Beruflich Dokumente
Kultur Dokumente
INTEGRATED POWER
DEVELOPMENT SCHEME
(IPDS)
(Approved by IPDS Monitoring Committee)
1.2
1.3
1.4
1.5
1.6
1|P age
areas and,
(iii) IT enablement of distribution sector and strengthening of distribution
network, as per CCEA approval dated 21.06.2013 for completion of the
targets laid down under R-APDRP for 12th and 13th Plans by subsuming
R-APDRP in IPDS and carrying forward the approved outlay for RAPDRP to IPDS.
3.
2.2
The approval has been accorded for components (i) and (ii) above
having scheme cost of Rs.32,612 crore including a budgetary support of
Rs.25,354 crore from Government of India during the entire
implementation period.
2.3
2.4
These guidelines shall be applicable only for the components (i) & (ii) above
of the scheme viz. Strengthening of Sub-transmission & Distribution system,
including provisioning of solar panels on Govt. buildings including Netmetering, metering of feeders / distribution transformers / consumers in the
urban areas and IT enablement of distribution sector. All the existing
operational Guidelines/ Standard documents/ procedures of R-APDRP shall
continue to prevail for implementation of R-APDRP component. All ongoing
projects under component (iii) of the scheme will be implemented as per
CCEA approval dated 21.06.2013, so as to ensure that commitment made /
targets fixed under RAPDRP are achieved.
2|P age
Chapter II
1. Project formulation: Project formulation under the scheme will be a two stage
process as explained below:
(a) 1st Stage: The utilities will identify need for critical gaps in subtransmission and distribution network considering all relevant parameters
such as consumer mix, consumption pattern, voltage regulation, AT&C
loss level, HT & LT ratio, optimum loading of transformers & feeders /
lines, reactive power management, power factor improvement, standard of
performance etc. and on-going works under other schemes for efficient
management of distribution system. Based on the assessment, utilities will
prioritize scope of work to ensure (i) 24x7 power supplies for consumers in
urban area, (ii) reduction of AT&C losses as per trajectory (discom-wise)
finalized by the Ministry of Power in consultation with States (iii) providing
access to all urban households. Utility shall prepare a Need Assessment
Document (NAD) in prescribed format (being circulated by nodal agency
separately) containing all relevant information along with justifications to
substantiate the proposed scope of work and cost estimates. The NAD
will be examined by the nodal agency to arrive at broad scope of work to
be covered under the scheme and the total cost in consultation with
concerned utilities.
(b) 2nd Stage: Based on the broad scope of work validated by Nodal agency
at 1st Stage, the utilities will formulate bankable Detailed Project Reports
(DPRs) based on detailed field survey and latest approved schedule of
rates for various items of work. These DPRs, duly recommended by the
Distribution Reforms Committee (DRC) at the State level, will be submitted
by the utilities to the Nodal agency for appraisal. The Nodal Agency will
separately provide comparable costs sourced from CPSUs for major
equipment for reference of the utility. These reference rates shall be used
as ceiling rates for sanctioning of the projects. Grant shall be extended on
the sanctioned cost or award cost of the project, whichever is lower. While
formulating DPRs, utility shall necessarily consult the public
representatives including Member of Parliament. Utility shall furnish a
certificate to this effect while submitting DPRs to Nodal Agency.
2. Scope of Works:
The projects under the scheme shall be formulated for urban areas (Statutory
Towns) only and will cover works relating to strengthening of sub-transmission
& distribution network, including provisioning of solar panels on Govt. buildings
including Net-metering, metering of feeders /distribution transformers /
consumers and IT enablement of distribution sector. Scope of IT enablement
extended to the statutory towns having population upto 5000 as per Census
2011. In 1st phase towns having population upto 15000 may be taken up and
the population threshold may be gradually reduced to 5000. For special
3|P age
4|P age
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
(xi)
(xii)
(xiii)
3. Eligible entities: All Discoms including private sector Discoms and State Power
Departments (referred to as Utilities) will be eligible for financial assistance under
the scheme. In case of private sector Discoms where the distribution of power
supply in urban areas is with them, projects under the scheme will be
implemented through a concerned State Government Agency and the assets to
be created under the scheme will be owned by the State Government / State
owned companies. These assets will be handed over to the concerned Discom
for their use during the license period on mutually agreed terms and conditions.
