Beruflich Dokumente
Kultur Dokumente
.0
1
General Requirements
The Instrumentation and Control System envisaged shall be complete in all respect and
adequate for safe, reliable, efficient operation of the Waste water treatment system under
normal and worst service and environmental conditions specified. The scope of work shall
include detailed design, supply, testing and commissioning of Waste Water treatment plant
C&I system.
The design of C&I system shall be such that isolation of any piece of defective equipment
would be possible without shutting down the main equipment or disturbing the operation of
associated instrument and accessories.
All instruments i.e. Primary elements, transmitters, Switches, controllers, level transmitters,
Level switches, shall be electronic based on modular construction, while control actuators for
regulating duty shall be pneumatic. Satisfactory operation of the electronic equipment and
components for temperature and humidity shall comply with the site climatic conditions
specified under Section 1 of this specification.
For process variable viz. Flow, pressure, temperature, level etc. electronic signal transmission
from field to PLC shall be isolated 4-20 mA dc / Potential free contacts.
Complete instrumentation cables required for this System i.e. from field sensors / actuators to
JB's, JB's to PLC system, field sensors to Local control station and from MCC / switchgear to
PLC system i.e. where one end or both ends equipments is in bidder's scope, complete
Supply, laying, termination, etc shall be in bidder's scope.
Shall be able to communicate with external system and intelligent field equipment
Commissioning support
The Control System shall have on-line simulation & testing facility.
The system shall have the flexibility to easily reconfigure any controller at any time
without requiring additional hardware or system wiring changes and without
disabling other devices from their normal operation mode. Modifications shall not
require switching off power to any part of the system.
Fault Diagnostics.
Ambient temp.
: IEC-255.4
: 16
: 0-50 degree C
Interrogation voltage
Status Indicator
: LED Type.
Isolation
: Optical
(ii)
: 24 VDC
Ambient temperature
: 8
Isolation
: Galvanic
Status Indicator
: LED Type.
: 0-50 degree C
: IEC-255.4
Redundant
Yes
Transmission rate
Control
Transfer procedure
SDLC
Data Protection
16 bit CRC
Proprietary Bus
Yes
Standard
IEEE 802.4
Software License
The bidder shall provide software license for all software being used in PLC based control
system. The software licenses shall be provided for the project and shall not be
hardware/machine specific. All licenses shall be valid for the continuous service life of the
plant.
Software provided shall be latest, modular, upgradeable and industrially proven. It shall have
capability for multi tasking, multi programming, multi user operation in real time environment
and support for third party system.
Training
Bidder's experienced personnel/engineers shall provide training courses on offered PLC
system to Employer's engineers in the following areas:
(a)
Operator training
(b)
Hardware Maintenance training
(c)
Software training
(d)
Any other specialized training as required for system operation and
maintenance.
The maintenance training shall include lectures and hands on experience on similar type of
equipment / system at manufacturer works and recently commissioned operating plant and / or
training simulator. The details of hardware and software training shall be finalized during
detailed engineering and shall be subject to owner's approval.
Power supply bus bars in cubicles shall be carefully routed and each bus bar shall be
shrouded. It shall not be possible to inadvertently short bus bars either between themselves or
to earth.
(c) Marshalling Cubicles
Marshalling cubicles shall be of fabricated steel construction of minimum thickness 2 mm,
galvanized and painted, dustproof and vermin proof and so designed that condensation shall
not affect the insulation of the terminal blocks or cables.
Sufficient space shall be included in the cubicle for terminals and cable trunking. The trunking
shall not be overfilled and adequate space shall be allowed for easy removal of lower cables.
All spare cables shall be contained in the trunking.
Marshalling cubicles shall be complete with ail necessary terminal blocks, wiring, washers or
tags, wiring ferrules, labels and door locks. All marshalling cubicles shall accept a common
key for locking.
In each marshalling cubicle circuits shall be grouped and labelled according to function (i.e.
system control, alarm and tripping circuits, telephone circuits, etc), with the labels attached to
the fixed portion of the terminal boards. Terminals shall be provided for connecting the screens
of screened twisted pair cables or the overall screen on multicore cables and shall be adjacent
to the termination of the associated twisted pair.
