Purpose
Introduce Availability Control Calculation in Projects.
Overview
Availability control compares the current distributed budget (or release) with the assigned value.
The Assigned Value can be difficult to reproduce due to the individual settings in Customizing and
business background.
The assigned value which is displayed in cost reports (called passive availability) quite often does
not match the assigned value of the active availability. This is due to the fact that the reports do not
take in the logic of the active availability control. Only the assigned value displayed in the budget
transactions are relevant for active availability control.
Below is a guideline of the logic behind the Assigned Value calculation. The customizing of your
system can affect how your active availability control calculates.
The Assigned Value, basic logic in projects, is calculated as follows (as stated by SAP):
Actual costs and statistical actual costs on the WBS element in question:
Actual costs and statistical actual costs of subordinate WBS elements if
these do not have a budget, that is to say, if they do not have 'budgeted' status.
Commitment on the WBS element in question:
Commitment of subordinate WBS elements, if they do not have a budget, that
is, if they do not have the 'budgeted' status.
Maximum from plan and the total from actual costs + commitment for assigned networks, network
activities or orders. (The plan value "reserves" the budget on the WBS element. Therefore this
budget cannot be consumed by another network, network activity, order or WBS element). Here,
the precise logic depends on the status of the assigned network, network activity or order and on the
Customizing settings.
In summary: In 'released' status, the assigned value always includes the maximum from the plan
value and the sum of actual and commitment. In 'Created' status, the plan value is included in the
assigned value if the 'Funds commitment in plan' indicator is set (Transaction OPSV) in
Customizing for the network type/order type.
Exception: Planned costs of networks or network activities that are used for forecasts are never
included in the assigned value.
In status 'Technically complete', 'Complete' or 'Deletion flag', the plan value is never
included in the
assigned value. The plan values of assigned networks are not taken into account for
valuated project stock.
If you set the availability control to validation against annual values, the values
planned at year level are
taken into account provided there is no overall plan value.