Sie sind auf Seite 1von 2

NEW PORT PROJECT

Construction Development Co. LLC


Boom Construction Co. LLC (JV)
NPP/0047: Centralised Customs
Inspection Area

Material Approval
Submittal
(MAS Form)

Contract:
MAS Ref:

NPP/0047 Centralised Customs Inspection Area


NPP0047-CDC-ACM-MEC-MAS-0000x_rev
Date on
ePM:
Manufacturer /
Faisal Jassim Industries (Flowtech) / F.J
Country of
Supplier name:
Trading and Engineering L.L.C
material
origin:
Supplier Pre-Qualification
NPP0047-CDC-ACM-PQ-00234_1
Reference:

United Arab Emirates

Description of
material:
Specification
details:
Location of use
on project:
Technical details:

Duct Accessories (Access Panels, Balancing Dampers, Motorized Dampers, Fire


Dampers, & Smoke Dampers)
Project Specifications Section 22 Part 6 Clause 6.2 Sub clause 6.2.8, Clause 6.3 Sub
clauses 6.3.1, 6.3.3, 6.3.4, 6.3.6 & 6.3.7
NPP0047-CCIA Project Inside the buildings except battery room exhaust ductwork
system (HVAC Ducting System)
UL 555 Class II Rated Smoke Dampers & UL 555 1.5 hours fire rated Fire Dampers,
Galvanized Steel Volume Control Dampers & Non Return Dampers, and Double Panel
Galvanized Steel Sheet Access Doors.
Attachments to support the materials submittal:
1 Compliance Statement with Project Specifications Remar Please refer to pages 01 12
ks:
2 Material Technical Data Sheet
Remar Please refer to pages 13 55
ks:
3 Material Test Certificate
Remar Please refer to pages 56 63
ks:
4 Previous Approvals
Remar Please refer to pages 64 71
ks:
5 Catalogue
Remar Please refer to pages 72 73
ks:
6 Supplier Local Registration
Remar Please refer to pages 74 78
ks:
7 Country of Origin Certificate
Remar Please refer to pages 79 80
ks:
8 Warranties/Guarantees
Remar Please refer to pages 81 82
ks:
9 Local Authorities Certificate
Remar Please refer to pages 83 87
ks:
10 Storage, Transport & Handling Requirements
Remar Please refer to pages 88 89
ks:
11 ISO Certificates
Remar Please refer to pages 90 91
ks:
12 Employer's Approval on the Pre-Qualification
Remar Please refer to pages 92 94
ks:
13 Material Sample
Remar Submitted along with this transmittal
ks:

Disclaimer
We understand that approval of the material(s) submitted herein is only intended to determine general
conformance with the intent of the project contract documents. By submitting these materials for approval,
we confirm we have performed all necessary on-site dimensional and building utility requirement
coordination, and if approval is granted, will further coordinate the information contained within with all
other concerned contractors employed by the NPPSC.
Action:

Prepare
d by:

Checke
d by:

NPP00100-ACM-PRO-1201-MAS
Revision 0 24 March 2014

Reviewe
d by:

Reviewe
d&
Approve

Design
Consultant stamp

Approve
d by:

Company
stamp

Page 1 of 2

NEW PORT PROJECT


Construction Development Co. LLC
Boom Construction Co. LLC (JV)
NPP/0047: Centralised Customs
Inspection Area

Material Approval
Submittal
(MAS Form)
d by
Design
Consulta
nt:

Name:

Marvin
Arinuelo
Sr.
QA/QC
Engineer

Amjad
Rawashd
eh
MEP
Project
Manager

Glisson
George
QA/QC
Manager

05-052016

05-052016

05-052016

Signat
ure:

Date:

PMC review comments


Review status:
Status A
(reviewed)

Status B

(reviewed as noted)

Status C

Status D

(revise and resubmit)

(cancelled)

(insert CSRC reference that refers to the details of the review outcome)

Reviewed by:

(insert full name)

Date returned
to Contractor:

NPP00100-ACM-PRO-1201-MAS
Revision 0 24 March 2014

Signat
ure:

Dat
e:

Copies
distributed to:

Page 2 of 2

Das könnte Ihnen auch gefallen