Agenda
Western look ahead: Sound wall construction
La Brea Piling Update
La Brea Decking: Phase l, ll ,lll detours, outreach and communication
Jet Grouting Schedule and Locations
Fairfax Updates: Tree/median removal, sound wall/driveway
construction, traffic reconfiguration, piling
La Cienega look ahead: Advance utility relocation, building demo
Eat Shop Play Wilshire
Question & Answer

Purple Line Extension


Project Alignment

Section 2 and 3
Status
Under Construction
Section 1

Forecasted Schedule
Section 2
Section 3

Length

3.92 Miles

2.59 Miles

2.48 Miles

New Stations

Wilshire/La Brea
Wilshire/Fairfax
Wilshire/La Cienega

Wilshire/Rodeo
Century City/
Constellation

Westwood/UCLA
Westwood/VA
Hospital

Pre-Construction Activities Current - 2016

2015 - 2018

2025 - 2027

Construction

2015 - 2023

2018 - 2026

2027 - 2035

Operations

2024

2026

2035

PLE Section 1
Alignment

Local Streets
Project Policies for Local Streets:
No hauling and no construction vehicles
on residential streets.
No parking on residential streets
outside of permitted closures.
Enforcement:
Training and take-home materials for
craft and sub contractors prior to
starting on the job.
Signage in the yards and on local
streets.
Flaggers strategically placed to avoid
violations.
Stand-down meetings with construction
supervision and craft.
Penalties for companies and employees
that violate policies.

Hard-hat sticker provided to


all craft and subs on the
project.

Examples of Mitigation Signage

Mitigation signage
commonly seen near
work zones.
Example of mitigation
signage installed in
staging yards.

7
Example of mitigation signage in the La Brea yards.

Mitigation Measures

A flagger at
Wilshire/Detroit
monitoring hauling
during an ongoing
closure.

Example of a map provided to subcontractors to show approved haul routes.

8 Parking meters
restored on Wilshire
between Detroit and
Cloverdale.

Purple Line Maintenance Facility


Butterfield Property
590 S Santa Fe Avenue

Located in Arts District


downtown, near 6th St Bridge
Continuation of Abatement work

Monday thru Saturday


Work Hours: 7am to 4:30pm

Design Advisory Group

Advisory group is made up of local


leaders and artists from the Arts
District.
Goal is to review and provide input on
exterior design of building.
Presentation from April 13th meeting
online.

Tie-in at Western Station


Future Western Staging Yard
Northeast corner of Wilshire and Manhattan

Place one block west of Western


Fencing and signage placed at site
Sound wall construction anticipated for early
July

Utility Investigation
Additional activities in Western area include
pot holing and street restoration
M-F, 9am-3:30pm
Sat-Sun, 8am-6pm

10
Wilshire/Manhattan Place staging yard

Crenshaw Yard Staging Site


Wilshire/Crenshaw
Used throughout Section 1 utility

relocation and construction


Mitigation efforts and maintenance:
Crenshaw Gate Entrance re-worked
and improvements made
Lorraine Gate temporarily closed
until further notice
Maintenance inside and outside of
yard

Signage at the Crenshaw Yard

Signage and blankets at the Crenshaw Yard Entrance

11

La Brea Station

Rendering shows length of the La Brea underground station box


on Wilshire Blvd from Orange Dr to Detroit St

12

Purple Line Extension


La Brea Schedule

*As of May 2016. Subject to Change

13

La Brea Station
La Brea Staging Yards
Staging Yard Activities and
Equipment

Yard usage: 7am to 11pm, (11pm


to 7am as needed).
Wall has openings where pile
installation and decking will occur
Sound wall is 20-24 feet high
Maintenance of equipment
Deliveries

Eat Shop Play promotions and construction phase artwork

Mitigations

Must comply with COLA noise


requirements
Noise Control Signage
Low Impact Back up alarms
Acoustical Insulation
Metro 5 Step Noise Plan

N La Brea Staging Yard Pile Work

14

La Brea Station
Pile Installation

*Dates and work activities subject to change

La Brea Pile Installation Overview


On Wilshire from Orange Dr. to Detroit St.
Pile installation includes:
Rig to construct approx. 95ft (L) deep
Crane lifting approx. 95Ft (L) , 24 Inch H-piles into holes
Approx. 590 piles total
Drilling, pile installation and backfilled concrete completed
same day

Pile Installation for South side of Wilshire


April 2016-Summer*

Orange Dr to Detroit St
Work hours: 7am to 11pm with potential nighttime work
hours from 11pm to 7am.
Will require directional closures on La Brea, Wilshire and
intermittent closures of Orange Dr and Sycamore.
Approved detour routes provided in construction notices
for directional closures.

