Beruflich Dokumente
Kultur Dokumente
S.No
1
1.1
1.2
2
3
Documents
Post Tender Meeting
Finalisation of Vendors
Engineering and Design Serivces
Drawing Numbers for (I&II)
Title Bolck Numbers for (I&II)
4 HSE Document
4.1 Loss and Prevention Program
5 Base Design Submission
5.1 Conductor
A TD for ACSR conductors(I&II) [GTP]
a.Data Schedule (10-TMSS-01 [rev.01])
b.Compliance Statement (01-TMSS-01[rev.02],10-TMSS-01
[rev.01])
c.Type Test Report
d.Manufactures responsibility Statement
e.Any other Qualifying Documents (Certification)
B
ITP of Conductor
5.2 OPGW
A TD of OPGW-I [GTP]
Data Schedule for OPGW 48 Cores.
Compliance Statement ( 01-TMSS-01, 10-TMSS-04 Rev.01 )
Type test report.
Manufactures responsibility Statement
5.3 Towers
A TD of Tower - I
Data Schedule for S1N, TA1N, TA2N, TA3N & DE towers.
Compliance Statement (20-TMSS-01 Rev.01 & 01-TMSS-01
Rev.02)
Type test report.
Manufactures responsibility Statement.
Any other Qualifying documents
B TD of Tower - II
Data Schedule for S1N, TA1N, TA2N, TA3N & DE towers.
Compliance Statement (20-TMSS-01 Rev.01 & 01-TMSS-01
Rev.02)
Type test report.
Manufactures responsibility Statement.
Any other Qualifying documents
C Shop & Erection Drawings of S1N (0-2 )tower -I
D Shop & Erection Drawings of S1N (0-2) tower -II
E Shop & Erection Drawings of TA1N (2-10) tower -I
F
G
H
I
J
K
L
5.6 Insulator
A
B ITP of Insulator
5.7
5.8 Grounding
A TD for Grounding-I& II
11 Soil Investigation
Boring at site
Report Submission
12 Access road & Structure
13 Foundation Design
Design Calculation
Foundation Drawings
PO of Insulators (I&II)
PO of Conductors (I&II)
PO of OPGW (I&II)
PO of Towers (I&II)
PO of Hardware fittings (I&II)
Source of Document
Approved
Vendor/contractor
/Company
SUBMISSION to client
with Date
A-accepted
A
DAR ENGG
1/26/2016
1/26/2016
4/17/2016
MIDAL Cables
2/28/2016
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
4/7/2016
LS Cables
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
4/7/2016
KPTL
Design.Dept Mumbai
3/14/2016
Design.Dept Mumbai
3/14/2016
Design.Dept Mumbai
Design.Dept Mumbai
3/9/2016
3/9/2016
Design.Dept Mumbai
3/13/2016
Design.Dept Mumbai
Design.Dept Mumbai
Design.Dept Mumbai
Design.Dept Mumbai
Design.Dept Mumbai
Design.Dept Mumbai
Design.Dept Mumbai
3/13/2016
3/16/2016
3/16/2016
4/10/2016
4/10/2016
4/10/2016
4/10/2016
MOSODORFER-AUSTRIA
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
DAR ENGG
DAR ENGG
4/13/2016
4/17/2016
Proj.Coordinator-Mumbai
4/13/2016
Proj.Coordinator-Mumbai
4/13/2016
Proj.Coordinator-Mumbai
4/7/2016
DAMP-ITALY
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
NGK-Insulators
3/2/2016
Proj.Coordinator-Mumbai
Proj.Coordinator-Mumbai
4/5/2016
Proj.Coordinator-Mumbai
AL HARITH-KSA
A
A
A
A
A
A
Approval of Client
B-accepted as with
note
Remarks
C-Resubmit
B
B
B
B
B
B
C
C
Vendor
Conductor
OPGW
Midal Cables
LS cables
Insulators
NGK insulators
Tower/S1N
Tower/TA1N
Tower/TA2N
Tower/TA3N
Tower/DE
Hardware Fittings
Spacer Damper
NFOC
Joint Box
Grounding
Technical Documents
Submited(28.04.16)
Accepted
ITP
Accepted
Submited(07.04.16)
Type Test
KPTL
KPTL
KPTL
KPTL
KPTL
Mosdorfer
Damp
Accepted
Accepted
Accepted
Submitted on (20.04.16)
Accepted
Submitted (02.05.16)
Submitted (02.05.16)
Submitted (02.05.16)
Accepted
Submited(28.04.16)
Submited(07.04.16)
Submited(11.04.16)
Submited(21.04.16)
Submited(11.04.16)
Placed
Placed
Intertek
Placed
SGS
SGS
SGS
SGS
SGS
Not Yet Decided
Not Yet Decided
Prysmian
KSA
Accepted
P.O
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Not Placed
Remarks
SEC reply awaited
Step-2:
Reciving Reply from SEC for Plan Profiles
Submission Comments based on the following Status we have to proceed
A: Acceptable - Approved of Plan and Profile
B: Acceptable as Noted- Requset for Some missing Digram Number ,plant number,Size mentioned and once it submited then it will become A status.
C: Not Acceptable (Resubmit) -Changed of Documents Required
See Attached Sheet-Comments on the Documents to Rectify.
Step-3:
All Documents Should get A status until that the Submission will Continue with Revisions.
