Beruflich Dokumente
Kultur Dokumente
U:
Safety advice
Foreword vii
Introduction
/2
14
Flexiblehoses /6
Articulated arms /6
Pipework for liquid chlorine 17
Permanentpipeworkat the iozloaclingpoint /7
Designcriteria for pipework transferring liquidchlorineto storage tanks' or
from storagetopoint of use 7
Protectionofpipeu'or/c 19
Marking 20
Protection ofliquidchlorine pipework againstoverpressure 20
Proi'ision ofrelief si'stems' 20
Valves 22
T'pe.v of ia/ic 22
Vertical globe vali'es 23
Conicalplug vali'e,r (PTFE-s'leeved) 23
Ball i'alve.s 24
Remote/i controlled vcili'es' 24
Storage vessels 24
Design criteria 26
Connecting pipc'work cmii ,necmn,s' for isolation of storage tc,nk.s' 27
Liquid chlorineinlet 25
Liquid chlorineoutlc'i 25
III
30
Relic! svsteni 30
andchlorinedetectorsystems30
Chlorine detectorsand alarms 32
Protection ofstorage vessels against ovcrpressure 33
Reliefsystem 33
B,,rstint' discs 34
Arrcoigcmentsfoi' ic//cf systems 34
Expansion vessels 37
Pressurealcirnis 37
Arrangements for unloading ofliquidchlorine from road tankers to storage 38
lJnloaclmg usingdcv conipressecic/jr Oc/ct' nitrogen 38
Suppli ofcirt'pcidcliog gas to ti/c system 39
lJn/oad/iog usingchlorinegas pm ssure 39
Useofrecompressed chlorinevapour 39
Chlorine \'aporisers40
Instro,neotation
T'pes 40
Regulcilion of throughput 41
Methods ofheating 41
Generalinstallation 42
HaarcIs 42
Routineand emergency isolcition 45
Pressure control vc,hi'e 46
Corrosion 46
Chlorine absorptionsystem 47
tent collectwn system 47
1bsorptionequipoient 48
Jnstrionentcution 48
Disposalofeffluentfroumu ti/c chlorine absorptionplant 49
Operating and maintenanceprocedures, trainingand PPE 51
Operating instructions5 1
Maintenance, inspection and installation 52
Generalouainteoance
rec/uirements52
Mc,intencunceofconnections 52
Insjcc'tion coid conioussioniog ofchlorine tank installations 53
inspection procea'ioe 54
Testing 55
Modification ofthechlorinesystem and clearance procedures 55
Unloading ofliquidchlorinefromroadtankers to storage 56
Use of ISO (demountable) tank containers 57
Transferofchlorine to the consuming units 58
Trcmnsfcrofgcmseouschlorine 58
Trcmnsfer of liquidchlorine using vapourpressure 59
Transfer ofhcjiocl chlorine hrpadding with dry conipressech gas 59
Transferofh/c/u/cl chlorine using asepclrate pionping tcmnk 59
Precceutions 59
iv
Training 61
Competence (10(1(Ilk/it 62
Personal Protective Equipment (PPE) 62
Seleciin' sintallc respiratort'protectiveequipment(RPE) 63
Emergencyarrangements 67
Emergency equipment 68
Control of leakages 68
Releases insideliuildins 69
Appendices 71
I Toxicologicalproperties and first aid 71
2 Characteristics ofchlorine 73
3 Relevantlegislationand HSE guidance 79
4 Useful
119
I
::ulIulllutuIIi!::
7'
he aim ofthis gLildance note is to help those responsible for ihe safe ue ol chlorinehum
bulk containers to meet their oliligatlons under health and salely law.
itli
This guidance. like the document that preceded it. was prepared
the help of the chlorine
producers, users, trade unions, the WaterServices Association (WSA), and the Chemical
Industries Association (CIA).
We are grateful to those whocontributedfor their assistanceand cooperation in preparing this
advice, and to Shaw Valvesand to Descote Ltd for permission to usethe photographs linked to
paragraph 74, to Weston Point Studios for permission to use the photographs linkedto
paragraph 216 and to Zeneca plc for pernhission to takethe remainingphotographs.
The guidelines maybe appliedto any bulk chlorineinstallationbut they are not intended to be
a detailed design code. Sonic existinginstallations maynot at present meetall the
recommendations and, in sonic cases, not all the recommendations may be appropriate. It is
for the occupier, usually in consultation with the chlorine supplierand/orspecialistadvisers, to
judge the need for further risk control measures,following an assessment ofthe actual risks. If
improvements are shown to be needed, a responsible decisionis required from the operating
company on the nature and timing of changes sothat they can be made safely.
Where reference to British. European and otherstandards is made in this document equivalent
standardsare equally acceptable alternatives.
If
given in Appendix 4.
Vii
()
l'orms a
outlined.
Employers havea legal responsibility under Sections 2 and 3 ofthe Health and Safety
at Work etc Act 1974 (HSW Act)2 to ensure, so )aras is reasonably practicable. the health
and safety oftheir employees and others who may be affected by their activities. Other
people. such as designers, installers and suppliers, also havesimilardutiesunderthe HSW
Act with respect to products. Since 1 974various regulations have been maderequiring
specific controls for particular hazards leg pressure systems), oractivities(eg manual
handling). A list ofthese and other current health and safety legislation, codes ofpractice
and guidance is published annually.3 This list also covers amendments to the regulations.
References in this docunient are to the base regulations. Appendix 3 gives au overview of
the main legislation and regulations relating tothe safe handling ofchlorine.
5
You must obtain planning permission for new installations in the usualway from the
6
Local Planning Authority, who will,when appropriate, referto HSEfor advice. If you store,
or plan to store. morethan 10 tonnesol chlorine. your site will be subject to a numberof
specific regulations.
7
The Notification of Installations Handling Hazardous Substances Regulations l982
require you to notify your activity to HSE ifmore than 10 tonnesofchlorine is liable to be
must alsonotify subsequent changesto your activity. New installations over 10
kept.
tonnes chlorine capacity, or proposals to increase the notified capacityto morethan three
times the original capacity, must be notified threemonths in advance. Theform ofthe
notification is in the Regulations.
ou
(a)
(h)
For sites which store 75 or more tonnes,or which process chlorine and haveinventories of
25 ormore tonnes, unless the process operation is incapable of producing a major accident
hazard, niore stringent regulations apply. These require the preparation of a safety report.
the preparation of oilsite and offsite emergency plans and the provision of information to
members ofthe public likely tobe affected by a major accident. CIMAH will be replaced
in February 1999 by the Control of MajorAccident Hazard Regulations (COMAH) which
implement the requirenients oftile Seveso II Directive6 on the control ofmajoraccident
hazards tile thresilold for the lowertier requirements is 10 tonnes, and 25 tonnes for the
top tier.
9
The Planning(hazardous Substances) Regulations I992 apply to sites with 10 or
more tonnesofchlorine. lJnderthese regulations tile consent'of the local Hazardous
Substances Authority (I-ISA) is needed for the presence ofclllorine in sucil quantities. The
HSA must consult HSE on the associated risk levels. To quantify the off-site risks HSE
mayrequest technical intornlation about the installation.8
10 In addition, any process wilicil involves the manufacture or useofclllorine or any
process wilicil is likely to result in the release ofclllorinc into tile air or water, is a
prescribed process undertile Environmental Protection (Prescribed Processes and
Substances) Regulations l99i. Otiler processes arealso prescribed in tile Regulations.
Undertile Environmental Protection Act 1990 no person shall carry on a prescribed
except underan autllorisatioil granted by the enforcingautllontyand in accordance
witil the conditions in the authorisation. Applications for the authorisation ofa prescribed
process in England and Wales must be made to the Environment Agency ([A) and in
Scotland to tile Seottisll Environnlental Protection Agency (SEPA). In addition in Scotland
wilere tile Alkali and Works Regulation Act 1906,11 as anlended by tile Health and Safety
(Emissions into Atmosphere) Regulations 1983,12 is still in force, suell processes are listed
as Scheduled works and must be registered amuiaiiy witll SEPA.
iocc
II If you fill containers from your bulk installation and transport themoffsite.you will
needto comply with the Carriage of Dangerous Goods(Classification. Packaging and
Labelling) and Use ofTransportable Pressure Receptacles Regulations 1996,13 aild the
Carriage of Dangerous Goods By Road Regulations 199614 (in the case of transportatioll
by road). The relevant legislation is outhned in an NSF booklet.15 Note: The (legal) ternl
for gas cylinders is now transportahlepressure receptacles'.
12 Although you must comply with health and safety legislation, regulatorycontrol
cannot compensate for deficiencies inthe way that safetyis nlanaged. Effective health and
safety managenlent is mainlyabout management (at all levels)taking a proacti\e approach
to minimise the chance of incidents occurringratilertllan putting tilings right after they
havegonewrong . Guidance on effective healtil and safety management is given
eisewllere' 7 which advocates and elaborates Oil tile following general principles of
good nlailagelllentpractice:
(a)
(b)
organise and train your staff to ensure effective communications, cooperation, and
their competence to control risks;
(c)
plan what you need to do, set perfomianccstandards, and establish systems
and procedures for controlling risks;
(d)
(e)
RISKASSESSMENT
The M1-ISW Regulations require you to conducta full risk assessment to
identify all the hazards and assess the associated risks. Therisk assessment needsto
include all sources ofhazards, including thoseassociated with transportaroundthe
site, accessto plant and security. The needfor risk assessment is also a requirement
ofother regulations (eg The Control ofSubstances Hazardous to Health Reulations
1994 (COSHH)20 and the Fire Precautions (Workplace) Regulations 1997.2!
13
14
In outline, a risk assessment for your chlorine operations requires you to:
(a)
(b)
(c)
(d)
(e)
(f)
15
Each site will have its own special featuresand you need to takethese into account when
conducting your risk assessment. A properrisk assessment will helpyou to:
(a)
(b)
establish adequate controls and safeworkingprocedures based on the advice in this note.
16 Your risk assessment will needto consider the mainpotential causes ofreleasesof
chlorine. For bulk chlorine installations these are (see paragraph 20):
(a)
plant damage causedby external sources (vehicles, hoists,flying debris from nearby
accidents, fires etc);
(b)
(c)
17 The people conducting your risk assessment must have relevant experience and
knowledge. Ifnecessary, you niust18 seek assistance from experienced and knowledgeable
people. Your chlorine supplier will be able to identify competent people able to conductthe
risk assessment on your belialiland supplyinformation to help youcarry out your risk
assessment and to manage safety.
18
The remaining sectionsofthis booklet provideguidance on the arrangements for
prevention and mitigation ofchlorine leaks and spillages through good design,operation
(including emergency procedures) and maintenance. The guidanceappliesonly to installations
storing liquid chlorine underpressure in bulktanks or tank containers. You should therefore
pay particularattention to the requirements ofthe Pressure System and Transportable Gas
Container Regulations 1989 (PSTGC).23 Precautions for the storage ofliquid chlorine in
refrigerated tanksat low pressure are outside the scopeofthis guidance. Additional sources of
advice and information are listed in Appendix 4.
19
Bulk chlorine installations operate under pressure. Consequently, the design,
installationand operation (includingperiodicexaminationand maintenance) of
these pressuresystemswill need to meetthe requirements of PSTGC.23 Pipework,
equipmentand protective devices for liquid chlorine are part ofthe system. The
regulations do not apply to systems operating at or below pressures of 0.5 bar
gauge, except for steam systems. Guidance on PSTGC is contained in an Approved
CodeofPractice24 and the publication A guide to the Pressure Systems and
Transportable Gas Containers Regulations I 989;25 see Appendix3 for brief
details.
POTENTIALINCIDENTS
20 When designing or modifying your installation,you should include provisions
to prevent the following potentialincidents whichcould result in a release of
chlorine:
(a)
if
(b)
(c)
(d)
(e)
Plant and equipment failure due to inadequate maintenance. eg 'passing' valves, or leaks
causedby corrosion or erosion, or use ofplant and equipment beyond the recommended
Iife.
(f
SITING OF INSTALLATIONS
The guidance in this section relates to general features which affectthe location of the
installation. More specific factors arc reviewed in the detailedsections dealingwith offloading (see paragraphs 134-147) and eniergency procedures (seeparagraphs 247-263). When
deciding the location of your installation an important consideration is the potential risksto
people and the environment. Theserisks decrease as the separation distance increases. The
site of such separation distances will depend upon a nuniberoffactors, including:
21
(a)
(b)
(c)
(d)
(e)
the design ofthe installation, eg length and diameter ofliquid and vapour lines; and
(f)
the size,distribution, and type (eg sensitive groups) ofthe surrounding population.
You should carefullyconsider these factors whendesigning and deciding the location of
installation
and when conducting your risk assessment (seeparagraphs 13-17). You
your
should involve your chlorine supplierat an earlystage. Consideration should be given to
maximising the distance between the site boundary and the chlorine installation. It should be
emphasised that your risk assessment and individual circumstances (see paragraph 21) will
determine the separation distances. The same considerations alsoapplywhen making
significant changes to an existinginstallation within a site.
22
When choosing the location for your chlorine area,you needto consider the location of
other onsitebuildings in relation tothe prevailing wind direction. It is recommended that the
chlorine area should be located downwind ofbuildings thatare regularly occupied. Ventilation
intakes to occupied rooms should be at least25 m from the chlorine installation, and
preferably at a high level.