Pile work at Wilshire/La Brea

15

Weekend Directional
Closures for Piling

*Dates and work activities subject to change

Weekend Directional Closures for


Piling on the South Side of Wilshire
April 2016-Summer*

Approved weekend directional closures start Friday


9pm-Monday 6am
Directional closures for piling on the south side of
Wilshire will include closures of southbound La Brea,
northbound La Brea and eastbound Wilshire.
La Brea directional closures use Highland, 6th St. and
8th St. as detours.
Wilshire directional closures use Fairfax, La Brea, and
6th St. as detours.
Work includes pot holing, pre-trenching, piling, jet
grouting.
Traffic officers dispatched to facilitate traffic
movement.

Pile work under a northbound directional closure on La Brea

Directional closure locations in the Wilshire/La Brea area.

16

Appendage Piles, South Side of


Wilshire

Appendage piles are the ancillary piles for the structures on the sides of the station box.
Located on the north and south side of Wilshire Blvd on La Brea, Sycamore, and Orange.
Appendage structures include:
Vent shafts, exit stairwells, and station entrance at La Brea
Appendage piles are smaller and shorter (40-60ft.) than the station box piles.
Requires closures on La Brea, Sycamore, and Orange.

This diagram shows the appendage structure locations on the south


side of Wilshire boxed in purple.

17

Appendage Piles
Schedule
South side of Wilshire Appendage Piles

South side appendage structures started in


May 2016

Traffic control

Sycamore and Orange will be closed to thru


traffic at Wilshire intermittently
Access from 6th, 8th, and alleys will be
maintained
Intermittent sidewalk closures
Sidewalk on the south side of Wilshire
between La Brea and Detroit closed thru
July

Northbound Sycamore Appendage Pile Work

18

LA BREA DECKING
19

La Brea Station
Decking Overview
Decking

On Wilshire, between Orange Dr. and Detroit St.


Construction of a concrete deck, curb to curb
Sidewalks be maintained, or pedestrian detours created
Decking will serve as the temporary street surface
Traffic will travel on the installed deck panels while the station
is constructed underground
La Brea Station:
Approx. 1,000 feet long
Approx. 70 feet wide
Approx. 60 feet deep
Will follow pile operations; anticipated to begin June 2016
Will work closely with First Responders on emergency access
and safety
Pending Board of Public Works approval in May
Additional activities under decking closures: jet grouting,
piling, temp. civil improvements.

20

20

La Brea Station
Examples of Decking

Full Closure of Crenshaw Blvd to install Decking

21

La Brea Station
Examples of Decking

Full Closure of Crenshaw Blvd to Install Decking

22

La Brea Station
Example of Decking Completed

Crenshaw Blvd and Rodeo Rd Decking

23

La Brea Station
Decking Schedule

*Dates and work activities subject to change

June 2016 through Fall 2016


Approximately 22 weekend closures (no work 4th of July or Labor Day weekends)
Work is scheduled in three phases.
Phase 1: Wilshire, from Detroit to La Brea
Phase 1B: Wilshire, from Cloverdale to La Brea
Phase 2: Wilshire/La Brea Intersection
Phase 3: Wilshire, from La Brea to Highland

Traffic plan for closures

Fridays 10am: Wilshire reduced to one lane each direction


Lane reductions at 10am will allow the design builder to start the loudest work
(breaking of concrete) during day time hours.
Friday 8pm: Full closure of Wilshire or Wilshire/La Brea intersection (Phase 2)
Monday 6am: Streets open
Work occurs 24/7

For information on closures and detours


WWW.METRO.NET/PURPLELINEEXT

La Brea Decking Phase 1


Wilshire, Detroit to La Brea
Essentials:
Wilshire reduced to one lane
in each direction, from Detroit
to Highland, on Fridays from
10am - 8pm
Full closure of Wilshire Blvd,
Detroit to La Brea, starting at
8pm on Fridays until
Mondays at 6am
Southbound La Brea reduced
to one lane between 6th and
Wilshire.

