Sie sind auf Seite 1von 7

TENDER

EVALUATION
REPORT
Proposed Restaurant &
Entrance Lobby for
Thilanka Hotels (pvt) Ltd.,
Kandy
Consultant Muditha Jayakody Associates

May 2016

Proposed Restaurant & Entrance Lobby Tender Evaluation


1.0 Introduction.
Scope of work of this Bid consists of Restaurant and Entrance Lobby for Thilanka Hotel (Pvt) Ltd.,
No.3, Sangamiththa Mawatha, Kandy.
2.0 Bid Invitation.
a. Bids were invited by M/S Thilanka
b. Basis of Bid
This Bid is on the basis of measure & pay with fixed rates.
3.0 Issue of Bid Documents.
Bids called from the following seven Bidders.
1.
2.
3.
4.
5.
6.
7.

M/S Electro Metal Pressings (Pvt) Ltd.


M/S Orient Construction Co. (Pvt) Ltd.
M/S Central Engineering Services (Pvt) Ltd.
M/S JSM Construction (Pvt) Ltd.
M/S Lego International (Pvt) Ltd.
M/S Buildmart Lanka (Pvt) Ltd.
M/S The Property Management & Construction (Pvt) Ltd.

Page | 1

4.0 Bid Opening & Bid Prices.


No.

C3
C1

142,462,421.94

Sampath Bank

1,300,000.00

C1

149,405,057.15

BOC

1,300,000.00

Electro Metal Pressings (Pvt)


Ltd.
Orient Construction Co. (Pvt)
Ltd.
Central Engineering Services
(Pvt) Ltd.
JSM Construction (Pvt) Ltd.

Bid Amount
(without PS + PC &
VAT)
136,578,156.80

C5

151,295,912.50

Not included

Not Included

Lego International (Pvt) Ltd.

C3

155,308,158.38

Peoples Bank

1,250,000.00

Buildmart Lanka (Pvt) Ltd.

172,174,575.96

Seylan Bank

1,500,000.00

The One Property


Management & Construction
(Pvt) Ltd.

227,804,769.60

Insurance
Policy

2,935,546.53

1
2
3

Name of Bidder

Grade

Bid Bond

Bid Bond
Amount

BOC

1,500,000.00

Table 1

* Details not given


5.0 Bid Examination.
5.1 Eligibility of Bidders
Tender document issued to the contractors who are registered in ICTAD under C3 or above
category.
5.2 Bid Bond
Bid Bonds were submitted by 5 No. Bidders only. (Refer- Table 1)
5.3 Discounts
No discounts offered.
5.4 Arithmetical Errors.
Arithmetical errors in the Bids were observed. Comparison of as submitted Bid price and
arithmetically corrected Bid prices excluding Provisional Sum, Prime Cost Sum & Vat are as
follows.

Page | 2

Name of Bidders

As submitted Bid price


(excluding P.S. +P.C.+Vat)

Arithmetically
corrected Bid price

Electro Metal Pressings (Pvt) Ltd.

136,578,156.80

136,467,411.79

Orient Construction Co. (Pvt) Ltd.

142,462,421.94

142,462,421.94

Central Engineering Services


(Pvt) Ltd.
JSM Construction (Pvt) Ltd.

149,405,057.15

223,087,397.15

151,295,912.50

151,296,321.28

Lego International (Pvt) Ltd.

155,308,158.38

155,308,158.38

Buildmart Lanka (Pvt) Ltd.

172,174,575.96

172,174,575.96

The One Property Management &


Construction (Pvt) Ltd.

227,804,769.60

227,659,329.68

Table 2

Refer attached Table 1 & 2 ( Table 1 - comparison of detail Bid Summary and Table 2 arithmetically corrected and adjusted summary ) for detailed comparison of Bid Summary
5.5 Covering letters and their contents
Only two Bidders have submitted covering letters.
M/S Buildmart Lanka (Pvt) Ltd
Buildmart Lanka (Pvt) Ltd has stated that rock penetration of H iron has not been taken
into consideration in their costing.
No deviation to the tender stated in the covering letter.
M/S Electro Metal Pressings (Pvt) Ltd.
No deviation to the tender stated in their covering letter.
M/S Orient Construction Co. (Pvt) Ltd.
No covering letter is given. Proposal for shoring system is attached with Bid.
M/S Central Engineering Services (Pvt) Ltd.
No covering letter is given.
M/S JSM Construction (Pvt) Ltd.
No covering letter is given.
M/S Lego International (Pvt) Ltd.
No deviation to the tender stated in their covering letter. Proposal for shoring system is
attached with Bid.
Page | 3

M/S The One Property Management & construction (Pvt) Ltd.