23
For a new installation, full account will have tobe takenofany requirements
attached to the planning permission granted by the Planning Authority. In addition
the local Planning Authority needsto ensure that theoverall planwill avoid
problems arising in thefuture from developments leading to a high density of
population near the installation, or from the introduction of other potential hazards
in an adiacent area (see Appendix 3: Planning (Hazardous Substances) Regulations
1992). For sites which maypresent such hazards HSF. may recommend that the
highest standards are applied, before consent can be granted by the HSA. In some
casesthe consideration of'off-siterisk levels by HSE may requirc control measures
in addition to those recommended in this guidance.
25
27 The location ofa new chlorine installation within a site shouldbe decided
following a risk assessment. In making your decisionyou should takeinto account
possible damage from flooding or subsidence, and the possible damage to the
installation if neighbouring plant or factories suffer a catastrophe by fireor
explosion. Installations shouldbe sited at a sufficient distance (25 iii minimum)
from public roads or main railway lines to reduce the riskof damage to the
installation ifthere is an accident. Protective haiTiersshouldbe installed where
necessary.
In all cases, suitable fences, together with adequatesecurity supervision,
should he provided to minimise the possibility of unauthorised access.
28
(b)
(c)
minimising the length and diameter ofpipework carrying liquid chlorine and ensuring
overpressure protection;
(d)
(e)
improving the leak-tightness ofany chlorine building against major leaks; and
(f')
UNLOADiNGAREA
Design and location
32 The unloading area should be on reasonably level ground with adequate surrounding
space providing goodaccess from different directions. The location should minimise the risk
ofimpact damage from vehicles, mobileequipment or fallingobjects from lifting equipment.
33 The unloading point shouldbe reasonably close tothe storage installation. To avoid
impact damage a protective barrierbetween the tankerbay and the storage installation is
recommended. The unloading point shouldalso be sitedat a safedistance from drains, rivers,
drainage collection points and any plantor equipment which might give rise to fire or
explosion.
34 Satisfactory accessshouldbe provided tothe permanent pipework for dischargeofthe
chlorine tankers and to ensure that connections tothe tankers can be madesafely. Wherethis
involves working from a place abovegroundlevel,a permanentstructure should be provided.
This should be designed so that, in case ofemergency, escape is possible with minimum risk.
You canachievethis by installing a substantial and non-flammable (eg steel) structure and
ensuringthat platforms are free ofobstructions and have non-slip surfaces, adequate toeboards and guard-rails. Alternative escapeways shouldbe providedwith stairways ofstandard
slope. Vertical ladders or steep stairways should be avoided. If vertical ladders are
unavoidable, ensure that safety hoops, etc. do not impede access for peoplewearingbreathing
apparatus. The design ofmoveable platforms givingaccesstothe top ofthe tankers needsto
minimise the possibility ofaccidents due to collision with thetankers. Interlock systemsmay
be used for this purpose, see paragraphs 39-41.
35
You needto provide for the safe isolation ofany leaks that may arise,
particularly from pipework carrying liquid chlorine, It is recommended that
remotely or automatically controlled valves should be installed on thetransfer line
to the storage tanks. When automatic isolation is employed, operated by chlorine
sensors in the unloading area, the detector systemneeds to closeboththe storage
tank isolation valveand that on the tanker. The possibility ofliquid chlorine being
trapped between closed valvesand the needfor pressure relief (seeparagraphs 6167) needs to be considered,
36
(a)
(b)
storage space for connectors used for transferoperations so that they can be
kept dry and protected from dirtand moisture gettingin, and possible impact
damage;
(c)
(d)
adequatelighting and emergency lighting covering the unloading area, and all
escape routes;
(e)
11
(a)
Provision of a separate and protected unloading areafor the sole use of chlorine tankers
(eg by erecting sideprotection ofthe motorway-type crash barrier).
(b)
(c)
(d)
(e)
(f)
Routing ofchlorine pipework in thearea to minimise the risk ofdamage from impact
by thetanker,other vehicles or mobileequipment.
38
Where a separate unloading area cannot be provided, and the unloading point
39
Interlocks should be used to prevent seriousincidents. For example, interlocks
can be used to ensure that the vehicle brakes are fully applied befoi-e the unloading
pipe is finally connected Ll and the tanker valve opened or, a barrieron the
unloading platform can be interlocked to the loading connector, so preventing
inadvertent movement ofa tanker still connected up. Alternatively the pressurein
the unloading pipecan activate a flashing sign to remind the driverthat the tankeris
--- still connected (the latter system may be appropriate at
a producerplantor a consumer plant with a large
throughput).
requiring the closure ofthe manual vent valve on the liquid chlorine delivery line before
starting thetanker discharge procedure, the vent valve shouldbe interlocked with the delivery
point or thetanker off-loading valve.
(h)
(c)
Close warning barriersand/orplace warning notices when the chlorine tankers are in
position.
(d)
(e)
Establish a system of work whereby one person is responsible for the whole operation of
unloading, and a second is within call during connection and disconnection. The second
person should be in the area and available throughout unloading.
Route chlorine pipelines in the area to minimisethe risk
ofdamagefrom collision by thetanker, other vehicles or
mobileequipment.
Owingto the very limited use of rail transport. the rest ofthis
guidance focuses on chlorine delivery by road tanker. When rail
transportis used, the sanie generalprinciples forthe safe
handling of bulk deliveries ofchlorine apply.
CONNECTIONSBETWEENTHE TANKERAND
THEFIXED LINES TO THESTORAGE
INSTALLATION(see also paragraphs 134 -147)
Flexiblecouplings to thetanker
forhquul chiorineondpadding
the.swo'elJolt?! (toil
iur.\otiee
li,
containment accidents.
(a)
(if
(ii)
(b)
Flexible hoses.
(e)
Articulated arms.
Flexible couplings are normally used,but flexible hoses or articulated arms may be
used by agreement with, or recommendation of. the chlorine supplier.
recommended.
49
Articulatedarms
Articulated arms, with swivelledjoints (knuckles). are Lisually used on high volume
installations. They should be designed to meetthe requirements specified in the Euro C'hlor
publication (lEST 75/44 and certilied as nleetmg this or an equivalent standard. They
shouldbe operated and niaintained as advised by the manulicturer. Arms shouldbe visually
inspected for dellcts and tested tor gas tightnessevery time they are Lised. Suspect arms
shouldbe immediately withdrawn from service fOr maintenance.
51
52
Where the seals at knuckle joints are purgedby a flovv of dry (dew point less than
40C) air or nitrogen. this gas should he continuously sampled by a chlorine detectorsystem
with an alarm. An isolation valve suitable for use with articulated arms should be attached to
the dischargeend of thearm to prczei1t air entering the arm after operation. It should:
(a)
ensure a gas tight seal when the arm is not in use to prevent moisture getting in an end
cap shouldalso be used and
(b)
permit the venting down of'the arm and depressurisation of'any connection adapter. The
arm should he ventedafter each operatioil and purged with a suitable dry gas.
Whenan arm is oLit of service the purge gas shoLild be maintained under a small pressure (eg
0.5 bar gauge).
You need to keep a register showing each operation and the quailtity (eg tonnes) of chlorine
trans rred
16
(a)
impact:
(ii)
heatino.
(c)
severe internal
(d)
(c)
erosion due to relatively high liquid velocities and inadequate inspection and
maintenance procedures. Liquid velocities less than 2 m's are recommended.
54 Routing ofpipcvork fir liquid chlorine should normally heabove ground and
should he sLich as to maximise protection from mechanical damage,corrosion and
fire. A minimum internal diameter of 25 mm (I in) is recommended to ensure
adequate mechanical strength.
lollowing lines:
(a)
pipework fi)r pressurisiigthe tanker with dry air, nitrogen or chlorine (see
alsoparagraph 1 34I47);
(h)
(c)
br
Your pipework will be part ofa pressure system and subject to (lie
requirements of the PSTGC RegLilations.232 It therefore needs tobe properly
designed. fabricated, inspected and tested in accordance with a recognised Code, eg
ANSI/ASME B3 1.332, and shouldhe sufficiently robust for all friresecable
conditions of work.
56
(a)
Design pressure. Should not be less than 12 bar gauge (174 psig).corresponding to a
design temperature of+45 O( Any part ofthe system which may operateat a higher
temperature shouldbe designed to withstand the corresponding vapourpressure (see
Appendix 2. Figure A2.l).
(b)
Design temperature. Should be lessthan the minimum at which the pipe is intended to
operate. or the temperature to which it will be cooled Lf liquid chlorine boils offat
atmospheric pressure (35C). Thenormal designrangeis 35C to +45C. In certain
uncommon situations lowertemperatures are possible due to chlorine cooling below its
boilingpoint,eg when purging systems with dry gas locations where liquid chlorine
has collected maycool to temperatures as low -50C due to evaporative cooling. Your
chlorine supplier should be able to provide advice on the needto design for such low
tei1peratures.
(c)
(d)
(e)
Radius of curvature ofany formed bends. Three pipe diameters minimum (weldelbows
must be used where tighterbends are necessary). Elbows, tees and reducing pieces
should be forged or hot-formed without reduction in wall thickness.
(f)
(g)
(h)
l560
832,
(i)
Manufacturers' instructions needto be strictlyadheredto. Avoid overtightening fittings asthis can result in leaks due to the subsequent failure of
the fixing nuts or packing.
(j)
57
(a)
Stress relief All fabricated items and butt welds should be stress-relieved
before final inspection and testing.
(b)
Inspection and pressuretesting. All weld spatter, scale and other foreign
matter should be removed. All butt welds should be fully radiographed or
ultrasonically examined. All pipework should be pressure-tested in accordance
with the design code. Where hydrostatic tests are made it is essential thatthe
complete piping system is thoroughly cleanedand dried to a dew point less
than -40Cbefore introducing chlorine. All traces of oil,greaseand solvents
mustbe removed (eg with steam or aqueous detergents or both) for the
reasons stated under 'Lubrication' in paragraph 56. Ifa hydrostatic test is
madeafter installation it will be necessary to change all gaskets to ensure
dryness. Appropriate leak tests will then be required to cheekthe newlymade
joints.
(e)
Protection ofpipework
58
(a)
(b)
(e)
(d)
adequately supported;
(e)
regularly inspected under any lagging to detect corrosion due to failure ofweathersealing.
Marking
59 The chlorine areaneedstobe clearlyidentified, marked3941 - see also the Dangerous
Substances Regulations in Appendix 3 - and secured against unauthorised entry. It is
recommended that chlorine pipework should be clearly labelledand paintedyellow in
accordance with BS 171042
to 08E5l-BS4800). The Health and Safety (Safety Signs
and Signals) Regulations
require clear labelling whenever risks to employees cannot
be avoidedor adequately reduced by other mcans advice is given in the associated
guidance.45
(e
l996
60
62 Therisk of liquid chlorine being trapped between closed valves is increased by the
following factors:
(a)
Isolation valves that are controlled by differentoperators. This may be a special risk
where there are long linesor complex pipework between units.
(b)
The simultaneous closure of automatically operated valves that have been installed for
plant isolation. This risk shouldbe assessed. In somecircumstances it may be preferable
to employ at least one manuallyinitiated remotely controlled valve.
You shoulddesign your system and operating procedures to minimise the risks of
overpressurisation. Whenappropriate, pressure reliefdevices should be fitted.
63
Provisionofreliefsystems
64 Reliefsystenis complicate pipework and introduce other potential hazards, and should in
general be avoided. However, ifthe capacity ofyour system is such thatrelease ofthe
chlorine present could lead to a serious incident, automatic means of releasing excessive
pressure in the pipework needs tobe provided. It follows that the configuration ofthe
pipework, positioning ofvalves, and valve-closing methods (see paragraph 62) haveto be
studied to see whether the hazardcan occur.
20
suitable collecting system (see Figure 1) The relief volume ofthe pressure vessel
shouldbe at least 20% ofthe line volume. Anyexpansion vessel should be
registered as a pressure vessel for examination and recordingpurposes.23
Lockedshutvalve
Pressure vessel
Chlorine pipeline
67
The pressure vessel should be fitted with a suitable alarmwhichoperatesas a
result oftherise in pressure in the vessel, ifthe bursting disc leaks or ruptures. The
vesseland line can then be vented to process, orto the chlorine absorption system
via a normally locked-closed valve. The heated bottle' system originally used on
older installations is now obsolete and not recommended.
21
VALVES
It is strongly recommended that Euro Chlorapproved valves are used on new
installations. Care isessentialin the choiceofvalves (eg see the publications on valves in
reference 22) as theyhave tobe resistantto chlorine and able to copewith the stresses to
whichthey may be subjected. The valve bodyshouldpreferablybe madeofforged steel:
cast ironis not acceptable. Ifthe valvedesign is such that liquid chlorine could be trapped
within the body when the valve is closed, provision should be madeto avoid excess
pressurewhichmay developwith temperature rise. Inothersituationsthe evaporation of
liquid chlorine may cause operating temperatures to fall below 350( (see paragraph
56(b)): the valves shouldbe selected so as not to fail ifthis occurs. Problems whichare
specific to coldor to liquid chlorine limit the application ofcertain designs of valve.
68
69 The selection ofthe appropriate type ofvalve for each application should be
reviewed with your chlorine supplierwho will be able to suggest manufacturers ofvalves
whose equipment has given satisfactory service with liquid chlorine.This will reduce the
possibility ofunsatisfactory valves being used \vhich will require replacement after a short
period and could he a potential source of hazard.
70 Valves which are 'permanently'open (eg to prevent inadvertent isolationofpressure
alarms), or 'permanently'closed(eg emergency vent lines) shouldbe securedin these
positions. The locking mechanisms should be capable ofbeing broken in the event of an
emergency, eg the lead or plastic seal type.