Work zone on Wilshire, Detroit La Brea

25

Phase 1 Detour
Wilshire, Detroit to La Brea Closure
Westbound: Northbound
La Brea to Westbound 6th
St. to Southbound Fairfax
Eastbound: Northbound
Fairfax to Eastbound 6th
St. to Southbound La Brea

26

La Brea Decking Phase 1B


Wilshire, Cloverdale to La Brea
Essentials

Full closure of Wilshire, from


Cloverdale to La Brea, during
Phase 1 of decking.
This closure will support decking,
paving, and staging.
The duration of this closure is
approx. 1-2 weekends
Detour same as for Phase 1.
Work zone from Cloverdale to La Brea

27

La Brea Decking Phase 1B Closure


Local Access for Detroit Street

Local access for residents on Detroit


maintained via Carling Way at 6th St.
Carling Way access from Detroit
restricted.
Traffic facilitated by flaggers, signage.
Door-to-door outreach for residents
and businesses prior to closure.
South Detroit Street access from 8th

La Brea Decking Phase 2


La Brea/Wilshire Intersection
Essentials:
Early start lane reductions on

Wilshire, Detroit to Highland,


reduced to one lane in each
direction on Fridays from 10am
until 8pm
Full closure of La Brea Ave.
starting at 8pm on Fridays until
Monday at 6am
Full closure of Wilshire Blvd.
starting at 8pm on Fridays until
Monday at 6am

Work zone, Wilshire/La Brea intersection

29

Phase 2 Wilshire Detour


La Brea/Wilshire Intersection Closure
Westbound Wilshire: Westbound
Wilshire to northbound Highland to
westbound 6th St. to southbound
Fairfax to westbound Wilshire.
Eastbound Wilshire: Eastbound Wilshire
to northbound Fairfax to eastbound 6th
St to southbound Highland to Wilshire
Local access on Wilshire for business and
residents will be maintained up to the
Wilshire/La Brea intersection. The farthest that
westbound thru traffic can travel before
needing to turn is: Wilshire/Highland. The
farthest that eastbound thru traffic can travel
before needing to turn is: Wilshire/Fairfax
Lane reductions on Wilshire going westbound
will start: Wilshire/McCadden
Lane reductions on Wilshire going eastbound
will start: Wilshire/San Diego Way

30

Phase 2 Southbound/Northbound La Brea Detour


La Brea/Wilshire Intersection Closure
Southbound La Brea: Southbound La Brea
to westbound 3rd St. to southbound Fairfax
to eastbound San Vicente to southbound La
Brea. Local access maintained between 3rd
and La Brea
Northbound La Brea: Northbound La Brea
to westbound Olympic to northbound
Fairfax to eastbound 3rd to northbound La
Brea.
Lane reductions on La Brea will start:
Southbound La Brea at 4th
Northbound La Brea at 9th

31

La Brea Decking, Phase 3


Wilshire, La Brea to Highland
Essentials:
Wilshire, from La Brea to
Highland, reduced to one lane
in each direction on Fridays
from 10am until 8pm
Full closure of Wilshire Blvd.
from 8pm on Friday until 6am
on Monday
Northbound La Brea reduced
to one lane from 8th to
Wilshire Blvd

Work zone - La Brea-Orange. Closure - La Brea-Highland to


avoid traffic on local streets

32

Phase 3 Detour
Wilshire, La Brea to Highland
Eastbound: Northbound La
Brea to Eastbound 6th to
Southbound Highland to
Eastbound Wilshire
Westbound: Northbound
Highland to Westbound 6th to
Southbound La Brea to
Westbound Wilshire

33

Bus Detours
Wilshire and La Brea
Phase I/II: 720/20, LADOT Dash, AVT
Eastbound/Westbound Wilshire Buses will be temporarily suspended between
Fairfax and La Brea
Nearest bus stop locations will be at Wilshire/Crescent Heights and Wilshire/
Highland.
LADOT Dash Buses will be temporarily suspended on 6th Street between Hauser
and La Brea
Antelope Valley Transit Authority (AVT) buses will also be temporarily suspended
on Wilshire
LADOT Dash and AVT Bus Detours will be coordinated with Metro bus operations.

34

Bus Detours
Phase I: 720/20 Bus Lines
Eastbound: Eastbound Wilshire,
to northbound Fairfax,
eastbound 3rd St, to
southbound La Brea, to
Wilshire.
Westbound: Westbound
Wilshire, northbound La Brea,
westbound 3rd St, southbound
Fairfax to Wilshire

35

Bus Detour
Phase II: 720/20 Bus Lines
Eastbound: Eastbound Wilshire,
northbound Fairfax, eastbound
3rd St, southbound Rossmore to
Wilshire
Westbound: Westbound
Wilshire, northbound Rossmore,
westbound 3rd St, southbound
Fairfax to Wilshire

36

Bus Detours
Phase II: 212/312 Bus Lines (La Brea)
Southbound: Southbound La
Brea, eastbound 3rd St,
southbound Rossmore,
eastbound Wilshire, southbound
Crenshaw, westbound Olympic,
southbound La Brea.
Northbound: Northbound La
Brea, eastbound Olympic,
northbound Crenshaw,
westbound Wilshire, northbound
Rossmore, westbound 3rd St,
northbound La Brea.

