Beruflich Dokumente
Kultur Dokumente
Box 576
Ipswich, MA 01938
Sincerely,
Wayne Castonguay
Executive Director
Attachment (1)
P.O. Box 576 * 143 County Road * Ipswich, MA 01938 * 978-412-8200 * fax: 978-412-9100
History
The dam and the surrounding area have a rich history
The dam is believed to be built on the site of a rocky ledge, the upper falls, that was used as a
ford for Native Americans and early settlers
c. 1637: First dam constructed at the site near the location of the upper falls of the Ipswich
River
The Dam was known for its role in powering hosiery production from the mid 19th to early 20th
centuries
c. 1908: The existing dam was constructed (or reconstructed) to provide power for adjacent mill
buildings
During the 20th century Sylvania manufactured light bulbs (and during WWII bomb fuses)
The mill buildings currently house EBSCO publishing.
While there are clear ecological and long-term cost/liability benefits of removing a dam like the Ipswich
Mills Dam, there are many important considerations that can influence the cost and value of a project
like this. Important considerations including impacts on other infrastructure, historical and social value
and changes to existing ecological communities can greatly influence project cost and/or a final decision
on whether or not a restoration project is viable. Dam removal feasibility studies can help to quantify
the relative costs and benefits associated with a dam removal project and help a dam owner decide
whether or not to pursue removal.
Beginning in 2009, the Town has partnered with IRWA, DER, NOAA Fisheries and other partners on
studies to investigate the prospect of removing the dam. The goal of these studies has been to gain a
better understanding of the full range of benefits and costs associated with removing the dam so that
the Town can decide whether to pursue removing the structure or choose to maintain it as is.
Previous studies
2006: MA Riverways funded site reconnaissance study for this and the South Middleton Dam
Identified Ipswich Mills dam removal as having substantial potential benefits to natural
resources and likely diminishing downstream flooding. Recommended further feasibility study
(Woodlot Alternatives Inc. 2006).
2014: Preliminary feasibility study. Ipswich Board of Selectmen voted to pursue funding for
preliminary feasibility study (Horsley Witten Group Inc. et al. 2014). This study found:
o
The removal of the dam would lower the level of the water upstream of the dam such
that the water elevation likely would be governed by the rock ledge identified by IRWA
in a preliminary site survey extending approximately 10 feet upstream from the dam
structure;
Dam removal would have no impact on downstream flooding and would decrease
upstream flooding;
o The preliminary assessment of the dam environment suggests that there is a minimal
amount of sediment trapped by the dam and what little sediment exists is minimally
contaminated contamination and may not pose a threat to human or aquatic health;
o The lowering of the water elevation upstream of the site as a result of dam removal
could pose a biodeterioration threat to the foundation of the EBSCO building on the
river bank just upstream of the Ipswich Mills Dam if the building is supported by wooden
piles. Methods exist to mitigate these potential impacts. More information is required
to understand better the existing foundation structure and elevation.
2014: Bathymetric survey shows that post-removal water levels upstream of the dam may only
drop a few feet.
Current Study
Based on the results of the studies referenced above, the Town and project partners decided to pursue
a full feasibility study with a goal of presenting Town officials with sufficient information to make a
decision as to whether to remove or retain the dam. The current study is funded by DER with support
from the National Fish and Wildlife Foundation (NFWF) grant that the Town provided a letter of support
for in 2014.
This study is underway now and will be taking place throughout 2016 and early 2017.
The scope of the current study includes:
Analysis and summary of the pre- and post- settlement history of the dam site and evaluation
of the historic value;
Detailed maps of existing conditions at the dam;
Hydrologic and hydraulic analysis of water levels and flows in a dam-out scenario considering
effects on flooding, effects of changes in upstream water levels, fish passage and ecology;
Investigation of EBSCO foundation to determine potential effects of dam removal on the
EBSCO building. Evaluate mitigation options if impacts are expected;
Evaluation of potential dam removal impacts to other structures;
Conceptual plans and cost estimates;
Conceptual renderings to show what we can expect the site to look like without the dam.
The Town and project team have planned an initial public meeting to discuss the project and hear
questions from interested citizens. The meeting will be held at Town Hall on Wednesday, June 8 at 7:00
PM. Representatives from the Technical Team will be on hand to discuss the project and take questions.
Literature cited
Haley & Aldrich Inc., 2009. Ipswich Mills Dam Phase I Inspection/Evaluation,
Horsley Witten Group Inc., GEI Consultants Inc. & Clean Soils Environmental Ltd., 2014. Ipswich Mills
Dam Partial Feasibility Study,
Martin, E.H. & Apse, C.D., 2011. Northeast Aquatic Connectivity: An Assessment of Dams on
Northeastern Rivers,
Woodlot Alternatives Inc., 2006. Site Reconnaissance for Ipswich River Dams, Available at:
http://ipswichriver.org/wp-content/uploads/2012/05/Site-Reconnaissance-Ipswich-RiverDams_Woodlot-Alt.pdf.