Types of valve
72 Valvesofthe following types have beendeveloped for use with liquid chlorine or dry
chlorine gas under pressure:
(a)
(b)
(c)
ball valves.
22
Verticalglobe valves
74 This typeofvalveis preferred to other types and is used for isolation of liquid
chlorine stocktanksor for large flows ofchlorine gas. The billet-globe valve is
recommended for installation on the liquid chlorine outlet line from chlorine storage
tanks(see paragraph 96). The gas seal aroundthe valve spindle in globe valvesmay
be formed by a packedgland (preferably usingringsor chevrons of PTFE) or by a
bellows seal. The bellows shouldbe backedup by a secondary gland seal. Globe
valves may, with advantage, be fittedwith a back seating arrangement which
isolates the gland from line pressure when the valve is fullyopen.
Glandpackedglobevalve
(('pica! si:e.s(0,01101)/c I5nim
In250mm)
76 Conical plug valves for use with liquid chlorine require provision for the
avoidance ofproblemsarising from liquid chlorine trapped in the bore when the
valve is closed. If this makes the valves uni-directional, they needto be marked
with an indication ofthe required directionof liquid flow to ensurecorrect
installation. Gas-tightness is providedby a PTFE sleeve inserted into the bodyof
thevalveand by a supplementary seal along the length ofthe spindle between the
valve bodyand head. Careshouldbe takento avoid the application ofside thrustto
thespindles ofplug valves.
Safety advice for bulkchlorineinstallations 23
Ball valves
77 This typeofvalvecan be used for isolation in liquid chlorine linesand should
incorporate the following:
(a)
(b)
straight-through flanging:
(c)
PTFE seals.
significantly greaterthan that ofthe largest delivery vehicle. The chosencapacitywill depend
on therate ofconsumption and the frequency ofdeliveries. Installation ofbulk storage
facilities shouldbe considered only ifthe annual consumption ofchlorine is sufficient to
justify bulk supplies ratherthanpurchaseof liquid chlorine in drums or ISO containers (see
paragraphs 216-221). An installation consisting ofsmallertankswhichwould require split
loads is not recommended. New sites should involve HSE at an early stage.
81
In considering the number of individual storage tanksfor a required total storage
capacity, take the following pointsinto account:
(a)
(b)
Ifcontinuity ofsupplyis essential, at least two tankswill be requiredto allow time for
necessary inspections and to facilitate maintenance. Thisalso providesgreater flexibility
ofoperation.
(c)
24
Increasing the numberofstorage tanks leads toan increase inthe ancillary plant and
equipment witha corresponding increase in complexity of operation.
used.
25
Designcriteria
88
Design criteriafor new liquid chlorine storage and expansion vessels are outlined below.
(a)
(b)
(c)
Filling ratio. Filling ratios fortransportable liquid chlorine containers are detailed in
BS 535547 for various size ranges ofmobilecontainers and for differenttemperatures.
Although there is no equivalent standard for fixed tanks, for simplicity a figure of
1 .25 kg ofliquid chlorine/litre capacity is normally used to fix the maximum level to
which thetank may be filledand the settingchosenfor the high level alarm. This
ensures that the volume of liquid chlorine does not exceed95% ofthetotal volume of
the vessel, even for a maximum temperature of 50C.
(d)
(e)
(f)
Supports and load cells. The vessel supports should be designed in accordance with the
design code to permit thermal expansion or contraction overthe design temperature
range. Special consideration may be necessary (checkwith your supplier) where load
cellsare used for determining the contents ofthe tank.eg certain types of weighing
device require secondary supports.
(g)
(h)
(i)
Gaskets. Use ofincorrect materials for gaskets can be dangerous, see paragraph 56(h)
for suitable materials.
(j)
to BS 550048
26
(k)
(a)
(b)
(c)
(d)
reliefsystem;
(e)
(seeparagraphs120 to 127)
27
Liquidchlorine inlet
94 The liquid chlorine inlet should not normally extendfurther into the tank than the
maximum liquid level. Some older installations use a dip-pipe on the inlet line. To avoid
liquid chlorine flowing back ifthe fillingline fails, holesare drilled in the top ofthe dip-pipe
so that liquid will not siphon back. A full dip-pipe maybe provided as an inlet to a vessel used
for both importation and exportation. Suchvesselsneedto be fittedwith the additional
controls appropriate to a liquid chlorine outlet. Youshould discuss the controls neededwith
your proposed chlorine supplierat an early stage.
95 The isolation valve on the chlorine inlet line, directlybolted to the flangeon the storage
tank,should preferably be a billetor high integrity globe valve. A back-upvalveshouldbe
provided, which maybe remotelyoperated. Ifa manualback-upvalve is used, the isolation
valveat the delivery point end of the pipework should be remotely operablefrom the
emergency stop points.
You needto back up the main isolation valvewith anadditionalvalveto enable isolation
28
poets(rriu9o)
need
pools Ipara
37d
Whtblth
Eopanniee
Valve A or B shOu
Ire rereotely operab e
Iron emergency slop
0..
stop
LPata
Storage vessel
be rvmvtely operab e
from emergeevystop
P0 nts (Peru 97)
0--
seapara
96
il rage vesse
bilage pipe
(pares 07 and tb8(
000 paId PA
J!
v<
- Vent absorber
(para t7t t89)
i:ri
Restrictingoritice
plants, the flow restriction can be replaced by the remotely operable shut-offvalves(see
paragraph Ill) controlled by a suitable flow or pressuresensor. Excessflow valvesmay be
advisable for linesnormally taking a flow ofchlorine much lessthan the flow which could
passthrough in fault conditions. They arenot suitable for lines in which the normal flow rate
is high, and for which other means of fault detection and flow isolation shouldbe used.
The prevention ofsuck-back of aqueous liquor into the vent line requires similar
precautions to those described for vaporisers (see paragraph 161). The prevention ofbackdiffusion ofmoisture is describedin paragraphs 1 78-181. The inlet tothe scrubbing system
should include a lute pipe(barometric leg) to prevent liquid from the scrubbing system
entering the chlorine system.
100
The procedure for transferring liquid chlorine to the storage tanksshouldprovide for the
vent valve to be opened slightly at the end of discharge for about a minute(see Appendix 6,
paragraph 17) to confirm that thetank has not been significantly over-filled. ie abovethe
extra-high level alarm(see paragraph 104). Overfilling is indicated by frosting on the vent
line, in which casepressurerelief maybe necessary (seeparagraphs 102-132).
101
Reliefsystem
102 The special requirements for the isolationvalveson the pressure relief system on the
storage tanksarecoveredin paragraphs 123-133.
106 To limitthe liquid volume in the storage tank to that permitted by the filling
ratio (seeparacraph88(c)). an ullage pipecan be screwed into the bottom ofthe
valve on the vent line. The length ofthis ullage pipeneedsto he consistent withthe
filling ratioso that, if liquid chlorine rises abovethe correctlevel, it will flow
through the ullage pipewhenthe vent valveis opened at the end of a delivery (see
Appendix 6) or in response to an alarm. The ullage pipe shouldbe checked when
the routine Inspection ofthe storage installation is made. A low temperature or other
alarm(see paragraph 107) shouldbe fittedon the vent line from the storage tanks to
warn if liquid chlorine is entering the ullagepipe on the vent line.
107 On a simpleinstallation, with good staffing and attendance at the tanks, an
ullage pipe (see paragraph 106) may serveasthe extrahigh level alarm. You need
to he awarethat this method requires the vent line to be left open, which is not
necessarily thecase for alternative methods, see Appendix 6. Ifa high contents
alarm is ignored during filling ofthe tank, the liquid reaches the bottom of the
ullage pipeand evaporates in the ventlineabovethevent control valve, producing
frostiig ofthe pipe. An ullage pipe therefore presents the risk ofliquid chlorine
being passed to the scrubber unless the line contains a knockout device fitted with
a high level alarm. A knockout pot in thevent line with level alarmsis also
recommended for other reasons (see paragraph 157). The minimum protection fitted
should be a restriction orifice plate (seeparagraph 98) and a low temperature alarm.
108 Ullage pipes arenot recommended for contents indication on new
installations: instead an extrahigh level alarm on thetank should be installed, see
also paragraph 105.
109 A low contents alarm ma be usefLil for operational reasons and may have
safety implications if, eg therecould be process upsets on thilure ofchlorine supply
or passage ofpadding air (seeparagraph 226) into a downstream vessel.
110 Storage tank pressure. The pressLirein the chlorine storage tanksis usLially
measured by gaugesspecially developed for use with liquid chlorine these have
silver or tantalum diaphragms. Before use, the gauges needto he completely
degreased (eg with steam and/ora detergent), dried and all traces of solvent
removed, and be pressuretested using only clean, dry. oil-treecompressed air. The
pressuregauges may be tOtedwith switches to give analarm ifthe pressure
exceeds, or tOlls below, a pre-set value. Alternatively, pressure switches maybe
used to give an independent signal for the high and low pressure alarms.
(a)
(b)
(c)
(d)
114 Audible alarms need to havea distincttone. In addition, warning lights ofthe amber
flashing ortraffic light type maybe fittedoutside each chlorine building. Whereappropriate,
eg at large, remote or sensitive sites, alarmsshouldbe connected to a telemetry systemto
providewarning at a staffed control point. The control point shouldbe able to isolate the
chlorine supply, preferably via a remotelyoperable valvefitted to the outletofthe tank.
storage or in use. Chlorine gas sensors should be tested regularlyin accordance with the
manufacturer's instructions to denionstrate that the detector and its associated circuits are
functioning correctly. A record ofsuch tests is recommended. The detection system should
operate thealarm circuits in the event ofpower loss, sensor failure,or low condition ofthe
standby batteries.All alarm relayoperations shouldbe protectedby a battery back-up facility.
The detector system should activate the low level alarmat a chlorine concentration of
1-5 ppm. Lower settingsare liable to activate the systemat every tank-fillingoperation, unless
I 17
32
level alarmat 0.5 ppm, but require the sensorto register this concentration for at
least30 seconds, to avoid spurious trips ofthe alarmsystemduringfilling
operations. For indoor installations, the lowalarmlevelshouldactivate the
ventilation fan, open the intake louvers, and activate local audio alarms and any
remotetelemetry alarm.
duration requirement.
On activation ofa high level alarmthe ventilation system should be shut off, the
auto-shutdown systemactivated (where fitted ) and the high level alarmsounded.
Thetone ofthe alarm at lowand high levelsshouldbe differentand operators
trained to recognise the difference and how to respondin eachcase. Local alarms
may be supplemented by telemetry links to control rooms, where appropriate. The
response to alarmsis coveredin paragraphs 247-263. Some sensors can be damaged
by high chlorine concentrations; detector systems should therefore be checked after
any high level alarm.
PROTECTIONOF STORAGEVESSELSAGAINST
OVERPRESSURE
Highpressure on the liquid chlorine storage tank is indicated by a high
pressure alarm (paragraph 110). Overpressure in the liquid chlorine storage tanks
can result from over-filling or excessive paddingpressure. Over-filling with liquid
chlorine is indicated by alarmson the weigh systemused to determine the liquid
chlorine content ofthe storage tanks (paragraphs 104-109). Overpressure on the
compressed air or nitrogen supplyto the storage tank is prevented by the installation
ofa reliefvalveon thesupply source of the compressed gas. The supply source
should be wellupstream ofthe tank and separated from it by isolationvalves
119
(paragraph 139).
Reliefsystem
120 The storage tanksneedtobe protectedagainstoverpressure by a suitable
automatic pressurerelief system which is set to operate at a pressurebelow the
design value. The preferred pressurerelief systemconsistsoftwo bursting discs
placed back to back. A bursting disc followed by a relief valve may alsobe used,
but is always subject to the risk of corrosion ofthe reliefvalve. Protection ofthe
relief valve from corrosion mustbe carefully considered ifthe bursting discrelief
valvesystem isused. The use of reliefvalvesaloneis not recommended because of
the corrosion or blockage whichcould occur ifa reliefvalve were left continuously
exposed to chlorine. Whichever system is used, you should provide a pressure
alarm/indicator between the two discs or between the disc and reliefvalve(see
paragraph 133). Inthe latter arrangement it is good practiceto remove and overhaul
the relieF valvewhenever the bursting disc is replaced.
121 The dischargeline from the pressurerelief system normally entersa closed expansion
vessel (except in a few specialised arrangements). Anypressure iii the expansion vessel or
between components in the relief system reducesthe protection given to the storage vessel
(seeparagraphs 85, 128-133). Special relief arrangements are usually requiredwhenthere is a
significant risk of overpressure from continuous pressure sources such as radiant heat oi by
pumping chlorine. Underthese circumstances relief into a closed expansion vessel may be
inadequate. Reliefarrangements based on relief valves into an 'open' system (cg a vent
scrubber) may be preferable to bursting discs,as the valves reseat once the source of
overpressure hasbeen removed. This arrangement is normallyonly found on larger
installationsyou shouldconsult your chlorine supplier.
Burstingdiscs
122 Bursting discs (which are designed to fail at or below the design pressure of storage
tanks) are commonly made ofnickel, although tantalum, silver or other compatible materials
may be used. Uncoated graphite is not recommended. Discs should coniply with BS 291 549
(or equivalent standard) and should he carefully selected for the operating temperature range,
as the rupture pressure is temperature-dependent.
