Quick Guide for Enhancement Pack 7 Upgrade:-

This post will help you to prepare plan for upgrading your system.

Insights of Enhancement Pack 7

What is Enhancement Pack:


Enhancement packages are provided by SAP for their customer to manage
and deploy new software functionality introduced by SAP. A set of new
integrated/individual functionalities can be deployed by implementing
enhancement packs. Best part is customers can select new/enhanced
functionalities out f the delivered software innovations by SAP and activate
as per business needs. This is the simplest online solution to introduce new
functionalities into the system without impacting ongoing business in faster
way. Enhancement packages are cumulative. Thus, enhancement package 7
contains all the previously delivered enhancements as well as the new ones.
Enhancement packages can be downloaded from SAP service using SAP
Solution Manager.

Enhancement Package 7 for SAP ERP 6.0


SAP has introduced more than 100 new functions in Enhancement package
7 for SAP ERP 6.0 and is the first EHP to be optimized for both the SAP HANA
database and the traditional certified databases.
Since enhancement package 5 for SAP ERP 6.0, customers have had the
option of deactivating certain business functions that were previously
activated. SAP enhancement package 7 also includes numerous new
functions for financial accounting, logistics, human resources, and quality
management, as well as cross-application functions and improvements for
SAP Master Data Governance and manager self-service (MSS).

Key features with EHP 7

SAP Fiori There are collection of 25 role-based productivity


applications in SAP Fiori which will help end users to complete their
daily tasks with enhanced speed and efficiency on handhold devices
like smartphone and tablet along with notebook or PCs.
Faster MRP runs As EHP7 is optimized for SAP HANA database, it
provides the option to use SAP HANA Live to check on material
availability and inventory days of supply in real time at exploded-view
level. All features of SAP HANA can be utilized to speed up complex
MRP runs and capacity planning.
Data aging The use of data in-memory platform of SAP HANA can be
used for implement a data aging strategy efficiently. This can provide
near real-time data to end user for day-to-day operations such as the
financial results for the last two years.

SAP Upgrade from ECC 6.0 EHP4 to ECC 6.0 EHP7:

Pre-upgrade Activities must be done on the existing level of software to


understand impact on the basic software level. Another installation check
should be done to identify any critical issues that could lead to additional
risks or work on total number of custom objects /customizing to identify the
impact of EHP7 enhancements on the existing custom transactions/reports

Study of Software components versions:


The component versions can be generated by Solution Manager System
which gives the overall components needs to be upgraded from EHP4 to
EHP7 SPS3. This can be done by SAP basis consultant using SAP Solution
Manager. A list of all the new versions of software components can be seen
and selected before upgrading to EHP7. Find below sample screenshots
which show the components selected that will be upgraded with new version.

Installation Check:

Installation check is the activity to must be done to understand if there are


any critical issues that could lead to additional risks or work when compared
with the average SAP EHP installation project.

This check can be done by development team or SAP support can be taken
to study and report the impact on the existing set of processes in the ERP
SAP system. SAP charges separately for doing such studies.

The objective of the SAP EHP Installation Check is to identify the most
significant risk and effort drivers for your planned project. For this purpose, it
collects technical information in your current production system and
evaluates it based on general experience obtained.

The table below shows the most critical risk and outlay drivers for any
software change project grouped by key focus areas. An explanation of the
key focus areas can be found in the upgrade white paper of the SAP
standards for solution operations.

An action plan for the activities can be prepared based on the priorities on
identified risk and precautions before upgrade initiation.
Installation check will be baseline for estimations of the efforts required for
adjustment during upgrade of enhancement package.

Security Authorization Check


Enhancement package impact on the security and authorization objects of
the end users. Once development upgrade is done in the landscape, a detail
check of modifies authorization object must be done by SAP security
consultant/team. This activity will mitigate further risk of authorization issues
after production upgrade.
The transports of the security adjustment must be transported just after
upgrading quality or production system.

Test Factory for SIT:


Test factory must be involved for SIT in project planning to avoid re-planning
or any impact the go-live date. Test factory do not always have all the
domain knowledge to be able to execute a full SIT. If test scripts are not
ready or up-to-date, it could cause adverse impact on the project timelines.

Its is highly recommended to execute knowledge transfer to test factory for


the areas where they are currently lacking the knowledge of the upgrading

system. There involvement during start-up of the project will help in the
efficient project planning. Test Factory can execute Regression Testing on the
upgrading system as a part of regular monthly release.

SAP Max Attention Support:


SAP Quality manager must be involved right from kick-off of the upgrade.
SAP quality manager can arrange support from SAP to expedite resolutions
from SAP. This is a paid service of SAP and must be arrange in advance to
avoid unexpected delays in project timelines due to software issues during
upgrade.