The responsibility of operation and maintenance of these assets would be of the
concerned Discom. The areas under franchisee shall be covered under the
scheme subject to compliance with the terms & conditions of their respective
agreements and Cooperative Societies shall also be eligible, but they would be
required to submit Audited statements annually regarding the utilization under
5|P age
5.
DPR for NOFN component: Government of India has already approved the
setting up of National Optical Fiber Network (NOFN) to provide connectivity to
2,50,000 Gram Panchayats spread over 6,600 Blocks and 641 Districts of the
country, which would ensure broadband connectivity with adequate bandwidth.
The existing optical fiber will be extended up to the Gram Panchayats. The
Programme is being implemented through Bharat Broadband Network Limited
(BBNL), which is a Special Purpose Vehicle set up by Government of India with
the mandate to create the National Optical Fiber Network (NOFN) in India.
The IPDS scheme envisages to connect all the 33 KV or 66 KV grid substations/billing offices/Regional/Circle/Zonal offices of Discoms by extending
optic fiber network being established under NOFN. Provision of 100% grant has
been made under the scheme for connecting the missing links of NOFN
including terminal equipment, provided such connectivity has not been included /
approved under any other scheme of Govt. of India / State Govt. A declaration of
the state regarding coverage of optic fiber missing links as per the provision of
the scheme shall form a part of tripartite/ bipartite agreement to be executed with
state.
A separate and consolidated DPR shall be prepared by the respective utility in
consultation with BBNL or any designated agency like BSNL, RailTel, PGCIL
etc. for the NOFN programme in the state. The DPR shall include the proposed
implementation methodology and milestones along with the cost. DPRs
recommended by the DRC shall be submitted to the Nodal Agency.
6.
Eligible Cost for determining grant: The project cost approved by the
Monitoring Committee or award cost of the project (including price variation, if
any), whichever is less, shall be the eligible cost for determining the Grant
6|P age
8.
9.
8|P age
b)
b)
c)
d)
e)
f)
b)
c)
d)
e)
f)
5. State Government
a)
c)
d)
To provide required land for sub stations and facilitate in obtaining other
statutory clearances (ROW, forest, railway clearance, safety clearance
etc.)
e)
f)
g)
To furnish guarantee for the loan component under the scheme in case
the utility is not able to provide any other mode of security.
11 | P a g e
1.
Funding Mechanism
1.1 Categorization of States: The states have been categorized in two
groups (i) Special Category States (All North Eastern States including
Sikkim, J&K, Himachal Pradesh, Uttarakhand) and (ii) Other than Special
Category States (all other states).
1.2 The financial support under the scheme shall be as under:
Nature of
support
Agency
Govt. of India
Quantum of support
(Percentage of project cost)
Other than Special
Special Category
Category States
States
Grant
60
85
Own Fund
10
Loan/own
fund
30
10
Grant
Grant
75%
90%
Discom Contribution*
Lender
(FIs/
Discoms own fund
Banks)/
1.3 The grant support from budget of Ministry of Power shall be as follows:
Instalment
No.
1
2
3
4
5
Release of Grant
Component of GoI
10%
20%
60%
10%
100%
12 | P a g e
metered consumption.
1.5 At the time of seeking additional grant, Utilities are required to submit
claims duly verified by Head of utility regarding achievement of milestones
mentioned under 1.4 above.
2.
Flow of Funds
2.1 PFC shall submit proposal to Ministry of Power for release of funds for
further release to Utility when all the formalities for release to utilities are
completed to ensure minimum time gap between receipt of funds by PFC
from Ministry of Power and release to utilities by PFC.
2.2 On request from PFC and after satisfying that the conditions specified for
release of particular installment have been complied with Ministry of Power
shall release fund against that particular installment directly to PFCs
dedicated bank account.
2.3 Release by PFC
2.3.1 On request from Utilities, PFC shall release funds to the dedicated
bank accounts of utilities.
2.3.2 In order to receive fund under IPDS each utility shall open separate
dedicated bank account in nationalized banks having e-banking
facility. The nature of Programme account shall be current account
with CLTD (Corporate Liquid Term Deposit) facility.