ArrangementsJbr reliefsystems
123 On simple installations, such asthose with a single storage vessel and associated
expansion vessel, a single bursting discsystem without any isolating valves, installed directly
on the storage vessel, may be acceptable. In practice, however, it is more convenient to install
a valvedsystemto allow replacement ofdiscs undera controlled system ofwork, without
needingto completely empty and purge the system. Wheretwo or more storage vesselsshare
an expansion vessel, the relief arrangements should allow prompt replacement ofdiscs and
venting 012111 excess pressureout ol the expansion vessel.
124 The preferred arrangements are shown in Figures 3 and 4 and shouldbe used on all new
installations. The kolatingvalvesmay be mechanically mterlocked (recommended for new
installations) so that one pair of discs is alwaysoperative, or the isolatingvalves may be
individually locked. To he cffi,ctive the bursting discs needtobeol the sLmple domed
unsupported type with the concave sidefacing in the directions shown in Figures 3. 4. and 5.
The identifying tags should be lefi attached to each disc so that they can be identified as
having been installed correctly. Existing older installations usingthe arrangement shown iii
Figure 5 should replace it with a prefi.rred arrangement (Figure 3 or 4) when major
modifications lire in hand.
125 The valves which remain open must permit the operational devices to discharge at the
required rate toan expansion vessel. Pipework before the isolating valves should beas short
and simple as possible to minimise the risk ofchlorine leakage fromjoints and pipework the
isolation using valves before the bursting discs should preferably be fitted directly on flanged
connections on thenianlid of the storage tanks.
34
Toexparsior vessel
Pressure alarmgauge
xx
Borstieg
::
ds S
Bursting dscs
valves
Pressure alarmgauge
Toexpansion vesse
fl
Ptessuealarmgauoe
Looked vane
at eastoneline
needstobe
B i uring discs
_i__(
onkedoper
____
Bursi
i pdsos
Loused ualves
35
Toexpansion vessel
\ alves
Lockedopen valve
Barsting discs
126 Your procedures for dealingwith a failure ofa bursting disc shouldbe clearly
defined. Base themon the principlethat at no timeshouldpressuresbeyondthe design
range beallowedto develop(see alsoparagraph 127).
127 At any installation where a 'locked'-open isolating valveprecedes a bursting disc, a
safe system ofwork should be defined to preventunacceptable pressures from any source
occurring in the vessel while the isolatingvalveis closed. The procedures needto cover the
safe removal ofthe vessel from normal service, stabilising the pressure, changing the
bursting disc, venting the expansion tank and returning the vessel to normal use. Such safe
systemswill vary with plantdesign hut should:
(a)
(b)
(c)
(d)
(e)
(f)
be rigidly adheredto.
36
Expansion vessels
128
The design requirements for the construction of
the expansion vessel aresimilarto thosefor the storage
tanks;the capacity of the expansion vessel shouldbe at
least 10% ofthe largeststorage vessel.
132 While the risk ofthe expansion vessel itselfbeing over-pressurised with
chlorine is minimal because ofthe precautions described in paragraphs 128-131,
you shouldestablish procedural or mechanical meansto ensure thatthis cannot
occur.
Pressurealarms
133 There should be a high-pressure alarm on every storage vessel, and an
additional pressure indicator/alarm at each important safetylocation on the relief
arrangement. Thismeansthat one additional pressure alarm may suffice on each
storage vesselthat has its ownexpansion vessel, and that alarmmay be eitherin the
reliefline (ifthere is a single bursting disc) or on the expansion vessel. When one
expansion vessel serves several storage vessels, thereshouldbean additional
pressure alarm withineach reliefassemblyand also one on the expansion vessel.
Test alarms regularly (at least monthly) by gas injection or moving contacts.
37
38
141 A pressure gauge, a vent line to the absorber and a connection for dry
compressed gas shouldbe installed close to theend ofthe permanent pipework at
the unloading point, with the necessary isolation valves, as detailed in Figure 2.
144 Diaphragm compressors shoulduse stainless steel double diaphragms withinert fluid
between them.Dry carbonring compressors shouldpreferablybe purged with dry air after
use, to avoid problems resulting from residualchlorine in the compressorleakingfrom
shaft glands. During operation ofthe compressor, the shaft glands should be pressurised
with dry, compressed, inert gas.
145 Ifcooling ofthe compressor body is required, this shouldpreferably be accomplished
by air cooling.Ifjacketcooling is necessary, this shouldbe achievedby circulation
through an external heat exchangerwith provision to detectleakage ofchlorine into the
heat exchange fluid. Direct water coolingshould be avoided.
146 The compressor needstobe fittedwith a bypassso that the chlorine can be recycled
until its temperature is raised sufficiently to prevent liquefaction in the delivery lines. The
temperature ofthe chlorine shouldbe monitored using an indicatorwhich is fitted with an
alarm, set to soundifit exceeds90C.
147 A pressure reliefsystemon the compressordelivery line should also be providedto
prevent the delivery pressure exceeding a pre-setfigure (see paragraph 139).
CHLORiNE VAPORISERS
148 Vaporisers (also known as evaporators) convert liquid chlorine into gas. A major use
ofchlorine vaporisersisin water treatment, to control weed and algae in coolingwater and
to sterilise drinking water. Theseunitsare frequently supplied as part ofa package with
other dosing or analytical equipment. Vaporisers are always required with a fixed or
demountable bulk tank, to obtain a regular. steadysupplyofgas to process. The drawing of
gas from the vapourspace ofa bulk tank is unsatisfactory and unsafe.There is the risk of
process liquids passing back into the tank, irregularity ofsupplyand the possible
accumulation ofless volatile,dangerous impurities, such as explosive nitrogen trichloride
in the tank.51 The safe handling ofchlorine containing nitrogen trichloride is discussed
elsewhere.52
Types
149 There are fourmain typesofvaporiser(see also Appendix 7):
(a)
(b)
Coil. The chlorine is evaporated in a coil ofsteel tubingrunning insidea wet steam
bath or a waterbath heated by steam or electricity.
(c)
40
Safetyadvice forbulkchlorineinstallations
(d)
Regulation ofthroughput
Coilinbath vaponerheated
bylowpressuresteam
Selfregulatingvaporisers
150
In sonictypes ofvaporiserthe liquid chlorine is
fed in at the bottomand gas is drawn offvia a control
valveat the top. Whendemandis high, the liquidchlorine level rises in the
container, and a greaterheat exchange surface areais presented to the liquid. When
demandis low, the greatervapourpressure at the temperature ofthe heating
medium drives the liquid chlorine out ofthe vaporiserback into the storage vessel
and the evaporation rate falls. This system is usually applicable to vaporisers witha
relatively small chlorine capacity. ie vertical tubebundles,coil typesand concentric
tubetypes. Bayonet vaporisers can be used for high vaporisation rates. On water
treatment plantsa self-regulating vaporiser, with an electrically heated water bath is
usually used.
Constantlevel vaporisers
151 Othertypes ofvaporisers, usually found only in large-capacity plants, sacrifice
certain advantages ofthe self-regulating types to achievemuch larger vaporisation
rates. These vaporisers requireseparate instrumentation and control arrangements to
provide a constant level ofliquid chlorine in the kettle or shell with high and low
level alarms. In such types(wherethere can be parts ofthe liquid chlorine pool
which arenot well-mixed), there is a greatertendency to concentrate the less
volatile impurities than in a self-regulating vaporiser. A separate purge and
vaporisercircuitmay be required to deal periodically with the residues. The design
and operation ofthese larger-capacity vaporisers is a specialised topic, and requires
consultation between the user, the designer,and the chlorine supplieras the risk of
52 You
nitrogentrichloride enrichmentand subsequent explosion is increased.
should involve your supplier when assessing this risk.
5l
Methods ofheating
152 The methods ofheatingthe vaporiser shouldminimiseboth the risk of
corrosion and vaporiserfailure. These include: heatingwithhot water; heating with
low pressure steam and usingclosedcircuitheatingwith heattransfer fluids other
than water. Directelectrical heating should not be used because ofthe risk oflocal
overheating and chlorine/iron fires (see paragraph 158 and Appendix 2).
(a)
Heatingwith hot water. This isthe most frequently used method; the normal working
temperature (60-70C)is well belowthat at which any significant reaction ofcarbon
steel occurs with dry chlorine.
(b)
I leating withsteam. The steam should be saturated and its pressure shouldbe limited to
lessthan I bar gaugeto avoid overheating, particularly ifthe vaporiseris madeofmild
steel.Any small leaks ofchlorine tothe watersideofhot water or steam types lead to
veryrapid corrosion ofthe steel by moist chlorine (see pararaph 169). Steam systems
must meet the requirements ofthe PSTGC Regulations.232 The greaterflexibility of
steam heating is useful on plants using chlorine gas at high or at very variable rates.
(c)
I leat transferfluids (otherthan water). Electrical or steam heat can be applied to a heat
General installation
153 The vaporiser should be installed in the storage area orin an adjacentspace
as close as
possible tothe chlorine storage tanks in orderto keeppipelines carrying liquid chlorine short.
Long pipe runswill require pressure relief(see paragraphs 61-67). Changeover of liquid
chlorine supplyfromone storage tankto another canaffect operating conditions in the
vaporisersystem and any such difficulties will be reduced ifthe spacing is not too great.
eg lessthan 5 metres. Nevertheless, the space between the vaporiser and thestorage system
should be such as to allow adequate access for emergency action in the eventofan incident at
the vaporiser.
Hazards
154 The quantity of chlorine in a chlorine vaporisersystem is relatively small compared with
that normally contained in the main chlorine storage tanks. Nevertheless, the systeni design
should be such that failure ofequipmentcan bedetectedand rectified quickly and that any
consequent releaseofchlorine to the environment is niinimised.
155 Potential hazards associated with chlorine vaporisers include:
(a)
(b)
(e)
(dl
42
(e)
Carry-over ofliquid chlorine as bulkfluidor droplets into the gas line or into
the process itself. Thiscan (depending on the materials ofconstruction and on
the process) cause daniage or hazard.
(f)
(g)
Excessive hydraulic forces, ifthe system is closed up and full of liquid due to
the expansion of liquid chlorine when heated.
br
157 You should consider fitting a knockout pot (or spray catcher) to prevent
chlorine droplets and sprayfrom passing into gas pipework when liquid chlorine
might damage the material ofthe pipes, or cause the process to become unstable. In
all caseswherethe possibility ofliquid passing to process is unacceptable, itis
strongly recommended thata low temperature alarm be fittednear the knockout pot
and arranged to cut off the liquid chlorine supplyto the vaporiseror (in selfregulating typesonly)the gaseouschlorine outlet maybe closed, driving the liquid
chlorine back into the storage vessel(s). Adequate instrumentation and alarms
shouldalwaysbe provided to give immediate warning ofthis condition. Highand
low bathtemperature and level alarnis with shut-down facilities are recommended.
gas pipework may alsoneed upgrading to ensure adequate resistance to corrosion at elevated
temperatures.
159 lfthe heating medium is steam, the temperature can bemonitoredby low pressure and
highpressurealarmson the steam inlet. The pressure of steam should normally be limitedto I
bar gauge (120C equivalent) and the steam has tobe saturated, not superheated.
Highpressure
160 Precautions must 23 be in place to protectthe systemagainstover-pressurisation,
eg a
pressure reliefdevice. Pressure reliefdevices and high pressure alarms, wherefitted, should
be properly designedand installed, maintained in an effective workingorder,and tested
regularly. They mustbe periodically examined by a competent person.53 A typical working
temperature for a vaporiseris 70C. The vapourpressure ofchlorine at 70C exceeds 21 bar,
(see Figure A2.1, Appendix 2). It follows that you need to take the following steps to:
(a)
Ensure thatthe vaporiser is not isolated when full ofliquid chlorine. Strict observance of
written procedures for shut-down is vital.
(b)
Avoid accidentally isolating the vaporiseron both sides. Care needsto betakento
ensure that the closing arrangements for the emergency valves take this into account (see
paragraphs 162-165).
(c)
Design the vaporiser shell and pipesto withstand the workingpressureand duty.
(d)
If your chlorine vaporiser is not supplied with a pressure relief device you will needto adopt
procedures. or fit suitable pressure relief, to ensure that the conditions in (a) to (d) are met.
Reverse flow
161 You should eliminate the possibility ofsuck-back intothe vaporisers by suitable design.
For example, water chlorinating package systenisusually incorporate a set ofvalvesin the
control systemto prevent suck-back or push-back. The arrangements vary, and careneedsto
be taken to ensure that the system provided does give protection intheeventof, eg, a leak at
theejectornon-return valve. You should alsoconsiderfitting a low pressure gas alarm to the
outletgas line. This gives warning ofloss ofsupplyto the process. and may indicate a needto
start purging the systcm, usingdry air or other suitable dry gas (dewpoint lessthan -40C)to
prevent suck-back. Whatever method is used,the systemneedsto be regularly inspected and
maintained, and adequate records kept.
44
ii
77
162
The vaporiserhas to be capable ofbeing
isolated for maintenance, orin an emergency, such as a
failure ofthe vaporiseritselfthrough leakage or a failure
ofthegas line downstream. In addition to a manual valve
on the liquidinletand on the gas outlet. reniotelyor
automatically operable valves are strongly recommended
on both inlet and outlet. A pressure-reducing or flow
control valve will almostalwaysbe fittedon the outlet
and it is sometimes possible for this valve to be the
remotely operable shut-offvalve.