Challenges and Risk:

Challenges

Enhancement pack 7 is the latest pack provided by SAP. Even SAP


doesnt have complete knowledge bank on the issues occurred. In our
case customer specific SAP notes had developed by SAP to resolve
issues in SAP standard code during technical upgrade.
Coordination with vendors for SAP security, Basis, EAI, Portals and SAP
for respective activities in different time zones.

Stringent timelines due to other projects based on business priorities.

Governance of emergency changes and fixes.

Risks

Issues encountered during upgrade and testing in (DEV/QUA) which


might need structural fix
Delayed response from SAP in providing required solution since issues
are not in knowlege bank of SAP

Upgrading CTP to EHP7 brings additional risk due to older versions of


other systems in the landscape.

Existing projects, new projects and project aftercare issues can be


impacted during upgrade activities of productive system

UAT issues/fixes of the ongoing projects can be impacted during


upgrade activities.

Communication Protocol:
Communication plan must be prepared and approved before actual execution
of the projects from IT and business.

Daily call There must be daily call on every working day with the
project team along with client IT team. Use Run book to review the status
on a daily basis. Meeting was chaired by the onsite/offshore PM.

Governance Board call It must be a bi-weekly call. All stakeholders


must be invited to join this meeting. It should always starts with a brief
status update on upgrade project. The objective of call should be to check
and approve/reject the high priority transports of operations or project that
need to move through the landscape during the freeze (e.g. severity 1
production issues or project after care issues). A tracker would help to
track these changes along with transport list.

Lessons learned call - At the end of each major project stage, a lessons
learned call must be scheduled to capture the lessons learned in the
lessons learned log.

Ad-hoc call - Calls when important decisions need to take place e.g.
Go/No Go and Changes to the project plan / freeze periods. All
stakeholders of the project were invited to join the meeting

Governance Board:

Governance Model Execution:

During the freeze period of upgrading SAP systems, there are two kind of
situations which can occur:
1. Aftercare issues ongoing projects
2. Production issues in operations

Governance board will work for smooth execution of these issues:


1. Aftercare issues:
Project Manager of the respective project must approach business, Tech
Lead/BA of that project an
operations lead in case of Change required and get the approval
ready.
Then formal approval in Governance board meeting.
Project Manager of the respective project to connect with Release Manager and QA
officer for transporting changes/fix
approved.

2. Production Issues:
Raise an incident in the ticket handling tool.
Corrective change/fix must be checked and Incident Manager/Service Lead must
approach Business and operational lead for approval.
Then formal approval in Governance board.
Service Lead/IM to connect with Release Manager for transporting
changes/fix if approved.

Lesson Learned and Recommendations:


Project Plan and Run book preparation:

All the stakeholders and involved parties must be involved while preparing
project plan. Most important activity is to gather run book from all vendors
supporting upgrade activity and merge into master run book and project
plan. Get POC from each of the vendors for interchanging information and
involve in meetings. Following contributors must involve for their respective
responsibilities:
Basis will be doing technical upgrade of the system. Involve POC right
from project kick-off and planning project activities.
Security and Authorization team must take care of arranging user access
for Basis and other dialog and non-dialog users (system users, batch users,
etc.).
Business must be involve to make sure availability of users for UAT.
Test Factory must be involve for regression testing
SAP Functional team must be involve for unit testing and functional
testing
SAP technical team must be involve to implement SAP notes, SPAU/SPDD
activities, bug fixing in functional testing/UAT/aftercare
Release Manager is an important participant to adjust system upgrade of
each system in continuation with regular/monthly activities
Prerequisites of EHP7:
SAP system must be well equipped before go-live. EHP7 brings loads of
additional functionalities to the existing SAP system. It creates considerable
reduction in the system response and generally contribute to system
performance. Make sure SAP system will be at latest software component
level. Go through the note mentioned below for further details.
There are several SAP notes available providing information about EHP7
package. Find below one of the note which is providing related information
about support packs.
1737650 - EHP7 for SAP ERP 6.0 SP Stacks - Release & Information Note
Test script and Test users:
Make sure test scripts must be updated with the latest approved testing
process and test users must be having similar role as that of the business

users executing certain business processes . Make sure Test factory testing
script are updated.
Security and Authorizations:
EHP7 modifies authorization objects at some extent. Involve security and
authorizations team in planning study of changes in authorizations and roles
of users. There is a separate exercise must be done after implementing EHP7
in DEV system to find change s in the authorizations. A separate run book
must be prepared for S&A activity and merge in master run book and project
plan
SAP involvement:
OSS messages raised due to various issues during upgrade of DEV or QUA
takes time since SAP do not allow to keep priority High/Very High for nonproduction system. Involvement of POC from SAP helps is arranging
appropriate in-time support during non-production system upgrades.
Other third party interfaces or applications POCs must be involve during
testing of interfaces/portals etc. Project managers of the
other ongoing projects will help in prioritize activities.