2.3.3 Eligible fund for execution of the project shall be released to
Programme account and all due payments related to execution of
project(s) shall be made by Utilities from this account. Utilities shall
maintain books of accounts both for receipt of fund from PFC and
release to Contractors for each of the project.
2.3.4 The project cost approved by the Monitoring Committee or Award
cost of the project (including price variation, if any), whichever is
less, shall be the eligible cost for determining the Grant (including
additional grant) under the Scheme. However any cost overrun after
approval of the project (by Monitoring Committee) due to any
reason whatsoever shall not be eligible for any grant and shall be
borne by the utility/respective State Government.
13 | P a g e
Nodal Agency Fee: Nodal Agency, PFC shall be eligible for 0.5% of the project
costs approved by Monitoring Committee or award cost whichever is lower as
its fee, which shall be claimed as below:
i. 1st installment: 40% of the nodal agency fee (i.e. 40% of 0.5% of
approved project cost) in the financial years in which the projects are
approved by the Monitoring Committee under IPDS.
ii. 2nd installment: 30% of the nodal agency fee (i.e. 30% of 0.5% of
approved project cost) on award of approved projects.
14 | P a g e
Utility shall adopt CINB. All project related payments to the contractors
(and others) by Utility shall be done directly from the dedicated bank
account and in no case, Utility shall open any other bank account(s)
under IPDS. PFC shall have the view right of Utility account.
6.2.
All payment (to contractors & others) shall be made directly from the
dedicated bank account as per the established procedure through ebanking only.
6.3.
6.4.
6.5.
The Utility shall ensure that funds released under IPDS is utilized for
the purpose for which it is released and will not be diverted for any
other purposes other than IPDS whatsoever. In case of any breach or
deviation further release of funds shall be stopped.
6.6.
The Utility shall ensure that IPDS fund shall not be invested in any
other bank/branch, whether for short term or medium term, including
fixed deposits.
Utilization Certificate
Utility shall submit utilization certificates (UC) for the funds released during the
financial year and the utilization thereof in prescribed format, latest by 30th
April of succeeded year. Release of further fund to the state utilities will be
subject to submission of UC in the prescribed format. The UC shall provide the
physical progress/achievements also apart from financial utilization.
Auditing
8.1 The Utility will ensure auditing of IPDS accounts relating to receipts of
funds from PFC and expenditure incurred by the Utility against such
receipts during the F.Y. by independent Chartered Accountant and
furnish a report to PFC latest by 30th June of succeeding year. PFC shall
consider release of further funds on the receipt of audited report and
certificate from Charter Accountant.
8.2 In addition to above, the works and any other aspects like quality,
quantity, financial etc. under IPDS would be open to audit by the office of
the Comptroller & Auditor General of India (C&AG) as well as Internal
Audit Wing, Office of Controller of Accounts, Ministry of Power.
Monitoring of Programme
9.1
9.2
9.3
10
16 | P a g e
10.3
10.4
11
12
Completion of works:
A Project Completion Certificate shall be furnished by the utility, signed by
Head of Utility, which shall contain the information regarding date of
completion, details of major items of works approved and completed,
justification for non-completion or shelving of any project component,
expenditure against the project with item wise breakup certified by a practicing
Chartered Accountant (CA) etc. The project completion certificate needs to be
submitted to nodal agency for release of final tranche of grant component. A
format for project completion certificate will be made available in the web
portal for the scheme.
13
14.2 The evaluation of criteria (b) and (c) will be done for three consecutive
years starting from the year of award. The additional grant will be divided in
18 | P a g e
16
17
Miscellaneous
Ministry of Power/PFC may, from time to time, issue such directions for
compliances of Utilities as may be necessary for smooth implementation of the
IPDS.
19 | P a g e
ANNEXURE-I
20 | P a g e
ANNEXURE-II
21 | P a g e
ANNEXURE-III
22 | P a g e
Annexure-III
DISCOM wise AT&C Loss trajectory up to 2021-22 (Finalised by MoP in consultation with Discoms)
Region
Eastern
North Eastern
Northern
State
Bihar
NBPDCL
SBPDCL
Bihar Total
Jharkhand
Orissa
CESCO
NESCO
SESCO
WESCO
Orissa Total
Sikkim
West Bengal
Arunachal Pr.