Each Revision the Step-1 Check lit should be followed and with the corrected and updated documents will be submitted
Along with that the Previous Comment Sheet also should be attached and Actions taken shoulbe be mentioned in Compliance Statement
Step-2:
Step-2:
All Documents Should get A status until that the Submission will
Each Revision the Step-1 Check lit should be followed and with t
Along with that the Previous Comment Sheet also should be atta
ical Documents
he following Status we have to proceed
ed and P.O can be placed
- Requset for Some missing Documents and once it submited then it will become
ubmit) -Changed of Documents Required
Comments on the Documents to Rectify.
ry Acceptance test)
- Requset for Some missing Documents and once it submited then it will become
ubmit) -Changed of Documents Required
Comments on the Documents to Rectify.
d Erection Drawings
ollowing Status we have to proceed
of Plan and Profile
equset for Some missing Digram Number ,plant number,Size mentioned and once it submited then i
mit) -Changed of Documents Required
ments on the Documents to Rectify.
Sheet also should be attached and Actions taken shoulbe be mentioned in Compliance Statement
submitted
d in Compliance Statement
Step-2:
B
C
See Attached
Step-3:
Submission
ument Submission
Documents Should get A status until that the Submission will Continue with Revisions.
ch Revision the Step-1 Check lit should be followed and with the corrected and updated
ong with that the Previous Comment Sheet also should be attached and Actions taken sh
Documents Should get A status until that the Submission will Continue with Revisions.
ch Revision the Step-1 Check lit should be followed and with the corrected and updated
ong with that the Previous Comment Sheet also should be attached and Actions taken sh
d every submission to Prequalification and Support Department of SEC normally takes 3 weeks for r
n Document Submission
B: Acceptable as Noted- Requset for Some missing Documents and once it subm
C: Not Acceptable (Resubmit) -Changed of Documents Required
See Attached Sheet-Comments on the Documents to Rectify.
Documents Should get A status until that the Submission will Continue with Revisions.
ch Revision the Step-1 Check lit should be followed and with the corrected and updated
ong with that the Previous Comment Sheet also should be attached and Actions taken sh
d every submission to Prequalification and Support Department of SEC normally takes 3 weeks for r
on Calculation Chart
uld submit along with Profiles)
rial tested)
y and submit
*ITP report
Step-2:
Step-3:
rts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
or Technical Documents
ed on the following Status we have to proceed
Approved and P.O can be placed
s Noted- Requset for Some missing Documents and once it submited then it will become
ble (Resubmit) -Changed of Documents Required
Sheet-Comments on the Documents to Rectify.
equalification and Support Department of SEC normally takes 3 weeks for reply.
equalification and Support Department of SEC normally takes 3 weeks for reply.
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
Step-2:
*ITP report
Step-2:
Step-3:
rts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
or Technical Documents
ed on the following Status we have to proceed
Approved and P.O can be placed
s Noted- Requset for Some missing Documents and once it submited then it will become
ble (Resubmit) -Changed of Documents Required
Sheet-Comments on the Documents to Rectify.
equalification and Support Department of SEC normally takes 3 weeks for reply.
equalification and Support Department of SEC normally takes 3 weeks for reply.
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
Step-2:
*ITP report
Step-2:
Step-3:
rts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
or Technical Documents
ed on the following Status we have to proceed
Approved and P.O can be placed
s Noted- Requset for Some missing Documents and once it submited then it will become
ble (Resubmit) -Changed of Documents Required
Sheet-Comments on the Documents to Rectify.
equalification and Support Department of SEC normally takes 3 weeks for reply.
equalification and Support Department of SEC normally takes 3 weeks for reply.
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
Step-2:
Step-2:
orts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
get A status until that the Submission will Continue with Revisions.
-1 Check lit should be followed and with the corrected and updated documents will be s
vious Comment Sheet also should be attached and Actions taken shoulbe be mentioned
C for ITP
based on the following Status we have to proceed
e - Approved for the FAT report submitted
e as Noted- Requset for Some missing Documents and once it submited then it will beco
table (Resubmit) -Changed of Documents Required
ed Sheet-Comments on the Documents to Rectify.
get A status until that the Submission will Continue with Revisions.
-1 Check lit should be followed and with the corrected and updated documents will be s
vious Comment Sheet also should be attached and Actions taken shoulbe be mentioned
requalification and Support Department of SEC normally takes 3 weeks for reply.
C for ITP
based on the following Status we have to proceed
e - Approved for the Type Test Submitted
e as Noted- Requset for Some missing Documents and once it submited then it will beco
get A status until that the Submission will Continue with Revisions.
-1 Check lit should be followed and with the corrected and updated documents will be s
vious Comment Sheet also should be attached and Actions taken shoulbe be mentioned
requalification and Support Department of SEC normally takes 3 weeks for reply.
Step-2:
*ITP report
Step-2:
Step-3:
rts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
or Technical Documents
ed on the following Status we have to proceed
Approved and P.O can be placed
s Noted- Requset for Some missing Documents and once it submited then it will become
ble (Resubmit) -Changed of Documents Required
Sheet-Comments on the Documents to Rectify.
equalification and Support Department of SEC normally takes 3 weeks for reply.
equalification and Support Department of SEC normally takes 3 weeks for reply.
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
Step-2:
*ITP report
Step-2:
Step-3:
rts (report valid for 5 yrs only from the Date material tested)
Responsibility Statement
alifying Documents(ISO certifcation ect..)
or Technical Documents
ed on the following Status we have to proceed
Approved and P.O can be placed
s Noted- Requset for Some missing Documents and once it submited then it will become
ble (Resubmit) -Changed of Documents Required
Sheet-Comments on the Documents to Rectify.
equalification and Support Department of SEC normally takes 3 weeks for reply.
equalification and Support Department of SEC normally takes 3 weeks for reply.
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement
s will be submitted
mentioned in Compliance Statement