1 March 2016
See Distribution
Dear Sir/Madam
CALIBRATION OF EQUIPMENT
ACCREDITED LABORATORIES
FOR
PILE
LOAD
TEST
BY
SAC-SINGLAS
This circular is to remind the industry on the regulatory requirements relating to pile
load tests carried out in connection with building works.
2
Under Regulation 39(2)(b) of the Building Control Regulations, any test for the
purpose of Section 7A(2) of the Building Control Act is to be carried out in a SAC-SINGLAS
accredited laboratory. These tests include calibration tests for equipment like load cells,
pressure gauges and movement gauges used in pile load testing.
3
Before commencement of any pile load testing at site, Qualified Persons (QP)
supervising the pile load test will have to inspect the test equipment to check that they are
functional and properly calibrated. BCA would like to remind QP to exercise vigilance to
check and verify the calibration reports issued by the laboratories.
4.
QPs are to take note that not all laboratories are SAC-SINGLAS accredited, and that
accreditation may only be for specific services rendered by these companies. QPs are
therefore reminded to ensure that the laboratory that you have engaged to carry out the test
is SAC-SINGLAS accredited for that specific scope of test. The accreditation status of
companies and their scopes of accreditation can be found at the Singapore Accreditation
Councils website (www.sac-accreditation.gov.sg).
5.
QPs are advised to check that each of the test equipment used in the pile load
testing bears a valid calibration certificate, issued by a SAC-SINGLAS accredited laboratory
to the full capability or capacity of the test equipment. QPs should also check for the SAC
accreditation mark on the endorsed calibration reports and certificates for the test equipment
as proof that the services has attained accreditation from SAC, before allowing them to be
used for pile load testing at site. A sample of an endorsed calibration report for load cell is
shown in Annex A.
6
QPs supervising building works that require the use of load cells or hydraulic jacks to
measure forces are also reminded to check and verify the calibration reports of these
equipment. Examples of building work that require the use of these equipment include preloading of ERSS struts, prestressing, ground anchors, etc.
7
I would appreciate it if you could bring to the attention of your members the contents
of this circular. Please contact Dr Yet Nai Song or Mr Kwa Chin Soon at Tel 6804 4600 or
email kwa_chin_soon@bca.gov.sg, if you need further clarification. Thank you.
Yours faithfully
PRESIDENT
SINGAPORE STRUCTURAL STEEL SOCIETY (SSSS)
1 LIANG SEAH STREET
#02-11/12 LIANG SEAH PLACE
SINGAPORE 189022
secretariat@ssss.org.sg
PRESIDENT
GEOTECHNICAL SOCIETY OF SINGAPORE
C/O PROFESSIONAL ACTIVITIES CENTRE
NUS FACULTY OF ENGINEERING
9 ENGINEERING DRIVE 1
SINGAPORE 117576
geoss@nus.edu.sg
PRESIDENT
PROFESSIONAL ENGINEERS BOARD, SINGAPORE (PEB)
52 JURONG GATEWAY ROAD, #07-03
SINGAPORE 608550
registrar@peb.gov.sg
PRESIDENT
BOARD OF ARCHITECTS (BOA)
5 MAXWELL ROAD
1ST STOREY TOWER BLOCK
MND COMPLEX
SINGAPORE 069110
boarch@singnet.com.sg
DIRECTOR
PROTECTIVE INFRASTRUCTURE & ESTATE
DEFENCE SCIENCE & TECHNOLOGY AGENCY
1 DEPOT ROAD #03-01J
SINGAPORE 109679
oyewhing@dsta.gov.sg
DEPUTY DIRECTOR
PROJECT DEVELOPMENT & MAINTENANCE BRANCH
MINISTRY OF EDUCATION
1 NORTH BUONA VISTA DRIVE
OFFICE TOWER LEVEL 9
SINGAPORE 138675
eng_wee_tong@moe.gov.sg
DIRECTOR
BEST SOURCING DEPARTMENT
PUBLIC UTILITIES BOARD
40 SCOTTS ROAD #18-01
ENVIRONMENT BUILDING
SINGAPORE 228231
koh_boon_aik@pub.gov.sg
lim_kim_tee@pub.gov.sg