Assam
Manipur
Meghalaya
Mizoram
Nagaland
Tripura
Delhi
BRPL
BYPL
NDPL
Delhi Total
2012-13
(PFC
Report)
56.00
53.97
54.63
47.49
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
43.49
46.63
46.63
46.63
39.49
42.63
42.63
42.63
36.49
38.13
38.13
38.13
32.49
34.00
34.00
34.00
29.49
30.00
30.00
30.00
27.00
27.00
27.00
27.00
24.00
24.00
24.00
24.00
21.00
21.00
21.00
21.00
18.00
43.61
39.61
49.36
41.87
42.94
53.51
34.43
60.26
31.85
85.49
26.60
27.55
75.30
33.85
39.55
35.92
44.76
37.97
38.94
49.51
30.51
56.76
29.85
78.49
33.11
27.02
67.21
29.85
37.58
34.13
42.53
36.07
37.00
45.51
29.00
53.26
28.35
71.49
31.29
26.14
64.21
27.35
35.55
32.29
40.23
34.12
35.00
41.51
28.00
49.76
26.85
64.49
29.79
25.77
59.21
24.85
33.51
30.44
37.93
32.17
33.00
37.51
26.00
46.26
25.35
56.49
28.29
24.59
53.21
22.35
30.98
28.14
35.06
29.74
30.50
33.51
24.00
42.76
23.85
48.00
26.79
23.49
47.21
20.85
28.44
25.83
32.19
27.30
28.00
29.00
23.00
39.26
22.00
40.00
25.29
22.13
41.21
20.00
25.90
23.52
29.31
24.86
25.50
26.00
22.00
36.00
20.00
34.00
23.79
21.13
35.21
18.00
23.36
21.22
26.44
22.42
23.00
23.00
21.50
33.00
18.50
28.00
22.29
19.75
29.21
17.00
20.82
18.91
23.56
19.99
20.50
20.00
21.00
30.00
17.00
22.00
20.79
18.62
24.21
16.00
15.16
17.94
13.12
15.22
14.67
17.35
12.69
14.72
14.17
16.76
12.25
14.22
13.92
16.46
12.04
13.97
13.67
16.17
11.82
13.72
13.17
15.58
11.39
13.22
12.95
15.32
11.20
13.00
12.45
14.73
10.77
12.50
12.21
14.44
10.56
12.25
11.96
14.14
10.34
12.00
Region
Southern
State
Haryana
DHBVNL
UHBVNL
Haryana Total
H.P.
J&K
Punjab
Rajasthan
AVVNL
JDVVNL
JVVNL
Rajasthan Total
Uttar Pradesh
DVVN
MVVN
PaVVN
PoVVN
KESCO
UP Total
Uttaranchal
Andhra Pradesh
APSPDCL
APEPDCL
AndhraTotal
Telengana
TSSPDCL
TSNPDCL
Telengana total
Karnataka
2012-13
(PFC
Report)
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
28.31
36.97
32.55
9.53
60.87
17.66
26.14
34.13
30.05
14.50
55.87
17.16
23.96
31.29
27.55
13.50
51.87
16.66
21.35
27.88
24.55
12.50
47.87
16.16
18.74
24.48
21.55
11.50
43.87
15.66
17.01
22.20
19.55
10.50
39.87
15.16
15.66
20.44
18.00
10.00
35.00
15.00
14.79
19.31
17.00
10.00
30.00
14.50
13.92
18.17
16.00
10.00
26.00
14.25
13.05
17.04
15.00
10.00
22.00
14.00
19.90
18.97
20.91
20.00
21.78
26.31
30.69
26.74
19.60
21.14
24.50
21.75
18.50
19.22
22.50
20.00
17.50
17.30
20.50
18.50
16.50
16.00
19.00
17.25
15.50
15.00
17.50
16.00
14.50
14.50
16.00
15.00
14.25
14.25
15.00
14.50
14.00
14.00
14.00
14.00
45.69
45.83
33.39
52.37
37.61
42.85
23.18
41.42
41.55
30.27
47.48
34.10
38.85
21.68
37.16
37.27
27.16
42.59
30.59
34.85
20.18
33.96
34.07
24.82
38.93
27.96
31.85
18.68
30.76
30.86
22.48
35.26
25.32
28.85
17.68
27.56
27.65
20.14
31.59
22.69
25.85
16.68
24.36
24.44
17.81
27.93
20.06
22.85
16.00
21.32
21.39
15.58
24.44
17.55
20.00
15.00
18.13
18.18
13.25
20.78
14.92
17.00
14.50
15.99
16.04
11.69
18.33
13.17
15.00
14.00
14.94
10.69
13.13
14.73
10.33
12.88
14.31
10.23
12.58
13.95
10.02
12.28
13.58
9.89
12.00
13.58
9.89
12.00
13.58
9.89
12.00
13.58
9.89
12.00
15.90
13.13
13.13
15.40
12.88
12.88
14.90
12.58
12.58
14.40
12.28
12.28
13.90
12.00
12.00
13.40
12.00
12.00
12.90
12.00
12.00
12.40
12.00
12.00
12.74
9.90
11.58
Region
Western
State
BESCOM
GESCOM
HESCOM
MESCOM
CHESCOM
Karnataka Total
Kerala
Pondicherry
Tamilnadu
Chattisgarh
Goa
Gujarat
DGVCL
MGVCL
PGVCL
UGVCL
Gujarat Total
Madhya Pr.
