Beruflich Dokumente
Kultur Dokumente
Page 1 of 4
Ref: EM/PROC/44_10
1. Meteorological Data
1.1.
Wind
Snowfall
100%
Rainfall
Average rainfall
Design Rainfall
1.4.
29.5 oC
-12oC
-15oC
1.5kN/m
0.75kN/m
Barometric Pressure
Maximum
Minimum
1030 mbar
970 mbar
2. Utility Data
The following data should be used for design purposes. Projects should wherever possible confirm
typical operating utility conditions for the area of the Refinery under consideration.
Particular attention should be paid with steam systems due to the large number of inconsistencies
which exist between the Refinery Offsites steam producing systems and internal to the unit
steam producing systems. For steam systems, the following guidelines should be followed.
SOL below refers to safe operating limit as defined in the pressure systems definition information at
the Refinery. The design pressure should be set at the SOL of the system.
LP Steam: If using unit generated LP steam, consult pressure system dossier for the unit concerned
to determine the SOL. If tying into the Refinery Offsites system, use an SOL of 3.5 barg.
MP Steam: Use an SOL of 15.5 barg (except for Hydrocracker complex where 17.2 barg should be
used)
HP Steam: If tying into a unit generated HP steam system refer to the Pressure system dossiers for
the unit to determine the SOL. If tying into the Refinery Offsites system, use an SOL of 50.barg
Issue No
3
Engineering Manual
Page 2 of 4
Ref: EM/PROC/44_10
Minimum
Maximum
Design
Temp
Pressure
Temp
Pressure
Temp
Pressure
Temp
Pressure
Plant Air
Amb
6.9
6.2
7.5
66
Instrument Air
Amb
6.9
6.0
7.5
66
8.6
Breathing Air
Amb
6.9
6.2
7.5
66
8.6
HP steam (640#
steam)
399
41.6
427
50.0 Note 1
MP Steam (200#
steam)
221
13.8
190
10.3
228
14.0
243
15.5 Note 1
LP Steam (40#
steam)
148
2.1
130
2.0
152
2.1
170
3.5
CW (supply)
4.5
3.0
24
5.0
66
8.6
CW (return)
1.7
1.2
43
2.0
66
8.6
Nitrogen
Amb
5.0
4.0
10.3
66
10.3 Note 1
Fuel Gas
Amb
2.1
1.9
2.8
121
3.5
Note 1
Pilot Gas
Amb
2.1
2.0
2.2
66
3.5
Note 1
Demin Water
Amb
2.1
2.0
2.2
66
Condensate
See Note 2
9.3
Note 1
Note 1
8.6
Note 1 :- Figure quoted is the Safe Operating Limit as defined in Pressure Systems Dossiers PSYS
40
Note 2 :- For condensate systems refer to the unit Pressure systems dossiers. However for LP and
MP condensate systems the SOL of the condensate system should be equal to the SOL of the
steam system itself.
Issue No
3
Engineering Manual
Procedure - Design Data
Page 3 of 4
Ref: EM/PROC/44_10
3. Civils
3.1.
The maximum allowed ground bearing pressure in the Refinery, Refinery Tank Farm and
Kinneil is 25k N/m. In other specific areas (eg RLPG), this is reduced to 12.5 kN/m.
Design groups shall ensure that appropriate ground loadings are applied in each design.
Additional information on soil and sub-soil conditions is held in Factory Drawing Office.
3.2.
Grade Level, as defined in RP4-3, for construction of new development work shall be based
on the local National Geographical Survey Level Datum:- A.O.D. Newlyn.
3.3.
Existing Drawings
It should be noted that levels on existing pre. 1973 drawings within the refinery area are either
referred to the now obsolete Ordnance Survey Liverpool Datum or to one of three
assumed datum with a known relationship to the Liverpool Datum. BP Chemicals also
refer all levels to an "Assumed Datum".
Later drawings are referred to Ordnance Survey Newlyn Datum currently used by National and
Local Authorities and industry throughout the country.
The Liverpool Datum is higher than the Newlyn Datum by an amount which varies from district
to district over the country because of inaccuracies in the original levelling. A similar
reason, along with instability of BP bench marks, explains a local difference in the
correction factor between BP Refinery bench marks and BP Chemicals bench marks.
To ensure that new structures are compatible with existing structures, it is essential that existing
drawings are checked for accuracy of elevation.
Many existing drawings show elevations based on an Assumed Datum :Refinery Grade Level (Refinery + Jetties) = 100 on drawings = 4.289m A.O.D. Newlyn.
Kinneil Grade Level = 100 on drawings = 4.225m A.O.D. Newlyn.
Chemicals Grade Level (Refer to Drawing No. 87630).
Chemicals Docks Grade Level = 100 on drawings = 4.016m A.O.D. Newlyn.
This conversion should only be used as a guide, as no account is made for long term differential
settlement etc..
Finnart - not a level site.
At the terminal, earlier existing levels have been shown in Feet above Ordnance Datum
Liverpool (obsolete). More recent levels are shown in Metres above Ordnance Datum
Newlyn.
Dalmeny - not a level site.
At the terminal, all existing levels are shown in Metres above Ordnance Datum Newlyn.
Where existing levels are shown in Feet above Ordnance Datum Liverpool, conversion
to Metres above Ordnance Datum Newlyn is as follows:Refinery (including Jetties and Kinneil) : add 0.32ft, multiply by 0.3048.
Issue No
3
Engineering Manual
Procedure - Design Data
Page 4 of 4
Ref: EM/PROC/44_10
Issue No
3