37

Bus Detours
Phase III: 720/20 Bus Lines
Eastbound: Eastbound Wilshire,
Southbound La Brea, Eastbound
Olympic, Northbound Crenshaw,
Eastbound Wilshire
Westbound: Westbound Wilshire,
Southbound Wilshire, Westbound
Olympic, Northbound La Brea,
Westbound Wilshire

38

La Brea Station Decking


Community Outreach
Robust Marketing Campaign
Social Media: Facebook, Twitter, Nextdoor
Advertising: print, radio, online (English, Spanish, Korean)
10 local papers
15 radio stations
Media Coverage: Press event, press releases
Business and resident outreach
Door to Door outreach La Brea area
Community Meetings
July 21, Petersen Automotive Museum
September 15, TBD
Marketing Items
Trifold, postcard, bus drop, TAP outreach
Landing page on PLE homepage

Decking Overview
Detour Maps
Photos/videos
Construction Notice updates

I-405 Freeway Closure Carmageddon

Board of Public Works Approval May 27 (tentative)


39

Communications and Outreach


La Brea Decking Outreach
August December 2015

65 Meetings/Briefings
68 Construction Notices
Sent via eblast, posted on website and social media
Community Meeting notices walked to 30,000 residents/businesses

Since 2016

78 Meetings/Briefings
133 Construction Notices
90,000+ flyers distributed
Construction Community Meetings: January 21, March 17, May 19
Wilshire/La Brea Business Meeting: June 2
Email Distribution List: 2,300+, Facebook 5,000+ likes, Twitter: 4,000+
Weekly emails to community leader for NCs, HOAs, Apartments

Tower Crane at Wilshire/La Brea


Tower approx. 100 ft.
Boom approx. 180ft.
Expected to arrive Summer 2016 in the
north La Brea yard at Wilshire/La Brea.
Function is to support station
excavation and tunneling excavation.

Tower cranes in New York City on the World Trade Center


project

Rendering of the tower crane in the north La


Brea yard at Wilshire/La Brea

41

Jet Grouting
Jet grouting is a construction process that uses high-pressure air

and grout to create a deep soil-concrete block.


The purpose of jet grouting is to reinforce and strengthen the
soil with concrete to support tunneling and cross-passage
excavation.

Examples of jet grouting at Wilshire and Detroit behind K-rail


42

Jet Grouting Locations


*Dates and work activities subject to change

Jet Grouting will occur at 16


locations along Wilshire between
La Cienega and Western.

There will be no more than two


jet-grouting operations being
performed at one time.
Approximately 6 weeks at each
location.

1.

On Wilshire between Rossmore and Arden

2.

On Wilshire between Arden and Lucerne

3.

On Wilshire between Citrus and Mansfield

4.

On Wilshire between Highland and McCadden Pl

5.

On Wilshire between Cochran and Cloverdale

6.

On Wilshire between Plymouth and Windsor

7.

On Wilshire between Norton and Bronson

8.

On Wilshire between St Andrews and Grammercy

9.

On Wilshire between Crenshaw and Lorraine

10. On Wilshire between Wilton and Van Ness


11. On Wilshire between La Jolla and Sweetzer (x2)
12. On Wilshire between Crescent Heights and La Jolla
13. On Wilshire between Burnside and Dunsmuir
14. On Wilshire between Spaulding and Ogden
15. On Wilshire between Fairfax and Crescent Heights

43

Jet Grouting Activities and Layout


Work Activities
Potholing, street level excavation ,
vertical drilling , trucking, cement
silos, pumps, generators
Layout
Concrete Barriers placed on the
middle lanes of Wilshire Blvd
Lanes reduced to two lanes each
direction at Jet grouting locations
Bus stops will be temporarily
relocated as required
Wilshire BRT lane not enforced in
these areas during jet grouting

44

Jet Grout Schedule

*Dates and work activities subject to change

Jet Grouting
Jet grouting will continue behind concrete barriers at Wilshire/Detroit.

