Sie sind auf Seite 1von 2

Following the Flow– Stop 1

Enlarged Erie Canal Lock 51


Locks are used in canals to allow boats to overcome changes in elevation in the landscape. Standing
here near the parking lot and looking (north) toward the stonework, the land to the right (east) is higher
than the land to the left (west). Lock 51 had a lift of 5.732 feet, which means that the canal to the east
was 5.732 feet higher than the canal to the west. Each lock had its own amount of lift, depending upon
the lay of the land. The highest lift on any Erie Canal lock was slightly over 11 feet. If the canal had to
overcome more than 12 feet, locks would be paired together.

There were 72 locks on the enlarged Erie Canal, which was 11 less the 83 on the first canal. This lock is
the 51st lock from Albany. All the locks look very similar since they all had to do the same job of lifting
the same boats. It would not make sense to have a lock larger or smaller then the other locks, since all
the boats were built to a maximum size. Each lock chamber was 110 feet long and 18 feet wide. Each
enlarged lock had two chambers, which was one of the improvements made over the first canal, which
had only one chamber. So instead of having boats alternate passing through the lock, two boats could
pass through at once. You will notice that the chamber closest to you is twice as long as the far chamber.
This is called a lengthened chamber, and it was another improvement made later in the 1880-1890’s.
Two boats could pass through at one time, and this was done during a time when steam-powered boats
were pulling other non-powered boats, or horses were pulling two non-powered boats tied together.

The sections of canal between locks are called levels. Lock 51 defines the western end of the Jordan
level, which was also a summit level since it was a high point in the canal. (Syracuse to the east is lower
than Jordan, as is Weedsport to the west. Jordan and Camillus sit on this small hill in the landscape,
which the canal must climb over on its way to the west.)

This lock was completed in 1853, but not put into use until 1858 because of the route change issues in
Port Byron. (Note the dash-line route of Clinton’s Ditch on the map. East is top of page.) This meant
that boats heading west would be using the new
canal up to this point and then they would use the
old 1820’s canal until they reached lock 52 in Port
Byron. This detour was necessary because of a
route dispute in Port Byron.

As was mentioned before, this boats passing


through this lock stepped down as they headed
west. This was not normal on the canal, where
most locks stepped boats up as they headed west.
This is because Lake Erie at Buffalo is 550 feet
higher than the Hudson River at Albany. But be-
cause of the little high spot at Jordan, this lock and
Lock 52 stepped boats down to the Seneca River
level. Out of the 72 locks, only 5 (47,48,49,51 and
52) stepped down to the west. All the others over-
came the 550 foot difference between Albany and
Buffalo.

Since the canal stepped down to the west, so did


water from Skaneateles Lake fed into the canal at
Jordan. As the canal was filled to its 7 foot capacity,
excess water would flow west until it reached the
lowest point at Montezuma. There the water
mixed with water from the west and spilled out
into the Seneca River. As water was removed from
the canal, either by seepage, lockage or evapora-
tion, replacement water from the lake would main-
tain the needed depth. The three large openings at
the east end of the lock are part of the water regu-
lating system. If the lock was used, water from the
upper level was released into the lower level. But
when the lock wasn’t being used, water in the canal
could by-pass the lock by flowing into the openings
and out to the lower end by way of a large tunnel.
This tunnel can still be seen today.

In 1887, the lengthened chamber was added


to the original 1853 stonework. You can no-
tice the difference in the stonework between
the two eras of lock construction. To save
money, only one chamber was lengthened. A
wooden platform and railing was built along-
side the stonework to allow room for boaters
and locktenders to walk and move around.

All the wood has since rotted and disap-


peared, leaving the stone to tell the tale of
the canal era.

Das könnte Ihnen auch gefallen