Beruflich Dokumente
Kultur Dokumente
Abstract
This paper describes an application of fuzzy logic in analysis o f delays in construction projects using Fuzzy toolbox of
MATLAB Program So ftware. Delays in construction projects are inevitable and may result in claims and disputes among
different construction parties. Delays in construction projects can be due to a number of causes, which need to be classified
and identified. For the success of a construction project, estimation of likelihood of delay resulting fro m different factors is a
must. Fuzzy logic provides a simple way to arrive at a definite conclusion based u pon vague, imprecise or missing input
informat ion. Fuzzy logic is a form of many-valued logic; it deals with reasoning that is approximate rather than fixed and
exact.
Keywords - Construction projects; Fuzzy logic; Delays; Delay cause; MATLAB; Fu zzy Logic Toolbo x
I.INTRODUCTION
The major problem occurring in any construction project is the delays occurring during the project, which cause the project to
take longer time than planned. A construction project is commonly acknowledged as successful, whe n it is completed on time,
within budget, in accordance with the specifications. A successful project means that the project has accomplished its technical
performance, maintained its schedule, and remained within budgetary costs. Projects may differ in si ze, duration, objectives,
uncertainty, complexity, pace, and some other dimensions. It does not matter how different or unique a project is; there is no
doubt that every project contains some degree of uncertainty. It is required to be aware of these uncertainties and to develop
necessary responses to get the desired level of the project success. Schedule delays are common in various construction
projects and cause considerable losses to project parties. It is widely accepted that construction project sched ule plays a key
role in project management due to its influence on project success . The common results of schedule delays are: Late
completion of project, increased cost, disruption of work, loss of productivity, third party claims, disputes and abandonmen t or
termination of contracts. Therefore schedule delays in construction projects give rise to dissatisfaction to all the parties
involved.
The aim o f this paper is to propose a schedule delay assessment model using Fuzzy Logic Too lbo x of MATLA B Program
Software. An interview was conducted in which construction project team members were asked questions about the delays
taking place in the project. The delay causes were grouped and categorized in different factors. The interview results were
used in the assessment model and probability of schedule delay was evaluated. According to the results obtained from the
model, the areas of most concern were discussed. The results obtained were accurate and acceptable.
Page 599
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
alterations in the planned schedule and result in delays, especially if the task is part of the critical path. Delay in critical
activities or near crit ical activities result in project delay. Some amount of delay on non -critical-path tasks can be tolerated, but
any slippage on critical-path tasks directly results in delay of the project as a whole.
COM PENSABILITY
Excusable delays
Non-excusable delays
3.
TIMING
Concurrent delays
Non-concurrent
IV.DELAY FACTORS
The project team members from different construction projects were interviewed about the delays occurring in their
projects. They were asked to fill in the questionnaire and give values to the delay causes ranging from 0 to 100. These values
were converted into percentage values and used as fuzzy weights to be used in the Fuzzy Logic Toolbox of Matlab as rule
weights to be given to the delay causes. They were also asked to give scores to the factors as Least causable; Medium
Causable and Highly Causable. The delay factors are shown below in the form of table:
Factors
Labor
Related
Factors
Project
Related
Factors
Causes
a)Labor strike
b)Conflicts among
labor
c)Inexperienced
Labor
d)Labor shortage
e)Absent labors
a)Short
original
contract duration
b)Delay penalties
c)Project co mplexity
d)Disputes
among
project parties
Values
0.34
0.37
0.70
0.79
0.49
0.69
0.54
0.36
0.60
Page 600
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
Consultant
Related
Factors
Contractor
Related
Factors
External
Related
Factors
a)Improper project
management
assistance
b)Inexperienced
consultants
c)Inspecting
and
testing delays
d)Conflicts between
consultants
and
design engineer
e)Poor
communication and
coordination
with
other parties
f)Delay in approval
of design documents
a)Poor
site
management
and
supervision
b)Poor planning and
scheduling of project
c)Shuffling
of
subcontractors
d)Poor
communication and
coordination
with
other parties
e)Rework due to
errors
f)Inexperienced
contractors
a)Inclement weather
conditions
b)Variat ions in price
c)Global financial
crisis
d)Changes
in
government
regulations and laws
e)Unexpected
surface
and
subsurface
conditions
0.56
0.72
0.80
0.47
0.74
0.61
0.79
0.83
0.34
0.74
0.50
0.81
0.81
0.61
0.87
0.42
0.79
Page 601
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
Owner
Related
Factors
Material
Related
Factors
Design
Related
Factors
Equip ment
Related
Factors
f)Delay
in
providing
services from utilities
g)Delay in transportation
a)Slow decision making
b)Delay in approving design
documents
c)Late site delivery
d)Change in orders by
owners
e)Improper study of designs
f)Progress payments delays
g)Poor communication and
coordination with other
parties
h)Inexperienced owners
a)Material
manufacturing
delay
b)Damage of material
c)Material shortage
d)Delay in delivery
e)Rising prices of materials
a)Inadequate experience of
design team
b)Co mplexity in project
design
c)Errors made by designers
d)Delays in making design
documents
e)Unclear details in drawing
f)Insufficient data collection
a)Damaged equipment
b)Equip ment shortage
c)Breakdown of equipment
d)Low efficiency
e)Problem in allocation
0.52
0.35
0.76
0.46
0.71
0.89
0.55
0.62
0.81
0.72
0.35
0.42
0.77
0.73
0.43
0.64
0.38
0.62
0.65
0.56
0.50
0.46
0.45
0.54
0.71
0.65
V. CAS E S TUDY
A real case study was undertaken and an interview was conducted in a housing project in Gwalior, to assess the causes of
scheduled delays in the project, thereby causing delay in the planned duration of the project. The project manager was
requested to form a group of decision makers to perform the fo llo wing tasks:
1. To check the delay factors cited in the questionnaire.
2. To cite additional factors if necessary.
3. To assign values to the factors ranging from 1 to 100 as probability of schedule delay (1 being probability very lo w and
100 being probability very h igh).Fo llo wing results were obtained after the interview.
Factors
Causes
Probabilit
y
20
a)Labor strike
Labor
b)Conflicts among labor
60
Related
c)Inexperienced Labor
65
Factors
d)Labor shortage
60
e)Absent labors
30
a)Short
original
contract
65
Page 602
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
Project
Related
Factors
Consultant
Related
Factors
Contractor
Related
Factors
External
Related
Factors
Owner
Related
Factors
duration
b)Delay penalties
c)Project co mplexity
d)Disputes among project
parties
a)Improper
project
management assistance
b)Inexperienced consultants
c)Inspecting
and
testing
delays
d)Conflicts
between
consultants
and
design
engineer
e)Poor communication and
coordination with other parties
f)Delay in approval of design
documents
a)Poor site management and
supervision
b)Poor
planning
and
scheduling of project
c)Shuffling of subcontractors
d)Poor communication and
coordination with other parties
e)Rework due to errors
f)Inexperienced contractors
a)Inclement
weather
conditions
b)Variat ions in price
c)Global financial crisis
d)Changes in government
regulations and laws
e)Unexpected surface and
subsurface conditions
f)Delay
in
providing
services from utilities
g)Delay in transportation
a)Slow decision making
b)Delay in approving design
documents
c)Late site delivery
d)Change in orders by
owners
e)Improper study of designs
f)Progress payments delays
g)Poor communication and
coordination with other
parties
h)Inexperienced owners
a)Material
manufacturing
20
50
40
50
60
30
75
40
60
60
55
35
60
65
25
25
70
95
85
20
65
35
55
55
40
85
45
60
50
20
30
Page 603
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
Material
Related
Factors
Design
Related
Factors
Equip ment
Related
Factors
delay
b)Damage of material
c)Material shortage
d)Delay in delivery
e)Rising prices of materials
a)Inadequate experience of
design team
b)Co mplexity in project
design
c)Errors made by designers
d)Delays in making design
documents
e)Unclear details in drawing
f)Insufficient data collection
a)Damaged equipment
b)Equip ment shortage
c)Breakdown of equipment
d)Low efficiency
e)Problem in allocation
30
60
85
65
60
75
60
70
50
40
50
20
30
40
50
The project members also estimated a range fro m 40-60 showing a mediu m probablity schedule delay of the project.
The results obtained from Table1 in the form of Ru le viewer of Matlab Program So ftware, were then used to obtain
graphs for probability schedule delay factors obtained from the interview, using Matlab Program Software. Fuzzy Logic
Toolbox of Matlab Program Soft ware d id the calculat ions easily and saved time, thereby giving suitable results . Following
schedule delay probability outputs of the case study was obtained using Fuzzy Logic Too lbo x of Matlab Program Soft ware:
Group of Factors
Labor Related Factors
Project Related Factors
Consultant Related Factors
Contractor Related Factors
External Related Factors
Owner Related Factors
Material Related Factors
Design Related Factors
Equip ment Related Factors
Schedule Delay
Probability output
44.8
41
49.1
40.1
42.2
49.6
57.5
61.9
36.8
47.7
2.
3.
Page 604
Shruti Singh, Dr. M.K. Trivedi /International Journal Of Computational Engineering Research
/ ISSN: 22503005
Very high probability
Conflicts between consultant and design engineer(75)
Very l ow probability
Inspecting and testing delays(30)
4.
5.
6.
7.
8.
9.
VII.REFRENC ES
[1] Hanouf M. A L-Hu madi (2007): A fuzzy Logic approach to model delays in construction projects
[2] Al-Hu maidi 2002 After the Fact Delay Analysis Techniques, Masters Thesis, Texas A&M University, 2002.
[3] Al-Ghafly, M.A. (1995) Delays in the construction of public utility projects in Saudi Arabia. Master thesis, CEM Dept.,
KFUPM, Dhahran, Saudi Arabia.
[4] Baldwin, J. and Manthei, J. (1971) Causes of delay in the construction industry. Journal of the Construction Division
ASCE, 97(2):
177- 87.
[5] Fuzzy Logic Toolbo x 2 Users Guide (2008), MATLA B, The MathWorks, Inc.
Page 605