163
Yourrisk assessment shouldconsiderthe need
for additional protection in theeventthat automatic
valves fail to operate (or remotelyoperable valves are
________________________ not activated)inan emergency. For example a flow
restrictionin the liquid inlet (typically on the exit from
Emergency shutdown push
buttonat the vaporiser.Also the storage tank(s)), will limitthe releasewhichcould
shown in oneofsix chlorine
occur in theevent ofa majorplant failure.
detectors atthisinstallation
which canalso automatically
164
The hazards oftotally isolating the vaporiserare
shutdown thechlorine
considerable and will be most severe when the
installation (seeparagraphs
evaporator is full (eg ifthe valvesclose together in a
_____________________ condition ofmajor gas line failure). Ifthere is a gas
space abovethe liquid chlorine when the vaporiseris
isolated and heated, the internal pressure will reachthat ofchlorine at the heating
medium temperature. The vaporiser, linesand valvesneed to be designed to
withstand such pressure or incorporate arrangements to relieve to a safe place. The
control ofautomatic valvesneedsto be arranged so thatthe valves do not close
together whenan alarm is raised(see alsoparagraph 160). One approach is to
arrange for the gas control valve to closeon alarms related to improper working of
the system (eg low gas pressure, downstream process alarms, low temperature) and
the liquid control valveat the storage tank to closeon chlorine release(eg detectors
local to the vaporiser and storage,or manual alarms). Ifthe plantis continually
staffed, manual intervention maybe a suitable alternative to providingwholly
automatic operation ofshut-down. However, procedures needtobe established to
ensure that this does not introduce significant delays into the responsetoan alarm.
An alternative approach isto use a pressure control globe valve for remoteisolation
oftheoutlet line so that excessive pressures will lift it slightly off its seat,
preventing excessive overpressures. Reliefpressuresand valvedirectionneed
careful consideration and shouldbe discussed with the valvesupplier.
165 Isolation ofthe vaporiscris still possible, but interlocks betweenthe inlet and
outletvalvesto prevent total isolation are rarely fitted. This is becauseit is
occasionally necessary to close both valvesduring cleaning and overhaul. A safe
system ofwork for maintenance and operation is thus a vital part ofthe safety
23
arrangements, and is a requirement underthe PSTGC Regulations.
Corrosion
167 CoiTosion of the vaporisertubesorcoils could lead to a loss-of-containment accident.
The consequence ofa minorchlorine leak from the chlorine sideofa vaporiserheating bath
could be very serious since the mixture ofchlorine and moisturewill lead to rapid corrosion of
the evaporator surfaces and a substantial releaseofchlorine.
168 You must arrange for a competent person to periodically examine your vaporiser and
other pressure systems in accordance with your written scheme ofexamination.4 A
must certify thatthe written scheme for examination is sUitable for the
competent person
of
purpose preventing reasonably foreseeable danger to people from the unintentional release
of stored energyfrom the system. The written scheme ofexamination should describe the
natureand frequency ofthe examination. This should bebased on risk assessment and give
due consideration to the duty and the condition of the vaporiserwhen it was last inspected.
The competent person will advise on suitable examination and test regimes, and when the
vaporiser shouldhe replaced. Examination intervals betweenone and five years are typical.
Coil-in-bath evaporators are commonly given a rigorous inspection every two years, and the
coils are discarded ifseriously pitted. Some manufacturers advisethat the coils should be
renewed every two years. Following examination the equipmentshouldbe thoroughly dried to
a dew point lessthan 40C before recommissioning. Moisture left in the system can lead to
very rapid corrosion. The procedure shouldbe coveredby a writtenoperating procedure.
169 Corrosion of the heat exchanger surfaces is not directly monitored. Instead the
evaporator vessel or tubes are frequently protected against water corrosion by cathodic
protection. Typically the anodes should be checked visually every threeto six months. The
frequency should be established by experience ofthe rate at which theanodesare consumed
and replaced. Ifthe anodesare found whollyconsumed at inspection, a thorough examination
ofthe vaporiser should be undertaken. The waterbathor condensate outlet should be
monitored for chlorine leaks by redox or conductivity measurements. This earlywarning of
minorleaks is helpful in all cases,and is very strongly recommended ifcathodic protection is
not provided or not maintained.
170 Accumulation ofsolid deposits reducesthe effectiveness ofa vaporiserand can also
enhance corrosion. The vaporiserneedstobe cleanedand dried to a dew point lessthan -40C
regularly. Closeattention tothe cleaning procedure will minimise corrosion but typically, the
chlorine evaporator cylinder in a hot water bath (see Appendix 7, type Ic system) should be
renewed after five years. The old one maybe submitted to a competent inspection body for
certification for furtheruse if required.
CHLORINEABSORPTIONSYSTEM
171 You should give detailed consideration to ensure that in all chlorineusing
operations chlorinecan. in an emergency, be ventcd to an absorber without
emission to the environment.
172 Control ofchlorine emissions from prescribed processes(see paragraph 10)
must be the subject of consultations with the Environment Agency in England and
Wales and SEPA in Scotland.
1 73
In some installations, the nature of the eonsunimg process is such that
absorption ofthe chlorineis possible without a special absorption unit. I lowever, in
such circumstances operators need to ensure that duringillaintenance periods
adequateabsorption capacity is alwayskept available to accommodate any chlorine
emissions. A separate absorption plant may not he essential in, tor example cooling
watertreatment plants and bleach liquor productionplants.
-IJ
if
47
Absorptionequipment
1 82 Varioustypes of absorbers are usedfor the treatment ofventgases; suitable absorbers
may be basedon the useofpackedtowers, vent injectorsor sparge absorbers. It can be an
advantage ifthe system selected givesa suction on the plant.
183 Caustic soda liquor is the most convenient reagent for absorption ofchlorine in waste
gases. The concentration ofcausticsoda should not exceed21% NaOH becauseofthe risk of
salt deposit causingblockages in the absorption plant. It is recommended that theflow of
chlorine is controlled or restricted by an orifice plate toan acceptable maximum, so that the
temperature risc in theabsorberdoesnot reduceits effectiveness.
184 Alternatively, for installations where there is no bulk storage for caustic soda liquorand
wherelime orsodaash is available on the site, a lime slurry or a soda ash solution may be
used.
Instrumentation
1 85 It is essential that faults aredetectedquickly. Adequateinstrumentation with alarms
shouldbe providedon the ventabsorption plantto ensurethere is a warning if equipment fails.
(a)
Lossofcirculation.
(b)
raisethe alarm.
to process;
OPERATING INSTRUCTIONS
One ofthe main risksofchlorine escapetothecnironmentis from incorrect
operation ofthe plant.Operating procedures and the selection and training of
process operators are therefore extremely important considerations for the efficient
and safeoperation ofchlorine installations. Your operating procedures needto
coer each process operation and meet legal requirements eg see references 18. 23,
and 55-60 and the standards recommended in industry guides (seeAppendix 4 and
reference 22).
190
191
(a)
(h)
MAINTENANCE,INSPECTIONANDINSTALLATION
General maintenance requirements
193 Satisfactory maintenance ofplant, equipment and instrumentation is essential to
minimise risks. Themain Regulations that you needto comply withare: COSHH
Regulations20, MHSW Regulations 18, and PSTGC Regulations (regulation 12). 23-25 The
CIMAH Regulations (to be replaced in February 1999 by the COMAH Regulations - see
Appendix 3), will also apply, depending on the size ofthe installation and the operating
conditions.
194 Youwill needto preparemaintenance schedules definingthe required frequency for
servicing, testingand inspection. These schedules shouldbe strictlyadheredto.
Appropriate recordsofthe results must be kept as required by the PSTGC Regulations
1989 and COSHFI Regulations. The needfora writtenscheme of examination (WSE) is
a separate requirement (ie regulations 8 and 9) ofthe PSTGC Regulations. Other aspects of
maintenance are indicated in paragraphs 19, 44, 51, 56-58, 71, 81, 86-89,98, 127, 136,
143, 160-162, 165, 169, 173, 174, 225, 232, 233, 237, and 255.
195 You needto ensure thatdetailedwritteninstructions covering all routinemaintenance
operations are available. These should be formally approvedand issued by the responsible
maintenance engineer. Supervisors should check regularly that work is carried out
according to these procedures. Pay particular attention to corrosion (see alsoparagraphs
167-170 ), especially where lagging is used; and to chlorine detectorsystems to keep such
monitoring equipment in effective operation.
Maintenanceofconnections
198 The inspection and replacement procedures for hosesand connections mustbe
documented in accordance with thewrittenscheme ofexamination. Records ofthe
inspections and replacements shouldbe kept. You needto:
52
(a)
(b)
(c)
Hydraulically pressure test replacement flexible connections and dry them with dry
air to a dew point lessthan -40C beforeuse.
200 You should determine the scopeofthe scheme for the examination ofthe
pressure system, with expertadvice being obtainedifrequired. The WSE must
specify all inspection and testingtechniques employed as requiredby Regulation 8
of PSTGC Regulations. The WSE reportmust contain specific details ofany
deterioration found in the vessel or vessel ancillaries (seeRegulations 9 of PSTGC
Regulations). It shouldstate which parts ofthe systemhave been examined, the
condition ofthose parts and the results of the examination.
Initial inspection and testing should be carried out in accordance with the
design code(seeparagraph88). Thefirst thorough in-service examination ofa
vessel specified for liquid chlorine duty shouldbe madeby a conipetent inspecting
authority 24 within five yearsofcommissioning and preferably within two or three
years. Thereafter the frequency offurtherthorough examinations shouldbe
determined by the inspecting authority and noted in the examination reportas
required by Regulation 9 ofthe PSTGC Regulations. The WSEcan only be
modified after an examination is complete. The examination interval should not
normally exceed five years.
201
(b)
(c)
Inspectionprocedure
Preparationthr internal inspection
Before opening the storage vessel for inspection (see also paragraph 168), the vessel
needstobe emptied ofliquid chlorine and purged to remove all traces ofchlorine.
Procedures for this should be covered by preciseoperating instructions 46 and normally
205
include:
(a)
breaking
blanking
(b)
removingthe manlid and filling the vessel with water to which soda ashhas been
addedto neutralise acidicmaterial which forms whenwater is addedto ferric
chloride - the contentsofthe vessel shouldbe stirred thoroughly throughout the
process;
(c)
siphoning offthe water and checking the atmosphere inthe vessel for chlorine and
oxygencontent;
(d) controlling internal inspection ofthe vessel in accordance with the conditions set out
in the Confined Spaces Regulations 1997
and the Code ofPractice 60 (see Appendix 3).
Re-assembly a/terinspection
thoroughly drying the vessel by dry air or nitrogen and removing and replacing joints
on all connections tothe vessel;
(c)
re-fittingthe manlid;
(d)
pressurisation ofthe vesselwith dry air and measurement ofthe dew point of theair
released;
(e)
successive pressurisation with dry air and release until the dew point ofthe air
leaving the vessel is less than -40C.
207 It is goodpracticeto overhaul all valveson the vessel at the time ofinspection.
Following overhaul they needtobe driedout and stored in individual plastic bags pending
reinstallation. Ancillary equipmentshouldalso be overhauled at each inspection. Bursting
discs should always be renewed.
54
(a)
leaktestwith dry compressed air or nitrogen at around 8 bar gauge for several
(b)
introduce a small quantity ofchlorine to the storage vessel and pressurise with
compressed air or nitrogen to around 8 bar gauge;
(c)
hours; then
If thereis flO sign ofleakage, you should leavethetank underpressure for about a
further 12 hours and then repeat the leakage test.
209 All associated pipelines, which needto have beendriedout to a dew point less
than -40C, are thengas-testedfor leakage. Anyleakingjoints needto bemade gastight before introducing liquid chlorine into the system.
Formal clearance procedures needto be established as part ofa permit-towork system 46 for:
212
(a)
(b)
55
(c)
213 The storage installation must be emptiedofliquid chlorine during inspection and
maintenance ofthe expansion vessel unless provision has been made for alternative means
ofreleaseofpressure.
(b)
Use ofnew gaskets(see paragraph 56(h)) each time connections are made to the
tanker.Compressed asbestosfibre(CAF) gaskets are not recommended for
environmental reasons.If CAF is used the discardedgaskets shouldbe collected
and disposed ofsafely, bearingin mindthat they contain asbestos.
56
(f)
ISOtankcontainer:derail 0/tile
conhiectionpoint
218 The design ofthe ISO berth should be similarto the requirements for an offloading bay for road tankers (see paragraphs 31-41) eg the ground must be level and
the area well-lit, awayfromtrafficetc. The ground surface needstobe resilient
enough to preventthe local loads from the landing legs damaging the surface or
allowing sinking. Considerspill containment (eg use kerbing, serni-bunding or
collection sumps) inthe eventofany incident. Although the frame provides
substantial impactresistance, to prevent damage to thetank and its fittings you
should providecrashprotection similarto that required for fixed tanks. Similarly,
you should providecrash protection for yourplant against inadvertent movement
during the berthing operation.
57
219 Youwill needto provide suitable flexible hose connections to connect the tank to
your process. Theseshouldbe ofsufficient length and unobstructed routing so that a leg
collapse would not stress the hose or connecting joint.
220 Youwill also needto drawup procedures for connecting and disconnecting the tank
to your process. Theseprocedures and the associated interlocks are effectively thesame as
for roadtanker unloading operations (see paragraphs 35, 39-41, 214, 215 and Appendix 6).
They needto be carried out with the motive unit uncoupled and always with the driver
present as it is thedriverwho is responsible for making/breaking and testing the integrity
ofthejoint. Barriers should be lowered whentheISO is berthed and thebarrier linked
mechanically or by softwaresequence tothe flexiblehose connection as drive away
protection. Asthe ISO tankeris not fittedwith a reliefvalve(a regulatory requirement 14)
measures must betaken to prevent overpressure from radiantheat sources such as stored
flammables, or from inert gas supplied to raisethe pressure in thetanker transferring
chlorine to the process.
