Beruflich Dokumente
Kultur Dokumente
1. SYMBOLS
A = Total area of section
Ab = Equivalent area of helical reinforcement.
Ac = Equivalent area of section
Ah = Area of concrete core.
Am = Area of steel or iron core.
Asc =
Ast =
Al =
= shear stress.
Vus
sc
2. INTRODUCTION
A water tank is used to store water to tide over the daily requirement. In the construction
of concrete structure for the storage of water and other liquids the imperviousness of
concrete is most essential .The permeability of any uniform and thoroughly compacted
concrete of given mix proportions is mainly dependent on water cement ratio .The
increase in water cement ratio results in increase in the permeability .The decrease in
water cement ratio will therefore be desirable to decrease the permeability, but very
much reduced water cement ratio may cause compaction difficulties and prove to be
harmful also. Design of liquid retaining structure has to be based on the avoidance of
cracking in the concrete having regard to its tensile strength. Cracks can be prevented by
avoiding the use of thick timber shuttering which prevent the easy escape of heat of
hydration from the concrete mass the risk of cracking can also be minimized by
reducing the restraints on free expansion or contraction of the structure.
1. Objective:
1. To make a study about the analysis and design of water tanks.
2. To make a study about the guidelines for the design of liquid retaining Structure
according to is code.
3. To know about the design philosophy for the safe and economical design of water tank.
4. To develop programs for the design of water tank of flexible base and rigid base and the
underground tank to avoid the tedious calculations.
5. In the end, the programs are validated with the results of manual calculation
given in concrete Structure.
3. WATER DEMAND
3.1 Water Quantity Estimation: The quantity of water required for municipal uses for
which the water supply scheme has to be designed requires following data:
Water consumption rate (Per Capita Demand in litres per day per head) Population to be
served.
Quantity= per demand x Population
3.2 Water Consumption Rate: It is very difficult to precisely assess the quantity of
water demanded by the public, since there are many variable factors affecting water
consumption. The various types of water demands, which a city may have, may be
broken into following class
Types of Consumption
1
Domestic Consumption
Normal Range
(lit/capita/day)
65-300
Average
160
35
2 Industrial and
45-450
135
30
20-90
45
10
45-150
62
25
Commercial Demand
Public including Fire
Demand Uses
Losses and Waste
3.3 Fire Fighting Demand: The per capita fire demand is very less on an average
basis but the rate at which the water is required is very large. The rate of fire demand is
sometimes treated as a function of population and is worked out from following
empirical formulae:
Authority
1
2
3
4
American
Insurance Association
Kuchling's Formula
Freeman's Formula
Ministry
Of Urban Development Manual
Formula
Formula (P in
Q (for 1 lakh
thousand)
Population)
Q(L/min)=4637P(1-0.01
41760
P)
Q(L/min)=3182 P
31800
Q(L/min)=1136.5(P/5+10)
35050
Q(kilo liters/d)=100P for
31623
P>50000
If this average demand is supplied at all the times, it will not be sufficient to meet the
fluctuations.
Seasonal variation: The demand peaks during summer. Firebreak outs are generally
more in summer, increasing demand. So, there is seasonal variation.
Daily variation depends on the activity. People draw out more water on Sundays and
Festival days, thus increasing demand on these days.
Hourly variations are very important as they have a wide range. During active
household working hours i.e. from six to ten in the morning and four to eight in the
evening, the bulk of the daily requirement is taken. During other hours the requirement
is negligible. Moreover, if a fire breaks out, a huge quantity of water is required to be
supplied during short duration, necessitating the need for a maximum rate of hourly
supply. So, an adequate quantity of water must be available to meet the peak demand. To
meet all the fluctuations, the supply pipes, service reservoirs and distribution pipes must
be properly proportioned. The water is supplied by pumping directly and the pumps and
distribution system must be designed to meet the peak demand. The effect of monthly
variation influences the design of storage reservoirs and the hourly variations influences
the design of pumps and service reservoirs. As the population decreases, the fluctuation
rate increases.
Maximum daily demand = 1.8 x average daily demand
Maximum hourly demand of maximum day i.e. Peak demand
= 1.5 x average hourly demand
= 1.5 x Maximum daily demand/24
= 1.5 x (1.8 x average daily demand)/24
= 2.7 x average daily demand/24
= 2.7 x annual average hourly demand
4. POPULATION FORECAST
10
5. WATER TANKS
11
5.1 CLASSIFICATIONS:
12
13
Fig (a)
A contraction joint may be either complete contraction joint or partial contraction joint.
A complete contraction joint is one in which both steel and concrete are interrupted and
a partial contraction joint is one in which only the concrete is interrupted, the reinforcing
steel running through as shown in Fig.(b)
Fig (b)
(ii)Expansion Joint. It is a joint with complete discontinuity in both reinforcing steel
and concrete and it is to accommodate either expansion or contraction of the structure. A
typical expansion joint is shown in Fig. (c)
14
Fig(c)
This type of joint is provided between wall and floor in some cylindrical tank designs.
6.1.2 CONTRACTION JOINTS:
This type of joint is provided for convenience in construction. This type of joint requires
the provision of an initial gap between the adjoining parts of a structure which by
closing or opening accommodates the expansion or contraction of the structure.
Fig (d)
(iii) Sliding Joint. It is a joint with complete discontinuity in both reinforcement and
concrete and with special provision to facilitate movement in plane of the joint. A
typical joint is shown in Fig. This type of joint is provided between wall and floor in
some cylindrical tank designs.
15
Fig (e)
6.1.3 TEMPORARY JOINTS:
A gap is sometimes left temporarily between the concrete of adjoining parts of a
structure which after a suitable interval and before the structure is put to use, is filled
with mortar or concrete completely with suitable jointing materials. In the first case
width of the gap should be sufficient to allow the sides to be prepared before filling.
Figure (g)
Fig (g)
16
shall be in accordance with Table 1. Where the calculated shear stress in concrete alone
exceeds the permissible value, reinforcement acting in conjunction with diagonal
compression in the concrete shall be provided to take the whole of the shear.
7.3 Permissible Stresses in Steel:
(a) For resistance to cracking. When steel and concrete are assumed to act together for
checking the tensile stress in concrete for avoidance of crack, the tensile stress in steel
will be limited by the requirement that the permissible tensile stress in the concrete is
not exceeded so the tensile stress in steel shall be equal to the product of modular ratio
of steel and concrete, and the corresponding allowable tensile stress in concrete.
(b) For strength calculations:
In strength calculations the permissible stress shall be as follows:
a) Tensile stress in member in direct tension 1000 kg/cm2.
b)Tensile stress in member in bending on liquid retaining face of members or face
away from liquid for members less than 225mm thick 1000 kg/cm2.
c) On face away from liquid for members 225mm or more in thickness 1250 kg/cm2.
d)Tensile stress in shear reinforcement For members less than 225mm thickness 1000
kg/cm2 for members 225mm or more in thickness 1250 kg/cm2.
17
e) Compressive stress in columns subjected to direct load 1250 kg/cm2.
18
7.6 Walls:
(i)Provision of joints
(a)Where it is desired to allow the walls to expand or contract separately from the floor,
or to prevent moments at the base of the wall owing to fixity to the floor, sliding joints
may be employed.
19
(b)The spacing of vertical movement joints should be as discussed in article 3.3 while
the majority of these joints may be of the partial or complete contraction type, sufficient
joints of the expansion type should be provided to satisfy the requirements given in
article
(ii) Pressure on Walls.
