Beruflich Dokumente
Kultur Dokumente
Calculation
Methodology and Sensitivity
What is LCOE?
Levelized Cost of Energy (LCOE) is the constant unit cost (per kWh
or MWh) of a payment stream that has the same present value as the
total cost of building and operating a generating plant over its life.
Initial Investment and Annual Costs
$150
$1,000,000
LCOE
$100
20
18
16
14
12
10
$50
6
$0
4
$75
$250,000
LCOE ($/MWh)
$500,000
Year
-2
$125
Equity Investment
Debt Service
Operating Expenses
Taxes
LCOE
$750,000
Solar PV
Wind - Offshore
Shallow
Wind - Onshore
0
-3
0.5
1
1.5
Levelized Cost of Energy (RMB/kWh)
CRF =
[(1 + i) n]-1
2.
-4
Discount rate
T echnology Assumptions
Project Capacity (MW)
Capital Cost ($/kW)
Fixed O&M ($/kW)
Fixed O&M Escalation
Variable O&M ($/MWh)
Variable O&M Escalation
Fuel Cost ($/MBtu)
Fuel Cost Escalation
Heat Rate (Btu/kWh)
Capacity Factor
Misc Revenue ($/MWh)
Misc Escalation
Degradation
Year
3,066
$139.35
$0.00
$427,249
3,035
$139.35
$0.00
$422,976
3,005
$139.35
$0.00
$418,746
2,975
$139.35
$0.00
$414,559
2,945
$139.35
$0.00
$410,413
$50,000
$0
$0
$50,000
$51,250
$0
$0
$51,250
$52,531
$0
$0
$52,531
$53,845
$0
$0
$53,845
$55,191
$0
$0
$55,191
$80,000
$36,830
$116,830
$77,054
$39,776
$116,830
$73,872
$42,958
$116,830
$70,435
$46,395
$116,830
$66,723
$50,106
$116,830
5
7
15
20
$0
$0
$0
$75,000
$222,249
$0
$111,124
$0
$0
$0
$144,380
$150,292
$0
$75,146
$0
$0
$0
$133,540
$158,804
$0
$79,402
$0
$0
$0
$123,540
$166,739
$0
$83,370
$0
$0
$0
$114,260
$174,239
$0
$87,120
(1,000,000)
149,295
179,750
169,984
160,515
151,273
Fixed O&M
Variable O&M
Fuel Cost
Operating Expenses
Interest Payment
Principal Payment
Debt Service
Tax Depreciation
Tax Depreciation
Tax Depreciation
Tax Depreciation
Taxable Income
PTC
T axes
-5
Total
Financial/Economic Asumptions
Debt Percentage
Debt Rate
Debt Term (years)
Economic Life (years)
Percent 5-year MACRS
Percent 7-year MACRS
Percent 15-year MACRS
Percent 20-year MACRS
Energy Price Escalation
Tax Rate
Cost of Equity
Discount Rate
1
$2,000
$50
2.5%
$0
2.5%
$0
2.5%
0
35%
$0
2.5%
1%
N
A
IN L
F
LE ODE
P
AM M
AL
I
C
2.
Real LCOE (with Inflation) (RMB/kWh) Nominal path that maintains Real
value constant (Nominal)
3.
Nominal (RMB/kWh)
0.80
0.8
0.70
0.7
3.) Nominal LCOE
0.60
0.50
0.6
0.5
1.) Real LCOE
(2010RMB)
0.40
Year
-6
20
19
18
17
16
15
14
13
12
11
10
0.4
Real (2010RMB/kWh)
0.9
2.) Real LCOE
with Inflation
(Nominal)
Inflation = 2.5%
Discount Rate = 10%
Real LCOE
Preferred by government/policy
makers
Nominal LCOE
Incorporates assumptions
regarding inflation
Preferred by developers/project
owners
Example: Real LCOE = 0.50 RMB/kWh and Nominal LCOE = 0.59 RMB/kWh
With 2.5% inflation, Nominal LCOE is 18% higher than Real LCOE
-8
Performance/resource
characteristics
Inflation (optional)
Transmission/integration costs
(optional)
-9
Capacity
Factor
LCOE
(RMB/kWh)
Onshore
Wind
9,000
250
40%
0.54
Solar PV
20,000
200
15%
1.72
Solar CSP
30,000
300
28%
1.66
Economic Life
20 years
Discount Rate
10%
20 years
Tax Rate
30%
WACC
8%
O&M
Escalation
- 10
2.5%
- 11
Capital cost
0.4
Capacity Factor
20%
Costequity-WACC
0.7
0.8
40%
12%
8%
O&M (RMB/kW)
- 12
0.6
30%
6%
-0.2
0.5
200
-0.1
250
300
0.0
0.1
LCOE relative to Base Case (RMB/kWh)
Low
0.2
High
0.3
Base Case
1.3
1.4
1.5
1.6
Cost equity-WACC
6%
16,000
18%
O&M (RMB/kW)
160
200
-0.2
1.9
-0.1
0.0
2.0
2.1
2.2
2.3
12%
24,000
20,000
16%
-0.3
1.8
8%
Capacity Factor
-0.4
- 13
1.7
20%
240
Low
High
0.1
0.2
0.3
0.4
0.5
LCOE relative to Base Case (RMB/MWh)
0.6
1.4
1.5
1.6
Costequity-WACC
6%
24,000
1.8
30,000
O&M (RMB/kW)
-0.2
1.9
2.0
2.1
2.2
2.3
2.4
12%
8%
Capacity Factor
-0.4
- 14
1.7
36,000
-0.1
0.0
0.1
0.2
0.3
0.4
LCOE relative to Base Case (RMB/kWh)
Low
0.5
High
0.6
0.7
Busbar Cost
+
Transmission Cost
+
Integration Cost
Capacity Value
Energy Value
- 15
Busbar Cost
Delivered Cost
Adjusted Delivered
Cost
Summary
- 16