PRESENTATION OBJECTIVES
Overview of Past Capital Planning & Funding
Proposed Capital Planning & Funding Approach
Preliminary CIP Needs
Highlight Representative Projects
Next Steps

long-term plan to manage our infrastructure


including maintenance, expansion and funding.

EXISTING INFRASTRUCTURE

Current Infrastructure represents well over $1 Billion


invested over 100 years by tax and rate payers

1000+ miles of streets


600+ miles of alleys
130+ miles of storm sewers
1200+ miles of water lines
1000+ miles of wastewater lines
3000+ acres of parkland
2+ M square feet of facilities
Water/wastewater treatments plants
Airport
2000+ computers and servers
Landfill
1,600+ vehicles/pieces of equipment

CAPITAL PLANNING & FUNDING


Comprehensive Plan
Master Plans
Assessments & Evaluations

CAPITAL PLANNING & FUNDING


Annual CIP as part of Annual Budget
Funded through debt (GO/CO/RevBonds), cash,
tax revenue, rates, fees, state loans, grants, etc
FY 15/16 $80 Million

CAPITAL PLANNING & FUNDING

Traditionally most General Fund Projects (Fire


Stations, New Equipment, Streets, New
Facilities, IT, etc) funded through cash realized
through preceding budget year savings
Traditionally most Utility projects (water,
wastewater, drainage, etc) funded through a
combination of cash realized through increased
sales and through debt backed by rate increases

CAPITAL PLANNING & FUNDING

Needs are outpacing resources at an increasing


rate. This means.

Not able to maintain pavement preservation program


within life cycle goals
Not able to address drainage needs of both growth
and existing problem areas
Not able to address utility needs of both growth and
existing problem areas
Not able to meet community level of service
expectations in parks and recreation, transit, etc.
Not able to meet internal service demands for IT,
communications, fleet, facilities, etc.

CAPITAL PLANNING & FUNDING

We are an aging and growing city

PROPOSED CAPITAL PLANNING & FUNDING

Strategic Approach to planning to address capital


needs Enhanced Process

Citizen Engagement
Council Priorities
Comprehensive/Strategic
Plans

Master Plans
Neighborhood, District,
Corridor Plans
Assessments &
Evaluations

Multi-Year Funded CIP


Enhanced Project
Administration and
Management

PROPOSED CAPITAL PLANNING &


FUNDING
Full accounting of current needs
Multi-year CIP fiscally viable
Annually Updated/On-Going Enhanced Product
Additional Revenues Required

PROPOSED CAPITAL PLANNING & FUNDING


Staff Identified Needs
$900+ Million
F1
F2
F3
F4
F5
F6
F7
F8
F9
F10
F11
F12
F13
F14
F15
F16
F17
F18
F19
F20
F21
F22

Facilities Maintenance
410214 Reroof Various City Buildings
410640 City Hall Cooling Tower Replacement
410782 Interior Lighting Upgrades
410818 R22 HVAC Systems Replacement
410822 Upgrade Police & Municipal Court Entrances
411102 City Hall Architectural and Engineering Design
411104 Central Library Streetscape
411105 Concrete Wash Bay
411106 Service Center Lighting Upgrade
411107 Service Center Loading Dock Replacement
411108 Service Center Space Study
411119 Bucket Truck
411126 Vital Statistics Remodel
411132 Legal Dept Remodel
411133 IT Department Remodel
411134 Parks Department Remodel
411135 Risk Mgmt & Benefits Department Remodel
411136 City Hall Restroom Remodel
411178 Coke Recreation Area Next to MPEV
411179 Liberty Theater and Park
411180 Santa Fe Depot Rehab
411181 Transit Hub
Total

1,000,000
52,000
750,000
250,000
108,500
488,250
505,610
488,250
379,750
352,625
80,000
125,000
103,750
300,000
300,000
450,000
150,000
850,000
4,958,800
4,860,000
7,290,000
3,888,000
27,730,535