(a) In liquid retaining structures with fixed or floating covers the gas pressure developed
above liquid surface shall be added to the liquid pressure.
(b)When the wall of liquid retaining structure is built in ground, or has earth embanked
against it, the effect of earth pressure shall be taken into account.
(iii) Walls or Tanks Rectangular or Polygonal in Plan.
While designing the walls of rectangular or polygonal concrete tanks, the following
points should be borne in mind.
(a) In plane walls, the liquid pressure is resisted by both vertical and horizontal bending
moments. An estimate should be made of the proportion of the pressure resisted by
bending moments in the vertical and horizontal planes. The direct horizontal tension
caused by the direct pull due to water pressure on the end walls, should be added to that
resulting from horizontal bending moments. On liquid retaining faces, the tensile
stresses due to the combination of direct horizontal tension and bending action shall
satisfy the following condition:
(t./t )+ ( c t . /ct ) 1
t. = calculated direct tensile stress in concrete
t = permissible direct tensile stress in concrete (Table 1)
c t = calculated tensile stress due to bending in concrete.
c t = permissible tensile stress due to bending in concrete.
(d)At the vertical edges where the walls of a reservoir are rigidly joined, horizontal
reinforcement and haunch bars should be provided to resist the horizontal bending
moments even if the walls are designed to withstand the whole load as vertical beams or
cantilever without lateral supports.
20
(c) In the case of rectangular or polygonal tanks, the side walls act as two way slabs,
where by the wall is continued or restrained in the horizontal direction, fixed or hinged
at the bottom and hinged or free at the top. The walls thus act as thin plates subjected
triangular loading and with boundary conditions varying between full restraint and free
edge. The analysis of moment and forces may be made on the basis of any recognized
method.
(iv) Walls of Cylindrical Tanks.
While designing walls of cylindrical tanks the following points should be borne in mind:
(a)Walls of cylindrical tanks are either cast monolithically with the base or are set in
grooves and key ways (movement joints). In either case deformation of wall under
influence of liquid pressure is restricted at and above the base. Consequently, only part
of the triangular hydrostatic load will be carried by ring tension and part of the load at
bottom will be supported by cantilever action.
(b)It is difficult to restrict rotation or settlement of the base slab and it is advisable to
provide vertical reinforcement as if the walls were fully fixed at the base, in addition to
the reinforcement required to resist horizontal ring tension for hinged at base, conditions
of walls, unless the appropriate amount of fixity at the base is established by analysis
with due consideration to the dimensions of the base slab the type of joint between the
wall and slab, and , where applicable, the type of soil supporting the base slab.
7.7 Roofs:
(i) Provision of Movement joints:
To avoid the possibility of sympathetic cracking it is important to ensure that movement
joints in the roof correspond with those in the walls, if roof and walls are monolithic. It,
however, provision is made by means of a sliding joint for movement between the roof
and the wall correspondence of joints is not so important.
(ii) Loading:
Field covers of liquid retaining structures should be designed for gravity loads, such as
the weight of roof slab, earth cover if any, live loads and mechanical equipment. They
should also be designed for upward load if the liquid retaining structure is subjected to
internal gas pressure. A superficial load sufficient to ensure safety with the unequal
intensity of loading which occurs during the placing of the earth cover should be
allowed for in designing roofs. The engineer should specify a loading under these
temporary conditions which should not be exceeded. In designing the roof, allowance
21
should be made for the temporary condition of some spans loaded and other spans
unloaded, even though in the final state the load may be small and evenly distributed.
(iii)
Water tightness: In case of tanks intended for the storage of water for domestic
purpose, the roof must be made water-tight. This may be achieved by limiting the
stresses as for the rest of the tank, or by the use of the covering of the water proof
membrane or by providing slopes to ensure adequate drainage.
(iv)
Protection against corrosion: Protection measure shall be provided to the
underside of the roof to prevent it from corrosion due to condensation.
7.8 Minimum Reinforcement:
(a)The minimum reinforcement in walls, floors and roofs in each of two directions at
right angles shall have an area of 0.3 per cent of the concrete section in that direction for
sections up to 100mm, thickness. For sections of thickness greater than 100mm, and less
than 450mm the minimum reinforcement in each of the two directions shall be linearly
reduced from 0.3 percent for 100mm thick section to 0.2 percent for 450mm, thick
sections. For sections of thickness greater than 450mm, minimum reinforcement in each
of the two directions shall be kept at 0.2 per cent. In concrete sections of
thickness225mm or greater, two layers of reinforcement steel shall be placed one near
each face of the section to make up the minimum reinforcement.
(b)In special circumstances floor slabs may be constructed with percentage of
reinforcement less than specified above. In no case the percentage of reinforcement in
any member be less than 0.15% of gross sectional area of the member.
7.9 Minimum Cover to Reinforcement:
(a) For liquid faces of parts of members either in contact with the liquid (such as inner
faces or roof slab) the minimum cover to all reinforcement should be 25mm or the
diameter of the main bar whichever is greater. In the presence of the sea water and soil
sand water of corrosive characters the cover should be increased by 12mm but this
additional cover shall not be taken into account for design calculations.
(b) For faces away from liquid and for parts of the structure neither in contact with the
liquid on any face, nor enclosing the space above the liquid, the cover shall be as for
ordinary concrete member.
8. DOMES
22
A dome may be defined as a thin shell generated by the revolution of a regular curve
about one of its axes. The shape of the dome depends on the type of the curve and the
direction of the axis of revolution. In spherical and conoidal domes, surface is described
by revolving an arc of a circle. The centre of the circle may be on the axis of rotation
(spherical dome) or outside the axis (conoidal dome). Both types may or may not have
as symmetrical lantern opening through the top. The edge of the shell around its base is
usually provided with edge member cast integrally with the shell.
Domes are used in variety of structures, as in the roof of circular areas, in circular tanks,
in hangers, exhibition halls, auditoriums, planetorium and bottom of tanks, bins and
bunkers. Domes may be constructed of masonry, steel, timber and reinforced concrete.
However, reinforced domes are more common nowadays since they can be constructed
over large spans membrane theory for analysis of shells of revolution can be developed
neglecting effect of bending moment, twisting moment and shear and assuming that the
loads are carried wholly by axial stresses. This however applies at points of shell which
are removed some distance away from the discontinuous edge. At the edges, the results
thus obtained maybe indicated but are not accurate.
The edge member and the adjacent hoop of the shells must have very nearly the same
strain when they are cast integrally. The significance of this fact is usually ignored and
the forces thus computed are, therefore, subject to certain modifications. Stresses in
shells are usually kept fairly low, as effect of the edge disturbance, as mentioned above
is usually neglected. The shell must be thick enough to allow space and protection for
two layers of reinforcement. From this point of view 80 mm is considered as the
minimum thickness of shell.
23
Shell of Revolution
Two forces N
) have the resultant N
)d as shown in Fig.(c) and the resultant acts
normal to the surface pointed towards the inner side. Forces N (r1d ) again have
horizontal resultant of magnitude N (r1 d ) d as shown in Fig (d). It has a component N
(r1d )d sin directed normally to the shell and pointing towards the inner side. These two
24
forces and the external force normal to the surface and a magnitude Pr(rd ) must be in
equilibrium.
