TECH SEMINAR ON
CAISSONS AND COFFERDAMS
FOR THE SUBJECT OF
ADVANCED FOUNDATION ENGINEERING
BY
RAJAT JAIN (11BCL020)
KARTIK GUPTA (11BCL047)
SUBMITTED TO
Dr. TRUDEEP N. DAVE
CONTENTS
1. INTRODUCTION 3
2. CAISSONS... 4 - 16
GENERAL.. 4
TYPES. 4
FUNCTIONS.. 8
THICKNESS OF CONCRETE SEAL IN OPEN CAISSONS.. 8
EXAMPLE.. 11
CAISSONS THROUGH THE AGES........ 12
CONSTRUCTION. 16
3. COFFERDAMS17 - 22
GENERAL..17
TYPES.17
ADVANTAGES OF COFFERDAM..18
TYPES OF IMPOSED LOADS..18
SCOUR....20
SHEET PILE SHAPES... 20
TYPES OF INTERLOCKS..... 21
EXAMPLES................ 22
4. REFERENCES.. 23-24
1. Introduction
1.0 GENERAL
During the construction of bridges, dams or any other structure where the foundation part
of the structure is most likely to lie underwater, we have to opt for underwater
construction. Construction in water poses many difficulties especially in the places where
there the depth is considerable. During underwater construction our main objective is to
create dry and water free environment for working in such manner that the structural
stability of the structure is not compromised.
Caissons
Underwater Construction
Cofferdams
2. Caissons
2.0 GENERAL
The name caisson is French and is to be translated as a large chest, which refers to the
general shape of the caissons. In geotechnical engineering, a caisson is a watertight
retaining structure used, for example, to work on the foundations of a bridge pier, for the
construction of a concrete dam, or for the repair of ships. These are constructed such that
the water can be pumped out, keeping the environment dry.
2.1 TYPES
Caissons are divided into three major types:
i.
Open Caissons
ii.
iii.
Pneumatic Caissons
Open caissons (Fig-2) are concrete shafts that remain open at the top and bottom during
construction. The bottom of the caisson has the cutting edge. The caisson is sunk into
place, and soil from the inside of the shaft is removed by grab buckets until the bearing
stratum is reached. The shafts may be circular, square, rectangular or oval. Once the
bearing stratum is reached, concrete is poured into the shaft (underwater) to form a seal at
its bottom. When the concrete seal hardens, the water inside the caisson shaft is pumped
out. Concrete is then poured into the shaft to fill it. Open caissons can be extended to
great depths, and the cost of construction is relatively low. However, one of their major
disadvantages is the lack of quality control over the concrete poured into the shaft for the
seal. Also, the bottom of the caisson cannot be thoroughly cleaned out. An alternative
method of open-caisson construction is to drive some sheet piles to form an enclosed
area, which is filled with sand and is generally referred to as a sand island. The caisson is
then sunk through the sand to the desired bearing stratum.
Box caissons (Fig-3) are caissons with closed bottoms. They are constructed on land and
then transported to the construction site. They are gradually sunk at the site by filling the
inside with sand, ballast, water or concrete. The cost for this type of construction is low.
The bearing surface must be level, and if it is not, it must be leveled by excavation.
Pneumatic caissons (Fig-4) are generally used for depths of about 50-130 ft (15-40 m).
This type of caisson is required when an excavation cannot be kept open because the soil
flows into the excavated area faster than it can be removed. A pneumatic caisson has a
work chamber at the bottom that is at least 10 ft ( 3 m) high. In this chamber, the
workers excavate the soil and place the concrete. The air pressure in the chamber is kept
high enough to prevent water and soil from entering. Workers usually do not counter
severe discomfort when the chamber pressure is raised to about 15 lb/in2 ( 100 KN/m2)
above atmospheric pressure. Beyond this pressure, decompression periods are required
when the workers leave the chamber. Workers enter and leave the chamber through a
steel shaft by means of a ladder. This shaft is also used for the removal of excavated soil
and the placement of concrete. For large caisson construction, more than one shaft may
be necessary, an airlock is provided of each one. Pneumatic caissons gradually sink as
excavation proceeds. When the bearing stratum is reached, the work chamber is filled
with concrete.
2.2 FUNCTIONS
The main functions of caissons generally are soil or water retention and transfer of
vertical and horizontal loads into the subsoil. Less frequent functions are provision of
space for equipment or machinery, and locking through of ships, if the caisson is part of a
lock or barrier.
With respect to application:
i.
ii.
Breakwater
iii.
Quay wall
iv.
Storage
v.
Tunnel element
vi.
vii.
v ( )/
Where,
And
= 0.85
2) Check for Buoyancy
If the shaft is completely dewatered, the buoyant upward force, Fu, is
Fd = Wc + Ws + Qs
Where
Wc = weight of caisson
Ws = weight of seal
Qs = skin friction
If Fd > Fu, the caisson is safe from buoyancy. However, if Fd < Fu, dewatering
the shaft completely will be unsafe. For that reason, the thickness of the seal
should be increased by t or
t = (Fu Fd)/Ai
10
Example:An open caisson (circular) is shown in Fig. Determine the thickness of the seal that
will enable complete dewatering.
v = (2 2)/ 22
= ()(7.5)2[(45)(62.4)-(2.5)(150)]/(2)( )(7.5)(2.5) 3650 lb/ft2
= 25.35 lb/in2
11
Fu = (R02) H
For R0 = 10ft
12
Later on in history, 13 years BC, king Herod the Great ordered the construction of the
port of Caesarea, Judea, which became the largest on the eastern Mediterranean coast.