You will need to agree precautions with yoursupplier to ensure there is no potential
forreverse flow from your plant into the ISOtank (seeparagraphs 224-229) and
221
implement them.
(a)
(b)
(c)
transfering the liquid chlorine to a separate tank from which it is pumped using a
pump specially designedfor use with liquid chlorine.
Methods (a) and (b) are normally themost satisfactory for customer installations.
58
Precautions
228 You shouldmakearrangements to rapidly stop theflow ofliquid chlorine
from the storage vessel in theeventoffailure at the chlorine consumingplant(see
paragraphs 35, 79, 95-97). Longliquid chlorine pipelines to consuming units may
need tobe protected against overpressure (see paragraphs 61-67).
229 You needto design the installation to prevent, or minimise the risk of suckback of aqueous solutions or process liquids from an absorption system. This
requiresdetailedconsideration at the design stage and might involve the installation
ofa non-siphoning barometric leg or a reverse flow/pressure-measuring device.
Generalguidelinesfortraining
People have legal duties to comply with the safetyprocedures associatedwith
theirwork. However, it is never sufficient simply topresume that staffwill know
andunderstandwhat to do. Positiveinstruction and training is needed. Health
andsafetytraining shouldtakeplace during working hours andshould bepart of
thejob.
Trainingis vital in helpingto preventincidentsandto minimise the consequences
iftheydo happen. Thinkabout who should be trained, in what, andto what level
ofcompetence.
Trainingwill helpemployees understandthe healthandsafetyaspects oftheir
work. Initial trainingfor new staffshouldbefollowedup with newor
refreshertraining as required.
Training must includeanyone whoworks on the site. Operators, managers, staff
230 It is essential that the personnel selected are ofadequatephysical fitness and
they shouldpass a medical examination beforeengagement. Operators needto be
capable ofeffective communication and be reliable understress conditions.
Previousexperience in the chemical or similarindustry is very desirable.
TRAINING
23 I
Youneedto ensure that site personnel are properly trained and practised in
each procedure. You should developand implement a training programmewhich
includesboth 'off-the-job' and 'on-the-job'aspects. You shouldregularly assess the
programme fir its effectiveness.
232 Off-the-job training needs to include basic information on the following:
(a)
(b)
(c)
safetyprecautions;
(d)
(e)
(f)
(g)
(h)
operational procedures;
(i)
maintenance procedures;
(j)
defectrectification;
(k)
(1)
ofchlorine;
(b)
(c)
(d)
46
special operations; eg, plant shut-down and start-up, methods ofisolation and
of
for
maintenance
and
preparation equipment
periodic
inspection;
(e)
(f)
the procedures to be followed ifa release occurs, these should include isolation and
containment ofthe releaseand emergency plans; the procedures will needto be sitespecific and cover different scalesofrelease(see alsoparagraphs 247-263);
(g)
PERSONALPROTECTIVEEQUIPMENT(PPE)
235 Chlorine is a highly toxicsubstance: acute exposure can be fatal (see Appendix I). You
thereforeneedto establish safe working practices and controlmeasures (including PPE) and
ensure that theyare understood by operatives. Safe procedures are vital where it is necessary
to enteran enclosed storage space or a room where a chlorine leak has occurred. Work in such
Guidance on how to
confined spaces is subject to The Confined Spaces Regulations 1997.
60
comply with the Regulations is given in an Approved CodeofPractice. The precautions
identified must be implemented and suitable traininggiven to operators.
236 A common soLirce of exposure to chlorine is in operations involving the making and
breaking ofchlorine pipework connections, particularly to containers. Stepsshouldbe takento
237 Respiratory protective equipment (RPE) that has beenapprovedby the HSE or
is claimed by the manufacturer to conform to a standard approved by HSE, and
whichwas manufactured before 1 July 1995, can continue to be used at work,
providedthat it is still suitable and maintained in good condition. All personnel who
arerequired to use RPE (eg, respirators, breathingapparatus, or escape breathing
apparatus) must receive adequate instruction and training in its safeand correctuse.
The RPE mustbe thoroughly examined and tested in accordance with the
manufacturer'srecommendations (typically at least onceevery month) and records
kept.20
Selectingsuitable respiratoryprotectiveequipment(RPE)
238 Where PPE including respiratory protectiveequipment (RPE) needsto be
worn, you must ensure that it is properly selected and that it provides adequate
64
66
protection. 63. When selectingRPE you shouldconsult relevantguidance 65,
20
and base your selection on the results of a risk assessment. The selected RPE
must:
(a)
(b)
The selected RPE should make theoverall risk ofinjurywhile wearing RPE as
low as reasonably practicable.
239 When selectingRPE for a particularapplication, a two-stage selection
procedure is therefore recommended:
(a)
(ii)
determine the minimum protection required from the RPE. This is done
using the equationbelow. In deciding the maximum allowable
concentration insidethe facepiece you will needto take account of
recognised exposure limits (see Appendix 1) or takeaccountofyour inhouse limits.
Minimum ProtectionRequired
For emergency escape purposes where the exposure will be lessthan 15 minutes, the maximum
allowable concentration in the above expression is the Short-Term Exposure Lmit (STEL) (see
Appendix 1). Now compare the Minimum Protection Required value with the Assigned
ProtectionFactors (APF) indicated in HSG5366and identify a selection ofequpment. (APFs
shown in HS(G)53 havebeenpublished by the British Standards institution ).6 These APF
figures are a guide, not a hardand fast rule. Indeed, it should be recognised that protection levels
belowthe APF are possible whenRPE is unsuitable for thetaskand is not suited to the wearer
and the environment. Where advice given in HSG53 is properly takeninto account, it is possible
to achieve protection at or above the published APF values. Youmay use higherAPFs ifyou
have good quality information (eg satisfactory face-fit results forthosewearing RPE) to
demonstrate that theyapply in your workplace conditions and to the selected RPE. Youcanuse
the AFF for the equipment selected to estimate concentration insidethe facepiece.
Concentration inside the facepiece
Note: NominalProtectionFactors (NPF)values have been used in thepast, for iclentij5'ing aselection
ofequipment. This procedureis no longer validbecauseworkplace studies haveshown that mani'
wearersmar notachievethelevel ofprotectionindicatedby NPFs.
(b) The next stage isto take accountofthe factors detailedin paragraphs36-47 of
HSGS3 to help narrow down the choice. Alwaysinvolve the wearers inthe selectionprocess,
and wherepossible provide them with a choice ofsuitable RPE. This will helpto ensure that it
is suited to them individually, and increase the chances that it will be acceptedand worn
correctly.
Where there is doubtaboutthe choice, you needto confirm with the manufacturer or supplier
that thechosen equipment is suitable for the task and the conditions in which it istobe used.
They have dutiesunderthe Healthand Safetyat WorkAct etc 1974 to provideinformation on
thelimitations and capabilities oftheir RPE.
240 At somechlorine installations it is common practice for personnel to carry halfmask
respirators fitted with suitable filters (eg: type and class:
B 1; colour: grey) for protection againstchlorine. The
respiratorhas tobe wornfor each operation, or be 'at the ready' to be put on in case
ofneed. A respirator(eg a maskfittedwith a filter or canister) is not suitable for use
in atmospheres which are immediately dangerous to life or health. In other words,
respiratorsare not suitable for operations where there is a potential for a significant
releaseofchlorine gas. In these circumstances a suitable breathing apparatus (BA)
shouldbe worn.
242 Filters havea shelf-life specified by the manufacturers beyond which they
shouldnot be used. Oncefilter-canister seals have beenbroken, filterlife will
depend on usage, contaminent concentrations, breathing rateetc. Your risk
assessment, combined with information from the filter manufacturer, will determine
the useful life ofrespiratorfilters; yourdecisionsneedto be communicated to the
wearers. Once unsealed, filters should not be stored for re-use, but they may be used
over a numberofconsecutive days, providedthey havenot been exposed to
concentrations of chlorine similartoor abovethose they are providedfor.
244
Note: Further guidance will be available when the COMAII Regulations come
into force in February 1999.
247 You needto inform the appropriate Fire Authority and Police Force of the
presence ofchlorine at your site. You shouldalso involve them and your chlorine
supplier at an early stage whendeveloping and updating your emergency plan and
procedures. Your emergency arrangements shouldbe basedon a risk assessment
and include procedures on how gas releases maybe dealtwith safelyby site
69, 70 Your
personnel and on whetherto call for assistance from beyondthe
risk assessment shoLild also address fire safety ofthe process or installation and
possible impacts from neighbouring sites. General fire precautions should
comply
with the requirements of the FirePrecautions (Workplace) Regulations l997.
site.'
249 Each installation needs to have means ofwarning all workers that a gas escape
has occurred. A wind direction indicator, mounted in a highly visible location,
needs to be provided to help personnel decide the bestdirection in whichto escape.
The appropriate actionto hetaken following a gas escape warning shouldbe
defined in written mstructions, and appropriate training given.
25() For a minorgas escape, you mayonly need to plan simple actions. In other
circumstances however, a further system ofspecialwarnings maybe required,
which initiatesthe emergency plan and, ifnecessary, the off-site emergency plan.
The first call for assistance shouldbetothe eniergency servicesfor incident control
and rescue, and then to Chlor-Aid, through your supplier who will offer advice on
how to deal withthe release. UnderChlorAid the chlorine producers and suppliers (see
Appendix 4) collaborate in dealingwith chlorine emergencies at bulk installations 71
throughout the UK.The arrangements are outlined in a booklet publishedby the CIA
underthe chemical industry'sResponsible Care initiative.
Arrange regularpractices ofthe emergency plan. Someoftheseshouldinvolve the
emergency services, whowill advise on a suitable frequency.
251
EMERGENCYEQUIPMENT
252 Yourrisk assessment should considerthe extent, type, and location ofthe emergency
equipment, including theneed for chemical protection suits whichprovidetotal
encapsulation. These can be compressed airline supplied full suits or full protective suits
worn over self-contained breathing apparatus (SCBA).
SCBA with fullfacemask confoniiingto BSEN 137 (SCBA) 72 or airline BA
confonmng to BSEN 139 has an APF of2000 (butsee paragraphs238-246). Selfcontained equipment will supply air for up to about 40 minutess (seethe manufacturer's
details). Thesesets are providedwith a warning systemto alert thewearerto leavethe
contaminated areawhenthe air cylinders are becoming empty. Compressed airline breathing
apparatus providesthe same protection withouta time limit, but doesrestrict freedom of
movement in search and rescue operation.
253
CONTROLOF LEAKAGES
256 Local alarmstationsto provide earlywarning of
chlorine escapesare an essential link in the emergency
procedure. The use ofchlorine detectors and alarms is
coveredin paragraphs 113-118. Localalarm stations
(push-button type preferred) should be located at
strategic pointsnear chlorine storage installations;
generally two alarm stations on convenient escape
routesfrom the chlorine unloading terminal! storage tank areaare sufficient. The local alarm
stationsmay actuate the worksemergency alarm directlyor indirectly by raising an alarmin
theemergency control centre and the main control room. Preferably in largeworks the local
68
alarm station should actuate a distinct local chlorine alarm to warn people offfrom
theaffected area.
Releasesinside buildings
Ifthe spill is indoors and contained by the useofsand or a bund it will rapidly
coveritself with a coatingofslushychlorine hydrate and a cold vapour layer. Such
a stabilised spill shouldbe coveredwith a plastic sheet(seeparagraphs 258 and
259). Fora severe leak,possiblyarising from a failure ofpipework, the chlorine
buildingwill providesome delay to the release of the gas to the open air, provided
vents and apertures areclosedor sealed. Thiswill give moretime forthe technical
staffand management to identify and deal withthe source ofthe release. In
dispersing the contained release from a chlorine roomit is stillessentialto consider
the off-site consequences and it maybe necessary to sound the off-site alarm(when
fitted)to alert people to go indoors and remainthere. It is for the emergency
services to consider clearingpeoplefrom the area immediately downwind of the
installation after such a release.
260
about the threshold concentration for thecloud tobe visible),personnel dealingwith the
release should take additional precautions and shouldwithdraw to a safe area as soon as they
are aware that they are breathing contaminated air.
70
D1
TOXICITY
aboe.7 Irritationof the mucousmembranesof the eye and nose, and especially
of the throat and lungs, is caused by exposureto chlorine at levels ofaround 1-15
FIRSTAID
5
When liquid chlorine comes into contact with the skin or mucousmembranesii can
produce seriousburns which need to be treated by a medically competent person. People
who have inhaled chlorine gas should be moved as quickly as possible into 'fresh air', laid in
a resifLil position with thehead and chest raised, and kept warm. It is essential that
qualified medical attention is obtained quickly, as serious symptoms may develop up to 48
hours later. Anyonewho has been affected by chlorine gas should be examined locally by a
medically competent person or sent to hospitalby ambulance.
(a) if chlorine has affected the eyes. they shouldbe irrigated with plenty of clean
(preferably rap) water:
(b) contaminated clothingshould be removed
washed with plenty ofwater
(c)
i
Chlorine is a grecnish-yel1ogas at ambient temperatureand pressure.
supplied commercial1 as a liquid under pressure.
It is
3
Traces of dissolved gaseous impurities in chlorine arenot normallysignificant
for most applications moisture contenthoweveris extremely important because
of the corrosive nature of wet chlorine.
