Beruflich Dokumente
Kultur Dokumente
Description of Activities
Completed up to
Previous Week
Total
Remaining
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
0.00%
0.00%
0.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
100.00%
0.00%
0.00%
0.00%
0.00%
0.00%
0.00%
100.00%
100.00%
0.00%
0.00%
10.00%
0.00%
0.00%
0.00%
5.00%
0.00%
0.00%
0.00%
15.00%
0.00%
100.00%
100.00%
85.00%
100.00%
75.00%
0.00%
75.00%
25.00%
60.00%
0.00%
0.00%
0.00%
5.00%
0.00%
5.00%
0.00%
0.00%
0.00%
5.00%
0.00%
65.00%
0.00%
0.00%
0.00%
10.00%
0.00%
35.00%
100.00%
100.00%
100.00%
90.00%
100.00%
0.00%
70.00%
0.00%
0.00%
10.00%
0.00%
0.00%
80.00%
0.00%
100.00%
20.00%
100.00%
20.00%
0.00%
55.00%
0%
35.00%
0.00%
5.00%
0%
55.00%
0.00%
60.00%
0%
45.00%
100.00%
40.00%
100%
85%
0%
85%
15%
90%
0%
90%
10%
92%
1%
93%
7%
40%
0%
40%
60%
2
3
4
5
6
7
j
1
2
3
k
1
l
m
n
B Electrical Works
a Erection of Filter Area
d Stability and
Transformers
sensitivity
test
of
Power
f Completion of PDS
g Testing and commissioning activities
77%
90%
3%
2.0%
80%
92.0%
20%
8.0%
100%
0%
100.0%
0%
85%
3%
88%
12%
69%
1%
70%
30%
b Plumbing System
31%
1%
32%
68%
65%
2%
67%
33%
C Mechanical Works
a HVAC System
60%
0%
60%
40%
80%
0%
80%
20%
0%
0%
0%
100%
1st lot has been delivered at site. FAT for 2nd batch is scheduled on 15-11-2013.
Not yet delivered at site despite of several site instruction notes, discussion during meetings and emails
Signals has been configured in the SAS system. These signals will be marked in red on the approved signal list and will
B Communication
a Accessories for communication duct banks, HH Partial delivery of material at site causing delay in close out activities related to communication HH, MH and duct banks
and MH.
b Media convertor Panels
C Mechanical
a Submersible Pumps
b HVAC balance duct material and accessories
c Mimic panels & balance fire detection &
protection system materials.
D Punch List
a
Punch List issued by DAR, CSD and after
walkthrough inspection needs to be rectified.
6 No. for safaaniyah 380kV BSP and 4 Nos. in loose form media convertor panels have been delivered at site and have b
Maadan S/S are yet to be delivered due to payment issue.
Delivered at site on 5/10/2013. (Closed)
Agreed delivery date 30-10-2013. Siemens confirmed in the Progress Review Meeting that delay in delivery of material
Agreed delivery date for Mimic panel and for remaining material date is 27-10-2013.
Siemens has been advised in progress review meetings & vide letter DAR-30933106/KA/059 to arrage dedicated manpo
and mechanical works. Siemens confirmed in the progress review meeting that punch list "A" catagory points will be rec
needs to increase manpower to meet the target.
ing delay in close out activities related to communication HH, MH and duct banks.
4 Nos. in loose form media convertor panels have been delivered at site and have been installed. For New Saudi Aramco and
e to payment issue.
d)
mens confirmed in the Progress Review Meeting that delay in delivery of material will not affect the commissiong schedule.
review meetings & vide letter DAR-30933106/KA/059 to arrage dedicated manpower for civil, electrical, communication
med in the progress review meeting that punch list "A" catagory points will be rectified by 10-11-2013. However Siemens
e target.