(d) Earthing
Earthing of electronic equipment is required to reduce the effects of electrical interference and
for the safety of operation and maintenance staff. Where there is a conflict between the two,
personal safety shall always take precedence.
Earthing should be generally in accordance with BS 6739, BS 7671 and BS 7430 or
equivalent international standards unless otherwise approved.
Protective screens around insulated cables shall be insulated from field instruments,
connected through any field junction boxes, and be continuous up to the earthing point in the
destination cubicle or panel.
Cubicles, desks etc, shall be equipped with a "clean" instrument earth comprising an insulated
copper earth bar for the connection of cable screens. All "clean" instrument earth bars shall be
clearly labelled as such. Connection of the instrument earth to the site earth shall be by
separate conductor to the equipment safety earth.
All non-current carrying metallic parts of plant, equipment, components, enclosures, racks etc,
shall be earthed by connection to the main plant earth bar in an approved manner and all
earthing terminals and connections shall be of adequate dimensions.
For all panel, cubicle doors or swinging frames, flexible cable or braid shall be used for
earthing these items; the door hinges shall not be accepted as a means of earthing this part of
the equipment.
The design of equipment shall be such that cable screens and cable armouring are kept
electrically separate throughout the equipment installation so as to avoid the introduction of
earth loops and minimize interference pickup.
Sl. No
Features
Minimum Requirements
01.
Type
02.
SS 316
03.
Movement Materials
SS 304
04.
SS / IP 65
05.
Dial Size
150 mm
06.
Scale
07.
Range Selection
08.
09.
Adjustment
10.
Shall be provided
11.
Element Connection
Argon welding
12.
Process Connection
13.
Performance :a)
14.
Accuracy
Operating Ambient
Temperature
15.
Safety Feature
16.
Feature
17.
18.
Accessories
Sl. No
Features
Minimum Requirements
01.
Type
Gas filled
02.
Stem
SS 316
03.
Movement Materials
SS 304
04.
SS / IP65
05.
Dial Size
150 mm
06.
Scale
07.
Adjustment
08.
Pointer
09.
Range Selection
10.
Shall be provided
11.
150% of FSD
12.
Instrument Connection
13.
Process Connection
14.
15.
16.
Performance :a)
Accuracy
b)
Repeatability
c)
Response Time
Operating Ambient
Temperature
Accessories
Sl. No
Features
Minimum Requirements
01.
Mounting
Side-Side
02.
03.
Gauge Glass
Borosilicate
04.
Packing
05.
End Block
SS
06.
Gland
SS
07.
Working temperature
08.
Process Connection
As per requirement
09.
Vent
Plug
10.
Drain
Ball Valve
11
Accessories
Sl. No
Features
Minimum Requirements
Non contact Microprocessor based 2 wire type,
01.
Type
02.
Accuracy
03.
Resolution
04.
Repeatability
3 mm or better
05.
Local Indication
To be provided
06.
Temp. Compensation
To be provided
07.
Range
08.
Power Supply
09.
Sensor Material
10.
False signal
11.
Outputs
12.
Enclosure protection
Weatherproof IP 65
13.
Electrical connections
inch NPT
14.
Process connection
As per requirement
15.
Mounting accessories
accessories
required
for
erection
and
commissioning.
(e) pH Meter
Sl. No
01.
Features
Type
Minimum Requirements
Cell - Flow through, Transmitter- Microprocessor
based
02.
Case
03.
Electrode
pH Glass
04.
Analyzer output
4 to 20 m Amp DC
05.
Power supply
240V AC, 50 Hz
06.
Accuracy
+ 0.03 pH
07.
Repeatability
+0.02PH
08.
Type of contacts
09.
No. of contacts
2 SPDT
10.
Rating of contacts
11.
Electrical Connection
NPT(F)
12.
Enclosure Protection
IP 65
13.
Automatic temperature
Provided
compensation
14.
Provided
12 month of operation
15.
Accessories
C&I Cables
All cabling and wiring shall be of the flame-retardant and fire-resistant type in accordance with
BS 5467, BS 5308, and relevant IEC.