Thus,Nf (rd)df+N (r1df)dsinf+Pr(rd)(r1d )= 0
Combining and as r = r2 sinf from Fig. (a)
Nf /r1+N/r2 = -Pr = pressure normal to the surface In this equation Pr is considered
positive when acting towards the inner side and negative when acting towards the outer
side of the shell. Value s and Nf and N will be positive when tensile and negative
compressive.
The equation is valid not only for shells in the form of a surface of revolution, but may
be applied to all shells, when the coordinate lines for = constant and = constant, are the
lines of curvature of the surface.
Forces in shell Force Nf act tangentially to the surface all around the circumference.
Considering the equilibrium of a segment of shell cut along the parallel to latitude
defined by the angle as shown in Fig
2PrNf sin f + W= 0,
Where W= total load in the vertical direction on the surface of the shell above the cut.
This gives,
Nf = -W/2Prsinf
Eq. is readily solved for Nf and N may then be determined by Eq. This theory is
applicable to a shell of any material as only the conditions of equilibrium have been
applied and no compatibility relationships in terms of deformation have been
introduced. It is, therefore, immaterial whether Hooke's law is applicable or not.
25
Fig (a)
Fig (b)
26
The requirements of thickness of dome and reinforcement from the point of view of
induced stresses are usually very small. However, a minimum of 80 mm is provided so
as to accommodate two layers of steel with adequate cover. Similarly a minimum of
steel provided is 0.15% of the sectional area in each direction along the meridians as
well as along the latitudes. This reinforcement will be in addition to the requirements for
hoop tensile stresses.
The reinforcement is provided in the middle of the thickness of the dome shell near the
edges usually some ring beam is provided for taking the horizontal component of the
meridian stress. Some bending moment develops in the shell near the edges. As shown
in Fig. it is normal to thicken the shell near the edges and provide increased curvature.
Reinforcements near the top as well as near the bottom face of the shell are also
provided. The size of the ring beam is obtained on basis of the hoop tension developed
in the ring due to the horizontal component of the meridian stress. The concrete area is
obtained so that the resulting tensile stress when concrete alone is considered does not
exceed 1.1N/mm2 to 1.70 N/mm2 for direct tension and 1.5 N/mm2 to 2.40 N/mm2 for
tension due to bending in liquid resisting structure depending on the grade of concrete.
Reinforcement for the hoop stress is also provided with the allowable stress in steel as
115 N/mm2 (or 150N/mm2) in case of liquid retaining structures and 140 N/mm 2 (or190
N/ mm2) in other cases. The ring should be provided so that the central line of the shell
passes through the centroid of the ring beam. Reinforcement has to be provided in both
the directions. If the reinforcement along the meridians is continued up to the crown,
there will be congestion of steel there. Hence, from practical considerations, the
reinforcement along the meridian is stopped below the crown and a separate mesh, as
shown in Fig (a), is provided. Alternatively, the arrangement of the bars may be made as
shown in plan in Fig (b)
In case of domes with lantern opening with concentrated load acting there, ring beam
has to be provided at the periphery of the opening. The edge beam there will, however,
be subjected to hoop compression in place of hoop tension.
Openings may be provided in the dome as required from other functional or architectural
requirements. However, reinforcement has to be provided all around the opening as
shown in Fig. (c). The meridian and hoop reinforcement reaching the opening should be
well anchored to such reinforcement.
27
The allowable stresses specified in IS 3370 for such tanks are as follows:
Type of stresses: Permissible stress in N/mm 2 High yield strength Plain bars confirming
to deformed bars as per Grade-I of IS 432-1966. IS 1786-1966 or is 1139-1966. Tensile
stress in members under no table of contents entries found direct load.
Direct tensile stress in concrete a may be taken as 1.1 N/mm2, 1.2. N/mm2, 1.32
N/mm2, 1.5 N/mm2, 1.6N/mm2 and 1.7 N/mm2 for M15, M20, M25, M30, M35 and
M40 respectively, the value in tension due to bending
i.e.,being1.5N/mm2,1.7N/mm2,1.82N/mm2,2.0 N/mm2, 2.2 N/mm2 and 2.4 N/mm2.
When steel and concrete are assumed to act together for checking the tensile stress in
concrete for avoidance of cracks, the tensile stress in the steel will be limited by the
requirements that the stress as mentioned above should not be exceeded. The tensile
stress in steel will be modular ratio multiplied by the corresponding allowable tensile
stress in concrete.
Stresses due to shrinkage or temperature change may be ignored if the permissible
stresses in concrete and steel are not exceeded and adequate precautions are taken to
28
avoid cracking of concrete during construction period, until the reservoir is put into use
and if it is assured that the concrete will never dry out. If it is required to calculate
shrinkage stresses, a shrinkage strain of 300 10-6 may be assumed.
When shrinkage stresses are considered, the permissible stresses may be increased by
33
%.
When shrinkage stresses are considered it is necessary to check the thickness for no
crack.
Minimum reinforcement of each of two directions at right angles shall have an area of
0.3% for 100 mm thick concrete to 0.2% for 450 mm thick concrete wall. In floor slabs,
minimum reinforcement to be provided is 0.15%. The minimum reinforcement as
specified above may be decreased by 20%), if high strength deformed bars are used.
Minimum cover to reinforcement on the liquid face is 25 mm or diameter of the bar,
whichever is larger and should be increased by 12 mm for tanks for sea water or liquid
of corrosive character.
29
(2) Sidewalls
(4) Floor beams, including circular girder
(7)Foundations
30
Usually a domed floor is shown in fig a result of which the ring girder supported on the
columns will be relieved from the horizontal thrusts as the horizontal thrusts of the
conical wall and the domed floor act in opposite direction.
Sometimes, a vertical hollow shaft may be provided which may be supported on the
domed floor.
The design of the tank will involve the following.
(1) The dome: at top usually 100 mm to 150 mm thick with reinforcement along the
meridians and latitudes. The rise is usually l/5th of the span.
(2) Ring beam supporting the dome: The ring beam is necessary to resist the horizontal
component of the thrust of the dome. The ring beam will be designed for the hoop
tension induced.
(3) Cylindrical walls: This has to be designed for hoop tension caused due to horizontal
water pressure.
(4) Ring beam at the junction of the cylindrical walls and the conical wall: This ring
beam is provided to resist the horizontal component of the reaction of the conical wall
on the cylindrical wall. The ring beam will be designed for the induced hoop tension.
(5) Conical slab: This will be designed for hoop tension due to water pressure. The slab
will also be designed as a slab spanning between the ring beam at top and the ring girder
at bottom.
(6) Floor of the tank. The floor may be circular or domed. This slab is supported on the
ring girder.
(7) The ring girder: This will be designed to support the tank and its contents. The girder
will be supported on columns and should be designed for resulting bending moment and
Torsion.
(8) Columns: These are to be designed for the total load transferred to them. The columns
will be braced at intervals and have to be designed for wind pressure or seismic loads
whichever govern.
(9) Foundations: A combined footing is usually provided for all supporting columns. When
this is done it is usual to make the foundation consisting of a ring girder and a circular
slab.
31
V2 =
p.h
( D2 +d 2+ d )=
12
V3 =
p h1
(3 r 2 +h12)
6
0.102D3
= 0.017D3.
32
13. DESIGN
13. DETAILS OF DESIGN:
Design of tank:
Design of an Intze tank for a capacity of 900000 lts .