NEEDS IN SUMMARY

$276M in Street and Drainage Projects


$124M in Parks and Recreation Projects
$27M in Facilities
$169M in Utilities
$21M in Airport
$16M in Solid Waste
$20M In IT
$23M in Public Safety
$166M in Civic Center
$4M in Traffic
Projects across all program areas
Projects across entire City
Projects take care of what we have and respond to new
growth

PROPOSED CAPITAL PLANNING & FUNDING

PRIORITIZATION OF PROJECTS

Staff Preliminary Prioritization will be based on:

Alignment with Blueprint


Assessment of Public Benefit
Assessment of Economic Benefit
Alignment with Plan/Study/Assessment
Assessment of Project Urgency
Assessment of Ability to Deliver Project
Alignment with Regulatory Mandates
Complimentary to Previous Expenditures

Further Refinement through Community


Engagement and Council Direction

HIGHLIGHTS OF REPRESENTATIVE
PROJECTS

Public Works
Utilities
Facilities
Parks & Recreation
Civic Center

PUBLIC WORKS
REPRESENTATIVE PROJECTS

Streets

Ridgemere Blvd
from NE 3rd to
Amarillo Blvd
Concrete Paving:
$2,675,000

Microsurfacing of
Various Streets:
$293,950

Drainage

SE 10th Ave. Railroad Underpass:


$2,910,000

Olsen Blvd. and S. Western Storm


Sewer Extension to Lawrence Lake:
$500,000

Solid Waste/Landfill

Gas Collection &


Control System:
$5,541,000

UTILITIES
REPRESENTATIVE PROJECTS

LIFT STATION 32

Lift Station # 32 was Identified in the 2013 WW Master


Study as being overloaded and it was determined that the
wet well was undersized
The study also identified that the wet well was in need of
repairs as soon as probable from deterioration from high
levels of H2S.
The City of Amarillo conducted a feasibility study with
Kimley-Horn to determine rehabilitation or replacement
options. The engineer and city staff determined that if LS
32 was moved north just under mile, we would gain
approximately 15 of depth and the ability to serve another
5 sections of land south and east of the proposed new
location of Lift Station 32.

Current Service Area for LS #32

New Service Area for LS #32

NORTHEAST OUTFALL LINE

Address the preliminary design of a new 3-MGD facility.


Consider two treatment processes: one using an oxidation
ditch and the other a conventional activated sludge plant.
Address the Northeast Interceptor as the proposed means of
conveying wastewater to either RR or in combination with a
scalping plant.
Determine a preliminary pipeline route allowing operation of
the interceptor main without pumping.

Identified in the 2013 WW Mater study in Task M section 5.2


under option #1.
In the WW Master study proposed CIP schedule as project #
37.

Identified in the WW Master Study the first option to relieve


the load from LS # 29 and expand the north east corridor

NORTHWEST OUTFALL LINE

The Northwest Wastewater Outfall Line was originally identified


in the 1995 City of Amarillo Wastewater Collection Master Plan
Further developed in the 2007 Northwest Amarillo Wastewater
Serviceability Study
Will consists of mains ranging from 10 to 30-inch beginning just
north of Lift Station 48 and extending north to Lift Station 40
The outfall line will eliminate/decommission the need for Lift
Stations 39, 44 and 45

Lift Stations 44 and 45 are small package lift stations that currently serve
very small areas along Citadel Dr
Lift Station 39 (a small wet well/dry well station) has a small service area
that flows into the station where it is pumped to the east parallel to
Fairway Dr. The wet well will continue to be used as a manhole.

Increase capacity for future growth and development of the


medical centers and surrounding basins.

