Sie sind auf Seite 1von 9

Method Statement for

Mobilization Works

TOTAL 9 PAGES
(Including Cover)

Purpose

PROJECT NAME

: Khabat Thermal Power Plant Units 1&2

DOCUMENT NO.

: KP-00+++-MQ758-V0002

TITLE

: Method Statement for Mobilization Works

For Approval

OWNER

: Ministry of Electricity (MOE) of


Kurdistan Regional Government

For Construction

17.09.2014

Rev.
No.

DATE

First Issue
DESCRIPTION

For Information
For Review

As-Built

MP

EO

AZ

TC

PREPARED

CHECKED

REVIEWED

APPROVED

GAMA POWER SYSTEMS ENG &CONTRACTING,INC.

Owner

Ministry of Electricity (MOE)


of Kurdistan Regional Government
Contractor

POSCO ENGINEERING
& CONSTRUCTION CO., LTD.
Main Subcontractor

GAMA POWER SYSTEMS


ENGINEERING & CONTRACTING,INC.

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

1/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

Khabat Thermal Power Plant Units 1&2 Project


132kV Air Insulated Switchgear

METHOD STATEMENT FOR MOBILIZATION


WORKS
DOCUMENT NO: KP-00+++-MQ758-V0002
SUBCONTRACTOR: SIEMENS
GAMA REVIEW
Discipline
Superintendent

HSE Manager

QA/QC Manager

Site Manager

Name
Date
Sign
Remarks:
Any such review or consent by GAMA, shall not relieve the Subcontractor, in any case or for any reason whatsoever,
from any obligation, liability or responsibility arising out of or in connection with the Contract, including without being
limited thereto, to the responsibility for errors, omissions, discrepancies and non-compliances. Within this context, this
document shall not prevail over or amend the Contract, or relieve the Subcontractor from any of its duties, obligations,
responsibilities or liabilities under the Contract.
Anything presented herein by the Subcontractor shall in no event
i) excuse the Subcontractors non-performance under the Contract, or
ii) entitle him to a variation under the Contract or an adjustment to the Contract Price.

SUBCONTRACTOR
Rev.
No.
A

Date

Description*

Prepared
by

HSE
Manager

QA/QC
Manager

Site
Manager

Project
Manager

17.09.2014

Mobilization
Work

Mustafa
Peker

Eyyp zbay

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

2/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

DOCUMENT HISTORY:
Rev.
No.

Date

17.09.2014

Remarks
(Reason for Revision)
First Issue

* Description:
Document issue purpose
-

First Issue

For Information

For Review

For Approval (or Issued for Construction)

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

3/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

CONTENT

1.0

PURPOSE ........................................................................................................................................ 4

2.0

SCOPE OF WORK ........................................................................................................................... 4

3.0

RESPONSIBILITIES ........................................................................................................................ 4

4.0

DEFINITIONS / ABBREVIATIONS .................................................................................................. 4

5.0

PERSONNEL ................................................................................................................................... 4

6.0

MATERIALS ..................................................................................................................................... 4

7.0

EQUIPMENT .................................................................................................................................... 5

8.0

SUBCONTRACTORS SUB-TIER CONTRACTORS ...................................................................... 6

9.0

EXECUTION ..................................................................................................................................... 6

10.0

TIME LINE OF ACTIVITIES ............................................................................................................. 7

11.0

PROGRESS MEASUREMENT ........................................................................................................ 7

12.0

QUALITY REQUIREMENTS ............................................................................................................ 7

13.0

RISK ASSESSMENTS ..................................................................................................................... 8

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

1.0

4/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

PURPOSE

PurposeofthissocumentistogivebriefdetailsaboutMobilizationActivitiesofKhabat
ThermalPowerPlant1&2132kVSubstationPart.
2.0

SCOPE OF WORK

ScopeofthisMethodofStatementisMobilizationActivitiesatKhabatThermalPower
Plant1&2132kVSubstationPart.
3.0

RESPONSIBILITIES

Allpersonnelassignedtothisprojectfrome.g.Engineering,QualityandPlanningOperations
etc.;arefunctionallyresponsibletotheProjectManager,workingasateamtoachievethe
objectiveofcompletingtheprojecttothecustomerssatisfaction.
TheProjectManageristheprimarycontactregardingcommunicationbetweenthecustomer
andSIEMENS
4.0

DEFINITIONS / ABBREVIATIONS

QEHS
QA
QC
LV
ITP
AIS
5.0

:Quality,Environmental,Health&Safety
:QualityAssurance
:QualityControl
:LowVoltage
:InspectionandTestPlan
:AirIsolatedSwitchyard