Assuming height of staging is 16 m.
Safe bearing capacity of soil 150 kN/m2 .
Assume Wind pressure as 1500 N/m2 .
Assuming M20 concrete
For which cbc = 7N/mm2, cc = 5N/mm2
Direct tension t = 5N/mm2
Tension in bending = 1.70 N/mm2
Modular ratio m = 13
For Steel stress,
Tensile stress in direct tension =115 N/mm2
Tensile stress in bending on liquid face =115 N/mm2 for t < 225 mm and 125 N/mm 2 for
> 225 mm.
Solution: 1. Dimensions of the tank :
Let the diameter of the cylindrical portion= D =14 m ; R=7 m.
Let the diameter of the ring beam B2 =D0 =10 m . Height h0 of conical dome = 2m.
33
2=35.50
tan 2 =0.7133 ;
cot 2 =1.4019.
2
3 h2 (3R2 - h2)
900 = 4
(14)2h +
2
12
34
p R1
1+cos 1
4000 14.51
1+0.8760
=30938 N/m.
30938
p R1 1
t1
2
4000 14.51
2 0.1
Since the stresses are within the safe limits, provide nominal reinforcement @ 0.3%.
As =
0.3
100 1000
100
=300 mm2.
1000 50
300
160 mm.
35
D
2
= 27102
14
2
= 189712
N.
Permissible stress in high yield strength deformed bars (HYSD bars) = 150 N/mm2.
189712
150
A =
sh
= 1265 mm2.
1265
189712
A+ 12 1257
= 1.2
D
2
14
=9800 5 2 =343000 N/m height
36
343000
150
Providing rings on both the faces, Ash on each face = 1143 mm2
Spacing of 12mm rings =
1000 113
1143
= 98.9 mm.
343000
1000 t +12 1190 2
= 1.2
300+ 200
2
Ash =
250100
0.1
450100
=0.24
325mm2
Spacing of 8 mm bars =
1000 50.3
325
= 155 mm.
37
2
To resist the hoop tension at 2 m below top, Ash = 5 2286 = 914.4 mm2
1000 113
914.4/2
Spacing of 12 mm rings =
1000 113
1.372/2
= 164.7 mm.
Hence provide rings @ 160 mm c/c in the next 1m height. At 4m below the top,
4
1000 113
1829/2
= 123.6 mm
Hence provide rings @ 120 mm c/c for the next 1 m height. In the last 1m height (4m to
5m) provide rings 95mm c/c.
5. Design of ring beam B3 :
This ring beam connects the tank wall with the conical dome. The vertical load at the
junction of the wall with conical dome is transferred to ring beam B3 by meridional
thrust in the conical dome. The horizontal component of the thrust cause hoop tension at
the junction. The ring beam is provided to take up this hoop tension. The load W
transmitted through tank wall, at the top of conical dome consists of the following:
(i)
(ii)
Load due to the ring beam B1 =0.36 (0.4-0.2) 1 25000 =1800 N/m.
(iii)
0.2+0.3
1 25000 = 31250 N/m.
2
38
(iv)
P3 = (PW + Pw) 2
14
= (58474+29400) 2
=615118 N
Stress in equivalent section = ( 1000 600 )+ 12 4241.4 = 0.95 N/mm2 < 1.2
Hence safe.
The 8 mm distribution bars (vertical bars) provided in the wall @ 150 mm c/c should
be taken round the above rings to act as stirrups.
39
Ww =
{(
N.
Let the thickness of conical slab be 400 mm.
Total self weight W is given by
s
14+ 10
2 2 0.4
Ws = 25000
2
= 1066131 N
=255613 N/m
40
Meridional stress =
W2
cos 0
361437
1000 400
(b) Hoop tension : Diameter of conical dome at any height above base is
h
( 1410
2 )
'
D = 10 +
= 10 + 2h
P0 =
p
+qtan 0
cos 0
D'
2
'
= {( 7h ) 9800 2+ ( 10000 1 ) }
10+2 h'
2
hoop tension
0
1
2
535075 N
558936 N
555079 N
For maxima,
d P0'
d h'
= 0 = 37720 2 13859 h.
41
Spacing of 16 mm bars =
1000 201
1869
= 107.5 mm
1000 201
100
= 2010 mm2.
560739
Max. tensile stress in composite section = ( 400 1000 ) +(12 2010 2) = 1.385 N/mm2.
This is more than the permissible value of 1.2 N/mm2 . Hence increase the thickness to
420 mm. This will reduce tensile stress to 1.198 N/mm2.
{ (
) }
420100
In the meridional direction, provide reinforcement @ 0.3 420100 0.1
% 0.21 %
Spacing of 10 mm bars =
1000 78.5
441
42
cos 2
= 0.8141
( 1.6 )
(10)2 7
(3 8.611.6) 9800
4
3
N = 4751259 N
290093
250 1000
Meridional stress =
5292241
Intensity of load per unit area =p2 = 2 8.61 1.6 =61142 N/m2
=
(safe)
61142 8.61
2 0.25
p2 R2
2t 2
43
250100
0.1 = 0.26 %
450100
Spacing of 10 mm bars =
100 78.5
650
=121 mm.
Hence provide 10 mm bars @ 120 mm c/c in both the directions. Also, provide 16
mm meridional bars @ 100 mm c/c near water face, for 1 m length, to take care of
the continuity effect. The thickness of the dome may be increased from 250 mm to 280
mm gradually in 1 m length.
Outward thrust from bottom dome = T2 cos 0 = 290093 0.8141 = 236165 N/m
10
Hoop compression in beam = 19448 2 = 97240 N
97240
600 1200
44
The load on beam = w= 424070 + 18000 = 442070 N/m.
No. of
Supports
4
C1
C2
C3
90
0.137
0.070
0.021
1
19 4
72
0.108
0.054
0.014
10
15 4
60
0.089
0.045
0.009
30
12 4
30
51 7
0.077
0.037
0.007
30
10 4
45
0.066
0.030
0.005
1
9 2
40
0.060
0.027
0.004
1
8 2
10
36
0.054
0.023
0.003
10
7 4
12
30
0.045
0.017
0.002
10
6 4
For Table, 2 = 45 = 4
; = 22.5 = 8
radians ;
10
m = 9 2
45
wR2(2 ) = 442070(5)2
( 4 )
= 8680024 N-m
For M-20 concrete (cbc =7 N/mm ) and HYSD bars (st =150 N/mm ) we have
2
572882 1000
600 1.156
= 909 mm
( )
= 868002 N
5 (22.5 - 9.5)
m , F = 442070
180 = 501512 N
10
m = 9 2 ) is given by
(sagging)
46
= 442070 (5)2
At the supports, = 0;
cos
= wR2 cos sin sin
= zero.
(b) At mid-span :
47
1
=9 2
Where MT = T
Ast1 =
1+ D/b
1.7
= 43400
= M =1421 ;
1+1.2/ 0.6
1.7
M e1
st jd
78009 1000
Me1 = M+MT
= 76588 N-m
48
Ast2 =
75167 1000
150 0.874 1160
= 494.3 mm2
point of maximum torsion, provide 2-25 mm bars each at the top and bottom.
