Beruflich Dokumente
Kultur Dokumente
Construction, Engineering and Management Department, Faculty of Engineering, Zagazig University, Zagazig,
Egypt; presently at Department of Building, Civil & Environmental Engineering, Concordia University, 1455 De
maisonneuve west, Montreal, Quebec H3G 1M7, Canada
2
Construction Division, School of Civil Engineering, Purdue University, West Lafayette, IN 47907, USA
3
Construction Engineering and Management Department, Faculty of Engineering, Zagazig University, Zagazig, Egypt
Received 24 May 2004; accepted 23 March 2005
Current research focuses on assessing productivity, cost, and delays for concrete batch plant (CBP) operations
using Artificial Neural Network (ANN) methodology. Data were collected to assess cycle time, delays, cost of
delays, cost of delivery, productivity, and price/m3 for the CBP. Two ANN models were designated to represent
the CBP process considering many CBP variables. Input variables include delivery distance, concrete type, and
truck mixers load. Output variables include the assessment of cycle time, cost of delays, delivery cost,
productivity, and price/m3. The ANN outputs have been validated to show the ANNs robustness in assessing
the CBP output variables. The average validity percent for the ANN outputs is 96.25%. A Time-Quantity (TQ)
chart is developed to assess the time required for both truck mixers and the CBP to produce a specified quantity
of concrete. Charts have been developed to predict cycle time/truck, delays/truck, cost of delays/truck, cost of
delivery/m3, and price/m3.
Keywords: Artificial Neural Network (ANN), productivity, cost analysis, cycle time, modeling, concrete batch
plant (CBP), truck mixer
Introduction
Artificial Neural Network (ANN) methodology is
applied to model the concrete batch plant (CBP)
operation and to assess productivity, cost, and delays.
This assessment procedure faces many problems due to
the large number of factors that affect the CBP
operation. Some of these factors can be summarized
as follows: concrete type; delivery distance; transit
mixer capacity; delays in the construction site; delays in
the CBP site; traffic conditions; and road conditions.
Therefore, the price of a concrete unit, which is
produced by the CBP, is affected by the abovementioned factors. Common practice prices out the
concrete based upon materials price plus overhead and
profit without considering the transporting distance,
delays in both construction and CBP sites, traffic
*Author for correspondence. E-mail: zayed@bcee.concordia.ca
840
Zayed et al.
841
distance (seven variables), concrete types (four variables), and truck load.
The output layer of the ANN designated model
includes: (1) cycle time elements (loading, hauling,
unloading, and return times); (2) delays (delay inside
the plant and delay in construction site); (3) cost of
delays; (4) price per cy (m3); and (5) cost of delivery
per cy (m3). Consequently, the number of output
neurons is eight in the output layer. From a practical
standpoint, eight outputs are many for the ANN to
learn through training and to recall for prediction in
future. Lots of information in the output layer results in
842
four neurons in the output layer is the best choice to
represent the operation with two networks. The
selection was made based on the learning process
performance. In other words, the iteration of each
ANN training has a goal to achieve, which is the least
sum of square error. If the goal (performance50.05)
has been met, the network learns the data and can
represent the operation. Otherwise, the learning process is not efficient and the developed model might
have problems in predicting the outputs. The degree of
goal achievement (performance) is the comparison
indicator that supports the best architecture to achieve
this goal. Using four neurons best meets this goal
because it has a performance of 0.06893, which is close
to 0.05. Other architectures produce larger performance (i.e. two output neurons architecture produce
an average performance of 14.6253; however, this is the
second closest to the goal (0.05)). Consequently, the
CBP operation can be represented using two ANNs
(each one contains four output neurons). Details of this
selection process are not included here due to space
limitation.
Each ANNs architecture involves 12 input and four
output neurons. The ANN1 contains loading, hauling,
unloading, and return times in the output neurons. The
ANN2 contains total delays, cost of delay, price per cy
(m3), and cost of delivery/cy (m3) in the output layer
neurons. Figures 2 and 3 show the input and output
neurons in both networks. Both figures depict the
architecture of the networks that represent the CBP
operation. Each network has the same inputs with
different outputs. The hidden layer is different in both
Zayed et al.
networks because it relies upon the data set and the
nature of the outputs.
Case study
To establish a decision-making framework, a Ready
Mixed Concrete (RMC) batch-plant operation, located
in the Lafayette, Indiana, was studied (Zayed and
Halpin, 2001a). The observed facility consisted of
storage bins for sand and gravel, a hopper tower, two
belt conveyors, two cement silos, and a discharge unit.
This facility serves an area of approximately 15 mi
(24 km) in radius. The production capacity of the plant
was rated as approximately 40 cu yd/h (30.4 m3/h)
(Zayed and Halpin, 2001a). Figure 4 shows the flow
diagram for the CBP and the transit mixer cycles.
Materials are withdrawn from the storage area to fill the
batch hopper through conveyor belt 1. There is a
scale to measure the aggregate weight in the hopper
tower before discharging to the transit mixer through
conveyor belt 2 (Zayed and Halpin, 2001a). Because
architecture design of the CBP might affect cycle time,
productivity, and cost, it is explained using Figure 4.