The mole (havenhoofd) was built on floating units; timber casing that were prefabricated,
transported over water (floating) and on the right location immersed by ballasting with
stone (Fig-7). The dimensions of these caissons were 15 x 5.5 x 2.7 m, the water
displacement was 220 tons. (Bernshtein 1994)
Fig-7 Timber caisson for the mole of the port of Caesarea, Judea, about 13 BC
Some centuries later, Robert Weldon, a British Engineer, invented a ship elevator, which
he called a Hydrostatic Caisson Lock. This caisson lock is a type of canal lock, and was
intended to raise and lower ships in the Shropshire Canal. The vertical transport of ship
took place in an immersed, sealed caisson box that moved up and down in a big water
container, a cistern (Fig-8)
13
Engineers found out that in the same way they could construct foundations for bridge
piers, which they first did in Vichy (France), later also in England (e.g. for the piers of
the Royal Albert Bridge in Cornwall, 1859 and the Firth of Forth railroad bridge in
Scotland, 1890) and the United Sates of America (e.g. the Brooklyn Bridge in New York
and the Mississippi Bridge in St. Louis), followed by other countries. (Nebel, 2007)
2.4.2 TWENTIETH CENTURY
Another important field of application of caissons nowadays are ports and harbors. The
variations in dimensions through the years is shown in Fig-9
14
Fig-11 Caisson pier foundation with watertight partition during construction of the HSL bridge over the
Hollandsch Diep
15
2.5 CONSTRUCTION
Standard caissons are generally prefabricated in the dry in a construction dock. When
ready, the dock is inundated and the caisson can be transported over water to the actual
site using its own buoyancy. There it is immersed to the river, sea or estuary bed and
ballasted heavily enough to remain at its place and fulfill its function. The life cycle of
caissons consists of the following stages:
i.
Idea/ Initiative
ii.
iii.
Prefabrication
iv.
Transport
v.
In situ construction
vi.
Operation, Maintenance
vii.
16
3. Cofferdams
3.1 GENERAL
A cofferdam is a temporary structure designed to keep water and/or soil out of the excavation
in which a bridge pier or other structure is built. When construction must take below the
water level, a cofferdam is built to give workers a dry work environment. Sheet pile is driven
around the work site, seal concrete is placed into the bottom to prevent water from seeping in
from underneath the sheet piling, and the water is pumped out. The word cofferdam comes
from coffer meaning box, in other words a dam in the shape of a box. There are different
types of cofferdam, some are used to support excavation operation and some are enclosed
type box placed in water.
3.2 TYPES OF COFFERDAMS
1. Braced: - It is formed from a single wall of sheet piling which is driven into the
ground to form a box around the excavation site. The box is then braced on the
inside and the interior is dewatered. It is primarily used for bridge piers in shallow
water (30-35 ft depth)
2. Earth Type: - It is the simplest type of cofferdam. It consists of an earth bank with
a clay core or vertical sheet piling enclosing the excavation. It is used for low level
waters with low velocity and easily scoured by water rising over the top.
3. Timber Crib: - Constructed on land and floated into place. Lower portion of each
cell is matched with contour of river bed. It uses rock ballast and soil to decrease
seepage and sink into place, also known as Gravity Dam. It usually consists of 12`
x 12` cells and is used in rapid currents or on rocky river beds. It must be properly
designed to resist lateral forces such as tipping / overturning and sliding.
4. Double Walled Sheet Pile: - They are double walled cofferdams comprising two
parallel rows of sheet piles driven into the ground and connected together by a system
of tie rods at one or more levels. The space between the walls is generally filled with
granular material such as sand, gravel or broken rock.
17
5. Cellular: - Cellular cofferdams are used only in those circumstances where the
excavation size precludes the use of cross excavation bracing. In this case, the
cofferdam must be stable by virtue of its own resistance to lateral forces.
18
19
3.5 SCOUR
Scour of the river bottom or seafloor along the cofferdam may take place owing to river
currents, tidal currents, or wave-induced currents. Some of the most serious and disastrous
cases have occurred when these currents have acted concurrently.
A very practical method of preventing scour is to deposit a blanket or crushed rock or heavy
gravel around the cofferdam, either before or immediately after the cofferdam sheet piles are
set. A more sophisticated method is to lay a mattress of filter fabric, covering it with rock to
hold it in place.
3.6 SHEET PILE SHAPES
Larsen/U Type
Flat/Straight Type
20
21
22
REFERENCES
Bernshtein, L.B. (chief edt.) Tidal Power Plants Korea Ocean Research and Development
Institute. 1996.
Gijt, J.G. de A History of Quay Walls Doctoral dissertation Delft, 2010
Nebel, B. Die Caissongrndung
http://www.berndnebel.de/bruecken/6_technik/caisson/caisson.html. 2007
FIGURES
Fig 1: Flowchart showing techniques of underwater construction
Fig 2: Drilled Shaft and Caisson Foundation, NPTEL
Fig 3: Drilled Shaft and Caisson Foundation, NPTEL
Fig 4: Drilled Shaft and Caisson Foundation, NPTEL
Fig 5: Drilled Shaft and Caisson Foundation, NPTEL
Fig 6: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 7: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 8: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 9: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 10: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 11: M.Z. Voorendt, W.F Molenaar, K.G. Bezuyen, Hydraulic Structures
Fig 12: Professor Kamran M. Nemati, Tokyo Institute of Technology
Fig 13: Professor Kamran M. Nemati, Tokyo Institute of Technology
Fig 14: Professor Kamran M. Nemati, Tokyo Institute of Technology
Fig 15: Professor Kamran M. Nemati, Tokyo Institute of Technology
23