M0t = 0
5728821000
49
Mc t = 0
Mc = 260401 N-m ;
For positive B.M., steel will be to other face, where stress in steel ( st ) can be
taken as 190 N/mm2. The constants for M20 concrete having c =7 N/mm2 and m =13
will be
k = 0.324 ;
260401 100
190 0.892 1160
= 1325 mm2
Transverse Reinforcement
(a) At point of max. torsional moment :
At the point of max. torsion, V = 501512 N
T
Ve = V +1.6 b
43400
V = 501512 + 1.6
e
0.6
ve =
Ve
617245
=
b d 600 1160
b = 600 mm = 0.6 m
= 617245 N
= 0.887 N/mm2
50
c max
100 (4 491)
600 1160
= 0.282
0.23 N/mm2
Since cve > c , shear reinforcement is necessary. The area of cross section Asv of the
stirrups is given by
Asv =
T . sv
b1 d1 sv
V . sv
2.5 d 1 sv
A sv
Sv
43400 1000
501512
A sv
Sv
Hence depth
=
A sv
Sv
0.8870.23
600
150
A sv ve c
b
Sv
sv
= 2.628.
= 2.628
x1+ x2
4
51
At supports,
c
v=
868002
600 1160
100 (8 491)
600 1160
= 1.25 N/mm2
= 0.564
sv . A sv . d
Vs
= 83.8 mm
(c) At mid-span:
52
b . sv f y
given by
Or
A sv 0.4 b
=
sv
fy
A sv 0.4 600
=
sv
415
= 0.578
Sv = 0.578 = 543 mm
Max. permissible spacing = 0.75d = 0.75 1160 = 870 or 300 mm, whichever is less.
Hence provide 10 mm 4 lgd stirrups @ 300 mm c/c.
Side Face Reinforcement: Since the depth is more than 450 mm, provide side face
reinforcement @ 0.1 %.
A l=
0.1
( 600 1200 ) = 720 mm2 .
100
Provide 3-16 mm bars on each face, having total A l=6 201 = 1206 mm2.
53
(i)
(ii)
(iii)
(iv)
2
Weight of column per metre height = 4 (0.7) 1 25000 = 9620 N
2
n
cos
n
sin
cos
8
sin
=5
= 3.83 m
54
Hence total weight of column just above each brace is tabulated below:
Brace GH:
W = 1736000+4 9620 = 1774480 N
Brace EF:
W = 1736000+8 9620+14085 = 1827045 N
Brace CD:
W = 1736000+12 9620+2 14085 = 1879610 N
Bottom of column:
W = 1736000+17 9620+3 14085 = 1941795 N
(b) Wind loads: Intensity of wind pressure = 1500 N/m2. Let us take a shape factor of 0.7
for sections circular in plan.
55
2
(5 14.4 ) + 14.2 1.9 + ( 212.8 )+(10.6 1.2) 1500 0.7
3
= 134720 N
This may be assumed to act at about 5.7 m above the bottom of ring beam.
Wind load on each panel of 4 m height of columns
=
56
1
Wind load at the top end of top panel = 2 23520=11760 N. The wind loads are shown
in fig. The point of contra flexure O1 , O2 , O3 and O4 are assumed to be at the mid-height
Level
O4
Qw (N)
146480
Mw (N-m)
134720 7.7+11760 2 = 1060860
O3
179540
O2
212600
245660
4 Mw
n Do
4 Mw
shear
force Smax = 2Qw/n = 0.25Qw in the column on the bending axis at each of the above
levels and bending moment M = Smax
Level
O4
O3
O2
O1
h
2
Vmax
53040
85650
124860
170950
M (N-m)
73240
89780
106300
153550
The farthest leeward column will be subjected to be superimposed axial load plus Vmax
given above. The column on the bending axis, on other hand, will be subjected to
superimposed axial load plus a bending moment M given above. These critical
combinations for various panels of these columns are tabulated below:
Farthest Leeward column
57
Panel
O4 O4'
O3 O3'
O2 O2'
O1 O1'
Vmax (N)
53040
85650
124860
170950
M (N-m)
73240
89780
106300
153550
According to I.S. Code, when effect of wind load is to be considered, the permissible
1
stresses in the material may be increased by 33 3 %. For the farthest leeward column
the axial thrust Vmax due to wind load is less than even 10% of the superimposed axial
load. Hence the effect of wind is not critical for the farthest leeward column. However,
column situated on the bending axis need be considered to see the effect of maximum
B.M. of 153550 N-m due to wind, along with the superimposed axial load of 1941795 N
at the lowest panel. Use M20 concrete, for which and cbc = 7 N/mm2 and cc = 5
1
N/mm2 For steel, st = 230 N/mm2. All of three can be increased by 33 3 % when
A sc = (30)2 12
4
= 8482 mm2
Ic =
8482(629)
(700)4 +(131)
64
8
cc
58
153550 1000
350
1.6676 1010
= 3.22 N/mm2
Or
or
3.99
3.22
+
<1
1.33 5 1.33 7
0.95 < 1
Hence safe.
Use 10 mm wire rings of 250 mm c/c to tie up the main reinforcement. Since the
columns are of 700 mm diameter, increase the width of curved beam B2 from 600 mm to
700 mm.
10. Design of braces: The bending moment m1 in a brace is given by equation its
maximum value being governed by:
( 8 )= 12 cot
tan +
Q w1 . h1+ Qw 2 . h2
cos 2 sin +
2
n
nsin
n
( )
( 245660 5 )+(212600 4) 2
180
cos 24.8 sin ( 24.8 +
)
2
8
= 222540 N-m
8 sin
8
59
(Sb)max =
2 cos
2
( 2 sin )
8
8
( 245660 5 )+(212600 4)
2
3.93 8 sin
8
For =
[ ( m1 ) ]= =
8
= 112870 N
( 245650 5 )+(212600 4) 2
cos sin +
2
8
8 8
8 sin
8
Twisting moment at = 8
= 221786 N-m
Thus the brace will be subjected to a critical combination of max. shear force (Sb)max and
).
The brace is reinforced equally at top and bottom since the sign of moment (m1) will
depend upon the direction of wind.
For M20 concrete, c = cbc = 7 N/mm2 , m=13, also st = t =230 N/mm2 ; k =
0.283 ;
j = 0.906 and R= 0.897. Depth of N.A = 0.283d. Let Asc =Ast = p b d and dc
= 0.1 d
Equating the moment of equivalent area about N.A.
1
2
b(0.283 d ) + ( 131 ) p bd ( 0.283 d0.1 d )=13 p bd ( d0.283 d )
2
60
MT = T
( 1+1.7D /b )
MT = 11090
1+700/300
1.7
= 21745 N-m
[ ]
c
n
d + ( mc 1 ) A sc . c ' ( dd c )=M e 1
2
3
9.31(0.2830.1)
0.283
= 6.02 N/mm2
Hence,
300 0.283 d
9.31
0.283
1
d + ( 19.51 ) ( 0.0056 300 d ) 6.02 ( 10.1 ) d
2
3
3
244285 10
Or
61
11090
Ve = V + 1.6 T/b = 112870 + 1.6 0.3 = 172017 N
ve =
172017
300 700
=0.82 N/mm2
This is less than c .max but more than c = 0.37 N/mm2. Hence transverse
reinforcement is necessary.
A sv =
T . sv
V . sv
+
b1 d 1 sv 2.5 d 1 sv
Where
2
Using 12 mm 2 lgd stirrups, A sv =2 4 (12) = 226 mm2.