A concrete batch plant, in Lafayette, Indiana, is
selected to apply the designated ANN models and
verify their robustness in assessing the delays and their
influence on efficiency, cost, and time. Data (205 data
points) have been collected from the CBP site during
five months period. Several techniques have been used
to collect data: (1) CBP daily reports; (2) interview
with CBP management using site visits and telephone
Figure 4 Flow diagram for the CBP and the transit (adapted from Zayed and Halpin, 2001a)
843
Table 1
Concrete
type
2000 psl
2500 psl
3000 psl
3500 psl
4000 psl
4500 psl
5000 psl
4.5 bag
(423 lb)
5.0 bag
(470 lb)
5.5 bag
(517 lb)
6.0 bag
(564 lb)
7.0 bag
(658 lb)
Therefore, current research developed a general framework that can be applied to any CBP so that
practitioners can build on and extend to suite their
plants. In other words, practitioners in different cities
can develop an appropriate conversion factor for the
results of current study framework to accommodate
market variations. Reviewing previous work shows lack
of research in the CBP area; therefore, current study
enriches the area of CBP management by developing a
robust ANN model that predicts different management
elements for the CBP. The developed ANN model is
essential for researchers who are engrossed in CBP
management.
Material
3
Total price
$/cy
($/m )
$/cy
($/m )
$/cy
($/m3)
($10.5)
($10.5)
($10.5)
($10.5)
($10.5)
($10.5)
($10.5)
($10.5)
$44.53
$46.17
$48.87
$50.80
$52.89
$55.99
$55.29
$52.61
$58.59
$60.75
$64.30
$66.84
$69.60
$73.67
$72.75
$69.23
$12.97
$13.83
$13.63
$14.20
$14.61
$14.01
$18.21
$9.74
$17.07
$18.19
$17.94
$18.69
$19.22
$18.44
$23.96
$12.81
$57.50
$60.00
$62.50
$65.00
$67.50
$70.00
$73.50
$62.35
$75.66
$78.95
$82.24
$85.53
$88.82
$92.11
$96.71
$82.04
$4 ($5.26)
$8 ($10.5)
$54.49
$71.70
$10.36
$13.63
$64.85
$85.33
$58.39
$4 ($5.26)
$8 ($10.5)
$56.37
$74.18
$10.98
$14.44
$67.35
$88.62
$46.06
$60.60
$4 ($5.26)
$8 ($10.5)
$58.06
$76.39
$11.79
$15.52
$69.85
$91.91
$49.82
$65.55
$4 ($5.26)
$8 ($10.5)
$61.82
$81.34
$13.03
$17.15
$74.85
$98.49
$/cy
($/m )
$32.53
$34.17
$36.87
$38.80
$40.89
$43.99
$43.29
$40.61
$42.80
$44.96
$48.51
$51.05
$53.81
$57.88
$56.96
$53.44
$4
$4
$4
$4
$4
$4
$4
$4
$42.49
$55.91
$44.37
($5.26)
($5.26)
($5.26)
($5.26)
($5.26)
($5.26)
($5.26)
($5.26)
$8
$8
$8
$8
$8
$8
$8
$8
844
Zayed et al.
AVP~1{AIP
Table 2
Items
Delays
Cycle time
Cycle time elements
Cost of delays
Cost of delivery/cy (m3)
Price/cy (m3)
Average
Output variables
Delays
Total
Loading
Hauling
Unloading
Returning
Cost of delays
Cost of delivery/cy (m3)
Price/cy (m3)
Average
AIP1
AVP1
AIP2
AVP2
8.27%
3.53%
NA
NA
NA
NA
4.56%
2.16%
0.23%
3.75%
91.73%
96.47%
NA
NA
NA
NA
95.44%
97.84%
99.77%
96.25%
8.27%
NA
23.20%
17.06%
7.78%
8.76%
4.56%
2.16%
0.23%
9.00%
91.73%
NA
76.80%
82.94%
92.22%
91.24%
95.44%
97.84%
99.77%
91.00%
845
846
Zayed et al.
Production analysis
A Time-Quantity (TQ) chart, Figure 9, has been
developed to assess time per truck mixer for delivering
a specified quantity of concrete; to determine the CBP
production time for this specified quantity; and to
select the number of trucks required for various travel
distances. The x-axis (horizontal) represents the
required concrete quantities that a client might request.
There are two y-axes (vertical): (1) the left hand side yaxis represents the time required from one truck mixer
to deliver the required concrete quantity; and (2) the
right hand side y-axis represents the time required from
the CBP to produce this required concrete quantity.
The CBP production time curve considers the delay
percentages of the truck mixers for various distances.
The TQ chart can be used efficiently when, for
example, a client requested 100 cy (76 m3) of concrete
for a 24 km delivery distance. The CBP management
will use the TQ in Figure 9 to calculate the delivery
time, the CBP production time, and number of truck
mixers that can be used. If a vertical line is constructed
847
848
Zayed et al.