PERSONNEL

SiteManager1

SiteForemen1

Workers2

Operators1

6.0

MATERIALS

RebarsS420(TSE500,fyk=420N/mm)

Concrete(Type:C25forFoundations,C20forLeanConcretes)

Formworks(timberandplywood/wood)

Gravelorcrushedstone

Perforateddrainagepipes

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

5/8

Doc.No:

KP-00+++-MQ758V0002

Bricks

Plasteringmaterials(roughcast,gypsumplaster)

Paints

Marble

CeramicTiles

DoorsandWindows

7.0

Date:

17.09.2014

EQUIPMENT

1.MandatoryPersonalProtectiveEquipment,
SafetyHelmet
SafetyShoes
SafetyVest
SafetyGloves
SafetyGlassess/Goggles
2.PersonalProtectiveEquipmentRequiredDuetoSpecificRisks,
SafetyHarness,
Dustand/orChemicalMasks
WeldingShield
3.SafetyBarricadingFence/NetlonFence
4.RelatedSafety/WarningSigns.
5.Machines

Crane1(10ton)

Manlift

Excavator

HandTools

Backhoeloader

Loader

Trucks

Scaffold

Concretevibrator

Concretemixer

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

8.0

6/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

SUBCONTRACTORS SUB-TIER CONTRACTORS

CompanyName

:SilopiAypanaatSan.Tic.Ltd.ti.

Address

:YesiltepeMah.2.Cad.iekApt.No:41Kat:1Silopi/SIRNAK

Tel

:04865186900

Fax

:04865186900

EMail

:mesut.aydin@silopiaypa.com

9.0

EXECUTION
9.1 Site Preparation

All materials, which will be used for installation of the prefabricated office building, will be stored
properly near installation area. The concrete platform, which will be used for installing on, will be
cleanedandpreparedforinstallation.
9.2 Carrier System Installation with External walls

Special shaped steel profiles will be fixed by using steel dowels on the concrete platform. After that
specialshapedprofiles,whichisusedasverticalcarrier,willbeinstalledbystartingfromonecornerto
another corner. At this time extarnal walls will be installed between two vertical profiles. Doors and
windowswillbeinstalledwhereisnecessary.
9.3 Interior wall Installation

Specialshapedprofileswillbeinstalledontheconcreteplatformbysteeldowelsforbuildingdesigned
rooms.Afterthatspecialshapedprofiles,whichisusedasverticalcarrier,willbeinstalledbystarting
from one corner to another corner. At this time internal walls will be installed between two vertical
profiles.Doorswillbeinstalledwhereisnecessary.
9.4 Roof Installation

Rooftrusswillbeliftedbyusingcraneandinstalledontheverticalprofiles.Afterthetrussinstallation
purlinswillbeinstalled.Afterthattheroofpanelswillbeinstalled.
9.5 Electrical wiring works

Electricalwiringswillbeinstalledbyusingsurfacemountedcablechannels.Andwiringswillbe
connectedtotheelectricboard.

9.6 Sanitary system installation

Necessarypipingwillbedonetoprovidefreshwaterandremovethesewagewateratthewet
areas.Aftertheinstallationiscompleteleakagetestwillbedonevisually.

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

10.0

7/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

TIME LINE OF ACTIVITIES

Approximate durations will be shown below for each section. Also each step of the work will
repeated and performed together for accelerate the work. Also working Schedule will be
followed.
ForecastedStart&FinishDatesofMobilization:01/09/201407/09/2014
11.0

PROGRESS MEASUREMENT

All Mobilization Activities will be completed in one week period. The missing Items will be
followedduringcontractperiod.
12.0

QUALITY REQUIREMENTS

Toolbox talk will be done with the team who is involved in the foundation works. Job Safety
Analysis(JSA)willbepreparedanddistributedtoSiteSupervisor(s).UsingrelatedJSA,
MethodStatementandRisk
Assessmentwillbediscussedduringthetoolboxtalk.
Whileexcavationworks,barricadewillbeinstalledtothearoundthepitandwarningsignswill
beputtowarnotherpeopletokeepaway.
MandatoryPersonalProtectiveEquipmentwillbeusedbythepersoninvolvedintheoperation.
ThereisnorequirementforadditionalPPE.
RiskAssessmentwillbetakenintoconsiderationandrequiredprecautionswillbetaken.

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

METHOD STATEMENT FOR MOBILIZATION WORKS


Page:

13.0

8/8

Doc.No:

KP-00+++-MQ758V0002

Date:

17.09.2014

RISK ASSESSMENTS

WorkRiskassessmentaboutallworksandpossiblerisksatthesite,islistedasfollow.

Guidance

Doc. No: KP-00+++-MQ758-V0002, Rev. No: A

Das könnte Ihnen auch gefallen