No covering letter is given.
5.6 Completeness of Bids.
a. M/S Buildmart Lanka (Pvt) Ltd.
Not quoted for following items.
Preliminaries
Page 1/1 item 12 Progress Chart
Page2/2 item 13 Setting Out
Page2/2 item 14 Temporary Water Connection
Page 2/2 item 16 Electrical Connection
Page 2/2 item 18 Protecting & Safeguarding
Page 2/2 item 19 Supplying Specimens
Page 2/2 item 20 Clearing Site on Completion
Page 2/2 item 22 Cutting down coconut tree & grubbins up
roots
Page 2/2 item 23 Removing of Vegetation
Attendance Fee
Page 11/1 item 3, 4, 5 & 6 Attendance Fee on PS
Page 13/1 item 1 Attendance Fee on PC
Day Work
Page 14/2 item 12 Day Work Schedule
Page 14/3item 29 Day Work Schedule
Page 14/4 item 51-54 & 57 Day Work Schedule
b. M/S JSM Construction (Pvt) Ltd.
According to the comparison after arithmetically corrected, the third lowest
responsive Bid has been submitted by JSM Construction (Pvt) Ltd at a sum of Rs.
151,296,321.28.
It is observed that the Bid security is not submitted with Bid and considered as a
incomplete Bid.
And attendance fee for prime cost sums are not quoted.

Page | 4

5.7 Comparison with Engineers Estimate/Cost Estimate.


Engineers estimate is Rs. 163,071,357.58 ( Without Provisional Sums + Prime Cost
Sums + VAT )
Comparison of as submitted Bid price , arithmetically corrected Bid price and corrected
amount with un priced items excluding Provisional Sums, Prime Cost Sums & VAT
are as follows.
Contractor's Name

As Submitted
Amount (Rs.)

Deviation
% (Rs.)

Engineer's Estimate

163,071,357.58

EMP Construction

136,578,156.80

-16.25

Orient Construction Co.


((Pvt) Ltd.

142,462,421.94

JSM
3 Construction

Corrected
Amount (Rs.)

Deviation
% (Rs.)

Corrected
Amount with Un
Priced Item (Rs.)
163,071,357.58

Deviation
% (Rs.)

136,467,411.79

-16.31

136,467,411.79

-16.31

-12.64

142,462,421.94

-12.64

142,462,421.94

-12.64

151,295,912.50

-7.22

151,296,321.28

-7.22

151,306,758.68

-7.21

Lego International

155,308,158.38

-4.76

155,308,158.38

-4.76

155,308,158.38

-4.76

Build Mart Lanka

172,174,575.96

5.58

172,174,575.96

5.58

175,432,701.33

7.58

Central Engineering

149,405,057.15

-8.38

223,087,397.15

36.8

223,087,397.15

36.8

The One Property

227,804,769.60

39.7

227,659,329.68

39.61

227,659,329.68

39.61

163,071,357.58

Table 3

The following responsive bids were considered for detailed appraisal.


Rank

1.

Bidder

Corrected Bid Price

Deviated from
Engineers Estimate (%)

136,467,411.79

-16.31

142,462,421.94

-12.63

3.

Electro Metal Pressings (Pvt)


Ltd.
Orient Construction Co. (Pvt)
Ltd.
Lego International (Pvt) Ltd.

155,308,158,.38

-4.76

4.

Buildmart Lanka (Pvt) Ltd.

172,174,575.96

+5.58

2.

Table 4

Page | 5

6.0 Observations.
1. According to the Bid summary, the pricing of the lowest Bidder namely M/S Electro Metal
Pressings (Pvt) Ltd. is well below market rates and therefore during the construction, this
contractor is likely to the delay work due to cash flow difficulties.
2. According to the comparison after arithmetically corrected, the second lowest responsive bid
has been submitted by M/S Orient Construction Company (Pvt) Ltd. at a sum of Rs.
142,462,421.94 No arithmetical errors found in their bid.
Given proposal for shoring system is not adequate for the nature of site condition.
3. According to the ranking of bids, the fourth lowest responsive bid has been submitted by M/S
Lego International (Pvt) Ltd. at a sum of Rs. 155,308,158.38 No arithmetical errors found
Proposal for shoring system is given and to be verify by structural Engineer.
All quoted rates are fair & reasonable.

7.0 Recommendation.
The total price quoted by M/S Orient Construction Co. (Pvt) Ltd. and M/S Lego International (Pvt)
Ltd. two eligible are very reasonable and workable. However it is recommended that the two
bidders are interviewed to get suitable adequate method for planking and strutting system,
ascertain their ability to complete this job satisfactorily.
The technical capabilities of two bidders are provide for handling this type of projects looking at
the past experience of the bidder.
The main cost difference in between two bids is in planking & strutting.
Two bid amounts are less than the Engineers estimate considering the above observations we
recommend to obtain clarification from these two bidders as follows prior to a decision on
awarding.
1. M/S Orient Construction Co. (Pvt) Ltd.
Method of planking and strutting system
2. Lego International (Pvt) Ltd.
Method of planking and strutting system

..
Project Architect

Chief Quantity Surveyor


Page | 6