Figure 10
Figure 11
849
Figure 13
concrete
the net cycle time for that distance will be (63 minus
17546 minutes). It is the responsibility of the CBP
management and truck mixers operators to reduce
these delays as much as they can so that they are able to
increase their productivity. The cost of delay for
11.2 km delivery distance can be predicted using
Figure 12. It shows that the cost of delay for an 8 cy
(6.08 m3) truck load, 4000 psi concrete, is approximately $43.00/cycle. It costs the CBP management
approximately $7.8/m3 (4000 psi concrete) to deliver to
an 11.2 km distance, as shown in Figure 13. It is
obvious from Figure 13 that the cost of delivery
decreases when the truck mixer load increases because
the truck mixer expenses are allocated to a small
quantity of concrete. On the other hand, Figure 14
shows the prediction of price/m3 for various truck
mixers loads and delivery distances. The price/m3
(including cost of delivery) for 4000 psi concrete that is
delivered for 11.2 km distance is approximately $90.5,
as shown in Figure 14. This shows the drastic increase
in the price/m3 to deliver a small quantity of concrete to
the various distances.
These developed charts (tools) are designated to be
helpful to the CBP management and operators of truck
mixers. They facilitate their decision-making process
particularly in pricing out the concrete unit for different
distances and quantities. The developed tools are
flexible enough to cover many variables that enable
the CBP management to answer a broad range of
questions.
Conclusions
Current research has discussed the role of ANN as a
tool for decision-making and resource management. It
adds one more dimension to the CBP management
analysis: delays and their effect on the price/cy (m3).
Two ANN models were designated to represent the
Figure 14
850
CBP process considering many input and output
variables. Input variables include various distances,
concrete types, and truckload. Output variables include
the assessment of cycle time, cost of delays, delivery
cost, productivity, and price per concrete unit. The
average validity percent for the ANN outputs is
96.25%, which shows the robustness of the designated
ANN models. A set of charts has been developed to
help the CBP management answer questions regarding
prices and expenses for different distances. The TQ
tool is developed to assess the time required from both
truck mixers and the CBP to produce a specified
quantity of concrete. Charts have been developed to
predict cycle time/truck, delays/truck, cost of delays/
truck, cost of delivery/m3, and price/m3.
This research is relevant to both industry practitioners and researchers. It provides sets of charts for
practitioners usage to schedule and price out the CBP
operation. In addition, it provides the researchers with
the methodology of applying the ANN approach to the
CBP operation, its limitations, and future suggestions.
Acknowledgements
The writers wish to express their gratitude and
appreciation to the concrete production companies,
which generously allowed us to collect data and access
their sites. The cooperation and assistance of plants
managers and operators are also gratefully acknowledged and appreciated.
References
Alsugair, A.M. and Chang, D.Y. (1994) An Artificial Neural
Network approach to allocating construction resources,
Proceedings of the Computing in Civil Engineering First
Congress held in conjunction with A/E/C Systems, Vol. 1,
June, pp. 95057.
Bode, J. (1998) Neural networks for cost estimation. Cost
Engineering, 40(1), 2530.
Garrett, J.H. Jr. (1992) Neural networks and their applicability within civil engineering, Proceedings of the 8th
Conference of Computing in Civil Engineering, June,
pp. 115562.
Zayed et al.
Moselhi, O. and Hegazy, T. (1994) Analogy-based solution
to markup estimation problem. Journal of Computing in
Civil Engineering, 8(1), 7287.
Moselhi, O., Hegazy, T. and Fazio, P. (1991) Neural
networks as tools in construction. Journal of Construction
Engineering and Management, 117(4), 60625.
Ogershok, D. and Phillips, D. (1999) National construction
estimator, 47th edn.
Portas, J.B. (1996) Estimating concrete formwork productivity, MSc thesis, Construction Engineering & Management,
Department of Civil Enineering, University of Alberta,
Canada.
Ready Mixed Concrete Company (1999) Price Sheet,
Lafayette, IN.
RS Means (1999a) Heavy construction cost data, 13th edn.
RS Means (1999b) building construction cost data, 57th edn.
Tsoukalas, L.H. and Uhrig, R.E. (1997) Fuzzy and Neural
Approaches in Engineering, Wiley, New York, NY, USA.
Zayed, T.M. and Halpin, D.W. (2001a) Simulation of
concrete batch plant production. Journal of Construction
Engineering and Management, ASCE, 127(2), 13241.
Zayed, T.M. and Halpin, D.W. (2001b) Construction
productivity assessment using artificial intelligence, 4th
Construction Specialty Conference of the Canadian
Society for Civil Engineering (CSCE), Victoria, British
Columbia, Canada, 30 May2 June, C55.
Appendix
Notations
C5cost of delays (delays at plant site and at
construction site)
b5batch plant cost per hour
d15delay at the plant site in minutes
t5truck mixer cost per hour
d25delay at the construction site in minutes
AIP5average invalidity percent for validation data set
AVP5average validity percent for validation data set
Ei5estimated output variables value by ANN for
data point i
Ci5collected output variables value for data point i
n5number of data points
i5data points