Clay soil whose bank unit weight is 105lb / cf is excavated and hauled by 22cy (loose measure) trucks that have an empty weight of 67500lb. For each 22cy of truckload that is hauled calculate the equivalent bank measure and loose measure volume. Estimate the total cost and cost per linear ft for excavating 16850ft of trench in hard clay for an underground cable.
Clay soil whose bank unit weight is 105lb / cf is excavated and hauled by 22cy (loose measure) trucks that have an empty weight of 67500lb. For each 22cy of truckload that is hauled calculate the equivalent bank measure and loose measure volume. Estimate the total cost and cost per linear ft for excavating 16850ft of trench in hard clay for an underground cable.
Clay soil whose bank unit weight is 105lb / cf is excavated and hauled by 22cy (loose measure) trucks that have an empty weight of 67500lb. For each 22cy of truckload that is hauled calculate the equivalent bank measure and loose measure volume. Estimate the total cost and cost per linear ft for excavating 16850ft of trench in hard clay for an underground cable.
---Clay soil whose bank unit weight is 105lb/cf is excavated
and hauled by 22cy (loose measure) trucks that have an
empty weight of 67500lb. An evaluation of the physical properties of the soil indicates a swell factor 30%. Based on four passes of the compaction equipment, it is anticipated the shrinkage factor will be 15%. For each 22cy of truckload that is hauled calculate the equivalent bank measure and loose measure volume. What is the total vertical weight of the hauling unit and payload of soil that is hauled on each truck trip? ---Excavation for trench in a confine area of a refinery requires excavation by laborers. Estimate the cost of excavating and backfilling the trench which is 3ft wide, 4ft deep and 15ft long in sandy loam. ---Estimate the total cost and cost per linear ft for excavating 16850ft of trench in hard clay for an underground cable. The trench will be 9in wide and average depth will be 66in. A rubber tyre trenching machine will be 65hp will be used. The cable will be installed in an open terrain so there will be no major obstructions to return the progress of the machine assume a 45min/hr effective working time. ---Estimate the total cost and cost/cy for excavating a drainage ditch 10ft wide at the bottom, 36ft wide at the top, 12ft deep and 15100ft long in good common earth. The excavated earth can be cast on one or both sides of the ditch. Use 1 cy dragline and an average swing pf 120. It will require 2 days to setup and remove the dragline. Two laborers will assist the excavating operation, which will be supervised by a foreman. Assume the dragline will operate an average of 45min/hr. Take the ff rates: dragline @P87.66/hr; dragline opr. @ P21.67/ht; laborer @ P15.56/hr; foreman @P25/hr; mob/demob of dragline P2500. ---Calculate the production rate of an excavator in cy/hr if its 3cy bucket is used to excavate material whose swell is 25% and the shovel can make 2.5cycles/min with effective working hour of 30min/hr. ---Estimate the probable output of a 4cy shovel for excavating common earth. For this shovel, the max digging height is 34ft. the average face cut is 15ft. assume a 120 angle of swing for the shovel to load the haul units. Assume an effective 35min hour for excavation operation. ---Estimate the probable output of a 2cy backhoe for excavation of hard, tough clay. Assume a swell 30% and 45min/hr effective working time for backhoe.
----
---Estimate the cost for bid purposes, furnishing and riving
180 steel piles, 40ft long. The piles are designated as HP14x73. The piles will be driven to full penetration into soil having frictional resistance. It will be driven to full penetration to soil having high frictional resistance. It will cost P9000 to move the pile driving equipment to and from the job. A single acting air-driven hammer will be used. This indicates that a hammer with 12000ft-lb of energy will be used. The pile driving hammer will be mounted on leads of a crawler crane, which will be used to lift the piles into position, support the leads and lift the hammer. ----
Estimate the cost of supply and driving steel sheet piles
for a cofferdam to enclose a rectangular area 60x100ft. The piles will be 15in wide and 24ft long and weigh 30.7lb/ft (section PSA23). The piles will be driven in pairs to full penetration into soil having normal frictional resistance. A hammer delivering approximately 6000ft-lb of energy per blow should be used. A suitable steel cap is place in top of piles to protect them from damage during driving. The hammer will be suspended from a crawlermounted crane. A portable air compressor will supply air. ----