Physicalproperties
Atomic weight
35.46
Molecular weight
70.91
Density liquid
1468 kg/rn3 at 0C
1410 kg/rn3 at 20C
gas
-34.05C
-101.6C
144C
77.1 barsabsolute
I volume of liquid chlorine = 463 volumes of chlorine gas at 0C and I bar absolute
1
kg of liquid chlorine
I bar absolute
The variationof the vapour pressure of liquid chlorine with temperature is given in Figure
A2.l.
Thermalproperties'
Specific heat (liquid chlorine between 1C and 27C) 0.236 kcal/kg!C
Specific heat (gas at constant pressure at 6.9 bars absolute or less and between 1C and
27C) 0.11 3 kcal/kg/C
Ratio of specific heat at constant pressure to specific heatat constant volume 1.355
Latentheat of fusion
21.6 kcal/kg
63.2 kcal/kg
at 20C)
0.002! per C
This coefficient is sufficiently largeto result in excessive pressure should liquid chlorine be
trapped in pipework between two closed valves with no gas space.
Heat of reaction of chlorine gas with sodium hydroxide liquor 348 kcal/kgof chlorine.
6 While the above data give a general summaryof the physical and thermal propertiesof
chlorine, more detailedinformation is needed fiir use in plant design calculations.
19
18
U)
U)
17
16
K!)
15
14
13
12
11
10
9
8
7
6
5
4
3
(1
60
50
40
30
20
10
20
30
40
50
60
Temperature C
Temperalure C
gramsofchlorineper litreoJwater
10
15
9.97
8.5
20
7.29
25
6.41
HCI + HOCI
chemicalproperties
Dry chlorine at ambient temperaturesreacts directly with many of the elements
producing chlorides both of non-metals (eg sulphuror phosphorus)and of metals (eg
iron in a finely divided form, aluminium or titanium).Dry chlorine at ambient
temperaturedoes not attack steel, copper or nickel, but these metals are attacked at
highertemperatures. Steel combineswith dry chlorine above 200C and, since the
reaction is exothermic, the rate ofreaction may increase rapidly. Reactionwith nickel
does not take place until the temperatureexceeds 500C.
10
II Traces of moisture in chlorine lead to rapid corrosion of steel, copper and nickel.
12 Titaniumis resistantto wet chlorine between 15C and 100C but reacts violently
with dry chlorine and shouldnot be used: but see paragraph 18.
LEARNINGFROMINCiDENTS
20
__
Si
'0
[I
L.J flfl
I
The basis of health and safety law in the UK is the Health and Safety at
Work etc Act 1974. This sets oUt general duties which employers have towards
employees and members of the public, and thosethat employees have to
themselves and each other. These duties are qualified in the Act by the principle
of so far as is reasonably practicable' ie the extent ofthemeasurestaken to
avoid or reduce a particularrisk to health and safety needs to he balancedagainst
the time, trouble, cost, and physical difficulty involved. This balancing process83
is often referred to as making risks as low as is reasonably practicable'(ALARP).
cover.
(a)
have a written, up-to-datehealth and safety policy if you employ five or more
people;
(b) carry out a risk assessment (and if you employfive or more people, record the main
findings and yourarrangementsfor health and safety);
(C)
(d) display
notify certain types of injuries, occupationaldiseases and events (see paragraph 23);
and
(g) consult employees and any appointed union safety representatives87 on certain
issues, such as any changes which might affect health and safetyand any
information,instruction and training which has to be provided.
6 The ALARP principle and the need for risk assessment enables the Health and Safety
Commission, where appropriate,to make Regulations in a goal-setting form: ie setting out
what must be achieved, but not how it must be done. Sometimes it is necessary to prescribe
in detail what must be done and set absolute standards.
THENOTIFICATIONOFINSTALLATIONS HANDLiNGHAZARDOUS
SUBSTANCES (NIHHS)REGULATiONS 1982'
These Regulations implement a notification scheme for installations with inventories
greater or equal to specified quantities(10 tonnes for chlorine). Notification is to the Health
and Safety Executive via your Local Area Office (see Appendix 4). Under NIHHS the
8
80
81
(a) general duties on all operators subject to the Regulations: to notify the competent
authoritiesof their activities, to takeall measures necessary for the prevention and
mitigationof major accidents, to prepare a major accident prcvention policy, and
report major accidents
(b) top-tier duties on operatorsof sites where the quantitiesofdangeroussubstances
exceed the higher thresholds. These operatorsmust, in additionto the duties in the
above paragraph,submit safety reports,prepare and test emergency plans and provide
information to the public.
In thecase of chlorine the thresholdquantities are 10 tonnes for the generalduties and
25 tonnes forthe top-tier duties. Application depends solely on the presence or anticipated
presence of the thresholdquantitiesof dangeroussubstances, including dangerous
substances which might be generated in the course ofan accident due to loss of control of
an industrial chemical process, with no differentiation between storage and processing. The
general duty for operatorsto take 'all measures necessary for the prevention and mitigation
of major accidents' is similar to theCIMAH Regulations which require manufacturersto
'take adequate steps to prevent ... major accidents... and limit their consequences ...'. In
judging how this duty should be complied with in practice. the competentauthoritieswill
base their view on whetherrisks have been reduced to ALARP. The main new
requirements are:
All operators within the scope of the Directive must produce a major-accident
prevention policy (MAPP) and ensure that it is properly implemented to guaranteea
high level of protection for humansand the environmentby appropriate means,
structures, and management systems.
82
Safety reports (top-tier sites only) have to be made availableto the public, but
companies can request that certain information,including commercial and
personal confidential information,is withheld.
'
Jr
83
(a) assess the risks to thehealth and safety ofyouremployees and non-employees
arising in, or from, youractivities and review the assessment when there is
significant change. Recordsof significant findings of the assessment must be kept
where there are five or more employees;
(b) plan, organise, control, monitor and review the preventative and protective measures
taken as a result ofthe assessment:
(c) appoint any competent person(s) needed to help you comply with legal obligations.
for example, when havingpressure systems examined:
(d) set out what should be done in case of serious and imminentdanger at your
premises, such asthe spillage ofan appreciableamount of chlorine:
(e) tell employees about the risks and precautionsinvolved in their work; and
(f)
You must:
84
(b) have chains, ropes. lifting tackle, hoists and lifts thoroughlyexamined every
six months by a competent person (often employed by an insurance
company)and obtain and keep the report;
(c) ensure tests and thorough examinations ofcranes are carried out before
they are first used and obtain a certificate of test and examinationspecifying
safe working loads. Periodic thorough examinations at least every 12 months
are also required, for which a report should be obtainedand kept.
HSE guidanceis available.90
Vote: These Regulations 'ill he revokedand i'eplacedin December 1998hi' the Litiing Operations
(01(1 lifting Equipment LOLER) Regulatiom (SI 1998/2307i. Guidance sill he publishedin an
4pprored (ode of Practiceon Safe Ue of Lifting Equipinesit. TheProvLdon and Ue of Work
Lqu,pmentRegulations1098 (see paragraph19) also app/c to ff11 ng equipment.
(a) avoid the need for hazardous manual lifting and handling
practicable;
if reasonably
(b) assess the risk of injury from any hazardous manual lifting and handling
which cannot be avoided;and
(c)
Employees must:
(a) follow safe systems of work laid down by their employers;
85
exposure.
Employers must:
where prevention is not reasonably practicable, control exposure by, for example,
isolatingor enclosing the process or, if this is not reasonably practicable, local
exhaust ventilation;
(1)
(a) provide work equipmentthat is suitable for the purposefor which it is used or
supplied;
86
(b) take steps to ensurethat the equipmentis not used under conditionsfor
which it is not suitable;
maintainwork
(c)
equipmentin an efficient workingorder and good repair and
that any maintenance log is kept up to date:
(d) provide peoplewho use work equipmentwith:
(i) clear health and safety information and, where appropriate,written
instructions; and
(f) providesuitable and sufficient lighting at any place wherea person uses work
equipment;
(g) ensure that work equipmentis marked in a clear and visible manner with
appropriatehealth and safety information and warnings and
(hj ensure that any warning device is unambiguous and easily perceived and
understood.
\'ote: These Regulations icill he revokedand reenactedin December 1998. The newPLIWER
Regulations (SI 1998/2306) include neii provisionsbr mobilework equipment.
THECONFINEDSPACES
REGULATIONS 199759,60
20 These Regulations apply when it is necessary for workersto carry out work
in a confined space including a chamber, tank, flue or a similar space, which, by
virtue of its enclosed nature, gives rise to a 'foreseeable specified risk'. In the case
of chlorine installations the most likely foreseeable specified risk is 'the loss of
consciousness or asphyxiation ofany person at work arisingfrom gas, fume
vapour or the lack of oxygen'. The Regulationsprohibitthe entry into a confined
space for the purposeof carryingout work where it is reasonably practicable to
carry outthe work by other means. In other situations(for example, the isolation
of a leak in a chlorine room) they impose requirements on employers including
theneed to:
(a) establish safe systems of work for entry to, or carrying out work in, or
leaving a confined space that rendersthe activities safe and withoutrisks to
health:
87
(b) establish suitable and sufficient arrangements for the rescue of people in the
confined space in the event of an emergency
(c)
THEPRESSURESYSTEMANDTRANSPORTABLE GASCONTAINERS
REGULATIONS 198923,24,25
These Regulations impose requirements for pressure systems containinga gas or
liquefied gas at a pressuregreater than 0.5 bar above atmosphericpressure. They impose
requirements on designers. suppliers of pressure systems and on employers of people
who modify or repair such systems. Tile intentionofthe Regulations is to prevent the
risk of serious injury from stored energy as a result ofthe failure of a pressure system or
part of it. A measure ofthe stored energy is given by multiplying the system pressure
(bar gauge) and volume (litres). A pressure system is:
21
(a)
(b)
(c)
The transportablegas containeris not part ofthe system. Employers must ensure that:
(a) all plant and systems are designed. constructedand installed to prevent danger;
(d) there is a written scheme for examination54 ofcertain pressure vessels, such as
chlonne vaporisers, fittings and pipework, drawn up by a competent person;
88
(e) examinations as set out in the writtenscheme are carried out by a competent
person; and
(f) records are kept.
Note: The transportable go container ( TGC') part ofthese Regulations 'as i'c'rokedin /996 and
inc'o;porated into The Carriage of Dangerous Goods (Classification, Packaging and L/'Iling) and Crc
of Transportable Pressure Receptacles Regulations /996. These PSTGCRegulations i/I be replacedin
jVorenilier199') hi ThePrescoreEquipmentRegulationsand The PressureSi'stems Sii/iii' Regulations.
(a) provide suitable PPE free ofcharge to protect employees against risks which
have not been controlled by other means;
(b)
(c)
(d) maintain the PPE provided in cleanand efficient working order and provide
suitable storage for it when not in use; and
(e) give information,instructionand training.
Employees must:
89
THEREPORTINGOFINJURIES,DISEASESANDDANGEROUS
OCCURRENCESREGULATIONS (RIDDOR)1995 91,92,93
23
These apply to all employers and self-employed people and cover everyone at work.
(d) report within seven days (on form F2508) injuries which keep an employee offwork
or unable to do theirnormaljob for more than three days;
(e) report certain diseases suffered by workers on form F2508A; and
(f) keepdetails of reported incidents.
ENFORCINGTHE LAW
24 Health and safety laws relatingto your firm will usually be enforced by a health and
safety inspector from USE. In somecases, eg a public swimming pool, health and safety
law is enforced by the local authority.
25 Inspectors may visit workplaces without notice but you are entitled to see their
identification before they come in. Theymay want to investigate an accident or complaint,
or inspect safety, health and welfare at your premises. They have the right to talk to
employees and safety representatives, take photographsand samples, and even in certain
cases to impounddangerousequipment. They are entitled to co-operationand answers to
questions.
26 Inspectorswill be aware of the main risksin handling chlorine and will giveyou help
and advice on how to comply with the law. Ifthere is a problem, they may issue a formal
notice requiring improvements or, where serious danger exists, one which prohibits the use
of a process or equipment. Inspectors have powers to prosecutea firm (or an individual) for
breaking health and safety law.
90
CHLORINEPRODUCERSAND SUPPLIERS
Hays Process ChemicalsSandbach, Cheshire CWI I 3PZ
ImperialChemicalIndustries plc, ChiorChemicalsP0 Box 13, The Heath,
Runcorn, CheshireWA7 4QF
RhodiaLtd Staveley, Chesterfield S43 2PB
The Associated Octel Co Ltd P0 Box 17, Ellesmere Port, Wirral,
CheshireL65 4HF
BOC Ltd Special Gases 24 Deer Park Road, London SWI9 31JF
(Note: BOC supplies only cylinders.)
HSE
You can find details of your local HSE office in your local telephone directory or the
currentedition of HSE35 The Healthand Safbtv Executive. Working withemployers,
available from HSE Books.
You can find details of USE Booksand HSE's enquiry service on the inside back cover
of this booklet.
ChlorineInstituteInc. 2001 L Street,NW, WashingtonDC 20036 USA
EuroChior Avenue E Van Nieuwenhuyse 4, Box 2. B-I 160 Brussels, Belgium
Tel: +32267672 II; Fax: +322 676 7241
Euro Chior publishes a wide range of relevant reports.22 The new series (AP) of
pamphletson learning fiwin accidents is essential reading(eg see reference 82).
UK suppliers ofEuroChior approvedglobe valves
Descote Ltd 19 Sandy Lane, Weston Point, Runcorn, Cheshire WA7 4EX
Tel: 01928 565666; Fax: 01928 565646
BritishStandardsInstitute
BS4275: 1997
94
andbars
Ui3]c
I
Bulk chlorine installations should preferably he located in the open air.