A sv
11090 100
112870
=
+
= 0.333+ 0.312=0.645
sv
230 630 230 2.5 630 230
b
sv
sv
sv=
A sv 0.820.37
=
300=0.587
sv
230
A sv
226
=
=350 mm
0.645 0.645
x1 + y1
4
and 300 mm
62
=231 mm.
Hence provide 12 mm 2 lgd stirrups at 230 mm c/c throughout. Since the depth of
section exceeds 450 mm, provide the side face reinforcement @ 0.1 %.
A l=
0.1
(300 700) = 210 mm2 .
100
Provide 2-10 mm bars at each face, giving total A l=4 78.5 = 314 mm2.
Provide 300 mm 300 mm haunches at the junction of braces with columns and
reinforce it with 10 mm bars.
Vmax due of wind load = 170959 8 , which is less than 33 3 % of the super
imposed load. Assume self weight etc. as 10% = 1553436 N
Total load = 15534360 + 1553436 = 17087796 N
Area of foundation required = 17087796/150000 =
113.9 m2
Circumference of column circle = 10 = 31.42 m
Width of foundation =
113.9
31.32
63
2
2
Area of annular raft = 4 (13.64 6.36 ) = 114.35 m2
4
4
Moment of inertia of slab about a diametrical axis = 64 [ 13.64 6.36 ] =1618.8 m4
13.64
2
= 54179233 N-m
m
Hence the soil pressure at the edges along a diameter are
(a) tank full :
114.35
1618.8
2
64
114.35
1618.8
2
Under the wind load, the allowable bearing capacity is increased to 150 1.333 = 200
kN/m2, which is greater than the maximum soil pressure of 167.96 kN/m2. Hence the
foundation raft will be designed only for super-imposed load.
The layout of the foundation is shown in fig. A ring beam of 700 mm
width may be provided. The foundation will be designed for an average pressure p:
15534360
135849 N/m2
114.35
p=
1 1
(1.47)
= 146778 N-m ; S.F. = 135849 1.47 = 199698 N
B.M. = 135849
2
d=
146778 1000
1000 0.897
= 405 mm
Provide 450 mm thick slab with effective depth of 410 mm. Decrease the total depth of
250 mm at the edges.
A st =
146778 1000
230 0.906 410
= 1718 mm2
Spacing of 16 mm bars =
1000 201
1718
Spacing of 10 mm bars =
0.15
1000 450
100
1000 78.5
675
= 675 mm2
110 mm c/c at the support. Increase this spacing to 200 mm at the edge.
65
Design of circular beam of raft: The design of circular beam of raft will be practically
similar to the circular beam B2 provided at the top of the columns.
Design load =
15534360
10
= 494474 N/m
The circular beam B2 was designed for w = 442070 N/m. Hence the B.M. etc. will be
increased in this ratio of 494474/442070 = 1.119
1
=m =9 ,
2
= 230 N/mm2 .
d=
640790 1000
700 0.897
= 1010 mm
However, keep total depth of 1200 mm from shear point of view. Using an effective
cover of 60 mm, d= 1140 mm
66
D/b
Where MT = T 1+ 1.7
A st =
1200/ 700
= 48545 1+ 1.7
M e1
79098 1000
=
st j d 230 0.906 1140
A st 2 =
= 77509 N-m
Since MT>M ,
= 333 mm2 ;
75920 1000
230 0.906 1140
= 319.6 mm2
640790 1000
230 0.906 1140
Mot = 0
= 2697 mm2 ;
5.49
However, provide 6 bars of 25 mm at the bottom of the section, near supports.
(c) Section at max. sagging B.M. (mid-span)
Mc = 291268 N-m ;
A st =
M ct = 0
291268 1000
230 0.906 1140
= 1226 mm2
67
0.166 = 0.83 or equal to L =
d
. st 230
=
=
4 bd 4 1.12
52 = 52 25 = 1300 mm
whichever is more.
Beyond this, discontinue 2 bars, while the remaining 4 bars may be continued
throughout the length.
Similarly, provide 4-25 mm bars at top, throughout the length. These bars will take
care of both the maximum positive B.M. as well as maximum torsional moment.
Transverse reinforcement:
(a) At the point of minimum torsional moment
V = 560960 N-m
T
V = V + 1.6
e
b
ve =
672152
700 1140
= 0.84 N/mm2
c max
A sv =
48545
= 560960 + 1.6 0.7
= 672152 N
T . sv
V . sv
+
b1 d 1 sv 2.5 d 1 s v
where
68
b
sv
sv
A sv
sv
Hence adopt
A sv 0.840.22
=
700
sv
230
= 1.887
x1 + y1
4
= 441 mm.
v=
970893
700 1140
= 1.22 N/mm2.
At supports,
69
2
The spacing of 12 mm 4-lgd stirrups having A sv = 4 (12) = 452.4 mm2 is given by
sv=
b . sv f y
or
sv = 314/0.675 = 465 mm
Max. permissible spacing = 0.75d = 0.75 1140 = 855 or 300 mm, whichever is less.
Side Face Reinforcement: Since depth is more than 450 mm, provide side face
reinforcement @ 0.1%
A l=
0.1
( 700 1200 )= 840 mm2
100
70
71
72
14. ESTIMATION
A (m2)
191.55 2
Earthwork in
excavation
H or
D
(m)
QTY
(m3)
REMARKS
383.09
A= d /4
13.842 / 4
= 191.55
2 Earthwork in
filling
77.2
154.4
A=ar ( Excavation)ar ( Annular raft )
=191.55-114.35
=77.2
73
R.C.C work in 1
Foundations
114.35 2
228.7
R.C.C work in 8
Columns
0.385
52.36
17
A= / 4 (0.7)2
0.385
R.C.C work in 8
Bracings @
4m from G.L
3.13
0.3
0.21
0.7
0.66
A=0.3 0.7=0.21
R.C.C work in 8
Bracing @ 8
m from G.L
3.13
0.3
0.21
0.7
0.66
A=0.3 0.7
R.C.C work in 8
Bracings @ 12
m from G.L
3.13
R.C.C work in 1
circular girder
0.21
0.3
0.21
0.7
0.66
A=0.3 0.7
0.21
0.7
0.84
1.2
26.39
Circumference=2 r
2 (5)
= 31.42
A=2 rh
R.C.C work in
Bottom dome 1
86.56
10 R.C.C work in 1
Conical Slab
0.25
106.63 0.4
21.64
2 8.61 1.6=86.56
42.65
A= ( R+ r)l
( 7+5 ) 2 2=106.63
11 R.C.C work in 1
Ring
Beam
(B3)
0.7
0.42
0.6
18.87
R= 7+0.15 = 7.15
Circumference=2 r
74
2 ( 7.15 ) = 44.92
12 R.C.C work in 1
Cylindrical
wall
0.25
13 R.C.C work in 1
Ring beam
(B1)
0.4
219.91
S . A=2 Rh
54.98
2 7 5=219.91
0.144
0.36
Circumference=2 r
6.33
2 (7)
= 43.98
A=2 r (r (r h))
14 R.C.C work in
