Ref. No.: BPS-121080-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia
No. 030

WEEKLY REPORT OF
11th Apr 2016 17th Apr 2016

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 1 of 6

1.
1.1

a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 11
PT Surabaya Prakarsa Fire Service (Fire Alarm)
: 10
PT Piping System Indonesia (Aboveground)
: 68
PT Valvtrol Global Flowsystem (Underground)
: 15
Total Manpower
: 104

1.2 Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Yaakop
Joey
Rahman

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Engineer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)

2.
-

SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.

3.
a.

QA/ QC
Hydrant Line & Dust Suppression Line Section 02 at Parking Area Hydrotest is done
on Monday 11th April 2016.
Official Line Check with PTCL for Hydrant Line at Oil Pump Area is done. Continue
Hydrotest, Excavation and Backfill this week.

b.

4.
PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission
4.2 Update Construction Progress
4.2.1 Fire System
4.2.2 Mechanical
Under Ground;
a.
Parking Area;
Progress :
- Line Section 02 at Parking Area Hydrotest is done on Monday 11th April 2016.
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 2 of 6

b.
c.
d.
e.
f.
g.

- Jointing Hydrant Line between Parking area Line (Admin Building) with North Line to
Pipe Bridge under the Drainage is done.
- Jointing Hydrant Line to Gate 01 area is on going.
- Excavation and Back Fill is on going.
BC-07A Inside Coal Yard; Jointing HDPE Pipe.
Progress : Install Hydrant Tees Spool
BC-07B Inside Coal Yard
Progress : Install Hydrant Tees Spool
BC-08.1 & BC-08.2 Southern Coal Yard
Progress : Install Hydrant Tees Spool and Flange
Oil Pump Area;
Progress : Official Line check is done.
Raw Water Electrical Building
Progress: Stringing and Jointing Hdpe Pipe to next reservation.
Fabrication HDPE tees spool pipe to prepare Hydrant Post installation from the ring
main line is continue.

Above Ground;
a.
Piperack
WTP area;
Piping Progress :
Boiler 1 Area;
Piping Progress :
b.
c.
d.
-

Fit-Up Progress: 12 Joints


Welding Progress: 3 Joints
Fit-Up Progress: 6 Joints
Welding Progress: 3 Joints

Pump House
Power Island:
Fire Pumps Leveling & Centering Internally is done.
Daily Fuel Diesel Tank Internal Leveling and Centering is done.
FHS:
Fire Pumps Leveling & Centering Internally still on going.
Daily Fuel Diesel Tank Internal Leveling and Centering still on going.
Boiler Cable Basement Unit 1;
Piping Progress :
Install Control Valve Header
Install Main Line to Header completed.
Install Pipe Support at Header Area.
Internal Line Check is done
Boiler Cable Basement Unit 2;
Piping Progress :
Install Deluge Valve Header
Install Main Line to Header completed.
Install Pipe Support at Header Area.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 3 of 6

- Internal Line Check is done


e.
Switchgear Cable Basement;
Piping Progress :
- Re-installed pipe, Replacing Pipe Hanger Support as per drawing is continue on going.
- Fabrication Control Valve Header & Continuing install Main Line to Header is continue
on going.
f.
CAB Cable Basement
- Re-installed pipe, Replacing Pipe Hanger Support as per drawing is continue on going.
- Fabrication Deluge Valve Header & Continuing install Main Line to Header is continue
on going.
g.
Workshop
- Fabrication;
Progress : Fabrication Header Control Valve, Pipe Support, Threading pipe.
- Painting;
Progress : Painting and Sandblasting is continue on going.
4.3 Fire Alarm
a.
Turbine Building; Continuing Install Cable Conduit.
4.4 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Dust Suppression Line Section 02 at Parking Area Hydrotest is done on Monday 11th
April 2016.
- Jointing Dust Suppression Line between Parking area Line (Admin Building) with North
Line to Pipe Bridge under the Drainage is done.
- Excavation and Back Fill is on going.
5 Action Plan for this Week (April, 18th April, 24th 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area:
- Excavation and Back Fill activities at Crossing to Pipe Bridge Line.
- Closing jointing under the U-ditch for Section - 01 (Crossing Area) Line.
- Closing jointing under Crossing Road for Section - 03 (Tanks Area) Line.
b.
BC-07A Inside Coal Yard; Jointing HDPE Pipe
Progress Target: Install Fittings for Hydrant Post and Valves.
c.
BC-09 Area;
Install tee pieces for future reservation near raw water electrical building.
d.
Raw Water Electrical Building Area:
Stringing and jointing HDPE Pipe.
e.
BC-07B Southern Area; Internal Line Check & Hydrotest preparation
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 4 of 6

f.
g.

Oil Pump Area; Hydrotest, Excavation and Back Fill, Install Valve Pit, Install Hydrant
Post, Install Outdoor Hydrant Box.
West Side Boiler Area; Spreading and jointing HDPE Pipe

Above Ground;
a.
Pipe Rack;
- WTP Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 7 Joints
- Boiler 1 Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 7 Joints
- FHS Cable Bridge:
Progress Target : Erection pipe to the Cable Bridge for 20 Lengths Pipe.
b.
Boiler Cable Basement Unit 1;
Progress Target: Install Control Valve Header, Official Line Check and Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Install Control Valve Header, Internal Line Check and Official Joint
Line check with Client
d.
CAB Cable Basement;
Progress Target: Complete piping installation, Install Control Header.
e.
Switchgear Cable Basement:
Progress Target: Complete piping installation, Install Control Header.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
h.
Fire Pump House
Power Island;
Progress Target: Joint Inspection for Leveling and Centering Pump Installation, Internal
Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Internal check continue to Joint Inspection Centering and Leveling
Pump Installation.
i.
BC-09
Progress Target: Install Piping Sprinkler System
j.
Workshop
- Fabrication;
Control Valve Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication,
Threading Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 5 of 6

5.2 Fire Alarm


a.
Turbine Building; Continue install cable conduit
b.
ACC Building : Install cable Conduit
5.3
a.
b.
c.

6.

Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Laying and Buried the Pipe under the drainage (Crossing Area).
Tanks Area : Continue Spreading and Joint pipe to Dust Suppression Pump.

MATERIAL DELIVERIES
- Raw Material for Piping and Pipe Support; 1 Truck

7.
TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.

Other Issues
- No Issues

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 6 of 6