Multicore cables shall have stranded copper conductors of 1.5 mm2 minimum cross sectional
area, thermoplastic insulation and an overall thermoplastic sheath. These cables shall have an
overall metallic shield. There shall be a minimum of 20% spare cores, but no less than two
cores, for future use.
Multipair cables shall have twisted pairs of stranded copper conductors of 1 mm2 minimum
cross sectional area, thermoplastic insulation and an overall thermoplastic sheath. These
cables shall have an individual insulated metallic shield applied to each pair and an overall
metallic shield. There shall be a minimum of 20% spare pairs, but no less than 1 pair, for
future use.
Optical fibre cables shall have a minimum of 4 fibres. There shall be a minimum of 20% spare
fibres, but no less than 2 fibres, for future use. All fibres to be terminated in approved terminal
boxes.
The cables shall be protected from physical abuse and attack from rodents/insects. The
Bidder shall advise his proposed methods for the physical protection of the cables and these
shall be subject to the approval of the Owner/Engineer.
Multipair cables shall be employed for the majority of l&C applications including analogue
circuits, up to a maximum of 20 mA, and digital circuits up to a maximum of 50 V dc. This shall
include 24 V dc solenoid valves.
(b) Cable Installation
(i) Separation
Running l&C cables along the same route as power cables shall be avoided. Where this
is not possible, the cables shall be segregated as fully as possible. It is not permissible
for power and l&C cables to share the same tray/rack/trun king/conduit.
l&C cables shall be run on dedicated trays with a minimum separation between the l&C
trays and ail other trays.
If l&C cable trays are to be installed in the same routes as power cable trays then the
l&C trays are to be installed at a lower level than the power cable trays to ensure that
heat generated by the power cables does not travel through the l&C cables.
A closed conduit l&C cabling system shall be used for individual field devices up to the
local junction box.
(ii)
Segregation
All l&C cables from one unit shall be segregated from those for any other unit. The
cables for common or station equipment shall be segregated from any unit cabling.
Cabling for redundant equipment shall be installed over separate routes. Cabling for
redundant instrumentation (e.g. two-out-of-three voted signals) shall be installed over at
least two separate routes.
(iii)
Laying and Terminating
l&C cables shall be fully supported either in conduits, on tray, racks or other support
systems subject to the Owners/Engineers approval. The cables shall be adequately
supported and clamped to prevent excessive sagging. Cable routes shall be such that
the cables are not exposed to extremes of temperature from the plant processes and
prolonged exposure to direct sunlight without some form of thermal protection.
The installation of the cable cores/pairs within the plant equipment, adaptable boxes,
junction boxes and marshalling boxes shall be such that a core/pair can be moved from
one extreme end of the terminal rail to the other end. In addition the core/pair shall be
capable of being re-terminated a minimum of three times.
All spare cores/pairs shall be tied back with a length capable of being terminated as
above.
(iv)
Identification
Each cable shall be identified with a cable number approved by the Owner/Engineer.
Each cable core shall be uniquely identified using interlocking ring plastic ferrules or
similar. Clip on or 'c' type ferrules shall not be used. The core identifier shall be to the
approval of the Owner/Engineer.
Where the route of the cable is through junction boxes, marshalling boxes, etc both the
incoming core and the outgoing core shal! carry the same unique core identification.
(v)
Cable Screens and Armouring
The design of equipment shall be such that cable screens and cable armouring are kept
electrically separate throughout the equipment installation. This separation shall be
maintained throughout by the installation of a suitable earth system subject to approval.
Instrument Installation
(a) General
All the instrumentation shall be installed so that it complies with BS 6739 and the
recommendations of the manufacturer. Only one instrument shall be fitted to each tapping
point.
(b) Local Measuring & Control Elements
Sensing elements shall be suitable for service fluid, temperature and pressure.
For sea water or brine service the wetted parts shall be Hastalloy C or Monel.
The body, Flanges, bolts and housing shall be stainless steel 304, 316L to suit the application
at the discretion of the Engineer.
Field instruments shall be located away from equipment/location where severe/continuous
vibrations or shocks occur or are expected.
Temperature and pressure compensation shall be provided, especially for steam/variable
specific gravity applications.