Top dome
1
164.10 0.1
16.41
2 rh
2 14.51 1.8
164.10
470.31
A=2 rh
2 14.46 1.8=163.54
r =14.51-0.05 = 14.46
A=2 rh
2 14.56 1.9=173.82
h=1.8+0.1 = 1.9
r=14.51+0.05= 14.56
43.98
0.0094
0.41
ar(Plaster)
=
-ar(without plaster)
ar(Total)
= 0.384 0.2120.36
0.2
= 0.0094
[2
=2
(7)=43.98]
75
18 Plastering in 1
CM
(1:2)
for
Inner
surface Of
cylindrical
wall
(12mm)
19 Plastering in 1
CM (1:6) for
outer surface
Of
cylindrical
wall
(12mm)
20 Plastering in 1
CM
(1:2)
Ring
Beam
(B3)
0.012 219.91 5
2.63
A=2 rh
= 2 (7)(5)
=219.91
0.012 227.76 5
2.73
r = 7+0.25 = 7.25
A=2 rh
= 2 (7.25)(5)
=227.76
44.92
0.024
1.08
ar(Plaster)=ar(Total)ar(without plaster)
0.6
= 0.024
Circumference=2 r
= 2 (7.15) = 44.92
21 Plastering in
CM(1:2) for
inner
surface of
conical
slab(12mm)
22 Plastering in
CM(1:6) for
outer
surface of
conical
slab(12mm)
A= ( R+ r) l
( 7+5 ) 2 2
= 106.63
23 Plastering in 1
CM (1:2) for
Inner surface
Of
bottom
A= ( R+ r)l
( 7.4+ 5.4 ) 2 2
= 113.74
R = 7+0.4=7.4
r = 5+0.4=5.4
A=2 rh
2 8.74 1.85=101.59
[
76
[h = 1.6+0.25 =1.85]
dome (12mm)
24 Plastering in 1
CM (1:6) for
outer surface
Of
bottom
dome (12mm)
25 Plastering in 1
CM (1:6) for
inner surface
Of
circular
girder (12mm)
26 Plastering in 1
CM (1:6) for
outer surface
Of
circular
girder (12mm)
27 Plastering in
CM (1:6) for
bracings at 4m
from G.L
(12mm)
28 Plastering in
CM (1:6) for
bracings at 8m
from G.L
(12mm)
29 Plastering in
CM (1:6) for
bracings at
12m from G.L
(12mm)
30 Plastering in
CM (1:6) for
columns
85.35
0.012 1.02
A=2 rh
2 8.49 1.6=85.35
[ r =8.61-0.125 = 8.49 ]
0.012 0.38
1.2
0.45
Circumference=2 r
= 2 (5) = 31.42
0.012 0.43
1.2
0.52
r = 5+0.7 = 5.7
Circumference=2 r
= 2 (5.7) = 35.81
3.13
0.2
0.626
ar(Plaster)=ar(Total)ar(without plaster)
=0.324 0.724 0.3
0.7
= 0.025
3.13
0.2
0.626
3.13
0.2
0.626
0.216
17
3.67
ar(Plaster)=ar(Total)ar(without plaster)
77
/4 (0.724)2 /4 (0.7)2
(12mm)
Total plastering
22.29
31 Thick
water 1
proof cement
painting
for tank
portion
723.91
173.82+33.4+227.76+
89.84+113.74+85.35
( Ring beam B1 =
2 rb
2 r h+2 ]
= 2 (7)(0.36)+ 2[
2 (7)(0.2)]
=15.8+17.9 = 33.4 )
( Ring beam B3 =
2 rb
2 r h+2 ]
= 2 (7.15)(0.6)+ 2[
2 (7.15)(0.7)]
=26.95+62.89 =89.84 )
32 Total White
washing
1253.8 723.91+80.66
8
+150.24+ 299.07
[ Circular girder area =
2 r1h + 2 r2h
= 2 (5)(1.2) + 2
(5.7)(1.2)
=37.69+42.97
=80.66 ]
[ Bracing area = 24(2
(3.13 0.3) + 2
78
(3.13 0.7))
= 150.24 ]
[ Column area = 8 (
2 rh)
= 8 ( 2 (0.35)
(17))
= 299.07 ]
ABSTRACT
S.NO
DESCRIPTION
OF WORK
QTY
OR
NOS
Earth work in
excavation
383.09
Beldars
Mazdoors
Total
26
20
Earth work in
Filling In
foundation
154.4
Beldars
Bhisthi
Mazdoors
Total
15
5
10
RATE
RS
PS
COST
RS
PS
250
250
6500
5000
11500
250
285
250
3750
1425
2500
7675
250
5000
Disposal
of 228.7
surplus earth in
a lead 30m
Mazdoors
20
79
Total
5000
24,175
Total cost of
earth work
FOUNDATION
MATERIALS
20mm HBG graded metal Cum
Sand
Cement
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
Concrete Mixer 10/7 cft
(0.2/0.8cum)capacity
Cost of Diesel for Miller
Cost of Petrol for Vibrator
Water (including for curing)
Add 20% in Labour (1st Floor)
Add MA 20%
Add TOT 4%
TOTAL COST
6.2
2.4
3.7
1.5
250
53
67
77
1550
127.20
247.90
115.50
48805.55
48805.55
9761.11
351400
80
COLUMNS
MATERIALS
20mm HBG graded metal Cum
Sand
Cement
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
Concrete Mixer 10/7 cft (0.2/0.8cum)
capacity
Labour centering
Material hire charges for centering
Water (including for curing)
Add 20% in Labour (1st Floor)
Add MA 20%
Add TOT 4%
TOTAL COST
2
2
2
1.5
250
971
89
77
500
1942
178
115.50
15172.38
15172.38
3034.47
109241.17
250
250
81
Labour centering
Material hire charges for centering
Water (including for curing)
Add 20% in Labour (1st Floor)
Add MA 20%
Add TOT 4%
TOTAL COST
Cum
Cum
KL
2
2
1.5
971
89
77
1942
178
115.5
2381.58
2381.58
476.31
17147.41
DOMED ROOF
MATERIALS
20mm HBG graded metal Cum
Sand
Cement
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
Concrete Mixer 10/7 cft (0.2/0.8cum)
capacity
Labour centering
Material hire charges for centering
Water (including for curing)
Add 20% in Labour (1st Floor)
Add MA 20%
Add TOT 4%
TOTAL COST
CONICAL SLAB
1
15
15
1.5
250
971
89
77
250
14565
1335
115.5
8475.53
8475.53
1695.10
61023.85
82
MATERIALS
20mm HBG graded metal Cum
Sand
Cement
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
Concrete Mixer 10/7 cft (0.2/0.8cum)
capacity
Labour centering
Material hire charges for centering
Water (including for curing)
Add 20% in Labour (1st Floor)
Add MA 20%
Add TOT 4%
TOTAL COST
0.86
10
10
1.5
250
971
89
77
215
9710
890
115.5
14490.69
14490.69
2898.13
104333
CYLINDRICAL WALL
MATERIALS
20mm HBG graded metal Cum
UNI
T
Cum
Sand
Cum
Cement
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
Concrete Mixer 10/7 cft (0.2/0.8cum)
capacity
Labour centering
Material hire charges for centering
Water (including for curing)
Add 20% in Labour (1st Floor)
Cum
Day
Day
Day
Hour
0.96
250
Cum
Cum
KL
2
2
1.5
971
89
77
240
1942
178
115.5
17586.73
83
Add MA 20%
Add TOT 4%
TOTAL COST
17586.73
3517.34
126624.49
0.96
2
2
1.5