MPMKVVCL
MPPKVVCL
MPPuKVVCL
MP Total
Maharasthra
2012-13
(PFC
Report)
2013-14
2014-15
2015-16
2016-17
2017-18
2018-19
2019-20
2020-21
2021-22
20.45
18.28
20.44
14.57
30.42
20.78
10.53
9.13
20.72
25.12
14.14
16.52
25.51
20.40
14.31
16.50
18.25
11.15
19.00
20.22
24.48
13.89
15.36
25.03
20.00
13.10
15.81
17.90
10.80
18.00
19.72
22.37
13.64
14.89
24.37
19.66
12.70
15.35
17.43
10.50
17.00
19.22
20.66
13.39
14.23
23.92
18.99
12.08
14.92
16.86
10.25
16.00
18.97
19.07
13.14
13.37
23.41
18.56
11.65
14.27
16.29
10.00
15.00
18.72
17.49
12.64
12.72
22.84
17.96
11.28
13.59
15.72
10.00
14.00
18.47
16.17
12.00
11.87
22.44
17.43
10.79
12.99
15.15
10.00
13.00
18.22
15.11
12.00
11.51
21.72
17.00
9.92
12.51
14.57
10.00
12.00
18.00
14.52
12.00
10.91
21.01
16.36
9.32
12.19
14.00
10.00
11.00
18.00
14.00
12.00
10.40
14.94
30.41
14.37
19.87
13.58
17.41
26.63
11.75
18.58
14.48
16.64
28.22
16.39
21.58
14.48
15.80
25.68
15.57
20.41
14.48
15.01
23.37
14.80
19.29
14.48
14.26
21.27
14.80
18.24
14.48
14.26
19.35
14.80
17.25
14.48
14.26
17.61
14.80
16.31
14.48
14.26
16.03
14.80
15.42
14.48
14.26
14.58
14.80
14.58
29.97
28.16
36.40
31.15
21.95
29.61
23.67
23.68
25.86
20.45
27.00
21.58
21.68
24.47
18.95
25.00
19.96
20.00
23.10
17.45
23.00
19.13
19.00
21.73
16.45
21.00
18.29
18.00
20.38
15.45
19.00
17.44
17.00
18.83
15.00
17.00
16.58
16.00
16.50
14.50
16.00
15.72
15.50
15.75
14.25
15.00
15.00
15.00
15.00
14.00
ANNEXURE-IV
23 | P a g e
Annexure-IV
Formula for AT&C loss in a Utility
ANNEXURE-V
24 | P a g e
Annexure-V
An example for calculating the eligibility of additional grant under varying
scenarios is as per para 14.2 of the guidelines
Scenario-II
Evaluation Year
2015-16 (Award)
2016-17
2017-18
Total
Scenario-III
Evaluation Year
2015-16 (Award)
2016-17
2017-18
Total
Scenario-IV
Evaluation Year
2015-16 (Award)
2016-17
2017-18
Total
In case, a project is awarded in 2016-17, the evaluation of both criteria (ii) &
(iii) will be done for three years starting from FY 2016-17 to 2018-19.