(c) Hazardous Areas
All l&C equipment shall be suitable for the specific area in which it is located. This shall take
into account the presence of any potentially hazardous conditions or substances.
If equipment is expected to operate in the presence of flammable or explosive materials
explosion proof construction is the preferred method of protection. All equipment offered for
use in such areas shall have the necessary certification by the appropriate Certification
Bureau and its proposed application shall fully comply with all conditions of the certificate.
The design and installation of the equipment shall take into account fully the appropriate
sections and requirements of BS EN 50014/BS EN 60079.
The Bidder shall provide a plant layout drawing and list defining the classification of all plant
areas taking into account all appropriate physical parameters including ambient and surface
temperatures of plant, dust/liquid/gas/water conditions, risk of fire and explosion.
(d) Primary Isolation and Instrument Valves
All instrument valves, proposed for use on this project, shall be approved by the
Owner/Engineer. All primary isolating and blow down valves shall be capable of being locked
in the open or shut positions. The direction of rotation shall be clearly marked on the handwheel.
The primary isolating valve shall be located at the tapping point, be of the parallel or globe
type and rated for the temperature and pressure of the main line. The primary isolation valve
shall be compatible with the system material to which it is connected.
Double isolation shall be provided for pressures above 40 barg and hazardous services.
Instrument isolating, equalizing and vent valves shall preferably be incorporated in a single
manifold, i.e. two/three way manifolds for pressure measurements and five way manifolds for
differential measurements. The instrument manifolds/valves shall be manufactured in stainless
steel unless the process conditions require different materials. Valve seatings and seals shall
be suitable for the process conditions.
Locking facilities for primary isolation valves and instrument valves/manifolds shall be
provided for l&C, related to safety/reliability of Unit/Plant.
(e) Impulse Pipe Work
Connections to instruments after the primary isolating valve shall normally be made using
stainless steel (316L) piping or piping suitable for the process conditions.
Instrument isolating valves, vent/test valves and instrument manifolds shall be attached to
measuring devices so that it is possible to disconnect the device from the connecting pipe
work without having to disconnect or drain the pipe work.
All instrument vent/drain points shall be directed to a safe position away from site personnel.
The primary instrument piping shall be 12 mm NB stainless steel piping. For applications up to
40 barg pressure, schedule 40 shall be used. For pressures above 40 barg, schedule 80 shall
be used.
(f) Pneumatic Pipe Work
Each individual air user shall be provided with an air filter regulator set with a lubricator to the
approval of the Owner/Engineer. A line size lockable isolating valve shall be provided
immediately upstream of the filter regulator.
The connection to the air user at the air supply manifold shall be supplied with an isolation
valve that shall have a locking facility. 20% spare connections, with isolating valves, shall be
supplied at each manifold.
The air supply pipe work and tubing shall be suitably sized to ensure that there is negligible
pressure drop during peak consumption of instrument air.
(g) Instrument Mounting
All indicating instruments and controls shall be grouped together, where possible, in suitable
housings and gauges shall be installed. They shall be readable and accessible from floor level
or permanent platforms. Gauge glasses shall be visible from any control valve that controls
the vessel level. Where gauge racks are used suitable sunshades shall be provided.
Transmitters and process switches shall be located in instrument housings containing up to six
instruments. Clearance shall be allowed for servicing and access to all items. Instrument
housings shall be provided with internal illumination, heaters, and a maintenance power
socket with an RCD and a communications jack socket.
Instruments, housings and gauge racks shall be positioned so that exits are not obstructed.
Post or bracket mounts for instruments shall not be attached to pipework, removable flooring,
handrails, or be directly affixed to machinery and equipment subject to vibration.
(h) Climatic Protection, Sealing and Purging
Instruments and their associated pipe work shall be mounted in heated or protected locations
wherever possible in order to minimize the effects of ambient weather conditions. Were this is
not possible a suitable means of ensuring and/or minimizing such effects shall be applied.
Instruments in liquid services, which solidify at ambient temperature, shall be provided with
diaphragm seals.
Seal chambers or diaphragm seals shall be used where fluid services are corrosive, viscous,
congealing, deposit forming, or dangerous. Seals shall be located as close as possible to the
primary isolating valve.