Jet Grouting on Wilshire Blvd


Start summer 2016
First three locations
Wilshire between Rossmore and Arden (approx. 6 weeks)
Wilshire between Arden and Lucerne (approx. 6 weeks)
Wilshire between Citrus and Mansfield (approx. 6 weeks)
Construction notices will be sent and outreach will be conducted for
each location

45

Deck Openings
What:

Deck openings are openings of the street-deck for


the purpose of delivering materials for underground
construction.
Deck openings will be done at locations of the deck
that are designed to open and close.
Deck openings will occur periodically, as needed
Deck panels are 8ftx14ft

When:

Following La Brea decking, late 2016


Throughout the duration of the project

How:

Off-peak hour (M-F, 9am-3:30pm) lane closures

Example of a deck opening


from underneath the deck

46

Deck Openings
Construction Activities

Concrete placement

Maintenance of deck beams, panels and utilities

Deliveries into excavation/station - rebar, struts,


lumber, MEP equipment, shoring and formwork
panels, construction equipment, ventilation,
utilities, waterproofing

Station backfilling

Installation of new and replacement utilities

Example of a beam delivery through a deck


opening as seen from street level.

47

Fairfax Station

Rendering shows length of the Fairfax underground station box


on Wilshire Blvd from west of Fairfax to just west of Ogden Dr.

48

Fairfax Station
Schedule

*Schedule is subject to change. Updated as of May 2016.

35

Fairfax Station
Advance Utility Relocation

Potholing continues
Work hours:
o

Monday thru Friday:


9am-3:30pm
Saturday-Sunday:
8am-5pm
Night work (if
necessary): 9pm-6am

Utility investigation during pot holing at Wilshire/Fairfax.

50

Fairfax Station
Activities at Ogden Staging Yard

Equipment for jet grouting stored in the Ogden yard.

Sound wall and driveway construction


Mobilization of equipment in advance of k-rail
installation

Sound wall pile installation underway in the Ogden Yard .

51

Ogden Staging Yard


Sound Wall Construction

Construction of sound wall and driveways


Work hours: 7am-5pm
Sound wall is 20-24 ft
Sidewalk closure on east side of Orange Grove (yellow highlighted area)
Eat Shop Play promotions and construction phase artwork will be added to the walls

52

Ogden Yard
Safety Measures & Mitigations
.

Examples fromWilshire/La Brea


Staging Yard
53

Fairfax Tree and Median Removal

Tree removal in the medians complete


Median removal, ongoing thru May
Work hours: 9:00am-3:30pm M-F, 8:00am-6:00pm Sat/Sun
62 agave plants were saved and donated to local recipients.
38 street trees will be removed.
Trees replaced at a ratio of 2:1 at the end of the project
Banner highlighting future landscape will be placed on Ogden sound wall
2.5 medians to be removed from Fairfax to Spaulding.

Students at Carthay Center School for


Environmental Studies watering donated
agave plants on campus

54

Fairfax Median Removal Locations

55

Future Landscape Medians at Fairfax/La Brea

Median design at Wilshire/ Ogden facing west (left rendering)


Median design at Wilshire/ Cloverdale facing west (right rendering)
56

Wilshire/Fairfax Bus Stop Relocations

New bus stop locations in the Wilshire/Fairfax area


Safely outside of construction zones
57

Fairfax Traffic Reconfiguration


Piling Preparation

Anticipated start is June 2016


Start date depends on DWP cable pulling, 3rd party relocations.
Install traffic reconfiguration over a single weekend.
Wilshire will be reduced to two lanes in each direction from
Spaulding to San Diego Way.
Ogden crosswalk to shift from west leg to east leg.
Potential off-peak lane reductions to one lane in each direction.
Left turn pockets will remain open at Wilshire and Fairfax during
north side pile operations only.

58

Fairfax Station
Pile Installation Overview

Pile installation includes:


Rig to construct 95ft (L) deep
Crane lifting 95Ft (L) , 24 Inch H-piles into
holes
Approx. 490 piles
Drilling, pile installation and backfilled
concrete completed same day
Piling anticipated to start on north side of Wilshire
between Ogden to just west of Fairfax.
Operation anticipated to take approximately 4-6
months on each side of the street.
Typical work hours 7am-11pm with potential
nighttime work hours from 11pm to 7am.
Wilshire is reduced to two lanes in each direction.
Directional closures on Fairfax and Wilshire will
take place on weekends.

PHOTO

47

Piling at the N. La Brea yard.