Sometimes it may be appropriate to locate the installationin a building.
The building may enclose the entire installation or part of it. eg the manlids,
valves, associated pipework,gauges and other equipment, leavingthe tank itself
2
outside.
3
The advantages, disadvantages and consequent requirements for outside or
inside installations are listed in paragraphs 4-8.
OUTSiDE INSTALL4TIONS
4
(a) leakagesare not confined, so the source of leakage is more safely accessible
from upwind:
(b)
it is easier to identify the point of leakage and take immediate local corrective
action:
(c) access
(a) leakages may be detected at an early stage only from downwind positions;
(b) small leakages, particularly thosearising from corrosion,can develop
unnoticed;
95
(c) maintenance and repair work may have to be carried out in adverseweather
conditions;
INSiDE INSTALLATIONS
7
(a) valves and other equipmentare protectedfrom rain and snow, and provided
the buildingis kept dry, there will be less risk of corrosion;
96
(e)
(a) following a medium or major leak, emergency access may have to be made
(b)
(c)
(a)
JL
iVote: This typicalprocedure assunies 1/ia! the storage tanks and avvociateditems of
equipment hine sate Forking pressure of at least 12 bar gauge. If this is not the case,
then steps isilIneed to he taken (eg adjust theair sssteni pressure, and relief va/ic
settings) to el/sure that the saf' working limitsfor the storage vessels and delivery
vvvtein are not exceeded. It is important that more detailed andsitespe(i/ic procedures
are developed and agreed hj' the customer, Ijaulier and chlorinesupplier.
Action by
Actionneeded
Joint
Customer
Driver
Driver
and employ
the drive-away protection. A variety of techniques may be used,
eg interlocks to the tanker brakes, wheel chocks, and the
removal of the vehicle ignition key to a controlled location.
These are in addition (see paragraph 7 below) to any drive-away
protection barriers and any interlocks to shut down the
discharge should movement of the vehicle or should chlorine be
detected (see main text, paragraphs 39-41).
Safety advice forbulkchlorineinstallations 99
Driver
In signing these notes the customer accepts the responsibility that there is
sufficient space available in the storage tank to receive the full load from
the road tank and that the installation is fit and ready for the discharge
to proceed.
Will tell the plant operator the weight of chlorine in the tanker so
that the operatorcan determine where the final reading will be on the
weighing machine dial or load cell indicator.
Driver
Customer
Will ensure that any warning notices are displayed and barriers are
erected, and will operate any safety interlocks associated with the road
vehicle berth.
Customer
Where there are two or more tanks the customer will determine which
tank is to receive and check that the storage tank cannotbe overfilled.
The pressure on the tank before starting the discharge should not
normally be greater than 5.9 bar gauge but in very hot weather it may be
8
higher.
Customer
The customer will ensure he,ftredischarge that the vent valve on the
stock tank filling pipe is closed. When fitted, the barrier mechanical
interlock key is used to activate the control panel sequence for the
discharging operation and release the off-loading arm.
Driver
tanker can he s/ow/v openedto fill the delivery line: tile pi-essure
observed will be the pressure on the road tanker. Alternatively.
and oilly wllen the driver is satisfied with the integrity of the
connections, the instrumeilt air connections are made which will
allow tile discharge valves to be operated. This may also
activate a brake interlock wilich is integral with the custonler's
shutdown systenl.
Joint
1.7
Joint
Joint
tile pressure.
joint
16
the padding air supply valve. Vent excess pressure from the
tanker via the vent valve to the scrubber. The driver then closes
the padding air inlet to the tankerand tIle liquid chlorine outlet
from the tailker, and disconnectstile operating air leads to them
so the tanker valves cannot be reopened. The connecting pipe
for padding air can now be vented and disconnected and the
tanker padding air connection capped. The operatorcracks
open the vent valve on tile liquid chlorine delivery line to the
stock tank filling pipe. When the pressure gauge on the liquid
Safetyadvice for bulkchlorineinstallations 101
chlorine delivery line shows zero (and any hoar froston the vent valve
has begun to disappear) the operatorcloses the valve on the chlorine
delivery line at the tanker dischargepoint. Close the delivery line vent
valve.
Customer
17 Crack open the vent valve on the stock tank for about one minute in
order to check that the level of liquid chlorine in the tank is below the
bottom of the vent dip pipe (no frosting should appear). This operation
also vents non-condensable gases. Check that the pressure in the tank is
reasonable for the temperature of the chlorine. The storage is now
isolated from the discharge line to the scrubber and the delivery line is
purged by pressurising and depressurising(open vent valve and close it
when pressure gauge shows zero) with dry air for a minimum of live
cycles. The operatorcan now shut down the air compressor if it is not
needed for other operations.
Driver
18 Wearing a gas mask, disconnect the liquid discharge pipe from the
tanker, replace the sealingplug to prevent the entry of moist air, and
swivel back to the staging. Tell the plant operator that the vent can be
closed. The short connecting pipes from the liquid and air valves can be
disconnected, both valves capped and the tanker dome securely fastened.
The RPE can now be removed.
Customer
Driver
19
to sign the advice note and consignment note after the words all
operations connected with the discharge of the road tank have been
completed satisfactorily'. Handone copy to the responsibleperson.
On leaving the works weigh again on the site weighbridge.
VERTICAL TUBEBUNDLE(TYPE 1)
lb Steam bayonet
Chlorine qas
Chlorine gas
S!eam
Liquid
chlorine]
Steam
----
I iqidctoeire
103
(a)
(h)
(c)
Chlorine gas
Liquid chlorine
Waterbath
Electric heater
2 Coil in bath
(a)
-
operate;
Hotwateroutlet
Hotwaterbath
L>(J
Chlorine gas
(b)
(c)
(d)
Coil
Liquid chlorine
Sted
- -
impurities;
104 Safety advice for bulkchlorineinstallations
(b) external corrosion of the iLibe can easily occur, especially near the liquid
surface;
(c) irregular internal erosionof the coil may occur: and
(d) internal inspection and cleaning of the coil is difficult.
CONCENTRICTUBEUNITS(TYPE3)
Chlonne gas
(a)
(h)
(c)
Steam
corrosion allowance;
Condensate
Liquid chlorine
(d)
(e)
(a)
(b) limitation
(c)
4 Kettle-type evaporator
Liquid chlorine
Chlorinegas
Control to inlet
Level
measuring
device
-T
Heating medium in
[J
////
LiquidCl2
medium out
operation is stable, providedthat either the level of chlorine in the kettle or the
pressureof chlorine fed to the vaporiser. is controlled.
(c) operation can result in concentrationof nitrogen trichloride; the purging process
required to i-educethis hazard may be difficult to carry out on consumerpremises:
106
/7, 70
I
The works shouldhave an on-site emergency plan for dealing with a major
chlorine release. The plan should include instructions for the emergency team and
for non-essential personnel, and for liaison with the emergency services. The
emergency plan should be based on paragraphs247-263. Your plan will depend on
the results ofyourrisk assessment and the need to comply with health and safety
legislation, eg section 3 of the HSWAct.2The following paragraphs contain some
elementsof a plan.
(h) investigating and assessing the source and extent of the chlorine release;
(c) alerting all personnel on-site or in neighbouring premises and the emergency
services;setting up emergency control centres, assessment by key personnel of
the incident and consequentemergency measures on and off-site;
(d) methodsfor controlling
thechlorine release;
(e)
(1)
(Ii) methods for assessing whether corresponding actionsare advisable for people
off-site and, in particular,liaison with the managerat any adjacent underground
workings where chlorine could enter the ventilation system: advice to emergency
services on the direction,spread and concentration ofthe gas cloud; and
(i)
first aid to on-site casualties, and arrangements for evacuation where advisable and
practicable; advice to ambulance service on routes to use.
Since each installation will have its own special features, a detailed plan relating to the
particLilarplant will be required. Local management should be responsible for preparation
of the plan which shouldhe developed iii co-operation with the local authority, the police,
fire, hospitaland ambulanceservices, andthe chlorine supplier. Specific duties are laid on
some of these people by the Control of Industrial Major AccidentHazards Regulations
1984. These will he superseded by the requirements of the COMAH Regulationsin 1999.
3
EMERGENCYCONTROL CENTRES
4 Basic requirements for a satisfactory system to deal with
serious escape ofchlorine are outlined as follows:
(a) two control centres should be providedso that, in the event of a gas escape,
operationscan be controlled from the centre which is least affected under
prevailing atmospheric conditions:
(b) each centre should be providedwith a separate external telephoneline, as well as
withconnectionsto the factory's external and internal telephone system;
(c)
(f)
(g) equipmentand information are needed to assess the likely extent of the gas
cloud for various sizes of release and variousweatherconditions.
The emergency plan should specify in advance the individuals and deputies
responsible for the action necessary to deal with the emergency.
5
SITEEMERGENCYTEAM
6
There shouldhe a trained emergency team with the following key personnel:
(a) Site incidentcontrol/er- the senior person on-site responsible for the direction
of on-site operations
(b) Sitemain control/er- normally the works manager or deputy with overall
responsibility for the operation ofthe emergency plan, maintaining close
liaison with the police and lire services, and for advising them on the risk
and
(c)
Otherkeypersonnel - including:
(i)
(ii)
the team responsible for the search for casualties, for first aid and for the
control of evacuation.
7
The police will be responsible for dealing with members of the public who
might be affected by the chlorine escape they will need to be advised ofthe size
and expected duration of the release together with the areas which could be
affected, to allow the police and the site main controller to agree whether the
pLiblic should remain indoors or be evacuated.
EMERGENCYASSEMBLY AREAS
8
1.
Safe haiidlingof ciiloriiie f/on! (1/71/115(1/id ci'linders HSG4O I ISE Books 1999
ISBN 0 7176 16460
CouncilDirective96/82/ECControlofmajor-accidenthazards involving
dangeroussubstancesOfficial Jofthe EC No LI0/40 CEC January 1997
10
11
12
13
14
15
16
17
18
19
20
21
22
23
br
2169 HMSO
24
25
112
26
27
The Carriage ofDangerous Goods hi; Rail Regulations /996 SI 1996/2089 HMSO
28
29
30
31
32
33
Specification
BS4882: 1990
35
Circularflanges
36
37
38
Specification
Polytetrafluoroethylene
42
Specfication
43
44
1996/0341
HMSO
45
Saf'tv signs and signals. The Healthand Sak'tv(Safe/v Signs and Signals) Regulations
1996. Guidanceon Regulations L64 HSE Books 1997 ISBN 0 717608700
46
47
The
fr
48
49
50
51
GEST 76/55 Maximum levels ofnitrogen trichloride in liquid chlorine 1990 Euro Chlor*
52
53
54
55
56
1992 Guidance on
58
59
60
61
62
63
64
ISBN 0717604152
65
GEST 92/171 Personal protective equipment for use with chlorine 1995
Euro Chlor*
66
67
BS4275: 1997
68
Prepared
69
70
71
72
73
74
75
76
ISBN07176 15766
77
78
79
GEST 89/145 Guidelines for medical management ofchlorine exposure (3rd ed) 1995
Euro Chlor*
80
81
82
83
84
Price listHSEBooks(publishedannually)
85
86
Health andSafety Law. Whatyou shouldknow (poster) HSE Books IBSN0 7176 1380
87
The Health and Safety (Consultation with Employees) Regulations 1996 SI 1996/1513
ISO
88
89
90
91
ACOP
ALARP
ANSI
APF
ASME
BA
BS
CABA
CAF
CEC
CIA
CIMAH
COMAH
COSHH
DTL
EA
EEC
EU
HAZOP
HMSO
HSA
HSE
I-ISR
HSW
ISO
LOLER
ApprovedCode of Practice
As Low As Reasonably Practicable
American National Standards Institute
Assigned ProtectionFactor
American Society of Mechanical Engineering
Breathing Apparatus
British Standard
Compressed Airline Breathing Apparatus
Compressed Asbestos Fibre
Commission of the EuropeanCommunities
Chemical Industries Association
LPA
MHO
MHSW
NIHHS
OEL
OES
OJ
PPE
ppm
PSTGC
PTFE
PUWER
RIDDOR
RPE
SCBA
SEPA
SI
Local PlanningAuthority
Manual HandlingOperations(Regulations)
Management of Health and Safety at Work (Regulations)
Notificationof installationsHandlingHazardous Substances
(Regulations)
Occupational Exposure Limit
Occupational Exposure Standard
Official Journal (of the European Communities)
PersonalProtective Equipment
Parts per million (by volume)
Pressure Systems and TransportableGas Containers (Regulations)
Polytetrafluoroethylene
UK
Statutory Instrument
Scottish Office, EnvironmentDepartment
Short-TermExposure Limit
TransportableGas Container
The StationeryOffice
United Kingdom
UPYC
WSE
SOED
STEL
TGC
TSO
1/99
C40
HSE
BOOKS
MAIL ORDER
HSE priced and free
publicationsare
available from:
HSE Books
P0 Box 1999
Sudbury
Suffolk C010 6FS
Tel: 01787881165
Fax: 01787 313995
RETAIL
HSE priced publications
are availablefrom
good booksellers
HEALTH AND SAFETY ENQUIRIES
HSEInfoLine
Tel: 054! 545500
or write to:
HSE Information Centre
Broad Lane
Sheffield S3 7H0
HSEhome page on the World Wide Web:
http://www.open.gov.uk/hse/hsehome.htm
14.00
ISBN 0717616452
9 780717 616459
HSG28(rev)
08c.