Residential

Average multi unit high-rise


Luxury unit high-rise
Individual prestige homes
Commercial
Average standard offices, high-rise
Prestige offices, high-rise
Major shopping center (CBD)
Industrial
Light duty factory
Heavy duty factory
Hotel
Three-star budget
Five-star budget
Resort style
Other
Multi-storey car park
District hospital
Primary and secondary schools

1 Residential
Low rise
Medium rise
High rise
2 Commercial
Low rise office (shell & core)
Mid rise office (shell & core)
High rise office (shell & core)
Fit-out basis
Fit-out medium
Fit-out high
3 Retail
Community
Regional mall
Super regional mall
4 Industrial
Light duty factory
Heavy duty factory
Light industrial unit
Data center tier 3 *based on USD/kW(IT)

5 Hotel
Budget
Mid-market
Up market
Resort
6 Car parks
Multi storey
Basement
7 Other
Schools primary, secondary academy
Healthcare district hospital

QR/m
5,717.00
7,805.00
7,260.00
6,716.00
7,623.00
4,538.00
3,594.00
4,175.00
7,623.00
12,705.00
14,339.00
3,086.00
13,794.00
4,719.00

Low
High
4,501.00
5,481.00
5,009.00
6,498.00
5,481.00
7,006.00
4,501.00
5,009.00
6,498.00
1,997.00
3,485.00
4,501.00

5,481.00
6,498.00
7,986.00
2,505.00
4,501.00
6,498.00

3,993.00
4,501.00
4,501.00

5,009.00
5,990.00
6,498.00

3,013.00
3,485.00
2,505.00
71,947.00

3,485.00
4,501.00
3,013.00
81,929.00

8,494.00
90,314.00
12,487.00
13,976.00

9,002.00
12,487.00
14,992.00
14,992.00

2,759.00
3,013.00

3,231.00
3,485.00

5,481.00
7,986.00

7,478.00
9,983.00

Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

Description
Basement excavation
Foundation excavation
Imported structural fill
Concrete in pad footings (25Mpa)
Concrete in walls (32Mpa)
Concrete in slabs (32Mpa)
Formwork to slab soffits (under 5m high)
Formwork to side and soffits of beams
Precast wall panel architectural with sand blast finish
Reinforcement in beams
Structural steel in beams
Structural steel in trusses
Hollow concrete block partition (200mm thick)
Aluminium framed window (6.5mm clear glass commercial quality)
Aluminium curtain wall system (including structural system)

Unit
m
m
m
m
m
m
m
m
m
kg
kg
kg
m
m
m

Average quality steel stud partition (with single layer plasterboard each side) m
Suspended mineral fiber ceiling
m
Paint on plasterboard walls
m
Ceramic tiles to walls
m
Average quality marble paving on screed
m
Anti static carpet tiles to office and admin areas
m

Excavation

Disposal of excavated material


Filling

m
m

Poured concrete, reinforced

Reinforcement

ton

Formwork/shuttering

Blockwork

Doors

No

Tiling to floors
Plaster to internal walls and ceilings

m
m

Painting to internal walls and ceilings

Rate
51.00
54.00
116.00
545.00
581.00
581.00
160.00
160.00
672.00
5.00
15.00
15.00
160.00
944.00
2,178.00
345.00
131.00
18.00
254.00
726.00
269.00
Standard/minimum specification
Excavation for trench foundation; depth not
excessive, i.e. no greater
51.00 than 1-2 m
Standard/minimum specification
54.00 Disposal away from site
65.00 Imported fill
Standard/minimum specification
Grade 20 or 30; superstructure, walls or slabs;
599.00 reinforced
Standard/minimum specification
5,990.00 20mm bars
Standard/minimum specification
120.00 Superstructure standard; fair face finish to walls
Standard/minimum specification
182.00 200mm solid blockwork, usually internal walls

Standard/minimum specification
Single leaf door, fire rated, timber, basic finish,
usually 900mm wide,
3,485.00 generally excluding ironmongery
Standard/minimum specification
250.00 300 x 300mm ceramic tiles
44.00 12.5mm thickness
Standard/minimum specification
22.00 Emulsion