FACILITIES
REPRESENTATIVE PROJECTS

FIRE STATION 3

6009 Estacado Ln.


Constructed in 1975
41 Years Old
4,800 SF

FIRE STATION 3
Oxford & Coulter Drive
City Owns The Property
New Station Will Match F/S 8
and 12 - 9,650 SF
Improved Response Time &
Service

SERVICE CENTER SPACE STUDY


Space Study $80,000
Constructed in 1966
Reorganization Needed To Improve Efficiency
Operations
Utilities
Public Works
Parks
Transit
Fire Garage
Radio Shop
Warehouse
Solid Waste
Municipal Garage
Welding Shop
Traffic

ANIMAL MANAGEMENT & WELFARE


Site Preparation

$268,707
Covered Dog Runs
$256,653
Drive Through Barn
$68,672
Employee Training Area
$457,185
Medical Treatment Barn
$384,230
Sally Port
$230,218

LIBERTY SQUARE
Development of a Useful Space
Enhance Green Space Downtown
Rehabilitate Historical Value of Property
$4,860,000

PARKS & RECREATION


REPRESENTATIVE PROJECTS

Existing Softball Complex


Renovations $4,210,000
Southwest Complex (5)
Southeast Complex
Martin Road Complex

$1,460,000
$1,375,000
$1,375,000

Complete field lighting replacement.


Demolish and replace restroom and concession
with ADA accessible building.
Fence repair and replacement.
Entry walkway asphalt to concrete.
Electrical service upgrade to facility.
Re-grade and replace infield material.

Youth Sport Field Expansion

Rick Klein Baseball


Complex Expansion
$11,606,000
6 field conversion to syn.
3 new lighted syn. Fields
1 new lighted field of dreams
400 parking

Youth Softball
Baseball Complex
$12,443,633
8 lighted 225 lighted syn. fields
Restroom/concession
550 parking
Access Roads/Widening of Grand

Rick Klein
Soccer Complex
$13,800,000
10 lighted syn. fields
Restroom/Concession
Stadium Field/Seating
750 parking

NEW
FACILITIES

Multi-Use Court Facility


$13,250,000
6 regulation basketball courts
12 regulation volleyball courts
Concession/Pro Shop/offices
800 parking

Natatorium (Indoor
Aquatic Center)
$29,362,820
50m x 25y indoor pool w/two bulkheads
Leisure pool
Therapy/fitness/instruction lanes
750 seating

Tennis Center Expansion


$5,040,000
Three indoor courts
300 parking

Active Adult Center


$5,550,000
12,000 -15,000 sq. ft. facility
Renovate existing facility
New construction

Park Renovation Projects


Gene Howe
Hilltop/Hines
Pleasant Valley
Mary Hazelrigg

New Park Projects


Colonies

$940,000
Pinnacle (design only) $125,000

$550,000
$1,925,000
$825,000
$660,000

John Stiff Park Development


Skate Park Expansion
Restroom Replacement
Hike Bike Trail Expansion
Dog Park Improvements
Parking Expansion (625)
Roadway Improvements
Multi-Use Field Conversion (3)

$400,000
$170,000
$340,000
$35,000
$687,000
$2,751,000
$2,975,000

Amarillo Zoo
Master Plan Completion
$135,000
Zoo Improvements & Renovations
$1,000,000

CIVIC CENTER
REPRESENTATIVE PROJECTS

Facility Needs Assessment Study


Dekker/Perich/Sabatini
Volume I May 2012
Existing Feasibility Assessment
& Market Study
Volume II Summer 2016
Master Plan
Financial Analysis

Civic Center Complex Rehabilitation and Expansion - $81


Million
75,000 ft2 contiguous, column-free exhibit hall (divisible)
30,000 ft2 ballroom (divisible)
20,000 ft2 breakout meeting space
Scope and scale of a convention center with main entrance and
true back of house areas

New Arena - $66 Million


Up to 7,500 fixed seats, yielding up to 9,000 seats for an end stage
concert
Up to 300 premium seats
Improved guest and user experience
Industry standard specifications and amenities (regulation ice floor;
correcting 38 clearance; quality and quantity of concessions, dressing
rooms, storage, service access, loading areas and meeting accessibility
codes)

New Parking Garage - $11 Million

Replace parking lost to proposed expansion and new arena

NEXT STEPS
Continue to Refine Projects and Priorities
Community Engagement May, June, July
Council Budget Workshops - August
Public Hearings, Tax Rates, Utility Rates, Fee
Schedules, Election Issues August/September
Budget Approval September
Budget In Effect October
Election (if scheduled) November
CIP Implementation November On-Going