59

La Cienega Station

Rendering shows length of the La Cienega underground station


box on Wilshire Blvd from La Cienega to Tower Dr.

60

La Cienega Utility Relocation


30 Months

*Schedule is subject to change. Updated as of May 2016

61

La Cienega Station
Advanced Utility Relocation
Water and telecommunication work continues along the alignment on

Wilshire from La Cienega to San Vicente.

Photo of recent AUR work for the La Cienega Station

62

La Cienega Station
Advanced Utility Relocation
Current AUR activities continue during
daytime and evening hours.
Days and Hours*
o
o
o

Monday thru Friday: 7am 4pm


Saturday or Sunday: 8am 6pm
Night Time Hours:
8pm 6am or
12am 7am
* Hours vary for events at The Saban Theatre
Photo of recent AUR work on Wilshire at La Cienega

63

La Cienega Station
Gale Yard
Demolition of buildings on Gale and
Wilshire Summer 2016
Future Gale Staging Yard

Beverly Hills Fire Department may use


abated properties for fire drill exercises
prior to demolition
Updates will be provided to the
community when drills are scheduled

64

La Cienega Station
La Cienega Yard

Future La Cienega Staging Yard

Buildings to be demolished,
anticipated in Summer 2016

65

La Cienega Station
Weekend Work
Weekends, Friday thru Sunday
Detours and turning restrictions will depend on
location of construction.
Wilshire, at least one lane open in each
direction
La Cienega, at least one lane open in each
direction
Days and Hours
o Start: Friday 10pm or 12am*
o End: Sunday by 6pm

Photo

*start time depends on the Saban Theatre performance schedule

Intersection at Wilshire and La Cienega

66

Eat, Shop, Play Wilshire


ESP Spotlight- West Segment
Lunch Meet Up
Friday May 20th, 2016
11:30am- 1:00pm
Book My Lot- Food Trucks

edian

logolo

5800 block of Wilshire Blvd


Los Angeles, CA 90036
Across from LACMA
(Between Spaulding and Stanley)
Book My Lot brings internationally diverse and gourmet
cuisine to the Miracle Mile on a daily basis by organizing and
scheduling some of the best food trucks LA has to offer- on
site 7 days a week
For more Information: Visit www.bookmylot.com or email:
patrick@bookmylot.com

67

Eat, Shop, Play Wilshire


ESP Spotlight- East Segment
Beauty Bar Los Angeles
5115 Wilshire Suite B, Los Angeles, CA 90036

$3.00 off for a Manicure or Pedicure on


Mondays, Tuesdays, or Wednesdays only!
Beauty Bar Los Angeles is a nail salon located a
few blocks from Wilshire and Highland.
Services include a nails salon, facials, eyelash
extensions and waxing.

68

Eat Shop Play Wilshire


In The Community

Design Build contractor and Metro


PLE team at the Miracle Mile La
Brea business stroll

Spare Tire Kitchen and Tavern Lunch Meet up

Prospect Gourmand located on


La Cienega Lunch Meet up

Crews buying lunch from Jack in the Box

69

Eat, Shop, Play Wilshire


Quarterly Drawing Winners

$1,000 winner from


Milk Jar Cookies
5466 Wilshire

$500 winner from


Next Gen Video Games
5360 Wilshire

$250 winner from


Beauty Images
678 S Cloverdale

70

Eat, Shop, Play Wilshire


Fortune Fridays
Support local businesses &
spread the word on social media
about your positive experience
for a chance to win $50!
Participation is easy!
Use #EatShopPlay and
#Wilshire in your positive social
media posts.
Like & Follow our pages to
see the winner announcements
every Friday!

71

72

Upcoming BIF Workshops


Purple Line Extension, Phase 1
Wednesday, June 29, 2016
11:30am-12:30pm
BREATHE LA (1st Floor, Conference Room)
5858 Wilshire Blvd., Los Angeles, CA 90036
*Street Parking Only

For more information visit


www.pcrcorp.org or contact Angela
Winston, Program Manager at
213.739.2999, ext 223

73

Next Meeting
Section 1 Construction Community Meeting
Thursday, July 21, 2016
6:00-8:00pm
Petersen Automotive Museum
6060 Wilshire Blvd, 4th Floor
Los Angeles, CA 90036
Agenda: La Brea decking update
Fairfax piling update
Art Program: Resources Needed!
74

Stay in Touch

www.metro.net/purplelineext
twitter.com/purplelineext
facebook.com/purplelineext
213.922.6934
purplelineext@metro.net
75

Das könnte Ihnen auch gefallen