boiler size on any future high elevation shop installations.