FUNDAMENTALS OF EARTHMOVING
Earthmoving Job Planning requires
Dividing the job (Breaking the Job Down) into manageable tasks
based on different types of Machines
Calculating task durations - based on machine productivity, where
machine productivity is based on
Machine Performance i.e. machine capability, and
Soil behaviour
Earthmoving task duration calculations are approximate. Task
duration calculations are often a check on the judgement of an
experienced person.