250
971
89
77
240
1942
178
115.5
6129.02
6129.02
1225.80
44128.98
MATERIALS
UNIT
Cum
Sand
Cement
1st Class Mason
Cum
Cum
Day
CIRCULAR GIRDER
84
Day
Day
12
16
285
250
3420
4000
Hour
0.96
250
Cum
Cum
KL
2
2
1.5
971
89
77
240
1942
178
115.5
8852.09
8852.09
1770.41
63735.08
0.38
2
2
1.5
250
971
89
77
95
1942
178
115.5
711.35
711.35
142.27
5121.76
UNI
85
T
Cum
Cum
Cum
Day
Day
Day
0.36
0.18
0.12
0.18
0.40
0.98
1405.04
509.92
1820
285
285
250
Hour
0.38
250
Cum
Cum
KL
2
2
1.5
971
89
77
RS
505.81
91.78
218.40
51.30
114
245
95
1942
178
115.5
711.35
711.35
142.27
5121.76
UNIT QTY
Cum
Cum
Cum
Day
Day
Day
0.36
0.18
0.12
0.18
0.40
0.98
RATE
RS
1405.04
509.92
1820
285
285
250
Hour
Cum
Cum
KL
0.38
2
2
1.5
250
971
89
77
AMOUNT
RS
505.81
91.78
218.40
51.30
114
245
95
1942
178
115.5
711.35
86
Add MA 20%
Add TOT 4%
TOTAL COST
711.35
142.27
5121.76
Plastering with
CM(1:6) & (1:2) (12 mm thick)
Material
Cement Mortar
1:6
1:2
Mason 1st class
Bhisthi
Mazdoor (unskilled)
Add MA 20%
Add TOT 4%
Grand Total
Unit
cum
cum
day
day
day
Qty
22.29
13.71
8.58
30
10
30
Rate
Amount
RS
1889
3200
25898.19
27456
8550
2850
7500
14450.83
2890.16
89595.18
285
285
250
Painting to new walls of tank portion with 2 coats of water proof cement paint of
approved brand and shade over a base coat of approved cement primer grade I
making 3 coats in all to give an even shade after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and
conveyance of all materials to work site and all operational, incidental, Labour
charges etc. complete for finished item of work as per SS 912 for walls
Material
Epoxy primer for Hi bond floor &
protective coatings : Procoat SNP2 or
Zoriprime EFC 2
1st class painter
Mazdoor
cost of water proof cement paint
Unit
Qty
Rate
Amount
RS
Pack
20
548
10960
Day
Day
Cum
4
4
40
355
250
35
1420
1000
1400
87
Day
Day
2
2
355
250
710
500
3198
639.60
19827.60
Painting to new columns of tank portion with 2 coats of water proof cement paint of
approved brand and shade over a base coat of approved cement primer grade I
making 3 coats in all to give an even shade after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, including cost and
conveyance of all materials to work site and all operational, incidental, Labour
charges etc. complete for finished item of work as per SS 912 for walls
Material
Cost of cement primer
1st class painter
2nd class painter
cost of water proof cement paint
1st class painter
Mazdoor (unskilled)
Add MA 20%
Add TOT 4%
Total cost
Unit
Qty
Rate
Pack
Day
Day
Cum
Day
Day
15
1
1
6
1
1
100
355
250
35
355
250
8,92,999
= 20,53,898
89,595
23,449
24,175
Amount
RS
1500
355
250
210
355
250
584
116.8
3620.80
88
= 30,84,116
4,62,617
Add 3 % contingency
92,524
Total Cost
36,39,257
15. CONCLUSION
Storage of water in the form of tanks for drinking and washing purposes,
swimming pools for exercise and enjoyment, and sewage sedimentation tanks
are gaining increasing importance in the present day life. For small capacities
we go for rectangular water tanks while for bigger capacities we provide
circular water tanks. Design of water tank is a very tedious method. Without
power also we can consume water by gravitational force.
Intze tank is constructed to minimize the project cost why because lower
dome in this construction resists the horizontal thrust.
89
16. REFERENCES
Table 16.2. Coefficients for moment in cylindrical wall fixed at base(As per IS3370)
Moment = Coefficient (wH3) Nm/m
Co efficient at points
H2
DT
0.1 H
0.2 H
0.3 H
0.4 H
0.5 H
0.6 H
0.7 H
0.8H
0.4
+ 0.0005
+ 0.0014
+ 0.0021
+ 0.0007
- 0.0042
-0.0150
- 0.0302
- 0.0529
0.8
+ 0.0011
+ 0.0037
+ 0.0063
+ 0.0080
+ 0.0070
+ 0.0023
+ 0.0068
0.0024
1.2
+ 0.0012
+ 0.0042
+ 0.0077
+ 0.0103
+ 00112
+ 0.0090
+ 0.0022
- 0.0108
1.6
+ 0.0011
+ 0.0041
+ 0.0075
+ 0.0107
+ 0.0121
+ 0.0111
+ 0.0058
- 0.0051
2.0
+ 0.0010
+ 0.0035
+ 0.0068
+ 0.0099
+ 0.0120
+ 0.0115
+ 0.0075
- 0.0021
3.0
+ 0.0006
+ 0.0024
+ 0.0047
+ 0.0071
+ 0.0090
+ 0.0097
+ 0.0077
+ 0.0012
4.0
+ 0.0003
+ 0.0015
+ 0.0028
+ 0.0047
+ 0.0066
+ 0.0077
+ 0.0069
+ 0.0023
5.0
+ 0.0002
+ 0.0008
+ 0.0016
+ 0.0029
+ 0.0046
+ 0.0059
+ 0.0059
+ 0.0028
6.0
+ 0.0001
+ 0.0003
+ 0.0008
+ 0.0019
+ 0.0032
+ 0.0046
+ 0.0051
+ 0.0029
8.0
0.0000
+ 0.0001
+ 0.0002
+ 0.0008
+ 0.0016
+ 0.0028
+ 0.0038
+ 0.0029
90
10.0
0.0000
+ 0.0000
+ 0 0001
+ 0.0004
+ 0.0007
+ 0.0019
+ 0.0029
+ 0.0028
12.0
0.0000
+ 0.0000
+ 0.0001
+ 0.0002
+ 0.0003
+ 0.0013
+ 0.0023
+ 0.0026
14.0
0.0000
0.0000
0.0000
0.0000
+ 0.0001
+ 0.0008
+ 0.0019
+ 0.0023
16.0
0.0000
0.0000
-0.0001
- 0.0002
-0.0001
+ 0.0004
+ 0.0013
+ 0.0019
Table 1:
Permissible stresses in concrete
All values in N/mm2
Grade
Of concrete
Direct
cbc
cc
M 10
3.0
2.5
M 15
5.0
4.0
0.6
M 20
7.0
5.0
0.8
M 25
8.5
6.0
0.9
M 30
10.0
8.0
1.0
M 35
11.5
9.0
1.1
M 40
13.0
10.0
1.2
M 45
14.5
11.0
1.3
M 50
16.0
12.0
1.4
Table 1.1:
91
Grade of
Concrete
Tensile
M10
M15
M20
M25
M30
M35
1.2
2.0
2.8
3.2
3.6
4.0
M40 M45
4.4
4.8
Stress (N/mm )
Table 2:
Moments for circular girders
For 8 columns
B.M@
B.M@
Support
centre
0.0083Wr
0.00416Wr
Torsion
0.0006Wr
M50
5.2
92
17 . REFERENCE BOOKS
93